Tender Value
₹4.1 L
EMD Value
₹8,140
Closing Date
16 Apr 2020, 1:00 pmClosed
Executive Engineer
Executive Engineer Gohana W/S Division Gohana
Dismantling of old bridges at RD 49792, 58800, 79100 of Butana Branch and repair of lining
2020_HRY_125561_9
3519/15A dt 20/03/2020
Open Tender
Civil Works - Canal
Works
75 days
GOHANA W.S Division Gohana
Please refer Tender documents.
3 documents required · 3 mandatory
₹500
Executive Engineer Gohana W.S. Divn. Gohana
₹8,140
Yes
6 Jun 2022
3 Apr 2020
16 Apr 2020
4 Apr 2020
16 Apr 2020
4 Apr 2020
Amount
Dismantling of RCC 1:2:4 with cleaning and straightening and cutting of bars if required. HSR item no. 8.6 (e) @ 108.05+550% ZP = 702.33/cum
Dismantling of Brick work 1:3 in cement. Motor HSR item no. 8.5 (b) @ 35.60+550% ZP = 231.40/cum
Earth work excavation in ordinary soil with lead up to 15 mtr. for slippers HSR item no. 6.2 (b) @ 586.60+425% ZP = 3079.65/100 cum
Laying CC 1:2:4 with stone agg. 20 mm nominal size for slippers (same as earthwork) HSR item no.10.64 @ 580.29+450% ZP =3191.60
Laying design mix C.C M-15, 15 cm. thick lining in bed as per PWD H.S.R.10.64=580.2+450 % @3191.60x0.15 = 478.24/sqm
Laying CC 1:2:4 side lining Laying design mix C.C M-15, HSR 10.64 15 cm. Thick side lining asper PWD specification @3191.60X0.15+478.24/sqm
Laying CC 1:2:4 with stone agg. 20 mm nominal size for coping. HSR item no. 10.41 @ 615.60 + 450% ZP = 3385.8/cum
1st class brick work laid in cement sand mortar 1:3 for coping HSR item no. 11.5 @ 461.40 + 650% ZP = 3460.50/cum
Cement pointing deep variety on brick C.M. 1:2 HSR item no. 15.60 @ 9.90 + 500% ZP = 59.40/sqm
Extra allowance for scaffolding in concrete lining HSR item no. 19.16 @ 1.58 + 450% ZP = 8.69/sqm
Dressing bed & preparation of sub grade for lining HSR item no. 19.1 @ 0.65+550% ZP = 4.23/sqm
Dressing side slope & preparation of Sub grade for lining HSR item no. 19.2 @ 0.97 + 550% ZP = 6.30/sqm
Putting cement (side slope ) send slurry 6 mm thick on prepared bed and side slope in C.M. 1:3 HSR item no. 19.12 @ 5.10 + 450% ZP = 28.05/sqm
Earth work excavation in ordinary soil exclusive undressed with a combined lead and overall lead upto 60 mtr on both bank HSR item No. 6.2 B,C (i) @ 586.60+22.65x6+425% ZP = 3793.12/100 cum
Credit of dismantled brick masanary
Credit/scrap of old steel bar
HARINDER PHOGAT
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .