Exeuctive Engineer, Panchayat, R. & B. Division, Patan
ANNUAL RATES FOR MAINTENANCE AND REPAIRS (ROAD WORK) TA-SAMI, HARIJ & SAN KHESWAR, UNDER JURISDICTION OF R & B (PANCHAYAT) SUB DIVISION SAMI (RE-TENDER)
315424
06/202627
Open
Civil Works - Roads
Patan
5 documents required · 5 mandatory
₹1,500
Executive Engineer, Road &Building (Panchayat) Division, Patan
₹1 L
19 Jun 2026
19 Jun 2026
19 Jun 2026
4 Jul 2026
19 Jun 2026
Name of work : Annual Rates for Maintenance and repairs (Road work) Ta- Sami, Harij & Sankheswar, under jurisdiction of R & B (Panchayat)
Sub Division Sami.
Memorandum showing items works to be carried out :
Items Quantities item of work Tendered Rates Unit Total amount
Items Quantities item of work Tendered Rates Unit Total amount
No. estimated In Figure 8[g0ZDF\ NXF¶J[, NZ
In words according to
Qty Rs. Ps estimated quantities
2 more 3 4 5 6 In 7Rs.
1 Earthwork for embankment including breaking clods,
dressing with all lead and lift (excluding watering and
consolidation)(S.O.R P.No 187 Code No 26001)
A 1.00 Cu.M. (A)From Borrow pits within land width (S.O.R P.No 187 114.44 Rupees One Hundred Cu.M.
Code No 26001A Sr.No 1) Fourteen And Paise
B 1.00 Cu.M. (B)From Borrow area within 0.5 Km.lead (upto 10 162.25 Rupees One Hundred Cu.M.
ton)(S.O.R P.No 187 Code No 26001BA Sr.No 2) Sixty Two And Paise
Twenty Five Only
C 1.00 Cu.M. (C)From Borrow area within 1.0 Km.lead (upto 10 ton) 165.43 Rupees One Hundred Cu.M.
(S.O.R P.No 187 Code No 26001CA Sr.No 3) Sixty Five And Paise
Forty Three Only
D 1.00 Cu.M. (D)From Borrow area within 2.0 Km. lead (upto 10 171.49 Rupees One Hundred Cu.M.
ton)(S.O.R P.No 187 Code No 26001DA Sr.No 4) Seventy One And Paise
Forty Nine Only
E 1.00 Cu.M. (E)From Borrow area within 3.0 Km. lead (upto 10 177.34 Rupees One Hundred Cu.M.
ton)(S.O.R P.No 187 Code No 26001EA Sr.No 5) Seventy Seven And Paise
Thirty Four Only
2 1.00 Cu.M. Earthwork in cuting in all sorts of soil and soft murrum 140.87 Rupees One Hundred Cu.M.
including conveying and spreading the stuff, embankment Forty And Paise Eighty
as and where directed within 200meters from the end of Seven Only
the cutting with all required lead and lift.(S.O.R P.No
It.Code No. 26005, Sr.No 13)
3 Pinting and lettering with enamel paint 3- coats etc
complete.(i) Ordinary K.M. Stone for N.H. S.H. and M.D.R.
A 1.00 No (i) Ordinary K.M. Stone for N.H. S.H. and M.D.R. (S.O.R 205.29 Rupees Two Hundred Each
P.No 196,It Cd.26058A, Sr.No 99) Five And Paise Twenty
B 1.00 No (ii) Ordinary K.M. Stone for O.D.R. and V.R. (S.O.R P.No 158.37 Rupees One Hundred Each
196,It Cd No.26058B, Sr.No 100) Fifty Eight And Paise
Thirty Seven Only
C 1.00 No (iii) Fifth K.M. Stone .(S.O.R P.No 196, It Cd. 26058C,Sr.No 392.99 Rupees Three Hundred Each
101) Ninety Two And Paise
Ninety Nine Only
D 1.00 No (iv) Hectometer stone.(S.O.R P.No 196, It Cd No.26058D 52.79 Rupees Fifty Two And Each
Sr.No 102) Paise Seventy Nine Only
E 1.00 No (v) Road sign board. (S.O.R P.No 196,It Cd No.26058E 469.25 Rupees Four Hundred Each
Sr.No 103) Sixty Nine And Paise
Twenty Five Only
F 1.00 No (vi) Village name board.(S.O.R P.No 196, It Cd NO.26058F 469.25 Rupees Four Hundred Each
Sr.No 104) Sixty Nine And Paise
Twenty Five Only
G 1.00 No (vii)Junction board.(S.O.R P.No 196, It Cd No.26058G, 1466.40 Rupees One Thousand Each
Sr.No 105) Four Hundred Sixty Six
And Paise Forty Only
4 Charges for Clearing Road site by removing by ganda Rupees Nil
baval akadas, bordies etc. upto 1.5 mt On Both sides from
edge of B.T. surface including serooting by Excavator
machine &throwing away all stuff branches etc. with all
lead and lift with all material,labour etc.comp.as directed.
4.1 1.00 Km dense forest BY MECHANICAL MEANS (R.A. ) 13955.76 Rupees Thirteen Km
Thousand Nine Hundred
Fifty Five And Paise
4.2 1.00 Km Scattered Forest MECHANICAL MEANS(R.A.) 11381.99 Rupees Eleven Km
Hundred Eighty One
4.3 1.00 Km dense forest By manual means (R.A. ) 47076.59 Rupees Forty Seven Km
Thousand Seventy Six
And Paise Fifty Nine
4.4 1.00 Km Scattered Forest By manual means (R.A. ) 35307.27 Rupees Thirty Five Km
Hundred Seven And
5 1.00 No Geru/Chuna of road side trees including 30 cm wide patta 44.14 Rupees Forty Four And No
of 3 coats of white bwashing at top & 90 cm wide patta of Paise Fourteen Only
3 coats of sona geru at bottom using saresh including
cleaning the surface etc as directed (R.A)
6 1.00 Hrs Engaging earth Excavator incl. cleaning sites for hire 860.64 Rupees Eight Hundred Hrs
charges of excavator incl diesel,1 labour and 1drivers etc Sixty And Paise Sixty
complete as directed.(Hydraulic Excavator 1 cum bucket Four Only
capacity @ 60 cum per hour)(RA)
7 Supplying and fixing reinforced concrete heavy duty non-
pressure pipes with collars for culverts carrying heavy
traffic as per IS 458-1991 specifications including setting
the pipes in C.M. 1:2 watering and laying (to level or
slopes) of class NP3 of following internal daimeters
1.00 Rmt (i) 300mm dia. (upto 10 ton)(S.O.R P No.238 It Cd.26131) 1095.18 Rupees One Thousand Rmt
Ninety Five And Paise
1.00 Rmt (ii) 450mm dia. (upto 10 ton)(S.O.R P No 238 It Cd 26132) 1462.01 Rupees One Thousand Rmt
Four Hundred Sixty Two
And Paise One Only
1.00 Rmt (iii) 600mm dia. (upto 10 ton)(S.O.R P No 238 It Cd 2108.86 Rupees Two Thousand Rmt
26134) One Hundred Eight And
Paise Eighty Six Only
1.00 Rmt (v) 900mm dia. (upto 10 ton)(S.O.R P No 238 It Cd 26135) 3271.56 Rupees Three Thousand Rmt
Two Hundred Seventy
One And Paise Fifty Six
1.00 Rmt (vii) 1200mm dia. (upto 10 ton)(S.O.R P No238 It Cd 5516.63 Rupees Five Thousand Rmt
26137) Five Hundred Sixteen
And Paise Sixty Three
8 1.00 Supplying and Stacking of quarry spall of hard stone free 1243.02 Rupees One Thousand Cu.M.
Cu.M. of dis integrated Pieces, deleterious and organic matter Two Hundred Forty
including royalties & filling measure boxes with all lead Three And Paise Two
and lift etc completed for road work (R.A.) Only
9 1.00 Supplying and stacking of machine crushed stone coarse 1384.47 Rupees One Thousand Cu.M.
Cu.M. aggregate chippings etc of hard stone of size 40mm to Three Hundred Eighty
63mm size free of disintegrated pieces,deleterious and Four And Paise Forty
orgenic matter including royalties & filling measure boxes Seven Only
with all lead and lift etc. completed for road work (R.A)
10 1.00 Supplying and stacking of hard morrum/sand/yellow 289.87 Rupees Two Hundred Cu.M.
Cu.M. earth/ binding materialapproved quality on road site Eighty Nine And Paise
including royalties & filling measure boxes with all lead Eighty Seven Only
and lift etc. road work (R.A)
11 1.00 Spreading the stone aggregate for solling & W.B.M. 274.73 Rupees Two Hundred Cu.M.
Cu.M. including filling the interstices forming the road surface Seventy Four And Paise
to required camber & Gradient (i) 45mm to 63mm size Seventy Three Only
M.C. aggregete (S.O.R. P.No 191 It Cd.26018A)
12 1.00 Spreading the binding material on road crust filling the 162.22 Rupees One Hundred Cu.M.
Cu.M. gaps in metal and leveling to camber and gradient as Sixty Two And Paise
directed.(S.O.R. P.No 191 It Cd.26020A) Twenty Two Only
13 1.00 Smt Providing and fixing pre-cast Rubber Dye / steel Dye inter 700.74 Rupees Seven Hundred Smt
locking concrete block 60mm thick with grade of concrete And Paise Seventy Four
M300 pnumatic compressed / vibrated mechanically and Only
as per approved design Confirming to IS 15658 :
including 35 mm Sand layer for levelling and filling the
joint with sand in proper line and level as per guidlines of
IRC : SP 63-2018 etc. Complete.(S.O.R P.No.135 It Cd
14 1.00 Providing and laying 23cm thick rubble stone pitching on 780.40 Rupees Seven Hundred smt
Sq.M. side slope on existing earthwork as per detailed drawing Eighty And Paise Forty
with pointing in CM 1:3 on rubble pitching and providing Only
coarse sand bedding 10 thick as filter media cm etc
15 1.00 Smt Rolling and consolidation of soling including filling in 22.75 Rupees Twenty Two Sq.M.
depression which occur during the process, with power And Paise Seventy Five
roler 8 tonne to 12 tonne.(S.O.R. P.No 191 It Cd.26021) Only
16 1.00 No 3787.50 Rupees Three Thousand Nos
Flood gauge sign Providing and fixing sign board made
Seven Hundred Eighty
out of 4mm aluminium composite sheet size200x43 cms
Seven And Paise Fifty
rectangle as per design of IRC -67-2012 3.1 mtr long
stand posted frame fabricated from suitable size iron
angle ,coated with one coat of epoxy primer and two coat
of best quality epoxy paint ,refectories with retro
reflective engineering grade sheeting as per latetest
M.O.S.T specification the fixing at site shall be in 1:2:4 cc
block of size 45x45x60 cms including excavation ,curing
etc.comp.B-high intensity grade sheeting(MR)
17 1.00 Cu.M. Excavation for foundation upto 1.5 m depth 128.79 Rupees One Hundred Cu.
including sorting out and stacking of useful Twenty Eight And Paise M.
Seventy Nine Only
materials and disposing off the excavated stuff
upto 50 Meter lead.(A) Loose or soft soil
( A ) Loose or soft soil.
18 1.00 Cu.M. Providing and laying cement concrete 1:4:8 (1 2749.06 Rupees Two Thousand Cu.
Cement : 4 coarse sand :8 stone aggregates 40 Seven Hundred Forty M.
Nine And Paise Six Only
mm nomial size) and curing complete excluding
cost of form work in (A) Foundation and
19 1.00 Cu.M. Demolition including stacking of serviceable 1133.89 Rupees One Thousand Cu.
materilas and disposal of unserviceable materials One Hundred Thirty M.
Three And Paise Eighty
with all lead and lift. (i) R.C.C. work
Sor Pg No153, It Cd NO.20002
20 1.00 MT Providing and fixing in position Fe 500D TMT for 73656.44 Rupees Seventy Three MT
R.C.C. bored piles as per detailed drawing, Thousand Six Hundred
Fifty Six And Paise Forty
including cutting, bending hooking tying and
welding complete and including forming the cage
and lowering it in position.
(S.O.R. Page no.260, It.No.27043C )
21 1.00 Cu.M. 4093.58 Rupees Four Thousand Cu.
Providing and casting in situ ordinary cement Ninety Three And Paise M.
Fifty Eight Only
concrete M 200 mix and providing necessary pin
headers including shuttering scaffolding, laying,
vibrating and finishing without V grooves
etc.complete. 0.0 to 5.0 mts . (SOR P No 262 It
22 1.00 Hour Hire Charges Tipper Truck/Dumper of minimum 1515.00 Rupees One Thousand Hou
15 ton or more capacity including operator, Fuel, Five Hundred Fifteen r
oil, Grease etc. all such complete. (MR)
23 1.00 Nos Engaing Labours for various Work on road site & 491.87 Rupees Four Hundred Nos
building as per instruction of engineering in Ninety One And Paise
Eighty Seven Only
charge SOR 2023-24 L037)
24 1.00 km Hire Charges Tipper Truck/Dumper of approx 25 54.54 Rupees Fifty Four And km
ton capacity including operator, Fuel, oil, Grease Paise Fifty Four Only
and taking Hot mix material from Batch mix or
hot mix Bitumin plant and spreading the same on
site as directed by Engineer Incharge etc. (R.A.)
25 1.00 MT Spreading the material of It no 14 on site as 223.34 Rupees Two Hundred Cum
directed by Engineer Incharge etc. (R.A.) Twenty Three And Paise t
Thirty Four Only
26 1.00 Hour Clearing of CD works pipe for monsoon treatment
including removing the jungle up to 15 mt on
boths sides U/S & D/S of CD work by JCB machine
providing the gutter on boths side up to 10 mt
opening the pipes by labour & opening the water
way etc complete
A 1.00 Nos 1 Row CD work Cleaning 3254.22 Rupees Three Thousand No
Two Hundred Fifty Four
And Paise Twenty Two
B 1.00 km 2 Row CD work Cleaning 4753.06 Rupees Four Thousand No
Seven Hundred Fifty
Three And Paise Six
C 1.00 MT 3 Row CD work Cleaning 6252.91 Rupees Six Thousand No
Two Hundred Fifty Two
And Paise Ninety One
D 1.00 Nos 4 Row CD work Cleaning 7751.75 Rupees Seven Thousand No
Seven Hundred Fifty
One And Paise Seventy
E 1.00 km 5 Row CD work Cleaning 9251.60 Rupees Nine Thousand No
Two Hundred Fifty One
And Paise Sixty Only
F 1.00 MT 6 Or More Row CD work Cleaning 10750.44 Rupees Ten Thousand No
Seven Hundred Fifty
And Paise Forty Four
27 1.00 km Clearing Of Box Culvert works for monsoon 6619.54 Rupees Six Thousand Cell
treatment including removing the jungle up to 50 Six Hundred Nineteen
And Paise Fifty Four
mt on boths sides U/S & D/S of Box Culvert / by
JCB machine,Removing unncesesarry
soil,grass,Vegitation etc cleaning and disposing
incluidng all labour and machinery etc complete
below box - culvert as per direction and
instruction of engineer incharge.
28 1.00 MT Clearing Of Slab Drain or Major Bridge works for 7497.23 Rupees Seven Thousand Spa
monsoon treatment including removing the Four Hundred Ninety n
Seven And Paise Twenty
jungle up to 50 mt on boths sides U/S & D/S of
Slab Drain by JCB machine,Removing
unncesesarry soil,grass,Vegitation etc cleaning
and disposing incluidng all labour and machinery
etc complete below Slab Drain as per direction
and instruction of engineer incharge.
29 1.00 MT Providing Before/After photography of any type 20.20 Rupees Twenty And No
of work at any site of taluka including Soft copy & Paise Twenty Only
Hard Photo Copy . as per directed by incharge
TOTAL AMOUNT PUT TO TENDER=
TOTAL AMOUNT PUT TO TENDER=
Dy.Executive Engineer
R. & B (P)Sub-Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
04 GR.pdf
01 SBD Mandli CR Road Work.pdf
SPECIFICATION INDEX CR MANDLI.pdf
Valid EMD.pdf
sharto sami.pdf
SCHEDULE-B FOR MANDALI CR RATE ROAD WORK.pdf
Download all tender documents and submit your bid