Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹99.5 LAccepted-AOC CHETTIYADA KANNADY PO PULINCUNNOO ALAPPUZHA | ₹99.5 L | L1 | Accepted-AOC L1 bidder |
| 2 | L2₹1.1 Cr+₹5.8 L (5.86%)Rejected-AOC | ₹1.1 Cr+₹5.8 L (5.86%) | L2 | Rejected-AOC L2 bidder |
| 3 | L3₹1.1 Cr+₹12.4 L (12.4%)Rejected-AOC | ₹1.1 Cr+₹12.4 L (12.4%) | L3 | Rejected-AOC L3 bidder |
Tender Value
₹1.3 Cr
EMD Value
₹50,000
Closing Date
15 Jun 2023, 6:00 pmClosed
SUPERINTENDING ENGINEER
SUPERINTENDING ENGINEER KD Circle Chengannur
GENERAL Padinjare 40 Thazhathu 40-KPMitigation of flood in Padasekharam of Kuttanadu Taluk Mitigation of flood in Padinjare 40 Thazhathu 40 Padasekharam of Ramankary Panchayath in Kuttanadu LA Constituency General Civil Work
2023_Irrig_580752_1
IRR/KP/TR/7549/2022_5_1_1/2
Open Tender
Civil Works - Others
Item Rate
545 days
Ramankary Alappuzha
Please refer Tender documents.
12 documents required · 12 mandatory
₹6,508
Yes
₹50,000
Yes
24 Aug 2023
8 Jun 2023
20 Jun 2023
8 Jun 2023
15 Jun 2023
8 Jun 2023
8 Jun 2023 - 15 Jun 2023
Amount
Appendix A Protection work and bund formation
OD20200/2022-2023:Earth work in excavation in or under water by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30cm in depth ,1.5 m in width as well as 10 sqm on plan)including disposal of excavated earth ,lead upto 50m and lift upto 1.5m, disposed earth to be leveled and neatly dressed .All kinds of soil. Certificate:- Certified that the observed data is prepared by taking the rate and labour charges as per schedule of rates and has been prepared as per the actual observation at site.
60.7.2:DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
60.7.3:DISMANTLING DR - Dismanling , clearing away and carefully stacking materials useful for reuse for any thickness of walls in DR masonry including disposal of debris within a distance of 150m.
60.7.8:DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site
60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
OD20201/2022-2023:Earth work in rough excavation, banking excavated earth in layers not exceeding 20 cm in depth, breaking clods, watering, rolling each layer with 1/2 tonne roller or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up in embankments for roads, flood banks, marginal banks and guide banks or filling up ground depressions, lead up to 50 m and lift up to 1.5 m:All kinds of soil
Appendix B - Constructing Motor thara Petti mukhom
OD23601/2022-2023:Putting up ring bund to a top width of 1.5m and average height of 2m with 1/4 :1 side slope and protect the side with 1/2 split coconut post of 3.5 m long driving down 1.5m below bed level at 60cm c/c. Providing 2 rows of wailing pieces with 1/4 split coconut posts on bothsides and 1/4 split cross ties to alternate post and screening the sides of bund with polythene sheets fixed properly using coconut post and wailing pieces using reaper and nails in full height including tying properly using iron wire and coir altogether and supply brush wood bundle 10kg each and filling inside with hard clay/cut earth upto 2m.
60.2.2:Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
60.64.1:Coconut Pile - Supplying and stacking well matured straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete.
OD30084/2022-2023:Driving down coconut pile to lines and levels through various strata including all hire charges and labour for fixing, staging platform and all other appliances necessary for pile driving down after pointing the bottom end where no accessibility to hydraulic excavator through land and water bodies having minimum width greater than 10 metre.
OD22051/2022-2023:Filling with sand Supplying and filling sand in foundation trenches of culvert for stabilizing the top clay layer including watering, ramming, consolidating and dressing etc complete for improving bearing capacity of soil.
60.7.2:DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.9.2:Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
4.1.6:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
OD3322/2023-2024:Filling with quarry muck Filling up low lying and water logged areas with quarry muck ,spreading in layers ,leveling the top at site and consolidation by ramming etc.complete for improving the CBR value of subgrade
Joseph Thomas
Sheffin.K.Francis
Bidder Name
Sheffin.K.Francis
Joseph Thomas
JOSHY VARGHESE
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_857590.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .