Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.6 LAccepted-AOC | ₹4.6 L | L1 | Accepted-AOC L1 lowest |
| Sl No | Description | Qty | Unit | ATHITHYA BUILDERS L1 |
|---|---|---|---|---|
| 1.00Construction Work of Toilet | ||||
| 1.00 | 2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | 50 | sqm | 18.35 ₹917.5 Lowest |
| 1.00 | 2.33.1:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 30 cm girth up to and including 60 cm girth | 1 | each | 556 ₹556 Lowest |
| 1.00 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 15.76 | cum | 363.12 ₹5,721.32 Lowest |
| 1.00 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 0.43 | cum | 8,007.87 ₹3,475.42 Lowest |
| 1.00 | 7.2.1:Random rubble masonry with hard stone in superstructure above plinth level and upto floor five level, including leveling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) at window sills, ceiling level and the like.Cement mortar 1:6 (1 cement : 6 coarse sand) | 3.36 | cum | 10,475.86 ₹35,198.89 Lowest |
| 1.01 | 50.6.7.2:Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for super structure above plinth level up to floor two level including all cost of materials, labour charges etc. | 3.08 | cum | 9,121.44 ₹28,103.16 Lowest |
| 1.01 | 50.6.7.1:Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for foundation and basement including all cost of materials, labour charges etc. | 2.02 | cum | 8,230.68 ₹16,593.05 Lowest |
| 1.01 | 50.2.25.1:Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge | 1.32 | cum | 736.27 ₹971.88 Lowest |
| 1.01 | OD287326/2025-2026:Construction of granular sub- base by Providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, Carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with manually prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in- Charge. | 0.88 | cum | 3,256.39 ₹2,865.62 Lowest |
Tender Value
₹4.2 L
EMD Value
₹10,409
Closing Date
15 Jun 2026, 2:30 pmClosed
Executive Engineer
P.H. Division Vatakara
State Plan-State plan - 2023-24- Construction of Toilet -at Kuttiady Raw Water Pump House
2026_KWA_854201_1
EE VTK 01/2026-27
Open Tender
Civil Works - Water Works
Item Rate
60 days
P.H. Division, Vatakara
Please refer Tender documents.
8 documents required · 8 mandatory
₹920
₹10,409
Yes
20 Aug 2026
4 Jun 2026
16 Jun 2026
4 Jun 2026
15 Jun 2026
4 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction Work of Toilet | |||||
| 1.001 | 2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | - | sqm | - | - |
| 1.002 | 2.33.1:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 30 cm girth up to and including 60 cm girth | - | each | - | - |
| 1.003 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | - | cum | - | - |
| 1.004 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 1 | cum | - | - |
| 1.005 | 7.2.1:Random rubble masonry with hard stone in superstructure above plinth level and upto floor five level, including leveling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) at window sills, ceiling level and the like.Cement mortar 1:6 (1 cement : 6 coarse sand) | 1 | cum | - | - |
| 1.006 | 50.6.7.2:Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for super structure above plinth level up to floor two level including all cost of materials, labour charges etc. | 1 | cum | - | - |
| 1.007 | 50.6.7.1:Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for foundation and basement including all cost of materials, labour charges etc. | - | cum | - | - |
| 1.008 | 50.2.25.1:Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge | - | cum | - | - |
| 1.009 | OD287326/2025-2026:Construction of granular sub- base by Providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, Carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with manually prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in- Charge. | 1 | cum | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
KWAGeneralConditionsforeTenderingV5.pdf
PDF • 0.69 MB
Tendernotice_1.pdf
PDF • 0.05 MB
Tendernotice_2.pdf
PDF • 1.85 MB
BOQ_1443697.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].