Executive Engineer, Panchayat (R&B) Division SURENDRANAGAR
ConstructionofBoxCulvert (15No.X1.5X1.5)on Sapar-Ratanpar-MorsalRoad(V.R.),Km. 4/8-5/0, Ta:Sayla, Dist:Surendranagar (SOR Year:2015-16)
351899
13/2026-27 Sr. no. 12 Remaining works
Open
Civil - All
Works
Surendranagar
6 documents required · 6 mandatory
₹1,500
Executive Engineer,R&B Panchayat Divison, Surendranagar
₹46,920
5 Oct 2026
5 Oct 2026
5 Oct 2026
19 Oct 2026
5 Oct 2026
Name of work :- Construction of Box Culvert (15 No. X 1.5 X 1.5) on Sapar - Ratanpar- Morsal Road
(V.R.),Km. 4/8 -5/0,Ta:Sayla, Dist:Surendranagar (SOR 2015-16)
Item Quantity Item of Work Tendered Rate in Total Amount
Item Quantity Item of Work Tendered Rate in Total Amount
No. Estimated but Figure Words according to
may be more or Estimated
1 25.00 cum Dismentaling the existing247.45 Rs two hundred forty
structure including removing and seven and paise forty
stacking the dismentelled five only
materials as and where directed.
(B) Rubble Masonry
2 21.00 cum Dismentaling the existing 562.57 Rs five hundred sixty
structure including removing and two and paise fifty
stacking the dismentelled seven only
materials as and where directed.
(A) R.C.C. work
3 787.00 cum Excavation for foundation in sand, 309.06 Rs three hundred nine
gravel, clay soft soils and murrum and paise six only
etc. including shoring, strutting
dewatering as necessary and
disposing of the excavated stuff
as directed.(A) Depth upto 3.0 M.
and lead upto 100m for 10 Cum
4 234.00 cum Excavation for foundation upto 270.68 Rs two hundred
1.5 m depth including sorting seventy and paise
out and stacking of useful sixty eight only
materials and disposing off the
excavated stuff upto 50 Meter
lead.(D) Soft rock not requiring
5 42.30 cum Providing and laying rubble for 727.20 Rs seven hundred
appron (each stone weighting not twenty seven and
less than 40Kg.) including and paise twenty only
packing and filing in the
interestices with quarry-spalls.
6 135.00 cum Providing and filling in foundation 2252.30 Rs two thousand two
with ordinary Cement concrete M- hundred fifty two and
100 mix and providing necessary paise thirty only
vertical pin headers including
formwork, vibrating, ramming and
curing complete.
Item Quantity Item of Work Tendered Rate in Total Amount
Item Quantity Item of Work Tendered Rate in Total Amount
No. Estimated but Figure Words according to
may be more or Estimated
7 195.00 cum Providing & casting in situ ordinary 2604.69 Rs two thousand six
cement concrete M-150 mix and hundred four and
providing necessary pin headers paise sixty nine only
including shuttering, scaffolding,
laying, vibrating, curing and
finishing complete without V-
Groves.(A) Height from 0.0 M. to
8 141.40 cum Providing and Casting in situ 3821.64 Rs three thousand
controlled Cement Concrete M- eight hundred twenty
200 for R.C.C. Raft and cutt-off one and paise sixty
walls including necessary four only
shuttering laying, vibrating,
ramming and curing complete.
9 252.40 cum Providing and casting in situ 4113.53 Rs four thousand one
controlled cement concrete M- hundred thirteen and
200 for R.C.C. return as per paise fifty three only
drawings including centering
shuttering, scaffolding where
necessary, laying vibrating, curing
and finishing complete.(A) Height
from 0.0 to 5.0 M. (1) Piers (2)
Abutment (3) RCC return
10 90.60 cum Providing and casting in situ 4289.27 Rs four thousand two
ordinary Cement concrete M-200 hundred eighty nine
for R.C.C. solid slab including and paise twenty
centering, scaffolding curing seven only
and finishing complete.
11 21.80 MT Providing and laying in position FE 43951.64 Rs forty three
415 TMT bar reinforcement thousand nine
including cutting, bending, hundred fifty one and
hooking and tying complete as per paise sixty four only
detailed drawings for the all the
12 27.40 cum Providing and casting in situ 3525.71 Rs three thousand five
controlled cement concrete hundred twenty five
concrete M-200 for approach and paise seventy one
slab including formwork curing only
and finishing complete.
Item Quantity Item of Work Tendered Rate in Total Amount
Item Quantity Item of Work Tendered Rate in Total Amount
No. Estimated but Figure Words according to
may be more or Estimated
13 0.30 cum Providing and casting in situ 3627.72 Rs three thousand six
ordinary cement concrete M-200 hundred twenty seven
forKerbs/Kerb blocks including and paise seventy two
formwork, curing and finishing only
14 6.60 sqm Providing Pre-moulded asphalt 735.28 Rs seven hundred
filler joints as per drawings.(A) thirty five and paise
12mm twenty eight only
15 173.00 sqm Providing and laying - Fitter Media 463.59 Rs four hundred sixty
600mm thick directed at the back three and paise fifty
of abutments, returns and wing nine only
walls as per detailed
specifications.
16 173.00 nos Providing & laying weep hole in 33.94 Rs thirty three and
Aburtments, and returns by using paise ninty four only
A.C. pipe of 100mm including
laying in proper grede and jointing
the completed as per detailed
17 60.00 rmt Providing temporary all weather 481.58 Rs four hundred eighty
and fair weather diversion one and paise fifty
suitable for traffic during the eight only
construction period of the Bridge
including porviding necessary
drains and all sagty measures
18 12.00 nos Providing and fixing precast 379.49 Rs three hundred
cement concrete guard stone as seventy nine and
per I.R.C. type design including paise forty nine only
white washing etc. complete.(i)
Fixing in Earth
19 440.00 cum Earthwork for embankment 152.51 Rs one hundred fifty
including breaking clods, dressing two and paise fifty one
with all lead and lift (excluding only
watering and consolidation)(B)
From Borrow area within
20 375.00 cum Rolling and watering of earthwork 21.11 Rs twenty one and
in layers with vibratory roller paise eleven only
including filling in depressions
which occur during the process.
Item Quantity Item of Work Tendered Rate in Total Amount
Item Quantity Item of Work Tendered Rate in Total Amount
No. Estimated but Figure Words according to
may be more or Estimated
21 45.00 cum Supplying & stacking of 40 to 63 664.08 Rs six hundred sixty
mm size machine crushed stone four and paise eight
aggregate on site of work as per only
sepcification and filling the
measure boxes of standard size
etc. complete with all lead.
22 10.00 cum Supplying & stacking of 6mm to 610.60 Rs six hundred ten
10 mm size machine crushed Key and paise sixty only
aggregate on site of work as per
sepcification and filling the
measure boxes of standard size
etc. complete with all lead.
23 5.00 cum Supplying and stacking of stone 446.02 Rs four hundred forty
dust on road site including filling six and paise two only
the measure boxes with all lead.
24 55.00 cum Spreading the stone aggregate for 158.57 Rs one hundred fifty
rolling and W.B.M. including filling eight and paise fifty
the interstices to required camber seven only
and gradient (excluding spreading
of Blindage) (ii) 40mm to 63mm
size aggreagates
25 5.00 cum Spreading blindage or road crust 93.63 Rs ninty three and
filling the gaps in metal and paise sixty three only
leveling to camber and gradient as
directed. (A) Murrum / Stone Dust
26 55.00 cum Rolling and consolidation using 75.75 Rs seventy five and
vibratory road roller 8 - 10 tonne paise seventy five only
capacity (C) Water bound
Macadam (Layer not exceeding
100mm thickness)
27 30.00 cum Providing and laying cement 2006.87 Rs two thousand six
concrete 1:4:8 (1- Cement : 4- and paise eighty seven
coarse sand : 8- hand broken only
stone aggregates 40 mm nominal
size) and curing complete
excluding cost of formwork in (A)
Foundation and Plinth
Item Quantity Item of Work Tendered Rate in Total Amount
Item Quantity Item of Work Tendered Rate in Total Amount
No. Estimated but Figure Words according to
may be more or Estimated
28 60.00 cum Providing and casting in situ 3187.36 Rs three thousand one
Ordinary cement concrete M-200 hundred eighty seven
for average 100mm thick wearing and paise thirty six
coat laid as directed including only
tamping, vibrating,finishing, curing
and filling in joints with bitumen
Credit dismantle
Rupees : Forty Six Lacs Ninty one Thousand Sevnety Eight and Paise Forty one Only
I/We___________________am/are willing to carry out the above work at
____% above / below ______ % ( should be written in figures and words ) of the
estimated rate mentioned above amount of my / our tender works as under :
Estimated amount put to tender Estimated amount put to tender
Add____________ % above Deduct _____________ % below
Total amount Rs._______________ Total amount Rs._______________
Total amount Rs._______________ Total amount Rs._______________
Note All work shall be carried out as per Public works Department Handbook and other specifications of
Division or as directed
Dismantle credit amount of Rs. 1726.00 will be deducted from the 1 st RA Bill of This
Executive Engineer Signature of the Bidder
Panchayat R. & B. Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
B-1 DTP box culvert on sapar - ratanpar - morsal.pdf
BOQ.pdf
Dtp box culvert on sapar - ratanpar - morsal q.pdf
sapar-ratanpar-morsal boxculvert drawing (1).pdf
test sch.pdf
nivida 13.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .