| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.3 CrAccepted-Finance VILLAGE PATHRA POST BADGO THANA KHORABAR DISTRICT GORAKHPUR UTTAR PRADESH | GORAKHPUR | UTTAR PRADESH | ₹4.3 Cr | L1 | Accepted-Finance As per financial evaluation |
| 2 | L2₹5.1 Cr+₹85.1 L (19.9%)Rejected-Finance KH NO 17 B H U NO 74A KAUSHALPURI COLONY KHARGAPUR GOMTINAGAR LUCKNOW U P | ₹5.1 Cr+₹85.1 L (19.9%) | L2 | Rejected-Finance As per financial evaluation |
| Sl No | Description | Qty | Unit | M/s Narayan Enterprises L2 | M/S AJIT CONSTRUCTION AND ORDER SUPPLIER L1 |
|---|---|---|---|---|---|
| 1.00 | Dismantling of old V.R.B. and proper disposal including all cost of materials,T&P and labours for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. | 477.98 | Cum | 560 ₹2,67,668.8 | 270 ₹1,29,054.6 Lowest |
| 2.00 | Dismantling of old & damaged Reinforced cement concrete slab and its proper disposal including all cost of materials, T&P and labours for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. | 145.97 | Cum | 740 ₹1,08,017.8 | 421 ₹61,453.37 Lowest |
| 3.00 | Earth work in filling for making diversion & maintaining section & dowla u/s & d/s of puliya with all lead & lift including cost of labour and T&P with proper completion of work as directed by Engineer-in-charge and as per I.D. specifications. | 5,575.6 | Cum | 110 ₹6,13,316 | 105 ₹5,85,438 Lowest |
| 4.00 | Earth work in excavation of foundation including digging and refilling the trenches with all lead & lift including cost of labour, T&P for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. | 4,881.93 | Cum | 80 ₹3,90,554.4 | 45 ₹2,19,686.85 Lowest |
| 5.00 | Laying C.C. 1:2:4 M15 in foundation with cement, sonbhadra coarse sand of FM. Not less then 2.50 and dala grit (20 mm to 40 mm.) including all cost of materials,T&P and labours and other accessories required for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. | 158.07 | Cum | 10,900 ₹17,22,963 | 9,050 ₹14,30,533.5 Lowest |
| 6.00 | Laying R.C.C. work in 1:1:2 (M25) sonbhadra coarse sand of FM. Not less then 2.50 and dala grit (4.75mm to 20mm) for abutment,wing wall,Slab, pier cap and parapet including all cost of materials,T&P and labours and other accessories required for proper completion of work as per direction of direction of Engineer in Charge. | 2,853.86 | Cum | 11,500 ₹3,28,19,390 | 9,900 ₹2,82,53,214 Lowest |
| 7.00 | Centering and shuttering for Plain Cement Concrete work including cost of all materials, labour and T&P etc with all leads and lift/down for proper completion of work and as directed by Engineer-in-Charge as per I.D. specifications. | 171.4 | Sqm | 200 ₹34,280 | 110 ₹18,854 Lowest |
| 8.00 | Centering and shuttering for R.C.C. work including cost of all materials, labour and T&P etc with all leads and lift/down for proper completion of work and as directed by Engineer-in-Charge as per I.D. specifications. | 4,562.86 | Sqm | 1,250 ₹57,03,575 | 700 ₹31,94,002 Lowest |
| 9.00 | Providing and laying Steel as Reinforcement (TATA,SAIL or JINDAL) including cost of steel carriage, bending, cutting, placing in position and binding with steel binding wire etc. including cost of all materials, labour and T&P with all leads and lift for proper completion of work as directed by Engineer-in-Charge and as per drawing and I.D. specifications. | 86.12 | MT | 80,000 ₹68,89,600 | 79,000 ₹68,03,480 Lowest |
| 10.00 | Earth work in removing diversion including digging and refilling the trenches with all lead & lift including cost of labour, T&P for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. | 5,016 | Cum | 82 ₹4,11,312 | 35 ₹1,75,560 Lowest |
Tender Value
Refer Docs
EMD Value
₹11.6 L
Closing Date
21 Jul 2026, 2:00 pmClosed
Superintending Engineer, Drainage Circle, Ballia
Superintending Engineer, Drainage Circle, Ballia
Reconstruction of 15 damaged culverts on Pur Rajwaha in Ballia District.
2026_UPIDC_1168611_4
05/SE/2026-27
Open Tender
Civil Works
Item Wise
180 days
Balllia
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,354
₹11.6 L
Yes
31 Aug 2026
15 Jul 2026
21 Jul 2026
15 Jul 2026
21 Jul 2026
15 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling of old V.R.B. and proper disposal including all cost of materials,T&P and labours for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. | 477.98 | Cum | - | - |
| 2 | Dismantling of old & damaged Reinforced cement concrete slab and its proper disposal including all cost of materials, T&P and labours for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. | 145.97 | Cum | - | - |
| 3 | Earth work in filling for making diversion & maintaining section & dowla u/s & d/s of puliya with all lead & lift including cost of labour and T&P with proper completion of work as directed by Engineer-in-charge and as per I.D. specifications. | 5,575.6 | Cum | - | - |
| 4 | Earth work in excavation of foundation including digging and refilling the trenches with all lead & lift including cost of labour, T&P for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. | 4,881.93 | Cum | - | - |
| 5 | Laying C.C. 1:2:4 M15 in foundation with cement, sonbhadra coarse sand of FM. Not less then 2.50 and dala grit (20 mm to 40 mm.) including all cost of materials,T&P and labours and other accessories required for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. | 158.07 | Cum | - | - |
| 6 | Laying R.C.C. work in 1:1:2 (M25) sonbhadra coarse sand of FM. Not less then 2.50 and dala grit (4.75mm to 20mm) for abutment,wing wall,Slab, pier cap and parapet including all cost of materials,T&P and labours and other accessories required for proper completion of work as per direction of direction of Engineer in Charge. | 2,853.86 | Cum | - | - |
| 7 | Centering and shuttering for Plain Cement Concrete work including cost of all materials, labour and T&P etc with all leads and lift/down for proper completion of work and as directed by Engineer-in-Charge as per I.D. specifications. | 171.4 | Sqm | - | - |
| 8 | Centering and shuttering for R.C.C. work including cost of all materials, labour and T&P etc with all leads and lift/down for proper completion of work and as directed by Engineer-in-Charge as per I.D. specifications. | 4,562.86 | Sqm | - | - |
| 9 | Providing and laying Steel as Reinforcement (TATA,SAIL or JINDAL) including cost of steel carriage, bending, cutting, placing in position and binding with steel binding wire etc. including cost of all materials, labour and T&P with all leads and lift for proper completion of work as directed by Engineer-in-Charge and as per drawing and I.D. specifications. | 86.12 | MT | - | - |
| 10 | Earth work in removing diversion including digging and refilling the trenches with all lead & lift including cost of labour, T&P for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. | 5,016 | Cum | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.73 MB
BID04.pdf
Tender Documents • 1.48 MB
BOQ_2192305.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .