| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹78.6 LAccepted-AOC COMPANY RAMPUR | ₹78.6 L | L1 | Accepted-AOC Found L1 |
| 2 | L2₹85.6 LRejected-Finance | ₹85.6 L | L2 | Rejected-Finance Found L2 |
Tender Value
₹95.4 L
EMD Value
₹6.8 L
Closing Date
30 Mar 2026, 12:00 pmClosed
SUPERINTENDING ENGINEER RAMPUR CIRCLE PWD RAMPUR
SUPERINTENDING ENGINEER RAMPUR CIRCLE PWD RAMPUR
Shaikhupura Badhpura NH 74 Road
2026_CEMBD_1125662_6
1597/ETEN_RC/25_26_D_09_03_26
Open Tender
Civil Works - Roads
180 days
RAMPUR
New Construction Under Rajya Sadak Nidhi Scheme With Maintenance cost
2 documents required · 2 mandatory
₹2,354
₹6.8 L
Yes
SUPERINTENDING ENGINEER RAMPUR CIRCLE PWD RAMPUR
18 Apr 2026
23 Mar 2026
30 Mar 2026
23 Mar 2026
30 Mar 2026
23 Mar 2026
27 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 2Providing laying and spreading material on a prepared sub base grade, adding cement @ 2% by weight to the spread material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined Compressive strength and to form a layer of sub-base. Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 3Providing, laying, spreading Material on prepared sub base, cement @ 4% by weight to the spread material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined compressive strengthe and to form a layer of base. Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 4Providing and applying tack coat with VG-10 using bitumen distributor at the rate of 0.30 kg per sqm on the prepared granular surfaces treated with primer/Bituminous surface as per Technical Specification Clause 503. Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 5Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates using VG-10 to required line, grade and level to serve as wearing course on a previously prepared base by manual means, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades as per Technical Specification Clause 508 (By Manual Means) Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 6Providing and laying Type "C" seal coat by manual means with VG-10 sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall as per Technical Specification Clause 510 ( By Manual Means) Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 7Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 8Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3 Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 9Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203(Cement Concrete 1:3:6) Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
| 10Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 (M20 ) Including all T&P, Labour, Material, Royalty Tax but excluding GST | |||||
stage.html
html • 0.04 MB
technical_2098557.pdf
techsummary_2098557.pdf
finance_2098557.pdf
BOQ Comparative Chart
xlsx
finsummary_2098557.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.25 MB
6T2.pdf
Tender Documents • 0.44 MB
BOQ_2098557.xls
BOQ • 0.23 MB
Download all tender documents and submit your bid