| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.8 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹9.8 L+₹94,327.58 (10.7%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹10.9 L+₹2.0 L (23.1%)Rejected-AOC KORATHARA KANNADY P O PULINCUNNOO ALAPPUZHA | PULINCUNNOO | ALAPPUZHA | KERALA | L3 | Rejected-AOC L3 |
Tender Value
₹8.9 L
EMD Value
₹22,307
Closing Date
27 May 2020, 6:00 pmClosed
AEE
Assistant Executive Engineer PWD Roads sub division kanjirappally
SR Construction of DR Protection wallin Elamkulam Thampalakadu 0/250
2020_PWD_357903_1
PWD/2020-2021/13238/KNGPY
Open Tender
Civil Works - Others
Item Rate
90 days
kanjirappally
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,970
online
₹22,307
Yes
18 Jun 2020
20 May 2020
1 Jun 2020
20 May 2020
27 May 2020
20 May 2020
Amount
PROTECTION WORKS
3.13.1.B : Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.<br> Ordinary soil - Mechanical Means - (Depth upto 3 m) <br>Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work. Ordinary soil - Mechanical Means - (Depth upto 3 m)
od29675/2019_2020 : :Plain cement concrete 1:4:8 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
od29676/2019_2020 : Dry rubble masonry for foundation and superstructure.
12.40 : Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical SpecificationsSupply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications
12.8.1.C : Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br> RCC Grade M20 - Using Concrete Mixer - (Without formwork) <br>Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer - (Without formwork)
8.8 : Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfacesPainting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces
12.4 : Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
2.3.2.A : Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness <br> In area of light jungle - By Mechanical Means<br>Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness In area of light jungle - By Mechanical Means
JOY ABRAHAM
THOMAS JOSEPH
Bidder Name
THOMAS JOSEPH
MATHEW
JOY ABRAHAM
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .