Tender Value
₹22.1 L
EMD Value
₹44,238
Closing Date
1 Oct 2026, 3:00 pm3d left
CHIEF ENGINEER
NAGAR NIGAM BAREILLY
Construction of a boundary wall and shed at the cremation ground on Rotha Road in Ward-45.
2026_DOLBU_1184273_1
302/CE/CD/26-27 (1 To 20) Sr No 18 Tender List 30 Date-05.09.2026
Open Tender
Civil Works
Percentage
90 days
BAREILLY
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,596
₹44,238
11 Sept 2026
11 Sept 2026
1 Oct 2026
11 Sept 2026
1 Oct 2026
11 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Dismantling of old damage BOE C.C. tiles Road work i/c stacking of dismantlled materials as directed by E/I.within a distance of 60.00M | 48.02 | CUM | 660 | ₹31,693.2 |
| 1.02 | Excavation in foundation in ordinary Soil (Loam, Clay or sand) including, lift upto 1.50 M and lead Upto 30m and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30.0m from the foundation trencches. excluding royalty.( S.I. No.251) | 92.98 | CUM | 209 | ₹19,432.82 |
| 1.03 | Providing and laying cement concrete in 1:6:12 (1 cement : 6 Fine sand : 12 Brick ballast 40 mm gauge) and curing complete, including cost of form work in foundation and floors-completion of the work as per direction of E/ I. (S.I No. 273) | 15.52 | CUM | 3,705 | ₹57,501.6 |
| 1.04 | RCC 1:2:4 with cement c'sand stone grit of 4 cm gauge in raft foundation and footing xcluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work | 22.42 | CUM | 8,173 | ₹1,83,238.66 |
| 1.05 | RCC 1:1.50:3 with cement c'sand stone grit of 20 mm gauge in Columns excluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work. | 7.11 | CUM | 8,976 | ₹63,819.36 |
| 1.06 | RCC 1:2:4 with cement c'sand stone grit of 20mm gauge in raft foundation and footing xcluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work | 13.34 | CUM | 8,534 | ₹1,13,843.56 |
| 1.07 | Mild steel or Iron for plain work such as reinforced concrete brought to proper shape as necessary including its bending with supply of steel with overlaps & wastage also required for proper completion of the work as per E/I SI No. 504 | 42.06 | QTL | 8,754 | ₹3,68,193.24 |
| 1.08 | First class brick work in 1:4 cement and fine sand of 1.25 FM. Mortar in foundation and plinth including supply of all materials, labour and T&P etc. required for proper completion of the work. | 36.36 | CUM | 5,500 | ₹1,99,980 |
| 1.09 | First class brick work in 1:4 cement and fine sand of 1.25 FM. Mortar in foundation and plinth including supply of all materials, labour and T&P etc. required for proper completion of the work. | 62.52 | CUM | 5,890 | ₹3,68,242.8 |
| 1.1 | 12 mm thick plaster in 1:5 cement & c'sand mortor over brick work minimume thickness not less then 10 mm including all supply of meterial , Labour T&P etc S.I.No. 584(i) | 606.06 | SQM | 217 | ₹1,31,515.02 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 16.68 MB
BOQ_2227814.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .