Loading…
Loading…
Tender Value
₹83,800
EMD Value
₹1,674
Closing Date
25 Aug 2026, 6:00 pmDue tomorrow
DFO Demarcation Forest Division Kashmir, Srinagar
Office of the Divisional Forest Officer Demarcation Forest Division Kashmir, Sheikh Bagh, Srinagar, Kashmir, Jammu and Kashmir
Construction of 13 No. Demarcation Boundary Pillars as per approved design along the forest Demarcation line (Main Line /Chak Line BP.s) as per the map in Forest Gujernad-Paranpelan Uri Range Forest of J.V Forest Division Baramulla.
2026_FD_318771_5
e-NIT NO 01 OF 2026-27 DATED 30-07-2026
Open Tender
Civil Works
Percentage
20 days
Gujernad-Paranpelan, Uri Range, JV Forest Division
Please refer Tender documents.
2 documents required · 2 mandatory
₹700
Centralized Pooling Account No. 0110010200001102
₹1,674
20 Aug 2026
20 Aug 2026
26 Aug 2026
20 Aug 2026
25 Aug 2026
20 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | E/W in excavation in foundation trenches or drains (not exceeding 1.5 mts in width as well as 10 sqmts on plan) including dressing of sides & ramming of bottoms, lift up to 1.5mts & lead of 50 mts including getting out the excavated soil and disposal of surplus excavated soil as directed. | 4.48 | Cum | 479.3 | ₹2,147.26 |
| 2 | Providing & laying dry stone solling including ramming, dressing etc complete in foundations and under floors,including carriage & head load | 0.34 | Cum | 1,000 | ₹340 |
| 3 | Reinforced cement concrete work in walls (any thickness ) including attached pilasters,buttresses,plinth and string courses,fillets,columns,pillars,piers,abutments,posts and struts upto floor five level , in 1:1.5:3 upto five level including curing but excluding the cost of centring, shuttering,finishing and reinforcement. | 2.2 | Cum | 9,395.7 | ₹20,670.54 |
| 4 | Providing & laying cement concrete 1:3:6 mix using 1 cement : 3 coarse sand : 6 graded stone aggregate 20 nominal size of specificied grade excl cost of centering and shuttering. All works up to plinth Level. | 2.76 | Cum | 5,733.6 | ₹15,824.74 |
| 5 | Reinforcement for RCC work incl. Straightening , bending and placing in position and binding all complete (TMT bars) including all carraiges | 195.42 | KG | 123.2 | ₹24,075.74 |
| 6 | Centering and shuttering including strutting, propping etc and removal of form work for in colums, pillars ,abettments, postsand struts. | 31.44 | SM | 286.35 | ₹9,002.84 |
| 7 | Finishing walls with textured exterior paint of required shade on new work (two or more coats applied @3.28 litre/10sqm over and including base coat of water proofing cement paint @2.20 kg/10sqm .including making of Prescribed Departmental LOGO on all Boundary Pillars with writing of Geo-locations (Exterior finishing) | 15.42 | SM | 268.45 | ₹4,139.5 |
| 8Carriage of material by Mechanical Transport from Source upto dumping site of work | |||||
| 8.1 | Sand average lead 30kmts | 2.23 | Cum | 553.59 | ₹1,234.51 |
| 8.2 | Bajri average lead 30kmts | 4.46 | CuM | 553.59 | ₹2,469.01 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.16 MB
BOQ_1075141.xls
BOQ • 0.30 MB
Demarcation_NIT-01_Extension_2nd.pdf
PDF • 0.62 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].