Loading…
Loading…
Tender Value
₹2.8 L
EMD Value
₹2,838
Closing Date
1 Oct 2026, 6:00 pm4d left
Superintending Engineer, Project Implementation Unit, Health & Family Welfare Department.
Demolition of Sub Center Buildings At Chunel, Sapla, Sanali and, Dadusar Ta:mahudha; At vastana, Ratanpur and Dethli Ta:Matar; At vanoda and Anghadi Ta:Galteshwar; At Kalaji and Telnar, Ta:Kapadvanj; At Apyuji and Kaniyel, Ta:Kathlal; At Saiyat, Sanadara, Khijalpur and, Jeshapura, Ta:Thasra, At Varsola, Devki vansol and Jalia ta:mahemdabad; At Rampu Ta:vaso, At Piplata Ta:Nadiad, At Goblej Ta:Kheda.
341756
2026-27/75/07
Open
Civil Works
Works
Gandhinagar
1 document required · 1 mandatory
₹600
PIU-General Fund A/c 11-114
₹2,838
3 Sept 2026
3 Sept 2026
3 Sept 2026
1 Oct 2026
3 Sept 2026
Main Schedule- B
Name of Work :- Demolition of Sub Center Buildings At Chunel, Sapla, Sanali and ,Dadusar Ta:mahudha;At
vastana,Ratanpur and Dethli Ta:Matar;At vanoda and Anghadi Ta:Galteshwar;At Kalaji and Telnar
,Ta:Kapadvanj;At Apyuji and Kaniyel,Ta:Kathlal; At Saiyat, Sanadara, Khijalpur and, Jeshapura,Ta:Thasra,At
Varsola ,Devki vansol and Jalia ta:mahemdabad;At Rampu Ta:vaso,At Piplata Ta:Nadiad,At Goblej
Facility Village/City Taluka Area in SMT Credit Value Rs.
1 Sub Center Chunel Mahudha 72.00 -17700.00
2 Sub Center Sapla Mahudha 60.95 -32200.00
3 Sub Center Sanali Mahudha 61.00 -32350.00
4 Sub Center Dadusar Mahudha 65.00 -6750.00
5 Sub Center Vastana Matar 62.26 -32750.00
6 Sub Center Ratanpur Matar 130.00 -13300.00
7 Sub Center Dethli Matar 65.00 -6750.00
8 Sub Center Vanoda Galteshwar 49.00 -8150.00
9 Sub Center Anghadi Galteshwar 167.00 -17450.00
10 Sub Center Kalaji Kapadvanj 65.00 -6750.00
11 Sub Center Telnar Kapadvanj 95.00 -9800.00
12 Sub Center Apruji Kathlal 65.00 -6750.00
13 Sub Center Kaniyel Kathlal 65.00 -8900.00
14 Sub Center Saiyat Thasra 85.00 -7250.00
15 Sub Center Sanadra Thasra 65.00 -6750.00
16 Sub Center Khijalpur Thasra 75.00 -8850.00
17 Sub Center Jeshapura Thasra 85.00 -8150.00
18 Sub Center Varsola Mahemdabad 110.00 -12800.00
19 Sub Center Devki Vansol Mahemdabad 85.00 -8700.00
20 Sub Center Jalia Mahemdabad 95.00 -9800.00
21 Sub Center Rampur Vaso 65.00 -6750.00
22 Sub Center Piplata Nadiad 75.00 -8450.00
Facility Village/City Taluka Area in SMT Credit Value Rs.
23 Sub Center Goblej Kheda 65.00 -6750.00
Total Amount -283850.00
Total Amount -283850.00
IN Words Rupees Two Lakh Eighty Three thousand Eight hundred Fifty Only
The Contractor shall exhibit a board with detailed specification and details of work as directed Kq the Engineer-In-Charge for which no
extra payment shall be made
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done
3 GST and Income tax Sa.L will be deducted at a source while making payments of bills
In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R.: PRC-10/2017 Cement
Consumption/16/C Date:11/05/2017 as stated in S.O.R. therefore in R.C.C. items where there is a change as per actual mix design the
cost of difference of cement consumption have been deducted from the rate of original item at the rate of input rate mentioned in all
the tender. Input rate is Rs. 5234 MT.
5 GST extra applicable in case of work based on SOR 2023-24 only.
Dy. Executive Engineer Executive Engineer
Project Implementation Unit Project Implementation Unit
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
20-Special Conditions-27-05-2026.pdf
Demolition Candition.pdf
SBD BOOK.pdf
SCHEDULE-B.pdf
Tender Details-75-07.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .