Tender Value
₹98,000
EMD Value
₹1,960
Closing Date
9 Oct 2026, 6:00 pm
Executive Enginner
Office Of The Executive Engineer REW Samba
Refer as per BOQ
2026_RDPR_326384_16
137 REW Samba of 2026-27, Date 28.09.2026
Open Tender
Civil Works
Percentage
30 days
Ghagwal
Please refer Tender documents.
3 documents required · 3 mandatory
₹600
Executive Engineer REW samba
₹1,960
29 Sept 2026
29 Sept 2026
10 Oct 2026
29 Sept 2026
9 Oct 2026
29 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: All kind of soil | 1.13 | Cum | 479.3 | ₹541.61 |
| 2 | P/L in position Cement conc. 1 cement:5fine sand:10graded crushed stone agg. 40 mm excluding the cost of centring & shuttering all work upto plinth level. | 4.09 | Cum | 4,826.5 | ₹19,740.39 |
| 3 | P/L in position Cement conc. 1 cement:3fine sand:6graded crushed stone agg. 20 mm excluding the cost of centring & shuttering all work upto plinth level. | 2.62 | Cum | 5,733.6 | ₹15,022.03 |
| 4 | Supply of stone | 1.16 | Cum | 700 | ₹812 |
| 5 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15°, landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases upto five level including curing but excluding the cost of centring, shuttering, finishing and reinforcement with 1:1.5:3 | 0.32 | cum | 7,788.4 | ₹2,492.29 |
| 6 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level using TMT Bars | 22.14 | kg | 123.2 | ₹2,727.65 |
| 7 | Centring and shuttering incl strutting, propping,and removal of same for foundation and footings | 13.01 | sqm | 286.35 | ₹3,725.41 |
| 8 | Suspended floor | 0.84 | sqm | 718.2 | ₹603.29 |
| 9 | Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 meter lead as per direction of Engineer-in-Charge | 60.41 | sqm | 93.4 | ₹5,642.29 |
| 10 | Laying old cement concrete interlocking paver blocks of any design/ shape laid in required line, level, curvature, colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the jointswith fine sand etc. all complete as per the direction of Engineer-in- charge. | 48.33 | sqm | 280.95 | ₹13,578.31 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.94 MB
BOQ_1103934.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .