Tender Value
₹6.8 L
EMD Value
₹7,000
Closing Date
9 Apr 2026, 6:00 pmClosed
Executive Engineer, Panchayat R & B Division, Vadodara
Constructing CC Road Waghodiya Faliya to Bhathiji Mandir to Mahadev Mandir at Gutal Village Ta.Waghodia Dist. Vadodara Under MLA Grant (2025-26)
291239
35 of 2025-2026
Open
Civil - All
Works
Vadodara
5 documents required · 5 mandatory
₹900
Yes
Executive Engineer, Panchayat (R&B) Division, Vadodara
₹7,000
Yes
28 Mar 2026
28 Mar 2026
28 Mar 2026
9 Apr 2026
28 Mar 2026
Name Of Work :- Constructing CC Road Waghodiya Faliya to Bhathiji Mandir to Mahadev Mandir at
Gutal Village Ta.Waghodia Dist. Vadodara Under MLA Grant (2025-26)
1 All works shall be carried out as per latest MORTH Specification Booklet and other specification
of Division as directed.
2 All Rates quoted include clearance of site (prior commencement of work and at its close) in all
respects and hold good for work under all conditions, site moisture, weather etc.
3 The contractor shall exhibit a board as per Government Circular No. Vernacular TNC/1090/24/S
dated 05.03.2011 with details specifications and details of works and amount involved at site at
his own cost as directed by Engineer-in-charge.
4 Testing of material shall be done as per statement attached with specification. The material should
be tested in GERI or Private laboratory approved by Govt. of Gujarat. Bill for testing charges
should be paid by Executive Engineer and computed after deducting the cost of materials to be
supplied by the Govt. and shall be recovered from the contractor's running bill as per Govt., R&B
Department No. TNC-1085/(4)/C dtd 20-12-91.
5 1.00 % of Construction cost shall be deducted form Bill. Amount of Contract as per the Building
and other Construction worker's welfare cess Act - 1996 (Labour & Employment Department
Letter No. CWA - 2004 - 1831 - M (3). Dt. 9-12-05, Notification of Labour & Employment
Department Dtd. 03-01-05 and Labour & Employment Department letter No. CWA / 2004-841-
6 In all R.C.C. items in rate analysis, standard cement consumption has been taken as per Govt. GR,
PRC-10/2017/Cement Consumption/16/C, Dtd. 11/05/2017 as stated in SOR therefore in RCC
items where there is a change as per actual mix design the cost of difference of cement
consumption shall be deducted from the rate of original item at the rate of input rate mentioned in
7 Bidders are advised to visit the site & make himself / themself aware of the scope & specification
of the work to be done & of conditions and other factors bearing on the execution of the work
before on line submission of his / their bids. Once the bid is finalized, under no circumstances
arguments for crust deficiency / additional / altered works will be heard until & unless Engineer in
charge deem so. Engineer in charge shall have right to reject & decision of Engineer in charge
shall be final & binding.
8 If found necessary, contractor will be intimated for negotiation. He will be intimated maximum
three times within validity period for negotiation. If contractor does not respond in time, his
earnest money will be forfeited and his tender will be rejected. Paneltative action will be taken on
such contractor.
Name Of Work :- Constructing CC Road Waghodiya Faliya to Bhathiji Mandir to Mahadev Mandir at
Gutal Village Ta.Waghodia Dist. Vadodara Under MLA Grant (2025-26)
Taluka :Waghodia District : Vadodara
INDEX OF SPECIFICATION
Applicable Separate Road
Tender Specification booklet attached
Discription of item as per schedule "B" of the tender.
Item No reference
Item No. Pg No.
1 Providing and laying compacted WBM of Grading-II MCBT metal of size 53 to 22.4 Attached Separetely
mm in required layers including using 24% stone screening 11.2 mm size and 8% stone
dust as filler including spreading watering & consolidation by vibratory roller etc. as
per MoRTH Specification compelete as directed by Engineer - in - Charge.
2 Providing and laying Compacted of Specified quarry Spall in side shoulder including Attached Separetely
carraige of material and spreading on prepared base including compacting as per
Specification etc... complete.
3 Providing and laying Controlled cement concrete M-250 For a concrete pavement made Attached Separetely
by Trimix system and mixed with heavy duty floor hardner at the rate of
Kg./Sq.M. including curing etc. complete over prepared sub base including providing
and fixing centering of MS channels of required thickness as per required level slope,
Grade and thickness of concrete road including leveling of placed concrete with surface
vibrators finishing surface with power floater and trowel light brooming on the surface
including providing construction joint of 10 mm x 25 mm by using concrete cutter
machine etc. complete as directed. The Payment Of this Item Shall be Made on Core
Cutter testing results.
4 Providing and filling in foundation with ordinary Cement concrete M-100 mix and Attached Separetely
providing necessary vertical pin headers including formwork, vibrating, ramming and
curing complete.
5 Providing ISI Mark TMT bar Fe-500D reinforcement for RCC Work including bendinf, Attached Separetely
binding and placing in position complete as per detailed drawinngs for Solid slab,
Abutment cap, dirt wall & Pier cap & Also for the (For Temperature Reinforcement of
Abutment, Return & Pier)
Deputy Executive Engineer Executive Engineer
Panchayat ( R & B) Sub Division Panchayat ( R & B) Division
Waghodia Vadodara
Name Of Work :- Constructing CC Road Waghodiya Faliya to Bhathiji Mandir to Mahadev Mandir at Gutal Village Ta.Waghodia
Dist. Vadodara Under MLA Grant (2025-26)
Taluka :Waghodia District : Vadodara
SCHEDULE FOR TESTING OF MATERIALS
For ensuring quality control and workmanship, various tests prescribed below for materials shall be taken at periodical intervals as stipulated below.
The material should be tested in GERI or Private laboratory approved by Govt. of Gujarat. Bill for testing charges should be paid Govt.
Item No. as Brief Description of materials to be Qty. of Unit Prescription of test which Frequency @ which test shall be Total Nos of
per tested. Materials shall be carried out carried out test to be
Schedule 'B' taken
1 45 to 90 MC.Metal Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
2 40 to 63 M.C.Metal 0.00 Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
1500 to 5000 - cum. 7 test
3 25 to 40 M.C.Metal 52.76 Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
1500 to 5000 - cum. 7 test
4 Kapchi 20 mm Nominal 88.46 Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
1500 to 5000 - cum. 7 test
5 Grit (6 mm) 0.00 Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
1500 to 5000 - cum. 7 test
6 Grit as Key aggregate (12 mm) 0.00 Cum *Gradation test 1 to 100 - cum. 1 test
*Impact Value 100 to 500 - cum. 3 test
*Flakiness Index of 500 to 1500 - cum. 5 test
1500 to 5000 - cum. 7 test
49 Sch B Const. Waghodiya Faliya to Mahadev Mandir road Ta. Waghodia.xls
Item No. as Brief Description of materials to be Qty. of Unit Prescription of test which Frequency @ which test shall be Total Nos of
per tested. Materials shall be carried out carried out test to be
Schedule 'B' taken
7 Supplying of Quarryspall 13.46 Cum *Gradation,CBR One test per work
8 Supplying of Sand/ 39.00 Cum *Silt Content,F.M One test per work
9 Stonedust 3.49 Cum *Gradation One test per work
10 Sel;ected Soil for Embankment 0.00 Cum P.I ,CBR,MDB
11 Rubble 0.00 Cum *Density & Los Angeles abrasion As per IRC:SP:116-2018
11 Natural GSB 0.00 Cum *Gradation,P.I,CBR
12 Asphalt (VG-30) 0.00 M.T. Viscosity Test Tanker test in Geri Lab. Only
as per I.S. 1206 Up to 10
Above 50 one per Tanker
Ductility Test As per I.S.
Specification Gravity test As per I.S.
Softening point test As per I.S.
Quality of binder test 3 test per 2 tankers on plant site.
13 Tack Coat *Binder Temperature for applicationIrregular close in intervals
*Rate of spread of Binder. 2 test per Day.
14 Carpet & Seal Coat. Mix Grading One Test on Individual
Temperature of binder in Boilor Constituents and mixed aggregates from the
aggregates in the dryer and mix dryer for each 100 tonnes of mix subject to
at the time of laying and rolling. minimum of Two tests per plant per day.
( Binder content vide 45/MD. One Test for each 100 tones of mix
2172) subjects to minimum of two per Day.
Rate of Spreaded mix materials. Regular control through checks on layer
15 Cement (OPC) 31.400 M.T. *Consistency,Soundness 1 test @ 50.0 M.T. 100 T 2 tests,
*Setting time,Finessness Test 200 T 3 tests, 300 T 4 tests, 500 T 5 tests,
49 Sch B Const. Waghodiya Faliya to Mahadev Mandir road Ta. Waghodia.xls
Item No. as Brief Description of materials to be Qty. of Unit Prescription of test which Frequency @ which test shall be Total Nos of
per tested. Materials shall be carried out carried out test to be
Schedule 'B' taken
*Compressive Strength. 800 T 6 tests, 1300 T 7 tests & 8 testd for
large consingment.
16 Steel (TMT) 2.12 M.T. *Tensile, (TMT) As per Manual of Quality Control
Yield 1 test/40 tonnes / per category
17 C.C.Cube Test 1:2:4 *Compressive Strength. 1 to 5 cmt - 1 No
M250 63.60 51 to above - 4 +1 additional sample
for each 50 cu.mt. Or part there of.
18 Retro Reflective Sheeting for the signage 0.00 Nos. as per Test schedule attached GR SOR/1018/715/Part file/C-1 Dtd.4/6/19
19 Road studs / Cat Eyes 0.00 Nos. as per Test schedule attached GR SOR/1018/715/Part file/C-1 Dtd.4/6/19
20 Hot Applied Thermoplast Road Marking 0.00 Sqmt as per Test schedule attached GR SOR/1018/715/Part file/C-1 Dtd.4/6/19
Note (1):- In case of excess in quantity. Further more test shall be carried out as per required frequency.
Note (2):- Apart from above listed materials for carrying out various tests during Road / Structure
Construction Works , if any other than above mentioned material/s are to be used during road /
structure construction work then it must be tested as per prevailing criteria of Govt. of Gujarat (R &
B Deptt.) and necessary tests should be carried out as per prevailing norms.
Signature of Contractor. Deputy Executive Engineer Executive Engineer
Panchayat (R & B) Sub Division Panchayat (R & B) Division
Waghodia Vadodara
49 Sch B Const. Waghodiya Faliya to Mahadev Mandir road Ta. Waghodia.xls
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
6. GR_to_be_attached_with_DTP_SBD_with_Index.pdf
49.1 SBD Const. Waghodia Faliya to Mahadev Mandir Road Ta. Waghodia.pdf
49.3.Speci. Const. Waghodia Faliya to Mahadev Mandir Road Ta. Waghodia.pdf
BOQ Notes - Index - Test Sch..pdf
BOQ.pdf
Drawing.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .