Loading…
Loading…
Tender Value
Refer Docs
EMD Value
₹8.7 L
Closing Date
9 Sept 2026, 6:00 pm
CHIEF ENGINEER (G)
Repair and Modification of Existing NDCT of 210MW Unit No. 3 through Design, Engineering, supply, erection, testing, commissioning and Performance guarantee testing of the Natural Draught Cooling Tower.
335753
ET-296
Open
Power/Energy Projects/Products/Services
Turn-key
Gandhinagar
4 documents required · 4 mandatory
₹17,700
GUJARAT STATE ELECTRICITY CORP. LTD.
₹8.7 L
18 Aug 2026
18 Aug 2026
18 Aug 2026
9 Sept 2026
18 Aug 2026
towards payment of EMD and Tender fee are found ok, then only Technical Bid
will be opened (On-line). Tenders submitted without Tender Fee-EMD by the
firms, will be rejected without entering into further correspondence.
Submission of required documents for exemption of Tender Fee & EMD is
The exemption in payment of Tender Fee & EMD shall be given to the,
1. Micro & small-scale enterprises which participate directly in tendering
process for the product which they are manufacturing / service which
they are providing and have Udyam registration for items / service under
2. Start-ups which participate directly in tendering process for the product
PUR-F-10 ET-296
which they are manufacturing/service which they are providing and re-
cognized by DPIIT under the Start-up India Program and has obtained
Udyam registration.
3. Organization which has registration certificate for the manufacturing
product of the tender, from Gujarat Khadi Gramodyog Board or Khadi
and Village Industries Commission(K.V.I.C)or Commissioner of Cottage
4. Board/Corporations/PSUs of the Central/State Government for their
own manufactured items.
5. State Government recognized organizations like(i) organizations for
blinds, dumb and deaf, disabled, mentally disabled persons;(ii)women's
self-help group recognized by Gujarat Livelihood Promotion Company;
which participate directly in tendering process for the product which they
are manufacturing / service which /they are providing.
1. Micro & Small Enterprises (MSEs) who participates directly in the tendering
process as Manufacturers or Service Providers, and holds a valid Udyam
Registration, are eligible for exemption from payment of Earnest Money Deposit
2. Agencies registered under Udyam in the capacity of Traders, Re-sellers, or
similar categories (i.e. other than Manufacturers/Service Providers) are not
eligible for EMD exemption.
3. Migration period for Reclassification of MSMEs: - ln case of an upward change
in terms of investment in plant and machinery or equipment or turnover or
both, and consequent re-classification, an enterprise shall continue to avail of
all non-tax benefits of the category (micro or small or medium) it was in before
the re-classification, for a period of three years from the date of such upward
Vendor Registration with GSECL is not compulsory for submitting this tender.
PUR-F-10 ET-296
GUJARAT STATE ELECTRICITY CORPORATION LTD.
THERMAL POWER STATION, GANDHINAGAR-382
Repair and Modification of Existing NDCT of 210MW Unit#3
TENDER through Design, Engineering, supply, erection, testing,
FOR commissioning and Performance guarantee testing of the
Natural Draught Cooling Tower.
1 Tender Notice
2 Important Notes (Online Only)
3 Bidder Details (Online Only)
4 Technical Bid (Online Only)
5 Price Bid (Online Only)
Annexure (1 to 15, Certificate-A, Important Instruction & Integrity Pact)
of Commercial Terms & Conditions (Online Only)
Important : Pl. ignore “ Submission of Physical Document” wherever
mentioned, i.e. either in Tender Document or Commercial Terms & Condition.
For & On Behalf of GSECL
Chief Engineer (Gen)
GSECL, TPS Gandhinagar
Download & Submitted by _______________________________
(Name of Firm with Seal)
PUR-F-10 ET-296
GUJARAT STATE ELECTRICITY CORPORATION LIMITED
Gandhinagar Thermal Power Station, Gandhinagar, India–382041.
e-mail: [email protected]; Website: www.gsecl.in
CIN:U40100GJ1993SGCO19988
(A Successor Company of Gujarat Electricity Board)
Repair and Modification of Existing NDCT of 210MW Unit#3
through Design, Engineering, supply, erection, testing,
commissioning and Performance guarantee testing of the
Natural Draught Cooling Tower.
CE [Generation], Gandhinagar, TPS invites “On-line Tenders” (e-tendering) for the
purchase of above subject item. Tender Papers & Specifications may be down loaded
from Web site https://gsecltender.nprocure.com (For view, down load and on line
submission) and GUVNL / GSECL web sites www.gsecl.in (For view & down load only).
“NO COURIER SERVICE OR HAND DELIVERY” will be accepted.
Tender No. ET-296
Tender Fees (Non-Refundable)
Earnest Money Deposit (EMD)
(Please refer page 1 & 2 of Tender Document)
Last Date of submission of Online [e-
tendering] tender / offer , Technical as
well as Price bid along with soft copy of all
other documents as stated here under up
to18.00 Hrs. (This is mandatory).
Only EMD/Tender Fee related physical
documents will be required from bidders
before due date. As per NIT Details
Date of opening of Online Technical bid at
15.30 hrs(if possible), all relevant
documents submitted through online
process. Online technical bid will be
opened for Bidders who have submitted
Physical Document against EMD/Tender
Fee within due date as per NIT.
Party has to be in touch with website
Tentative date of On-line opening of price https://gsecltender.nprocure.com and
bid at 15.30 hrs. (if possible) also with e-mail sent by above website.
120 Days from the Date of
Validity of Rates (Compulsory)
Opening of Technical Bid.
Delivery of Goods/Completion of work As per Technical Bid
Sample Approval As per Technical Bid
Security Deposit As per Cl. No. (1) of Notes for
Supplier mentioned under
PUR-F-10 ET-296
Important Notes to Bidders:
(1) It is mandatory for all the bidders to submit their tender documents Online (e-
tendering) and in schedule time. Please note that Price bid is to be submitted
online only. Bidders should have to fill and submit the tender documents
on n-procure websites only. Tender documents submitted in tenderer’s own
printed paper or format other than GSECL’s format is liable to be ignored.
(2) Any technical information and clarifications that may be required pertaining to
this tender should be referred to the Chief Engineer (Gen), Gujarat State
Electricity Corporation Ltd., Thermal Power Station, Gandhinagar–382041,
Gujarat (India).
(3) Bidder has to upload scanned copies of original (Notarized/ self attested copies
of original – as specified in tender document) documents with online bid and no
physical documents are to be submitted. If physical Tender documents
submitted by any bidder then offer of the same bidder is liable to be ignored and
no further communication in the matter will be entertained.
(4) It shall be sole responsibility of the bidder that the uploaded scanned
documents (in PDF format) remain legible and should not be password
protected. The size of PDF is to be suitable so that it can be uploaded online (n-
procure). No any documents will be accepted offline or hard copy.
(5) Bidder should have to give Validity of their offer for minimum 120 days from the
actual date of opening of Technical Bid otherwise their tender/offer will be
ignored/rejected. Bidder shall have to extend validity further for 60 Days, if
required on all tender items (not for individual items), otherwise your offer is
liable to be ignored.
(6) GSECL reserves the rights to reject any OR all tenders without assigning
any reasons thereof.
(7) Please note that Conditional Offers will liable to be ignored.
(8) Bidders should be in touch with N-Procure and GSECL websites for information
regarding revision/ corrigendum/ amendment in tender till due date of on line
submission and thereafter. No separate correspondence will be done in this
(9) If the bidder wish to submit Bank Guarantee (BG) in lieu of Earnest Money
Deposit (EMD)/ Security Deposit (SD) / Performance Bank Guarantee (PBG),
then the bidder should ask his BG issuing Bank to give intimation to our Bank
of Baroda (Beneficiary Bank), , SECTOR-21, GANDHINAGAR branch having IFS
Code as BARB0GANDHI (fifth letter is zero) through Structured Financial
Messaging Solution (SFMS). BG should be valid for minimum one year.
(10) Bidder shall have to submit scanned copy of Active GSTIN registration and PAN
in online bid. Tenders submitted without Active GSTIN by the bidders, the offer
will be rejected without entering into further correspondence.
(11) If any deviation in your offer with respect to Tender specification, then please
mention clearly in separate deviation sheet Annexure-12, otherwise your offer
will be considered exactly as per our Enquiry / Tender specification.
(12) Whichever terms conflict with “GENERAL COMMERCIAL TERMS AND
CONDITIONS” the terms mentioned in “TENDER DOCUMENT/NIT” will be
(13) GSECL reserves the right to place the order on technically qualified bidders for
item wise lowest quoted party.
(14) Party has to accept part order.
(15) If participating bidder/agency have stake in one or more other agencies /
bidders who are participating in same tender and on account of submission of
PUR-F-10 ET-296
wrong information / declaration in the tender / enquiry certificate – A, then the
bidder will be declared as disqualified automatically and EMD/SD will be
forfeited, Further, GSECL shall take stern action including Stop dealing with
(16) GSECL reserve the rights to accept/reject/cancel any or all the offers/tenders,
extend dates and/ or re-advertise tender, and/ or the whole process of
tenderization at any stage without assigning any reasons thereof.
(17) In case of short submission of documents with bid, GSECL reserves the right to
ask through e-mail / electronic mode / letter to submit the required details /
documents and/or clarification in physical form as well as in electronic form as
the case may be. The bidder has to submit the required document / details /
clarification asked by GSECL within stipulated time limit, failing which the bid
will be liable for rejection.
(18) The party must agree to participate in the VMS during tendering process and
provide necessary details to streamline the VMD registration process to avoid
delays in payment for supplies.
(19) Dispute Resolution Mechanism: Arbitration through the Arbitration Centre
(Domestic and International) High Court of Gujarat at Ahmedabad.
19.1) Amicable settlement
“Any dispute, difference, controversy or claim between the parties
arising out of or relating to this contract with reference to the
construction, interpretation, breach, termination or validity
thereof (herein after referred as “the Dispute”) shall, upon the
written request of either party by referred to the authorized
representatives of the disputing parties for resolution. The
authorized representatives shall promptly meet and attempt to
negotiate in good faith a resolution of the dispute within
days of the service of the request.”
19.2) Arbitration
If the parties fail to amicably resolve the disputes or
differences or contrary claims as indicated herewith in sub
clause (1) of Clause 19 arising under or in connection with the
present agreement, the same shall be referred to the
Arbitration Centre (Domestic & International) High Court of
Gujarat at Ahmedabad (“the Centre for short”), currently
functioning in the High Court Complex, Sola Ahmedabad for
appointment of arbitrator and thereupon, the Centre shall
appoint a sole arbitrator and conduct the arbitration
proceedings in accordance with its rules. If the parties
unanimously agree to appoint three arbitrators then in that
case, each party shall appoint one arbitrator from the panel of
arbitrators of the Centre, and the Centre shall appoint the
third arbitrator, who will act as the Presiding Arbitrator. Such
arbitration shall be the sole and exclusive remedy between the
parties for all disputes arising under or in connection with this
agreement. The arbitration shall take place at The Arbitration
Centre Ahmedabad, High Court Complex, Sola, Ahmedabad,
Gujarat, in accordance with the provisions of the Arbitration
and Conciliation Act, 1996 as amended from time to time, and
the proceedings shall be conducted in English. The arbitration
award shall be final and binding on the parties.
(20) Bidder should read and verify the documents of Commercial Terms & Conditions
of Tender & Supply (i.e. clause No. 1 to 71) of GSECL, Gandhinagar TPS and
confirm that all the above documents are verified & certified by you as below.
PUR-F-10 ET-296
“I/we read the above documents and agree for the Conditions of Tender &
Supply (i.e. Clause No.1 to 71) of GSECL, Gandhinagar, TPS and accordingly
submitted my / our offer.”
(a) It is mandatory to accept the Cl. 1 to 71. Bidder may accept the same on
a single paper instead of all 37 pages. [Pg. 1 to 37] and attach PDF copy
of seal & signed paper in online documents.
(b) It is mandatory to submit duly filled, stamped and signed PDF copies of
Tender Document up to Technical Bid, Annexure – 1 to 15 including
Annexure 10 (GSECL-GTPS), Integrity pact, Important Instruction and
certificate-A through online (n-Procure) process only.
(21) “All bidders shall submit the details/documents in support of Technical
Qualification Requirements duly certified and verified for authenticity from
Specified Third-Party Inspection Agency (TPIA) along with a certificate regarding
verification of authenticity of documents as per the format placed at Annexure-1.
All the documents submitted by the bidder in support of meeting Technical QR
only shall be digitally signed by the Specified Third-Party Inspection Agency
(TPIA). The verification and certification of authenticity of documents is
acceptable from any of the following TPIAs:
1. M/s Competent Inspectorate and Consultants Pvt. Ltd, Hyderabad, India.
2. M/s Gulf Lloyds Industrial Service India Pvt. Ltd.- Ahmedabad.
3. M/s International Certifications Services.
4. M/s Intertek India Pvt. Ltd.
5. M/s SGS India Pvt. Ltd.
6. M/s Moody International (India) Pvt. Ltd.
7. M/s TUV SUD South Asia (P) Ltd.
8. M/s TUV Rheinland (India) Pvt. Ltd.
9. M/s Bureau Veritas (india) Pvt. Ltd.
10. Hertz Inspection & Services Pvt. Ltd.
11. IRCLASS Systems and Solutions Pvt. Ltd.
The Bidder shall be responsible for getting their documents/ credentials verified
& certified by the Specified Third-Party Inspection Agency (TPIA) in support of
Technical QR. All the costs pertaining to third party verification and certification
(including those by statutory auditors) shall be borne by the Bidder. GSECL
shall have no liability (financial or otherwise) towards the same and shall not be
liable for any claim/ dispute between the bidder and the Specified Third-Party
Inspection Agency (TPIA).”
For & On Behalf of GSECL,
Chief Engineer (Gen)
GSECL, TPS Gandhinagar
PUR-F-10 ET-296
Undertaking from Third Party Inspection Agency/Statutory Auditor or
Practicing CA/CA Firm
(On letter head digitally signed by a person duly authorized to Sign on behalf of the
Power Station Gandhinagar.
Subject: Authentication of veracity of documents submitted by M/s
…………………………… in support of Meeting the Qualifying Requirements.
Ref : Tender no.: …………………..
Name of the Package/ Tender: ………………………………………
M/s. …………………… (hereinafter called Bidder) having Registered office at
…………………… intend to participate in above referred tender of GSECL.
The tender condition stipulates that the bidder shall submit supporting Documents
pertaining to Qualifying Requirement duly verified and certified by Third-Party
Inspection Agency (TPIA) as per the list mentioned in the bidding documents.
In this regard, it is hereby confirmed that we have examined the following
documents, which are also attached with this letter. The same has been verified from
the Original Documents and / or Client for authenticity.
We hereby confirm that the following documents are found to be genuine and
1. Doc ref. no. ……….. dated …….. (Name of Documents)
2. Doc ref. no. ……….. dated …….. (Name of Documents)
All the aforesaid documents have been digitally signed by us as a certificate of
We further confirm that we neither have any vested interest in aforesaid tender nor
have any conflict of interest in respect of above tender.
This certificate is issued at the request of M/s ………………. (Bidder) for the purpose
of participating in the subject tender/s.
Bidder’s Signature
with Seal & Date
PUR-F-10 ET-296
GUJARAT STATE ELECTRICITY CORPORATION LTD
Thermal Power Station, Gandhinagar-382
Note: Bidder has to fill following Details without fail (It is Mandatory).
1. (a) Full Name and Address
2. Particulars of Registration as a
Contractor and class in which
(a) In the Gujarat Elect. Corp. Ltd.
(b) In other Government
3. Reference to be made to (Name &
4. Previous experience in Railway, PWD
and other works
5. Any other information the contractor
may desire to give
Bank Account Number
Name of Beneficiary
Type of Account
Branch Name & Address
Contact Number of The
Cancelled Cheque copy Scan copy of the same is mandatory
PUR-F-10 ET-296
Sub: Repair and Modification of Existing NDCT of 210MW Unit#3 through
Design, Engineering, supply, erection, testing, commissioning and
Performance guarantee testing of the Natural Draught Cooling
Description of Material Unit
UPVC PIPE CONFIRMING TO IS: 4985, CLASS
1 RATING, PIPES ARE WITH SOCKETED ENDS: UPVC
PIPE, SIZE : 200 MM OD
UPVC PIPE CONFIRMING TO IS: 4985, CLASS
2 RATING, PIPES ARE WITH SOCKETED ENDS:UPVC
PIPE, SIZE : 160 MM OD
UPVC END CAP THREADED FOR 160MM OD UPVC
4 UPVC SOCKET 160MM OD Numbers
UPVC REDUCER OF SIZE 200 MM OD TO 160 MM
6 COUPLING FOR 160MM DIA PIPE Numbers
7 FRENCH SPRAYER NOZZLES Numbers
8 PVC TRIANGULAR BAR (LATHE)
FRP RAILING WITH ACCESSORIES & HEIGHT Running
Loading, unloading & shifting of UPVC pipes to work Running
Removal & re-erection of UPVC piping system with
11 supports and end caps. Shifting of Old Pipes within
the plant area as per EIC instruction
12 Nozzle installation with adaptor Number
13 PVC Lath (Triangular Bar) installation
Two-coat Bituminous Paint ? IS: 9862:2017 /
14 IS:158:2015, min. 100-micron DFT. Coat 1: diluted
(penetration); Coat 2: full strength
15 FRP Railing installation with accessories
Pre-shutdown baseline performance test & Post-
intervention performance test
Dewatering, cleaning, scrapping, removal of debris &
disposal as per scope of work
Note: Overall Lowest party’s offer (for all 17 items) will be considered for
placement of order i.e. considering supply & installation work.
Part/Partial offer will not be considered.
PUR-F-10 ET-296
Technical Specifications:
The proposed tender shall cover the complete execution of the work, including
detailed engineering, supply of all required materials, dismantling and modification
activities, erection, testing, commissioning, and successful completion of Performance
Guarantee Tests (PGT) as specified in the tender documents.
It is clarified that the specifications mentioned in the item code description against
Item Sr. No. 7 are provided solely for GSECL identification and inventory reference
purposes. The bidder shall be required to quote, supply materials, and execute the
work strictly in accordance with the technical specifications, requirements, and
conditions detailed in the enclosed tender documents.
The scope of the proposed work shall broadly include the following:
1. Scope of Supply
Supply of all materials, components, consumables, accessories, and other items
required for the repair and modification of the existing NDCT as specified in the
tender documents.
2. Scope of Work
Design, detailed engineering, repair, modification, erection, installation, testing,
commissioning, and Performance Guarantee Testing of the cooling tower system
as detailed in the tender.
3. Terms and Conditions for Works
Compliance with all contractual, technical, quality assurance, inspection,
testing, completion schedule, and performance requirements specified in the
tender documents.
4. General Terms and Conditions of Supply and Works
Compliance with all commercial, contractual, warranty, guarantee, statutory,
and other applicable requirements.
Compliance with all applicable labour laws, statutory regulations, wage
provisions, EPF, ESIC, and other legal requirements during execution of the
6. Safety Norms
Strict adherence to GSECL safety standards, safety procedures, permit systems,
PPE requirements, and all applicable safety regulations throughout the
execution period.
PUR-F-10 ET-296
Pre-Qualification Criteria (PQC) (To be submitted with Technical Bid):-
The bidders who wish to participate in the bidding shall satisfactorily
establish that they fulfill the following Qualifying Requirements.
The bidder should have executed / completed similar works during the last
seven (7) years in Government / semi government / state electricity board /
private limited company / public limited company / IPP, as on last date of the
month preceding the month of publication of tender, having minimum contract
/order values as indicated below
a. One similar completed order of value not less than the amount equal to
1. b. Two similar completed works costing not less than the amount equal to
c. Three similar completed order each of value not less than the amount equal
Similar work means the “Supply, Erection & commissioning / R & M/
Modification work of NDCT ( i.e. Natural Draught Cooling Tower) / IDCT ( i.e.
Induced Draught Cooling Tower) in a unit having capacity of 210 MW or above
B Financial qualification criteria:
1) The Average Annual Turnover of the bidder, shall not be less than
Rs.87,39,286.20 during the preceding three (3) financial years as one date
of Techno-Commercial bid opening
2) Net worth of bidder shall not be less than 100% of the bidder’s paid up
share capital as on the last day of the preceding financial year. In case the
Bidder meets the requirement of Net worth based on the strength of its
Subsidiary (ies) and / or Holding company and / or Subsidiaries of its
Holding Companies wherever applicable, the Net worth of the Bidder and its
Subsidiary (ies) and / or Holding company and/or Subsidiary (ies) of the
Holding Company, in combined manner should not be less than 100% of
their total paid up share capital. However individually, their Net worth
should not be less than 75% of their respective paid share capitals.
Net worth in combined manner shall be calculated as follows:
Net worth (combined )= (x1+x2+X3)/(y1+y2+y3) X 100, where x1,x2, x3 are
2. individual net worth which shall not be less than 75 % of the respective
paid up share capitals and y1, y2, y3 are individual paid up share capitals.
3) In case the bidder is not able to furnish its audited financial statements on
stand-alone entity basis, the unaudited unconsolidated financial statements
of the bidder can be considered acceptable provided the bidder further
furnishes the following documents for substantiation of its qualification.
Copies of the unaudited unconsolidated financial statements of the bidder
along with copies of the Audited consolidated financial statements of its
Holding Company.
A Certificate from the CEO/CFO of the Holding Company, stating that the
unaudited unconsolidated financial statements form part of the
Consolidated Annual Report of the company.
4) In cases where audited results for the last preceding financial year as on the
date of techno-commercial bid opening are not available, the financial
PUR-F-10 ET-296
results certified by a practicing Chartered Accountant shall be considered
acceptable. In case, Bidder is not able to submit the Certificate from
practicing Chartered Accountant certifying its financial parameters, the
audited results of three consecutive financial years proceeding the last
financial year shall be considered for evaluating the financial parameters.
Further, a Certificate would be required from the CEO/CFO, stating that
the financial results of the Company are under audit as on the date of
Techno-commercial bid opening and the Certificate from the practicing
Chartered Accountant certifying the financial parameters is not available.
Note for point No.1, 2, 3 & 4:
a) Other income shall not be considered for arriving at annual turnover.
b) “Holding Company" and “Subsidiary Company” shall have the meaning
ascribed to them as per Companies Act of India, in vogue.
c) Net worth means the sum total of the paid up share capital and free
reserves. Free reserve means all reserves credited out of the profits and
share premium account but does not include reserves credited out of the
revaluation of the assets, write back of depreciation provision and
amalgamation. Further, any debit balance of Profit and Loss account and
miscellaneous expenses to the extent not adjusted or written off, if any,
shall be reduced from reserves and surplus.
Bidder shall have to submit list of Tools Tackles and Equipment possessed
Relevant to the Job and
3. Also furnish the Details of Project Engineer, Supervisors / Site-Engineers,
Skilled / Semi-Skilled Persons Employed with experience details for said kind of
Bidder should have a separate valid GST registration number and submit the
Copy with tender technical bid.
4. Further if bidder has two registrations out of which one is cancelled than bidder
has to provide the No due certificate from GST department for the cancelled
GST registration.
5. Bidder shall have to submit the copy of PAN number.
6. Copy of P.F. Code from the appropriate provident fund authorities.
Labour License for Labour Contract: The contractor on getting the work order
but before starting the work shall have to furnish the copy of Labour License
7. under the Contract Labour (Regulation & Abolition) from the appropriate
authorities. Also required workman group insurance policy covering labour
The bidder must submit performance certificates or satisfactory work
completion certificates (issued directly by the utility) or Copy of Processed Final
Bill of the executed / submitted PO from the utility. Bidders shall be required to
8. submit all the documents, in support of Technical QR (Such as copies of
Purchase orders/work orders / Contract Agreements, Client Certificates, etc),
shall be digitally signed by the Specified Third party inspection Agency (TPIA) /
Approved by GSECL.
The bidder must submit Average Annual Turnover and Net worth Certificate in
support of Financial QR, duly certified and verified for authenticity from
Independent Statutory Auditor of their company / Practicing Charted
9. Accountant/ C.A. Firms / TPIA (Third-Party Inspection Agency ) empanelled /
approved by GSECL along with copy of Annual Audited Accounts of last three
10. Tender fee & EMD will be applicable as per NIT
PUR-F-10 ET-296
1. The Chief Engineer (Gen.), GSECL, GTPS reserve right to reject any tender or all
tenders without assigning any reason thereof and to split up the work between
more than one party as the case may be.
2. Non-compliance of above criteria the technical bid is liable to be rejected.
After acceptance of the Technical Bid, the Price Bid will be considered for
Chief Engineer (G)
GSECL: Gandhinagar TPS
Dated seal & signature of
Bidder/Contractor
PUR-F-10 ET-296
DETAIL SCOPE OF SUPPLY:
(1) Item Sr.no.1: UPVC Pipe 200 mm OD
(2) Item Sr.no.2: UPVC Pipe 160 mm OD
(3) Item Sr.no.3: UPVC End Cap Threaded 160 mm OD
(4) Item Sr.no.4: UPVC Socket 160 mm OD
(5) Item Sr.no.5: UPVC Reducer 200 mm × 160 mm OD
(6) Item Sr.no.6: UPVC Coupling 160 mm OD
Piping & Fittings material may include:
UPVC distribution pipelines as per IS 4985 / ASTM D1785 / DIN8061
(Virgin grade, Rigid type), Corrosion-resistant, UV-Stabilized, Pressure
rating class PN6/Pn10 suitable continuous operation at 50 Deg C. Make:
Astral / Finolex / Supreme only
UPVC Fitting i.e. End Caps, Sockets, Reducers, coupling confirming ASTM
D2466 / D2467 / IS standard equivalents for Pressure rating class PN6
suitable continuous operation at 50 Deg C. Make: Astral / Finolex /
It should be Lead free compound and UV stabilized grade mandatory.
It should be corrosion resistance and having No-scaling properties.
Resistance to CW chemical / Chlorination.
Having smooth internal surface.
The Bidder Shall Provide:
Manufacturer test certificates
Material composition & data sheets
Quality assurance documentation
(7) Item Sr.no.7: Nozzles with Adaptor
The Bidder shall Supply and install new nozzles
FRENCH SPRAYER nozzle or
Open type Gravity Deflector spray nozzles or
PP/HDPE spiral type open non clogging spray nozzle with high
(B) Nozzle Specifications:
Nozzles shall be:
Non-clogging type.
UV resistant.
Corrosion resistant.
Suitable for circulating water quality.
Hydraulically balanced.
PUR-F-10 ET-296
The Bidder Shall Provide:
Manufacturer test certificates
Material composition & data sheets
Quality assurance documentation
(8) Item Sr.no.8: PVC Lath (Triangular Bar)
Supply of PVC Triangular Bar (Lathe Type) splash fills suitable for 210MW – Old
design NDCT application.
Material Specifications:
UV stabilized rigid PVC
High mechanical strength
Heat and chemical resistant
Non-corrosive and lightweight
Suitable for circulating water temperature conditions
Typical Parameters:
Shape: Triangular bar / lathe profile
Color: Grey/white/black as approved
Length and section: As per approved design
Support spacing compatibility with existing structure
Contractor Shall Provide:
Manufacturer test certificates
Material data sheets
Quality assurance documentation
(9) Item Sr.no.9: FRP Railing with accessories & height 4.5ft
The Bidder shall supply the corrosion-resistant FRP handrail systems complete
Vertical posts
Kick/toe plates
Base plates and clamps
Fasteners and accessories
Typical Technical Requirements
Material: Pultruded FRP sections
Resin System: Isophthalic polyester / Vinyl ester resin
UV protection: UV-resistant surface veil
Flame spread rating: Maximum
Colour: Safety yellow / as approved by owner
PUR-F-10 ET-296
Handrail height: Minimum 1100 mm
Toe plate height: Minimum 100 mm
Design load: As per applicable industrial platform standards
All fastening hardware shall be SS-304/SS-316.
The Bidder Shall Provide:
Manufacturer test certificates
Material composition & data sheets
Quality assurance documentation
DETAIL SCOPE OF WORKS
1.0) - INTRODUCTION
The Natural Draft Cooling Tower (NDCT) at Gandhinagar TPS has been in operation
since 1980s and has experienced deterioration due to aging, environmental exposure,
and operational stress. This DPR outlines the scope, methodology, cost estimates,
and implementation plan for Renovation & Modernization (R&M) aimed at restoring &
improving thermal efficiency, and ensuring compliance with current operational
Plant & System Overview
Station: Gandhinagar Thermal Power Station
Owner: Gujarat State Electricity Corporation Limited
Each Unit#3 Capacity: 210 MW
Cooling System: Natural Draft Cooling Tower (NDCT)
Type: RCC Hyperbolic Shell
Age: ~30–40 years
Cooling water Flow (Closed circulation) – 27000 m3 / hr.
Current Issues:
o Reduced cooling efficiency
o Fill media deterioration
o Drift losses and water inefficiencies
o Aging mechanical components
This Scope of Work covers complete repair, modification, replacement of damaged
components; performance improvement, testing, commissioning, and performance
guarantee testing of the existing Natural Draught Cooling Towers (NDCTs) associated
with 210 MW Unit #3 of the Power Station.
The contractor shall execute all activities on a turnkey basis including detailed
survey, design verification, engineering, procurement, dismantling,
structural/mechanical works, erection, testing, commissioning, and handing over of
the NDCTs in healthy operating condition meeting guaranteed thermal performance
The scope shall include all labor, materials, consumables, tools & tackles, temporary
facilities, supervision, equipment, cranes, scaffolding, safety arrangements, statutory
PUR-F-10 ET-296
approvals, and all incidental works necessary for successful completion of the
2.0) OBJECTIVE OF THE WORK
The primary objectives of the project are:
Improvement of cooling tower thermal performance.
Replacement/modification of deteriorated and damaged components.
Reduction of cooling water temperature and enhancement of cooling efficiency.
Enhancement of reliability, safety, and operational life of the cooling towers.
Compliance with applicable standards, statutory regulations and
environmental requirements.
3.0) BROAD SCOPE OF WORK
The broad scope shall include but not be limited to:
1. Dewatering, cleaning, scrapping and removal of debris from basin, HW ducts,
structural supports etc…
2. Detailed inspection and condition assessment.
3. Design and detailed engineering.
4. Replacement/modification of cooling tower internals.
5. Replacement/repair of piping and nozzles.
6. Replacement/modification of fills / louvers / splash bars, etc.
7. Repair/replacement of staircases, handrails, platforms, and access systems.
8. Corrosion protection and protective coating / painting works.
9. Testing, commissioning, and performance guarantee testing.
10. Preparation and submission of all drawings, reports, manuals, and as-built
4.0) DETAILED SCOPE OF WORK
4.1) PRELIMINARY INVESTIGATION & CONDITION ASSESSMENT
{Pre-Testing Scope - Before Modification Work}
4.1.1) General Assessment
Contractor shall carry out detailed inspection and performance evaluation of the
existing NDCT including:
Visual inspection of internal components
Assessment of existing water distribution system condition
Inspection of fill condition, clogging and deterioration
Inspection of nozzle performance and spray pattern
Inspection of basin condition and water flow pattern
Identification of leakages, bypassing and dead zones
4.1.2) Thermal Performance Testing
PUR-F-10 ET-296
Contractor shall conduct baseline thermal performance test under operating
conditions to establish existing cooling tower performance parameters including:
Parameters to be measured:
Hot water temperature
Cold water temperature
Ambient wet bulb temperature
Dry bulb temperature
Cooling range
Cooling approach
Circulating water flow rate
Water loading
Airflow condition
Fan/air draft behaviour (if applicable)
Performance Calculations:
Cooling tower effectiveness
Thermal efficiency
Heat rejection rate
Approach temperature
Cooling capability
4.1.3) Hydraulic & Water Distribution Assessment
Contractor shall evaluate:
Uniformity of water distribution
Spray coverage over fill area
Nozzle choking/damage
Uneven flow zones
Overflow/spillage conditions
Pressure drop across distribution system
Water carryover losses
4.1.4) Drift & Water Loss Assessment
Measurement/assessment of:
Splash losses
Water leakage
Basin overflow losses
Air bypassing effects
4.1.5) Structural & Mechanical Assessment
Existing support structures
PUR-F-10 ET-296
Pipe supports and clamps
Fill support integrity
4.1.6) Pre-Test Reporting
Contractor shall submit detailed pre-test report containing:
Existing operating condition data
Thermal performance improvement calculations
Deficiency analysis
Performance shortfalls
Photographic records
Recommendations for repair and modification improvement
Benchmark performance values
4.2) DESIGN & ENGINEERING
The contractor shall perform complete design and detailed engineering including:
4.2.1) Mechanical Design
Water distribution system design.
Fill arrangement design.
Nozzle system design.
Louvers and splash bar configuration.
4.2.2) Preparation of Engineering Documents
Detailed fabrication drawings.
Repair drawings.
Method statements.
Inspection & test plans.
Construction methodology.
Erection procedures.
Safety procedures.
4.2.3) Design Codes & Standards
Applicable latest editions of:
CTI Standards
BS/EN Standards
PUR-F-10 ET-296
Relevant power plant standards
4.3) CIVIL DETAIL SCOPE OF WORKS
This Scope of Work covers complete dewatering, sludge cleaning, scrapping, disposal,
inspection, minor repair, surface preparation, painting, and protective bituminous
coating works for the existing Natural Draught Cooling Tower (NDCT) Basin, Fill
Structure Members, and Water Ducts of 1980s vintage cooling towers.
4.3.1) OBJECTIVE OF THE WORK
The objective of the work is to:
Remove accumulated sludge, algae, debris, and deposits.
Restore hydraulic flow conditions.
Carry out inspection& identification of damage parts of Basin, ducts, supports
Improve corrosion resistance and waterproofing protection.
Apply protective coating/bituminous paint systems.
Improve service life and maintainability of the NDCT
4.3.2) SCOPE OF WORK
The scope shall include but not be limited to:
1. Dewatering of basin and water ducts.
2. Sludge removal and disposal within 5.0 km area as per instruction of EIC.
3. Cleaning and washing of all accessible areas.
4. Scrapping and cleaning of all accessible structural members.
5. Inspection and marking of damaged locations of Basin, Hot water ducts, Fills
structural members.
6. Surface preparation for painting/coating.
7. Application of primer and protective coating.
8. Bituminous protective painting/coating confirming Black Bituminous Paint as
per IS: 9862:2017 / IS 158:2015. Minimum thickness 100micron with 01 coat
Primer + 02 coat Finish
9. Final cleaning and disposal of debris within 5.0 km area as per instruction of
10. Testing and handing over.
4.3.3) DETAILED SCOPE OF WORK
A). PREPARATORY WORKS
The contractor shall:
Visit and inspect the complete site before execution
Verify dimensions and accessibility.
Arrange temporary power, lighting, pumps, hoses, pipelines, and tools.
Arrange scaffolding, staging, walkways, ladders, and safety platforms.
Obtain necessary work permits from plant authorities.
PUR-F-10 ET-296
Coordinate shutdown activities with Owner.
B). DEWATERING WORKS
B.1) Dewatering of Basin
The contractor shall:
Completely drain/dewater cooling tower basin and discharge the fresh
water to nearest CW sump and muddy water as per instruction of EIC.
Deploy adequate pumps, hoses, and standby systems.
Remove stagnant water from all pockets and compartments.
Maintain dry working condition during execution.
B.2) Dewatering of Water Ducts
Dewater all CW ducts and channels connected to NDCT.
Remove residual water using portable pumps/manual methods.
Ensure safe access inside ducts for cleaning and inspection.
B.3) Temporary Arrangements
Contractor shall provide:
Temporary drainage arrangement.
Sump pumping arrangement.
Dewatering pipelines.
Barricading and access control.
C). CLEANING & SLUDGE REMOVAL WORKS
C.1) Basin Cleaning
The contractor shall:
Remove accumulated sludge, algae, muck, and biological growth.
Scrape deposited materials from basin floor and walls.
Carry out manual/mechanical cleaning.
Use high-pressure water jet cleaning wherever required.
C.2) Water Duct Cleaning
The work shall include:
Cleaning of inlet/outlet ducts.
Removal of settled silt and sludge.
Cleaning of corners and dead pockets.
Removal of obstructions affecting water flow.
C.3) Fill Structure Cleaning
The contractor shall:
Remove sludge deposits from fill support structures.
Clean structural members manually/mechanically.
Remove scales and loose deposits.
PUR-F-10 ET-296
D). PAINTING & PROTECTIVE COATING WORKS
The contractor shall supply and apply all paints/coatings including primers,
intermediate coats and finish coats complete in all respects.
D.1) RCC Protective Coating
The coating system shall include:
Surface cleaning.
Primer application.
Waterproof protective coating.
Bituminous protective coating where specified.
Basin inner surfaces.
Water retaining surfaces.
Splash zones.
Damp-prone areas.
D.2) Bituminous Protective Painting as per IS: 9862:2017 / IS 158:2015
The contractor shall:
Apply approved grade bituminous coating/paint.
Ensure uniform thickness and coverage.
Apply multiple coats as required.
Areas of Application
Water duct surfaces.
Embedded metallic surfaces.
Moisture-prone RCC surfaces.
Underground/exposed damp areas.
E). DISPOSAL OF SLUDGE & DEBRIS
The contractor shall:
Collect all sludge/debris.
Transport and dispose at approved location within 5.0KM of GTPS plant
premises as per Instruction of EIC.
Follow environmental regulations.
Maintain cleanliness around working area.
No debris shall be allowed to enter circulating water system.
F). FINAL CLEANING & RESTORATION
After completion of work, the contractor shall:
PUR-F-10 ET-296
Remove temporary arrangements.
Clean all work areas.
Restore access pathways.
Ensure basin and ducts are free from foreign materials.
G). TESTING & INSPECTION
The contractor shall carry out:
Joint inspection before and after cleaning.
Coating measurement.
4.3.4) MATERIALS
Materials to be used shall include:
Bituminous coating.
Epoxy primer.
Other require material not in list but require to complete the works.
All materials shall be approved by Owner before use.
4.3.5) TOOLS & EQUIPMENT
The contractor shall arrange:
Dewatering pumps.
Sludge pumps.
Safety equipment.
High pressure jet machines.
Grinding/wire brushing tools.
Lighting arrangement.
Any other require for execution & completion for the works.
4.3.6) SAFETY REQUIREMENTS
The contractor shall strictly follow:
Confined space entry procedures.
Work at height safety.
Electrical safety.
PPE requirements.
Gas testing requirements.
Mandatory provisions:
Safety helmets
Ventilation blowers
PUR-F-10 ET-296
Gas detectors
4.3.7) QUALITY REQUIREMENTS
The contractor shall ensure:
Proper surface preparation.
Approved coating thickness.
Uniform paint application.
Complete sludge removal.
4.3.8) DOCUMENTATION
The contractor shall submit:
Daily progress reports.
Inspection reports.
Material test certificates.
Paint manufacturer certificates.
Completion report.
4.3.9) COMPLETION CRITERIA
The work shall be considered complete after:
Complete dewatering and cleaning.
Sludge removal and disposal.
Successful application of coatings/paint.
Final inspection and acceptance by Owner.
4.3.10) MEASUREMENT & PAYMENT
Measurement Basis
Item Description UOM
Dewatering, cleaning,
scrapping, removal of debris & Lump Sum (01 job)
disposal as per scope of work
Painting & Coating Square Meter
4.3.11) GUARANTEE
The contractor shall guarantee:
Coating performance.
Guarantee period: Minimum 12 months from completion.
4.3.12) EXCLUSIONS (IF ANY)
Unless specifically included:
Major structural rehabilitation.
PUR-F-10 ET-296
Replacement of complete fill system.
Major basin reconstruction.
4.3.13) APPLICABLE CODES & STANDARDS
SSPC standards
ASTM coating standards
Plant safety regulations
4.3.14) CONTRACTOR RESPONSIBILITIES
The contractor shall be fully responsible for:
Material handling
Quality control
Environmental compliance
Protection of nearby equipment
Timely completion
4.4) MECHANICAL DETAIL SCOPE OF WORKS
This Scope of Work covers complete mechanical repair, refurbishment, replacement,
modification, supply, erection, testing, commissioning, thermal performance
evaluation, and Performance Guarantee Testing (PGT) of the existing 1980s Natural
Draught Cooling Towers (NDCTs).
The work primarily includes rehabilitation and performance enhancement of:
Water Distribution System
High Performance & Fouling resistance Splash Fill System
Modern Spray Nozzles
Associated Support Structures
Mechanical Internals
Thermal Performance Related Components
The contractor shall execute the work on turnkey basis including design verification,
dismantling, supply, installation, alignment, testing, commissioning, and guaranteed
thermal performance demonstration.
4.4.1) OBJECTIVE OF THE WORK
The objectives are:
Improvement in cooling tower thermal performance.
Uniform water distribution across fill area.
PUR-F-10 ET-296
Reduction in cold water temperature.
Reduction in drift losses and pressure losses.
Replacement of deteriorated internals.
Improvement in operational reliability and maintainability.
Enhancement of cooling tower service life.
4.4.2) SCOPE OF WORK
The scope shall include but not be limited to:
1. Detailed inspection and assessment.
2. Dismantling and disposal of damaged components.
3. Repair/replacement of water distribution piping.
4. Replacement/modification of spray nozzles.
5. Replacement of fill media.
6. Repair/replacement of support structures.
7. Alignment and balancing of water distribution system.
8. Mechanical erection and installation works.
9. Trial run and commissioning.
10. Performance Guarantee Testing (PGT).
4.4.3) DETAILED SCOPE OF WORK
4.4.3.1) PRELIMINARY INSPECTION & CONDITION ASSESSMENT
The contractor shall carry out detailed inspection, survey and conditions assessment
of existing NDCT for complete replacement of Water distribution system and spray
nozzles include
(A) Existing Water Distribution System
Study of complete water distribution network including headers, branches and
Measurement of flow distribution and pressure loss in existing system.
Verification of structural supports and pipe alignment.
Identifications of dead zones and non-uniform water distribution areas
(B) SPLASH Fill – PVC Lath (Triangular Bar) System Assessment
Inspection of Existing splash fills and support system
Assessment the fills conditions, blockage and deterioration
Verification of suitability with proposed new arrangement.
(C) Complete Nozzle Replacement to FRENCH nozzle or Open type Gravity
Deflector spray nozzles or PP/HDPE spiral type open non clogging spray
nozzle with high performance
Hydraulic Assessment and design review for complete replacement system
PUR-F-10 ET-296
Suitability assessment for modern high performance nozzles such as FRENCH
sprayer nozzles / Open type Gravity Deflector nozzles / PP-HDPE spiral non-
clogging spray nozzles.
Evaluation of nozzle spacing, spray coverage and operating pressure
Assessment for achieving uniform water distribution over complete fill area.
(D) Thermal Performance Assessment
The contractor shall conduct existing thermal performance study including
measurement of:
Existing thermal performance study
Measurement of:
o CW inlet temperature
o CW outlet temperature
o Air flow condition
o Cooling tower performance efficiency
4.4.3.2) DETAILED ENGINEERING & DESIGN REVIEW
The contractor shall perform:
Thermal performance (Effectiveness / Efficiency) review.
Water loading calculations.
Nozzle distribution calculations.
Fill performance evaluation.
Drift loss calculations.
Structural adequacy verification of supports.
The contractor shall submit:
Detailed engineering drawings.
Material specifications.
Thermal design calculations.
Performance improvement proposal.
4.4.3.3) DISMANTLING WORKS
The contractor shall dismantle, remove, segregate and dispose off the materials
1. Removed Completely Existing Distribution Main distribution headers, branch
pipes, lateral pipes, nozzle pipes, supports, fitting etc… carefully without
affecting adjacent structures.
2. Removed all existing Nozzles carefully without affecting adjacent structures
3. Fills shall be dismantled carefully without affecting adjacent structures.
PUR-F-10 ET-296
4. Dismantled reusable materials shall be stacked separately as directed by EIC.
5. Scrap materials shall be disposed of in designated areas only.
6. Care shall be taken to prevent falling debris from damaging basin floor,
supports or equipment
4.4.3.4) WATER DISTRIBUTION SYSTEM WORKS
The contractor shall replace with Modification of complete water distribution system
Main distribution headers
Lateral pipes
Supports and hangers
Pipe fittings
Expansion joints where applicable
Piping & Fittings material may include:
UPVC distribution pipelines as per IS 4985 / ASTM D1785 / DIN8061 (Virgin
grade, Rigid type), Corrosion-resistant, UV-Stabilized, Pressure rating class
PN6/Pn10 suitable continuous operation at 50 Deg C. Make: Astral / Finolex
UPVC Fitting i.e. End Caps, Sockets, Reducers, coupling confirming ASTM
D2466 / D2467 / IS standard equivalents for Pressure rating class PN6
suitable continuous operation at 50 Deg C. Make: Astral / Finolex / Supreme
It should be Lead free compound and UV stabilized grade mandatory.
It should be corrosion resistance and having No-scaling properties.
Resistance to CW chemical / Chlorination.
Having smooth internal surface.
Contractor Shall Provide:
Manufacturer test certificates
Material composition & data sheets
Quality assurance documentation
C). Work Requirements
The contractor shall ensure:
Uniform water distribution.
Proper hydraulic balancing.
Minimum pressure drops.
Proper alignment and leveling.
Leak-proof system.
PUR-F-10 ET-296
Corrosion protection.
The contractor shall:
Repair/replace pipe supports.
Replace corroded fasteners.
Provide anti-corrosion treatment.
E). Erection & Installation Instructions
All piping/header supports shall be checked for alignment and integrity before
Pipe routing, slope and nozzle orientation shall be maintained as per approved
All supports, clamps and fasteners shall be properly tightened.
Pipe joints shall be leak-proof and properly aligned.
Internal cleaning/flushing of piping shall be carried out before commissioning
4.4.3.5) SPRAY NOZZLE WORKS
The contractor shall:
Remove all existing nozzles.
Supply and install new nozzles
o FRENCH SPRAYER nozzle or
o Open type Gravity Deflector spray nozzles or
o PP/HDPE spiral type open non clogging spray nozzle with high
Ensure proper spray pattern.
B). Nozzle Requirements
Nozzles shall be:
Non-clogging type.
UV resistant.
Corrosion resistant.
Suitable for circulating water quality.
Hydraulically balanced.
Contractor Shall Provide:
Manufacturer test certificates
Material composition & data sheets
Quality assurance documentation
PUR-F-10 ET-296
C). Spray Pattern Verification
The contractor shall verify:
Uniform spray distribution.
Complete fill coverage.
Absence of dry pockets.
E). Erection & Installation Instructions
Nozzles shall be installed in correct orientation and spacing to ensure uniform
water distribution.
Nozzle openings shall be checked for blockage before installation.
Damaged or defective nozzles shall not be used.
Contractor shall ensure easy accessibility for future
maintenance/replacement.
4.4.3.6) SPLASH FILL SYSTEM WORKS
A). Scope of Work
A.1). Preliminary Inspection and Condition Assessment
The contractor shall carry out a detailed inspection and assessment of the existing
splash fill system and associated structural supports inside the NDCT
Activities Include:
Visual inspection of all RCC splash fill layers and support systems.
Identification and marking of:
o Cracked RCC splash bars
o Broken or displaced splash fill members
o Corroded support beams/brackets
o Sagging or unstable fill arrangements
o Blocked water distribution zones
Assessment of accessibility and safety conditions.
Measurement and quantity verification of damaged RCC fills.
Preparation of condition assessment report with:
o Damage mapping
o Replacement recommendations
o Estimated quantities
A.2). Site Preparation and Safety Arrangements
The contractor shall arrange all necessary safety systems and access facilities.
Scaffolding/platforms/lifelines inside tower
Temporary lighting and ventilation
PUR-F-10 ET-296
Barricading and restricted area marking
Confined space safety compliance
PPE for all personnel
Shutdown coordination with plant authority
Debris collection arrangements
A.3). Dismantling and Removal of Damaged RCC Splash Fills
Careful dismantling/removal of damaged RCC splash fill members without affecting
adjacent reusable components.
Manual dismantling of damaged RCC splash bars/fill elements
Removal of loose concrete debris
Segregation of reusable and scrap material
Safe lowering and disposal of dismantled RCC materials
Cleaning of support grids and surrounding areas
Avoid damage to existing support beams and columns
Prevent falling debris hazards
Ensure structural stability during dismantling
A.4). Inspection and Repair of Supporting System
After removal of damaged fills, supporting members shall be inspected.
Checking RCC/steel support beams and brackets
Minor repair of supports if required
Tightening/replacement of corroded fasteners
Alignment correction of support system
B). Supply and Installation of PVC Triangular Bar Splash Fills against damaged
Fills as per observation & marking and as per instruction of EIC
B.1). Material Supply
Supply of PVC Triangular Bar (Lathe Type) splash fills suitable for NDCT application.
Material Requirements:
UV stabilized rigid PVC
High mechanical strength
Heat and chemical resistant
Non-corrosive and lightweight
Suitable for circulating water temperature conditions
Typical Parameters:
Shape: Triangular bar / lathe profile
PUR-F-10 ET-296
Color: Grey/white/black as approved
Length and section: As per approved design
Support spacing compatibility with existing structure
Contractor Shall Provide:
Manufacturer test certificates
Material data sheets
Quality assurance documentation
B.2). Installation of PVC Splash Fills
Installation of new PVC triangular splash bars in designated damaged/replaced
Alignment and leveling of support arrangements
Fixing of PVC triangular bars on support grids
Proper spacing as per cooling tower thermal design
Secure fastening to prevent vibration/displacement
Ensuring unobstructed airflow and water distribution
Installation Requirements:
Uniform splash pattern
Adequate rigidity and stability
Proper drainage and water breakup efficiency
Compatibility with existing remaining RCC fills
C). Cleaning and Final Inspection
Activities Include:
Removal of all debris and waste materials
Cleaning of work area and basin
Final alignment inspection
Checking for loose members
Verification of installation quality
D). Testing and Performance Verification
Contractor Shall:
Assist during trial operation
Check water distribution over replaced fills
Verify splash action and airflow passage
Inspect vibration/stability during operation
Rectify defects observed during testing
PUR-F-10 ET-296
E). Deliverables
Contractor shall submit:
Inspection report
Damage assessment drawings
Material test certificates
Installation methodology
Completion report
As-built replacement quantities
F). Measurement Basis (Typical)
Payment may be measured based on:
RM of splash fills replaced
Number of PVC triangular bars installed
Lump sum dismantling and cleaning
Actual repaired support quantities
G). Completion Criteria
The work shall be considered complete after:
Successful installation of all designated replacement fills
Cleaning and debris removal
Inspection approval by client/consultant
Satisfactory operational trial run
4.4.3.7) Replacement of Existing MS Railings with FRP Material railing.
The scope covers design verification, supply, dismantling, fabrication, installation,
testing, and commissioning of FRP (Fiber Reinforced Plastic) railings, gratings,
structural platforms, supports, and associated accessories in place of existing
corroded/deteriorated MS (Mild Steel) railings and platforms.
The work shall be executed in operating plant conditions with minimum interruption
to existing facilities and in compliance with all applicable safety standards, statutory
regulations and plant operating requirements.
A). Detailed Scope of Work
A.1) Site Survey & Engineering
The contractor shall carry out detailed site survey, measurement verification, and
condition assessment of existing railings and supports, and fastening arrangements
before commencement of work.
The scope shall include:
Detailed measurement and preparation of GA drawings.
Structural adequacy check of existing support structures.
Preparation of fabrication and installation drawings.
Preparation of dismantling methodology and erection methodology.
PUR-F-10 ET-296
Submission of design calculations for FRP members and support systems.
Preparation of safety plan, work procedure, and risk assessment.
A.2) Dismantling of Existing MS Railings & structure
The contractor shall dismantle existing corroded/damaged MS railings, gratings, toe
plates, support members, and fastening hardware.
The dismantling work shall include:
Safe removal without damaging adjoining structures/equipment.
Cutting, shifting, segregation, and disposal/stacking of scrap materials as
instructed by the EIC.
Temporary barricading and restoration of safe access during execution.
Removal of rusted anchor bolts and damaged supports where required.
A.3) Supply & Installation of FRP Railings
The contractor shall supply and install corrosion-resistant FRP handrail systems
Vertical posts
Kick/toe plates
Base plates and clamps
Fasteners and accessories
Typical Technical Requirements
Material: Pultruded FRP sections
Resin System: Isophthalic polyester / Vinyl ester resin
UV protection: UV-resistant surface veil
Flame spread rating: Maximum
Colour: Safety yellow / as approved by owner
Handrail height: Minimum 1100 mm
Toe plate height: Minimum 100 mm
Design load: As per applicable industrial platform standards
All fastening hardware shall be SS-304/SS-316.
Contractor Shall Provide:
Manufacturer test certificates
Material composition & data sheets
Quality assurance documentation
A.4) Structural Repair & Modification
The contractor shall carry out necessary modifications and strengthening of existing
support structures wherever required for proper installation of FRP systems.
The scope may include:
PUR-F-10 ET-296
Replacement of damaged support members
Fabrication of new support brackets
Drilling, cutting, welding, and alignment work
Surface preparation and touch-up painting of modified MS supports
B). Design Criteria & Standards
All materials, design, fabrication, and installation shall confirm to the latest editions
of applicable standards including but not limited to:
ASTM D635 – Flame resistance
ASTM D638 – Tensile properties
ASTM D790 – Flexural properties
ASTM E84 – Surface burning characteristics
OSHA industrial platform and handrail requirements
BS/IS standards applicable for industrial platforms and access systems
Manufacturer’s design recommendations
FRP systems shall be suitable for:
Outdoor operation
Corrosive industrial environment
High humidity and thermal exposure
Long-term UV exposure
C). Quality Assurance & Inspection
The contractor shall implement a documented QA/QC system covering:
Raw material certification
Dimensional inspection
Visual inspection
Load/strength verification
Fastener quality verification
Installation inspection
Final alignment and finishing checks
The following documents shall be submitted:
Material Test Certificates (MTC)
FRP manufacturer data sheets
Inspection reports
Calibration certificates
Warranty certificates
As-built drawings
Owner/Consultant inspection approval shall be obtained prior to dispatch and
D). Safety Requirements
PUR-F-10 ET-296
The contractor shall strictly comply with plant safety regulations.
The scope shall include:
Work permit compliance
Height work safety arrangements
Scaffolding and lifeline systems
Barricading and warning signage
Fire and electrical safety precautions
Housekeeping during and after execution
The contractor shall be fully responsible for safety of manpower, equipment, and
nearby operating systems.
E). Testing & Commissioning
The contractor shall carry out:
Physical inspection of all installed FRP systems
Stability and rigidity checks
Fastener tightness verification
Alignment verification
Joint and support inspection
Load adequacy checks where required
Any defects observed during inspection shall be rectified by the contractor at no extra
F). Completion Deliverables
The contractor shall submit the following after completion:
As-built drawings
Final measurement sheets
Test certificates
Warranty documents
Inspection clearance reports
Completion report
4.4.3.8) Inspection& Quality Control
All materials shall be inspected before installation.
Installation alignment and levels shall be checked periodically during erection.
Any damaged fill media, nozzles or eliminators shall be replaced immediately.
Contractor shall maintain proper QA/QC records during execution.
Stage-wise inspection shall be offered to Owner/EIC.
4.4.3.9) TESTING& COMMISSIONING
PUR-F-10 ET-296
A.1). Pre-Commissioning Checks
The contractor shall carry out:
Alignment checks.
Tightness checks.
Water flow checks.
Spray pattern checks.
Support inspection.
A.2). Trial Run
The contractor shall conduct:
Continuous operation trial.
Verification of:
o Water distribution
o Structural vibration
4.5) Post-Modification Testing Scope
After completion of repair/modification works and replacement of new systems,
contractor shall carry out comprehensive post-testing and performance validation.
4.5.1) Mechanical & Installation Inspection
Inspection and verification of:
Water distribution piping alignment
Nozzle orientation and locking
Fill installation quality
Support integrity
Tightness and leakage checks
Cleanliness of cooling tower internals
4.5.2) Pre-Commissioning Activities
Contractor shall carry out:
System flushing and cleaning
Removal of debris and loose materials
Functional checks of nozzles and piping
Verification of water flow distribution
Inspection of all fasteners/supports
4.5.3) Post-Performance Thermal Testing
PUR-F-10 ET-296
Performance testing shall be conducted after stabilization of operation under design
operating conditions.
Parameters to be measured:
Hot water temperature
Cold water temperature
Ambient wet bulb temperature
Cooling range
Cooling approach
Circulating water flow
Water loading
Airflow condition
Water distribution uniformity
Performance Evaluation:
Contractor shall demonstrate improvement in:
Cooling tower effectiveness
Thermal efficiency
Heat rejection capability
Cooling range performance
Reduction in approach temperature
Uniformity of cooling
4.5.4) Guaranteed Performance Verification
Contractor shall demonstrate and guarantee achievement of specified performance
improvements including:
a) Thermal Performance
Improved thermal efficiency of cooling tower
Improved effectiveness compared to pre-modification condition
Reduction in approach temperature
Improved heat transfer efficiency
b) Hydraulic Performance
Uniform water distribution over complete fill area
Elimination/reduction of dry spots
Improved spray pattern
c) Drift & Water Loss Reduction
Reduced drift losses
Reduced splash and carryover losses
Controlled overflow conditions
Reduced water wastage
d) Operational Stability
Stable flow operation
No abnormal vibration or structural instability
PUR-F-10 ET-296
No excessive pressure drop
No flooding/choking of fill sections
4.5.5). PGT Duration
Performance testing shall be conducted under stabilized operating conditions for
specified duration as approved by Owner.
4.5.6). Performance Comparison Study
Contractor shall prepare comparative analysis between pre-test and post-test
performance including:
Design Pre- modification
PARAMETER Improvement
Data modification
Effectiveness 69% More than 65%
Drift Losses 0.05% - 0.1%
Distribution ≥ 95%
4.5.6) Testing Instruments
Contractor shall provide calibrated instruments including:
Temperature sensors/RTDs
Digital thermometers
Pressure gauges
Drift measurement instruments
Data logging systems
Valid calibration certificates shall be submitted before testing.
4.5.7) Acceptance Criteria
The modified NDCT shall be considered acceptable only after:
Successful completion of post-performance test
Achievement of guaranteed thermal performance
PUR-F-10 ET-296
Demonstration of improved cooling tower effectiveness
Stable hydraulic and thermal operation
Reduction in drift and water losses
Acceptance by Owner/EIC
4.5.8) Documentation & Deliverables
Contractor shall submit:
Pre-test methodology
Post-test methodology
Calibration certificates
Raw test data sheets
Performance calculations
Comparative performance analysis
Final performance guarantee report
Recommendations for operation & maintenance
Final test certificates and commissioning report
4.5.9) Contractor Responsibility
Contractor shall arrange:
Testing manpower and specialists
Measuring instruments
Temporary arrangements required for testing
Data collection and analysis
Safety arrangements during testing
Coordination with plant operation team
All costs associated with testing, retesting and performance demonstration shall be
included in contractor scope
5.0). QUALITY ASSURANCE & QUALITY CONTROL
The contractor shall Establish &maintain:
QA/QC procedures.
Material inspection records & traceability.
Stage-wise inspection records.
Installation checklists.
Testing procedures.
Test certificates.
Calibration certificates.
Stage inspection records.
All works shall be subject to inspection and approval by Owner/Consultant.
6.0 SAFETY REQUIREMENTS
PUR-F-10 ET-296
The contractor shall comply with:
Indian Electricity Rules.
OSHA/IS safety requirements.
Plant safety regulations.
The contractor shall provide:
Scaffolding certification
Fire protection arrangements
No work shall commence without approved safety procedures
7.0 DOCUMENTATION
The contractor shall submit:
Before Commencement
Work methodology
Detailed schedule
Engineering drawings
Design calculations
Material specifications
During Execution
Daily/weekly/monthly progress reports
Inspection reports
Material certificates
After Completion
As-built drawings
Test certificates
Performance test reports
Guarantee certificates
Completion dossier
8.0 GUARANTEE / DEFECT LIABILITY PERIOD
PUR-F-10 ET-296
The contractor shall provide a defect liability/guarantee period of minimum
months from the date of successful commissioning & completion of PG test.
Any defects arising during the guarantee period shall be rectified by the contractor at
The contractor shall provide guarantee for:
Thermal performance.
Material quality.
Water distribution efficiency.
9.0 COMPLETION CRITERIA
The work shall be considered complete after:
Successful completion of installation.
Stable operation.
Achievement of guaranteed thermal performance.
Submission of all documentation.
Final acceptance by Owner.
10.0 EXCLUSIONS (IF ANY)
The following items may be excluded unless specifically mentioned:
Major RCC rehabilitation.
Cooling water pump replacement.
Major electrical system modification.
Major shell repair.
Civil foundation extension outside NDCT area.
Plant shutdown beyond agreed duration.
11.0 APPLICABLE CODES & STANDARDS
Works shall conform to latest editions of:
CTI Standards
ASTM Standards
ISO Standards
Plant safety standards
IEC Standards
Relevant environmental regulations
11.0 TIME SCHEDULE
The contractor shall complete all activities within the stipulated contract period
PUR-F-10 ET-296
Works execution
Commissioning
A detailed bar chart/PERT/CPM schedule shall be submitted.
12.0 CONTRACTOR RESPONSIBILITIES
The contractor’s scope shall be on complete turnkey basis including:
Loading/unloading
Transportation
Testing & commissioning
Disposal of dismantled scrap as per owner instruction
All tools, tackles, consumables, manpower, and supervision
Any item not specifically mentioned but required for safe, complete, and satisfactory
execution of the work shall be deemed included in the contractor’s scope
Also the contractor shall be fully responsible for:
Safety of personnel and equipment.
Quality of workmanship.
Material handling
Timely completion.
Performance guarantees.
Compliance with statutory regulations.
Coordination with plant authorities.
13.0 COMPLETION CRITERIA
The work shall be considered complete after:
Completion of all repair/modification works.
Successful testing and commissioning.
Achievement of guaranteed performance.
Submission of all documents.
Acceptance by Owner.
PUR-F-10 ET-296
14.0 TECHNICAL DELIVERABLES
The contractor shall submit:
Detailed engineering package
Repair methodology
Structural analysis report
Thermal design calculations
Material specifications
Inspection and test reports
Final completion report
As-built drawings
PUR-F-10 ET-296
GENERAL TERMS & CONDITIONS FOR CONTRACTOR
a) The contractor shall be fully responsible for complete execution of the work in
accordance with tender specifications, drawings, technical requirements and
instructions of Engineer-in-Charge (EIC).
b) The contractor shall visit the site before submission of offer and satisfy
himself regarding:
Site conditions.
Accessibility.
Existing structures and systems.
Working constraints.
Availability of utilities.
Safety conditions.
Storage space and approach roads.
No extra claim arising due to ignorance of site conditions shall be entertained
c) The work shall be executed in running plant conditions and contractor shall
plan the work accordingly without affecting nearby operating systems.
d) Contractor shall arrange all required:
Skilled/unskilled manpower.
Supervisors and engineers.
Tools & tackles.
Lifting equipment.
Safety equipment.
Scaffolding/staging.
Temporary power distribution.
Illumination and other resources required for successful completion of
2.0 SCOPE RESPONSIBILITY
a) The scope of work shall include dismantling, shifting, supply, transportation,
unloading, erection, storage, handling, erection, alignment, installation, testing
and commissioning of all items covered under the contract
b) Any minor item/accessory required for successful completion of work but not
specifically mentioned in BOQ/specification shall be deemed included in
contractor’s scope without extra cost.
c) Contractor shall verify all dimensions and interfacing details at site before
fabrication or installation.
d) Any mismatch observed at site shall immediately be brought to notice of
Engineer-in-Charge before proceeding further.
PUR-F-10 ET-296
e) Contractor shall be fully responsible for safe handling and protection of
existing structures and nearby equipment during execution
3.0 DEPLOYMENT OF MANPOWER
a) Contractor shall deploy experienced, qualified and competent manpower for
execution of work.
b) The Engineer-in-Charge may ask for removal of any worker/supervisor found:
Indisciplined.
Violating safety rules.
The contractor shall immediately replace such personnel.
c) Contractor shall maintain attendance records and statutory registers as per
a) All materials supplied shall be new, unused and of approved quality.
b) Materials shall conform to relevant IS/BS/ASTM/CTI/DIN standards and
approved specifications.
c) Test certificates and inspection reports shall be submitted whenever required
by Engineer-in-Charge.
d) Rejected or damaged materials shall immediately be removed from site by
5.0 QUALITY OF WORKMANSHIP
a) All works shall be executed using standard engineering practices and good
b) Contractor shall follow approved drawings, QAP and ITP during execution.
c) Any defective workmanship observed during execution or guarantee period
shall be rectified / replaced by contractor at no extra cost.
d) Inspection by GSECL shall not relieve contractor from responsibility of quality
and performance.
5.0 SAFETY REQUIREMENTS
a) Contractor shall strictly comply with all GSECL safety rules, regulations and
permit systems.
b) Work shall not commence without valid work permit from concerned
c) Contractor shall provide mandatory PPEs including:
Safety helmet.
Safety shoes.
PUR-F-10 ET-296
Reflective jacket.
Full body safety harness for height work.
d) Safety nets, barricading, caution boards and illumination shall be provided
wherever required.
e) All lifting tools, tackles and scaffolding shall be tested and certified.
f) Contractor shall be fully responsible for any accident, injury, loss of life or
property damage during execution of work.
g) Any penalty imposed by statutory authority or GSECL due to safety violation
shall be recovered from contractor.
6.0 MATERIAL HANDLING & STORAGE
a) 6.1 Contractor shall arrange proper transportation, unloading, shifting and
storage facilities of materials at site.
b) 6.2 Materials shall be stored systematically and shall be protected against:
Corrosion / deterioration
Mechanical impact.
c) Damaged materials shall not be used and shall be replaced by contractor at
7.0 HOUSEKEEPING
a) Contractor shall maintain proper housekeeping throughout execution period.
b) Scrap, debris and unused materials shall be removed daily from work area.
c) Work area shall be cleaned properly after completion of work.
d) Unused materials shall be shifted to designated location as instructed by
Engineer-in-Charge.
8.0 POWER & WATER
a) Power and water may be provided by GSECL at one point subject to availability
b) Further distribution arrangements including cables, hoses, DBs, lighting
arrangements and safety protection shall be in contractor’s scope.
c) Contractor shall ensure safe electrical connections with proper earthing and
9.0 TOOLS, TACKLES & EQUIPMENT
a) Contractor shall arrange all required:
Welding machines.
Gas cutting sets.
Grinding machines.
Drilling machines.
PUR-F-10 ET-296
Lifting tools.
Chain pulley blocks.
Measuring instruments.
b) All tools and equipment shall be maintained in safe working condition.
c) Calibration certificates for measuring instruments shall be produced whenever
asked by Engineer-in-Charge.
10.0 QUALITY OF WORKMANSHIP
a) All works shall be carried out as per approved drawings, specifications and
standard engineering practices.
b) Inferior workmanship shall not be accepted.
c) Any defective work observed during execution or guarantee period shall be
rectified by contractor free of cost.
d) Contractor shall follow approved Quality Assurance Plan (QAP) and Inspection
& Test Plan (ITP).
11.0 INSPECTION & APPROVAL
a) All materials and works shall be subject to inspection by Engineer-in-Charge.
b) Inspection or approval by GSECL shall not relieve contractor from
responsibility for quality and performance.
c) Contractor shall offer work for inspection at appropriate stages.
12.0 SUPPLY & WORK EXECUTION AND COMPLETION SCHEDULE
a) Validity of work order: – 18 months from the Date of issue LOI.
b) SPECIFIC TIME LIMIT –
1) Supply Part – Tender Material to be supply within 03 months from the
date of issue of LOI.
2) Works part – Time limit for work completion is within 60 Days as per date
of commencement given by the EIC (AS per schedule shutdown work
Mobilization: Contractor shall have to mobilize sufficient men power with all kind
of resources prior to shutdown schedule upon instruction given either by
telephonically / Email / Post to commence the work.
Contractor shall execute work as per site requirements and as per approved plant
shutdown schedule. The period of shutdown will be given for per unit - 45 to
days from the date of shutdown along with PG test.
c) Contractor shall deploy sufficient manpower and resources to complete work
within stipulated time.
d) Contractor shall submit detailed work schedule/bar chart before
commencement of work.
e) In case of delay attributable to contractor, GSECL reserves right to impose
liquidated damages as per contract conditions.
f) Contractor may be required to work in shifts, holidays or round-the-clock to
meet completion schedule without extra cost implication
PUR-F-10 ET-296
13.0 TESTING, COMMISSINING AND TRIAL RUN
a) Upon award of the contract (i.e., issue of the Letter of Intent), the contractor
shall depute the required technical personnel within 07 days from the date of
intimation by the Engineer-in-Charge (EIC), GTPS for inspection, assessment,
pre-commissioning checks and testing and planning of the repair and
maintenance activities in line with Shutdown schedule.
b) Prepare the Pre-commissioning report and accordingly planning the supply &
execution of various works in line with schedule planning of shutdown.
c) After completion of the repair and maintenance works as per pre-
commissioning check reports, the contractor shall carry out all necessary
inspections, checks, functional tests, and trial runs to verify the satisfactory
performance of the repaired/maintained equipment/system.
d) Any defects, deficiencies, or abnormalities observed during inspection, testing,
or trial run shall be rectified by the contractor at no additional cost, and the
equipment/system shall be retested until satisfactory performance is achieved.
e) The repaired/maintained equipment/system shall be offered for final
inspection and acceptance in the presence of the Engineer-in-Charge. The
work shall be considered complete only after successful testing/trial run and
acceptance by the Engineer-in-Charge.
f) The contractor shall submit a brief completion report indicating the works
carried out, test results, and observations, if required by the Engineer-in-
14.0 GUARANTEE / DEFECT LIABILITY
a) Contractor shall guarantee all materials and workmanship for a period of
months from the date of successfully completion of PG test.
b) Any defect/failure during guarantee period shall be rectified / replaced by
contractor free of cost.
15.0 STATUTORY COMPLIANCE
a) Contractor shall comply with all applicable:
Factory rules.
PF/ESIC provisions.
Safety regulations.
Environmental regulations.
b) Contractor shall maintain valid insurance policies including:
Workmen compensation.
Third party liability.
Insurance for manpower and equipment.
c) Contractor shall indemnify GSECL against all legal/statutory liabilities arising
out of contractor’s activities.
16.0 SECURITY & GATE PASS
a) Contractor shall arrange gate passes for manpower as per CLIMS procedure
and vehicles and materials as per GSECL rules & regulation and procedures.
PUR-F-10 ET-296
b) Verification records of manpower shall be submitted whenever required.
c) Contractor personnel shall follow plant security rules strictly.
Contract Labour Information Management System (CLIMS):
GSECL has developed a Contract Labour Information Management System
(CLIMS) — a comprehensive digital platform designed to manage all activities
related to contract labour transparently and efficiently.
The primary objectives of CLIMS are to save time for both agencies and GSECL
personnel, to ensure full legal and regulatory compliance and to reduce the
operational burden on agencies, allowing them to focus on their core activities. To
ensure the successful implementation and operation of CLIMS, the following
guidelines are hereby issued.
1) CLIMS is a web-based system that can be accessed by agencies from any
location using a desktop, laptop, or mobile device.
2) To begin using the system, agencies must register by entering their EPO (E-
Urja Order) number. All other necessary details are automatically fetched from
the E-Urja system.
3) The issuance of gate passes for contract labour is managed entirely through
CLIMS. Agencies can generate and track gate passes within the system.
4) In order to enable gate pass issuance, agencies are required to input and
upload the necessary details of their contract labourers into the system.
5) Once the required information is submitted, the gate pass approval process is
initiated and managed through the system. The request automatically moves
through the predefined workflow levels. Agencies can monitor the real-time
status of their gate pass applications via CLIMS.
6) Upon completion of all required approvals within the system, the gate pass is
issued to the agency.
B. Attendance and wages of workers:
1) Once contract workers gate passes are approved in the system, they are
required to be registered in Bio-Metric/Face Reader Punching machines by
2) The attendance of all contract workers can be monitored and maintained
through CLIMS by contractors.
3) Access to data of Bio-Metric is given to agencies. It should be the duty of
agencies or his supervisor to ensure the supply of specified number of
manpower and to ensure their Bio-Metric punching and reporting at the
location of work.
4) Attendance register and wage register of the worker will be generated by
CLIMS from the login of agency only.
C. Compliance to various labour laws:
1) All the contractors have to comply various labour laws and they shall submit
the attached Declaration-cum Indemnity Bond before starting of work. This
Bond may also be made part of ensuing tenders/contracts.
PUR-F-10 ET-296
2) Contractors shall upload the CLIMS generated previous month attendance
sheet, wage register duly signed by workers, wage bank statement, ECR copy,
PF Challan and Remittance slip.
3) The said submitted documents in CLIMS will go to user department, after
verification of completeness of documents, user department will forward it to
HR Department for further verification and approval.
4) If the documents are complete, HR Department will approve in CLIMS and
send to Account Department for further process of bill.
5) If non-compliance is found in submitted documents, it will be returned to user
department in CLIMS with specific remarks and user department will forward
it to contractor for compliance. In such cases, 75% of the bills may be released
subject to a maximum ceiling of 20% of the contract values. Such system of
payment shall be allowed only for 3 monthly Running Accounts (RA) bills
(Maximum cumulative amount up to 20% of the contract value) of the
contractor in a period contract (AMC) of 12 months or 6 RA bills in a period
contract (BMC) of 24 months if there is non-compliance. All other RA bills and
specifically final bill shall not be processed ifthe previous & current
compliances are not made by contractor. No such relaxation will be granted for
non-periodic, one time or overhauling type contract.
D. Special Case:
In case of work order issued for expert services to PSU or OEM/OES following
procedure may be adopted.
1) If officers / specialized manpower / expert Engineers from Govt. / Semi Govt.
Companies / PSUs / OEM / OES /foreign experts are deployed for short-term,
specialized, or adhoc technical / consultancy services (e.g., commissioning.
maintenance, consultancy or inspections), concerned Engineer In-Charge (EIC)
shall certify the same.
2) The EIC must obtain following documents from the concerned Govt. / Semi
Govt. Companies / PSUs/ OEM /OES etc:
I. Declaration cum undertaking (As per Annexure A) that visiting experts
are their regular employees with documentary proof; and
II. Declaration towards compliance of applicable labour laws.
3) The above documents shall be submitted along with the bill / Invoices by EIC
to HR department for the purpose of HR clearance in lieu of the procedure at
Clause -C above.
17.0 INSURANCE & STATUTORY COMPLIANCE
a) Contractor shall comply with:
PF & ESIC rules.
Environmental regulations.
Safety regulations.
b) Contractor shall maintain valid:
Workmen compensation insurance.
Third-party liability insurance.
Equipment insurance.
PUR-F-10 ET-296
c) Contractor shall indemnify GSECL against statutory/legal liabilities arising
due to contractor activities.
18.0 MEASUREMENT & BILL PAYMENT CONDITIONS
Party has to accept payment terms as per GSECL rules only i.e. as per actual work
done. NO ADVANCE payment will be allowed.
For SUPPLY Part:
Party shall have to accept GSECL Payment Terms and Conditions as follows…
1) 60 % amount of supply part on receipt of Material for cooling tower as certified
by EIC and raise the invoices/bills accordingly. As per A/T conditions, amount
of GST and applicable cess will be kept under retention till submission of
documentary proof of payment of GST or till reflection of payment of GST
pertain to respective bill amount in GST Return for concern Order after due
2) Further 20% shall be released after successful erection of supplied materials
in Cooling tower after due verification & certification given by the concerned
GSECL Engineer in-Charge.
3) Further 10% shall be released after successful performance testing &
commissioning of cooling tower after due verification & certification given by
the concerned GSECL Engineer in-Charge.
4) Balance 10% shall be released after completion of defect liability period i.e.
month from the date of successfully completion of PG test.
90% amount of works part paid on actual work done on satisfactory
Completion of job work, jointly recorded and certified by the Engineer-in-
charge and the contractor will be paid 90% amount of actual work
Balance 10% shall be released after completion of defect liability period i.e.
month from the date of successfully completion of PG test.
Payment will be released within 30 days from receipt of recorded bill in all
aspects .However amount of GST and applicable Cess Will be kept under
retention till Submission of Documentary Proof of Payment of GST or till
reflection of Payment of GST Pertain to respective bill amount in GST Return
after due Verification
Contractor shall submit running account (RA) bills along with measurement
sheets, work progress details, test certificates, and other supporting
documents as required by Engineer-in-Charge.
The rates quoted by contractor shall be deemed to include cost of all materials,
labour, transportation, loading/unloading, tools & tackles, scaffolding,
consumables, testing, taxes & duties, insurance, supervision, safety
arrangements, and all incidental expenses required for completion of work.
No separate payment shall be made for transportation, loading/unloading,
scaffolding, temporary supports, consumables, or minor civil repair works
unless specifically mentioned in schedule of items.
Payment shall be released only after satisfactory inspection and certification of
work by Engineer-in-Charge.
Deduction of statutory liabilities such as GST-TDS, Income Tax, Labour Cess,
or any other applicable deductions shall be made as per prevailing rules.
Contractor shall submit GST compliant tax invoice along with each bill.
PUR-F-10 ET-296
Final bill shall be processed only after:
Completion of entire work
Submission of all documents
Clearance of punch points
Submission of as-built drawings and test reports
Successful testing and commissioning
Security Deposit/Retention amount shall be deducted and released as per
tender/contract conditions.
In case of defective or incomplete work, Engineer-in-Charge may withhold part
or full payment till rectification/completion of work.
No escalation shall be payable unless specifically mentioned in contract
Any recovery towards damages, penalties, safety violations, material shortages,
or non-compliance of contract conditions shall be deducted from contractor’s
The contractor shall be responsible for payment of wages, statutory dues, PF,
ESIC, insurance, and other liabilities related to deployed manpower.
Owner reserves the right to recover any excess payment or financial loss
observed during execution or after completion of work from contractor’s
pending bills or security deposit.
19.0 PENALTY & RECOVERY & LIQUIDATED DAMAGES (LD)
a) Cost of damages caused to existing equipment / structures due to contractor
negligence shall be recovered from contractor.
b) Recovery shall also be made for:
Safety violations.
Poor housekeeping.
Delay in completion without any genuine reasons / unforeseen
conditions, the delay penalty will be recovered at the rate of ½% per
week and maximum 10% of total contract value.
Material wastage due to negligence.
c) If contractor fails to complete work within stipulated period, LD shall be
imposed as per GSECL norms. LD Charge shall generally be:
0.5% of contract value per week of delay, subject to maximum 10% of
contract value.
d) Recovery of LD shall not relieve contractor from contractual obligations.
20.0 TERMINATION OF CONTRACT
a) GSECL reserves right to terminate the contract in case of:
Poor progress.
Unsafe practices& frequent Safety violations.
Repeated quality failures.
Violation of contract conditions.
PUR-F-10 ET-296
Abandonment of work.
Non-compliance with instructions.
b) Risk & cost consequences arising due to termination shall be borne by
21.0 DOCUMENT SUBMISSION
Contractor shall submit:
Material test certificates.
Inspection reports.
Calibration certificates.
Warranty certificates.
As-built drawings.
Completion report.
Safety documents.
22.0 FINAL HANDING OVER
a) Contractor shall hand over the completed system in clean and safe condition.
b) Contractor shall hand over the system after:
Completion of all works.
Removal of debris/scrap.
Submission of required documents.
Successful trial operation and acceptance by GSECL
c) Final acceptance shall be subject to satisfactory performance of modified
Chief Engineer (G)
GSECL: Gandhinagar TPS
Dated seal & signature of
Bidder/Contractor
PUR-F-10 ET-296
GENERAL CONDITIONS OF CONTRACT
1. The contractor shall at their own expense make all necessary provision for
housing water supply and sanitary arrangement for their employee as well as for
works and shall pay direct to the authorities concerned all rates and taxes.
2. The contractor shall make their own arrangements for the necessary approach
road, for transport of their materials and be responsible for the Compensation on
account of damage to crop on Corporations’ property.
3. All the royalty charges octroi other duties will be paid by the contractor and no
extra could be claimed on this account.
4. The organization will supply articles at the place and rates mentioned in
schedule ‘A’ of Tender form. In case of the materials issued either through or
with the recommendation of this organization it will be absolutely necessary for
the contractor to maintain a correct and honest record of the daily consumption
of the said materials/with inside particular reference to the work during the day.
The Engineer-in-charge of this department or his authorized agent shall have the
right to inspect and check the stores containing these materials and the account
for these materials shall be presented for inspection whenever asked for by them.
Every facility shall be afforded by the contractors for all these inspections
Engineer-in-charge will supply the materials in any quantity as deemed fit.
5. Godown of sheds hired or constructed for storage of controlled materials and
more/ particularly of cement shall be such as would prevent the materials from
getting damages in any way.
6. It will be absolutely incumbent of the contractors to have on the site of work only
such of the materials as have been dully passed by the Engineer-in-charge
Materials that have been rejected must on no account be allowed to remain on
the side and in spite of written order to do so any such rejected material is on
the site beyond a period of 48 hours, notice the Engineer-in-charge shall have
the right to remove it at the risk and cost of the contractor and even destroy it.
7. It must be distinctly understood that the conditions of the contract and of claims
in respect of extra work will not be allowed, unless the works to which they relate
is clearly without the spirit and meaning of the specifications or unless such
work are ordered in writing by the Engineer-in-charge and claimed for in
specified manner.
8. On completion of the work, the site shall be cleared by the contractors within the
stipulated period, and ground brought to original state and they shall not be
entitled for any extra claim on this account.
9. DAMAGE CAUSES TO WORKS:
The work whether fully constructed or not, and all materials, machinery plant
tools, temporary building and other things connected there shall be at the risk
and in the sole charge of the contractor until the works have been delivered,
completed to the Engineer- in-charge and certificate from him to that effect
obtained until such delivery the contractor shall at their own cost take all the
precautions reasonably necessary to keep all the aforesaid works materials
machinery, plant, tools, temporary building and other things connected with the
work, free from any loss or damage and in the event to the same or any part
there of being lost or damage shall from with within possible speed, reinstate and
make good such loss or damage at contractor’s own cost.
10. Supply of controlled articles will be invariably recommended after the actual
requirements have been carefully scrutinized. In the event of any such materials
remaining in surplus in charge of the contract, on account of some modifications
either in the design or changes in construction or any other reason will be
returned to the department.
11. There will be generally no objection on the component parts of the works being
PUR-F-10 ET-296
given over to responsible sub contractors but it must be borne in mind that this
department would under no circumstances recognize these sub contractors and
responsibility of executing the work in accordance with the condition of the
contract will entirely rest on the main contractors. The main contractors will
therefore always have the very responsible member preferably a technical hand,
present on the works with power to sign all work order issued on the site of work
and to take requisite actions in the interest of very efficient execution of works.
12. With a view to ensure rapid progress on the works purchaser may store at work
sites certain quantities of the materials such as cement etc. and it will be
incumbent on the tender to purchase these materials, at the rates mentioned in
schedule ‘A’ of tender form for supply of necessary articles, all necessary help
will be tendered but in must be clearly understood that the purchases does not
accepted and responsibility for the delay that may be cause in their supply on
account of circumstances beyond the purchaser’s control.
13. Contractor will be asked to present the sample of materials and the approved
sampled will be preserved at the site of work and no change in the approved
sample will be allowed without the written permission of the Engineer-in-charge.
14. Contract will have to communicate the name of his authorized agent who shall
be presentation the works and shall be authorized to sign the materials
requisitions receive instruction given verbally, or on the order book on behalf of
the contractor.
15. The materials issued to the contractor as per schedule ‘A’ of the tender shall not
be removed from the work and all surplus material at the end of the works which
is considered serviceable shall be returned to the organization even the
unserviceable material shall be removed only with the prior permission to the
EIC in writing.
16. The contractor will have to sign the conditions of the contract and execute the
agreement, send the list of previous works executed solvency certificates and pay
up the security deposits, failing to that the tender will be rejected and earnest
money deposit will be forfeited. The value of the stamp paper and stamp duty
charges shall be borne by the contactor.
17. The contractor must arrange for all transport of materials weighting of material
issued at department stores and all such cost include in the rates of schedule
18. The competent authorities can delete to any items in the schedule ‘B’ of the
tender order if they feel that the items is not essential to be executed.
19. A schedule of quantities is included in the tender document it shall definitely
understood that the Corporation does not accept any responsibility for the
correctness or complication of this schedule-B. The tender documents shall be
written legibly and free from grouser, over written on conversion of figures
correction where unavoidable shall be made by crossing out initialing dating and
rewriting both in figures and in words in case of my discrepancy in figures the
price quoted in words shall prevail.
20. This notice to tenders shall form a part of the contract.
21. The entire work is to be completed within the stipulated time limit from the date
of LOI. The contractor will not be eligible for any extra for the idle period of work
or waiting period that may be required to suit other considerations and no claim
for compensation on account of such will be considered. However in case or
delay due to circumstances beyond the control contractor either in date of
commencement or due to waiting during construction extension time may be
considered for completion of work.
22. In case contractor is unable to account for full quantity of materials issued to
him from the department stores, recovery will be effected from him at cost rates
or market rates prevailing at the time of issue whichever is higher, plus 15% to
cover Corporation’s departmental supervision charges for all material
unaccounted for.
PUR-F-10 ET-296
23. Bill shall be submitted by the contractor monthly on or before the date fixed by
the EIC, for all works executed in the previous months.
24. SUPPLY OF WATER AND ELECTRICITY:
Water supply for Execution of work will be provided at FREE of Cost by GSECL
at only one point nearest to the working site (Around 100mtr area) and bidder
shall have to take tapping from the existing water supply line with proper
isolation valve. After completion of work, bidder shall have to provide blank to
tapped connection before left the GSECL, GTPS site.
Electric supply is required the contractor shall be given Free of cost by GSECL.
(Applicable to CIVIL WORKS only).
25. Should this tender be accepted, I/We have agreed to abide by and full fill all the
terms and provision of ‘Tender and Contract of works’ as applicable, and in
default thereof, to forfeit and pay to the Corporation the some of money due.
26. The work will have to be carried out in co ordination with other Agencies on the
same site on account of this in case the contractor has to stop or delay his works
for same time he will not claim anything extra only Corporation may consider to
give suitable extension in time limit if necessary on such account.
27. Any disputes arising out of the contract if not settled mutually, than the same
shall be settle by Gujarat Public Work Arbitration Tribunal act-1992.
28. Following clauses of this section are not applicable to this contract i.e.
The following are the major obligations to be fulfilled by the Contractors as per
the Contract Labor (R&A) Act 1970 and rule mentioned there under:
1. License to be obtained before starting the Work where number of contract
laborers in Fifty or more.
2. Payment to contract laborers has to be made in presence of IRO/LWO. Wages
rates for contract laborers are applicable as per the terms and conditions of the
license. The contractor shall have to pay wages to workers as notified by
Government of Gujarat., from time to time
3. Every contractor shall have to maintain the muster roll and wages register in
respect of his contract labor.
4. Every contractor is required to issue employment card, wages slip and
attendance card to their laborers.
5. The contractor has to maintain the register No. 13 containing details of contract
labors employed by him.
6. Earned leave register/ card as per the Factories Act. And Rules.
7. Other registers required under Contract Labor Rules and the Factories Act. And
8. Every contractor shall have to obtain insurance policy in respect of the contract
labors engaged by him to cover them under workmen’s Compensation Act.
9. To send half yearly return to licensing officer as per Rule 82 (1) as per schedule
10. Before starting the work as per the contract awarded to him, he should make
arrangement to enter into the agreement in the prescribed format on the stamp
paper as applicable. Before fulfilling the above requirement the contractor is
instructed not to start the work. The responsibility will be on his head in case he
11. Contractor should posses separate P.F. code on their firm, name otherwise their
offer may must be considered.
All the contractors are informed to adhere to the rules and regulations applicable
to them, particularly in respect of the laborers engaged by them, the contractor
not fulfilling the obligations will not be allowed or continue with work/ not be
PUR-F-10 ET-296
held qualified to carry out the work at Gandhinagar TPS – Ta.-Gandhinagar.
It has been directed by our CO that, no new labor contract be entrusted to any
agency without getting prior approval from CO. Further the existing contract, on
their expiry, may not be extended without approval from HO, Vadodara.
In light of the instruction conveyed by HO, it is necessary to check up the
following documents of each and every contractor before awarding the contract
to these contractors. For preliminary checking of valid contractors, the following
documents are required to be checked by the concern DE/EE/SE. On their
checking the same and by recommending the number of labors, gate pass will be
issued by the Sr. Security officer. But before awarding and finalizing any
contracts, following information must reach to IRO for his confirmation.
1. The contractor should not allowed to engage fifty or more contract labors without
initiating to obtain the labor license under the Contract Labor Act of
Commissioner of Labour as per the contract labour (Regulation and Abolition)
Act. (The same number i.e. fifty or more includes Supervisor and other staff).
2. Number of days of the contract should be informed first before allowing the
contract to start. The Contractor also must obtain group insurance under WC
Act before starting the work.
3. The contract laborers must be paid minimum wages as per notification issued by
competent authority under the said Act from time to time upon issuance of
Circular by Chief Engineer, GTPS. The above instruction must be followed
scrupulously to avoid labour liabilities under Contract labor Act.
“GENERAL SAFETY RULES / NORMS” TO BE OBSERVED BY THE
All the contractors working in Gujarat State Electricity Corporation Limited
Factory like Coal/Lignite/Gas/Hydro/Pumping Station shall have to strictly
observe the following Safety Rules. Concern principle contractors are responsible
for informing & observance of these rules by their supervisors/contract workers
as well as the owner/supervisors/ workers of sub-Contractors engaged, if any,
by them for the work contract awarded to them. Prior to commencement of the
work, Contractor shall have to submit a written assurance on their letterhead to
the concerned Sectional Head / Engineer-in-charge that they have thoroughly
gone through these Rules, have educated their employees / workers of their sub
contractor and will strictly observe the said Rules while execution of work under
work contract awarded to them. They will have to indemnify the company for any
loss or damage / accident / injury to the company’s property / employee or
employee of their own in default of non - observing these rules.
1. Contractor should issue photo gate pass for their workers from GSECL Factory
Manager as per Gujarat Factories rules, 1963 & details shall be filled up in
GSECL gate pass format as per Aadhar card /Election card id proof & to follow
the gate pass issue procedure through concern department EE & SE, Security
Officer, LWO/IRO/DGM, Factory Medical Officer, Safety Officer/Dy. Safety
Officer & Factory Manager.
2. In case of emergency, temporary photo gate pass shall be issued by Security
Officer only for three days with prior permission of Factory Manager only. More
than three days, Permanent photo gate pass procedure shall be completed by
contract agency for their contract workers.
3. Certificate of Fitness of employment in hazardous process & operations in form
no.33 of Gujarat Factories rules, 1963 shall be issued by GSECL Factory Medical
Officer for all contractor workers before commencement of work & examination
responsibility shall be taken by contractor as well as concerned Head of
Department .Pre-employment & Periodical medical examination of contractor
workers shall be carried out in form no.32 from GSECL Factory Medical Officer
PUR-F-10 ET-296
after every six (06) months of contractor with their contractor workers.
Contractor shall be fulfilled all health requirements before commencement of
work. After completion of medical examination in form no.32/33, GSECL Factory
Medical Officer shall be signed in contract worker gate pass procedure format.
4. If work executed outside factory premises, Principle Contractor shall be
registered compulsory under The Building & Other Construction Workers
(Regulation of Employment and condition of service) Act, 1996 and The Gujarat
Building & Other Construction Workers (Regulation of Employment and
condition of service) Rules, 2003 before execution the ”building or other
construction work” means the construction, alteration, repairs, maintenance or
demolition, of or, in relation to, buildings, streets, roads, railways, tramways,
airfields, irrigation, drainage, embankment and navigation works, flood control
works (including storm water drainage works), generation, transmission and
distribution of power, water works (including channels for distribution of water),
oil and gas installations, electric lines, wireless, radio, television, telephone,
telegraph and overseas communications, dams, canals, reservoirs, watercourses,
tunnels, bridges, viaducts, aqueducts, pipelines, towers, cooling towers,
transmission towers and such other work as may be specified in this behalf by
the appropriate Government, by notification but does not include any building or
other construction work to which the provisions of the Factories Act, 1948 (63 of
1948), or the Mines Act, 1952 (35 of 1952), apply.
5. Contract worker gate pass will issue after completion of safety induction 3D
animation movie & Training record is to be maintained in IMS/OHSAS training
format by TK Office/LWO.
6. As per Gate pass format of GSECL, Safety Officer/Dy. Safety Officer shall be
checked the issue PPE to contract workers as per nature of job, Form no.10 of
lifting tools and tackles, Driving license, Electrical contractor license, Electrical
trade qualifications, Safety induction training, SOP, supervisor qualifications etc.
After fulfillment of all Safety compliances, Safety Officer/Dy. Safety Officer shall
be signed in Contract worker Gate pass procedure format.
7. Work Contract shall be completed by principle contractor/agency/person who is
awarded the work order. Subletting of contract shall be allowed only if prior
approval of Power station chief before execution of work. Contractor/agency shall
be submitted the entire subletting contract documents with gate pass
application through concern department EE & SE, LWO/DGM, Safety
Officer/Dy.Safety Officer & Factory Manager.
8. Under The Conditions Framed Under Rule-45 Of The Indian Electricity
Rules, 1956, Valid Electrical contractor License shall be submitted to concern
electrical department EE/SE/Electrical Safety Officer/ Safety Officer/Factory
Manager at the time of apply gate pass by agency/Contractor with latest renewal
from Chief Electrical Inspector, Gandhinagar- Gujarat. Electrical License
photocopy shall be checked by Concerned HOD of Electrical
Department/Electrical Safety Officer/Dy.Safety Officer/ Safety Officer/Factory
9. As per nat ur e of job/ wo r k, Qualified supervisor (Diploma (Electrical/
Mechanical/Civil/C&I) + 3 years experiences or ITI + 10 years) shall be engaged
by contract agency & qualification certificate with experience certificate shall be
submitted to concern EE/SE/LWO/IRO/DGM/ Dy.Safety Officer /Safety
Officer/Factory Manager at the time of apply gate pass.
10. As per rule 3 of CEA regulation ,2010: Designating person(s) to operate and
carry out the work on electrical lines and Apparatus, Contract person/worker
possesses a certificate of competency or electrical work permit, issued by the
Appropriate Government. That means, Electrical trade Qualification of contract
worker/person like ITI-wireman/ Electrician, Diploma (Elect), BE/B. TECH
(Elect), ME/ M. TECH (Elect) shall be submitted to concern
EE/SE/LWO/IRO/DGM, Dy.Safety Officer/ Safety Officer/Factory Manager at
the time of apply for photo gate pass procedure.
PUR-F-10 ET-296
11. As per nature of job/work & during capital overhauling work /Annual
overhauling work /24X7 round the clock work/major shut down work, Qualified
Safety Officer/Manager/Supervisor (BE/Diploma (Elect/Mech/Civil) + PDIS-Post
Diploma in Industrial Safety) shall be engaged by contractor during dangerous
operations/dangerous works as well as day to day dangerous activities, safety
supervision, tool box talk, Safety awareness programme, SOP preparation with
hazards & its control measures with each step , checking of lifting tools &
tackles, hydra mobile crane, Safety precautions, coordination with Safety
Department etc.
12. License of driver shall be submitted with gate pass issue application as per
nature of vehicles & to follow the Motor vehicle Act,1988, the Central Motor
Vehicles (Amendment) Rules,2016 as well as Gujarat Motor Vehicles rules,1989
& driver license shall be checked every day by security shift in charge before
entry in the Factory premises.
13. SOP with JSA (Job Safety Analysis) shall be prepared by contractor through
competent person as per GFR, 1963 or Qualified Safety Officer as per GFR,
with 05 years experiences. SOP will review & approve by concern
JE/DE/EE/SE/Elect. Safety Officer/Dy. Safety Officer /Safety Officer/Factory
Manager before execution of work.
14. It is compulsory to use standard make Personal Protective Equipments (P.P.Es.)
as per the job requirement. Do not work without use of required P.P.Es.
Contractor is responsible to provide standard make (ISI/DGMS/CE/EN/ANSI
approved) & to checked standard/make in PPE issue format by concern
JE/DE/EE/SE/Safety Officer/Factory Manager. Personal Protective Equipments
/ Safety Gadgets suitable to give sufficient protection against hazards involved in
their work / job to their staff, as per the job requirement and insist / enforce
their workers to put on the same while at works.
The ongoing work is liable to be stopped at any time if your contract
workers/staffs found working without P.P.Es. Following is the list of various
P.P.Es (as per ISI/DGMS/CE/ EN/ ANSI approved only) to be used for various
works / worksites.
In any work, Contractor shall be issued the minimum 06 nos. of PPEs like Safety
Shoes, Safety Helmet, Safety goggles, Mask & Reusable Ear plug, hand gloves to
their workers/supervisor compulsory & it will check by concern section HOD &
Dy. Safety Officer /Safety Officer at the time of gate pass procedure.
Quality of PPE shall be approved from Safety Officer as per Indian Standard and
International Standard before executions of work or at the time of gate pass
apply procedure.
List of safety equipments
Industrial Safety Helmet For protection of head against falling objects
or during fall of person from height. Yellow
Colour helmet is used for contract worker
with agency logo.
Safety Goggles/welding For protection of eyes against flying particles /
goggles/ chemical splash dust, chemical splash, welding spark, arc,
goggles flashover etc.
Full Face shield For protection of face against flying particles /
dust, chemical splash, spark, arc, flashover
Reusable Earplug / Ear For ear / hearing system protection while
muffs. working in high noise level area.
PUR-F-10 ET-296
Chemical suit/Gas tight suit For body protection against chemicals, oils,
/Fire proximity suit/FR sharp edged objects, heat, hot objects etc.
Safety Hand Gloves For protection of hands against chemicals,
oils, sharp edged objects, heat, hot
metals/objects, electricity etc.
Safety shoes/ Gum Boots For protection of leg/feet against falling
with objects, sharp edged objects, heat, hot
Oil/Chemical/water/heat/ metals/objects, electricity etc..
Electrical resistance etc.
Safety Belt(full body For fall prevention while working at heights or
hardness with double lanyard in depth, working in vessel or in confined
& shock absorber) / Rope / space.
Life line / Fall arrestor etc.
Dust Mask/Respirator with Protection of respiratory system against dust.
Chemical Cartridge Protection against toxic chemical fumes /
Respirator with full face gases/vapors/dust etc.
mask type A2B2E2K2
Trolley mounted Air line Working in oxygen deficient zone or confine
respirators with full face space area
Portable Single gas detector Working in hazardous storage/process area
like Chlorine, Ammonia,
Portable Multi gas Detector Working in oxygen deficient zone & use in
( LEL,O2,CO,H2S,SO2, etc) entry of confine space & Major fire
Automatic voltage detector To check the present voltage or induction
voltage of electrical equipments/ bus/switch
gears from 01 (one) feet distance before
starting the any electrical work .
Auto darkening welding The new auto darkening welding helmet
helmet (EN 379 & EN 175 combines legendary Speed glass quality and
Level-B) with PAPR as per EN auto darkening technology with an innovative
12941:1998, class TH2 and wide-view grinding visor to give welders an
AS/NZS 1716 all-in-one solution for more flexibility,
precision, and efficiency.
Respiratory System is a combined face and
breathing protection device, for increased
comfort and safety in welding. The unit is
equipped with a particle filter which removes
particles from the air. The unit provides a
constant airflow independent of filter
combinations and clogging. The unit can also
be equipped with a gas filter (for example
A1B1E1). The unit supplies air to the head
top via the connecting breathing tube. The
airflow creates a slight positive pressure
which together with the sealing to the face
prevents particles and other contaminants
from entering the head top.
15. All PPEs (as per ISI/DGMS/CE/EN/ANSI approved only) Should issued by
party/agency/contractor to their contractor workers as per nature of job and
allotment of PPE list shall be submitted to Safety Officer, GTPS on his letter head
PUR-F-10 ET-296
as per below mentioned format by Contractor before commencement of work
through concerned JE,DE,EE/SE .
Sub: Issue of PEE to Contractor workers
Sub of work Order:
Name of Agency:
Date of Commencement:
Time limit for work order:
Sr Na De Name Name of IS Make Q Uni Dat Recei
. me sig of PPE :Code of ty t e of ving
N of na Secti no. of PPE iss signa
o wor tio on PPE ue ture
16. Shift Security Inspector/Security Officer shall be checked Safety Shoes & Safety
Helmet of all contractor workers at entry gate of Factory Premises & shall entered
contractor workers with Safety Shoes & Safety Helmet with photo ID Gate Pass.
17. Shift Security Inspector/Security Officer shall be checked validity of Gate pass of
all contractor workers on daily basis.
18. During the work execution, one trained & competent supervisor of agency should
always remain present at work site. Concern JE/DE of GSECL shall be
supervised the contract work as per SOP .
19. Approved NABL laboratory calibration certificates of
electrical/mechanical/Civil/C&I/Environment survey/Chemical etc measuring
/testing equipments/instruments which are used during contract work shall be
submitted before starting the work & shall be checked by concern JE/DE/EE
before starting work & it’s record shall be maintained in concern section.
20. The contractor shall take all the required safety measures prior to
commencement of work on dangerous substances, machineries or area at which
cautionary notice is displayed and obtain “Line Clear” or “Work Permit” through
the concern Department / Section JE/DE and shall be informed to concern
section JE/DE for closed/ returned after completion of work.
21. Safety talk/Safety work instructions shall be given to contractor workers by
concern JE/DE regarding hazards of specific work, risk & it’s control measure
(mentioned in HIRA) before starting the job work and records shall be maintained
for each & every job works.
22. Display Safety instructions shall be strictly followed by all workers who are
working in factory premises.
23. Material Safety Data Sheet (MSDS) of each chemical shall be available with Chief
Chemist/Control room &work related Chemical information shall be taken by
PUR-F-10 ET-296
contractor & contractor workers from Concern EE/Chief Chemist before starting
of chemical handling work.
24. The contractor shall be checked & securely covered or securely fenced any
opened fixed vessel, sump, tank, pit or opening in ground or in floor which, by
reason of its depth, situation, construction or contents ,is or may be a source of
danger before starting the work each & every days or after interval/recess.
Contractor supervisor shall be informed to concerned HOD regarding any unsafe
25. Prohibition of smoking, fires, lights, spontaneous ignition substance, matches;
fuses, mobile phone etc are to be strictly followed by all workers who are working
in factory premises.
26. Prior to carrying out welding, gas cutting, furnace heating or any other hot work
job, remove all the inflammable material lying at or nearby worksite or cover it
properly by suitable protective covering. Also, special care shall be taken before
carrying out such job & see that all possible contributing factors to set fire shall
be removed / vanished prior to commencement of the work. Advance intimation
shall be given to concerned section / fire section to commence the work in fire
prone areas. They should also keep ready all the First Aid Fire Extinguishers /
equipments& fire extinguishing media / material like sand / water buckets or
other appropriate equipment at such place.
27. While carrying out work in confined space or inside vessel, obtain necessary
“Confined Space / Vessel Entry Permit” from concerned department prior to
commencement of the work.
For lighting in such areas, only 24-volt (ISI certified & with proper guard) hand
lamp shall be used. For taking care of the persons working inside the confined
space / vessel, a supervisor / person capable to keep continuous watch on
person(s) working inside, assist them in case of emergency or arrange to get
immediate outside help, shall remain present at entry point. Use full body safety
belt without failed.
While working inside sewage, trench or in-depth, a person to warn outsiders /
entrants / passers etc shall remain available near entry point or the entry point
shall be cordoned by a barricaded tape with a cautionary notice. After completion
of the works, all the lids / covers / grills / grits opened, shall be re-fixed / re-
placed in the original position as it were prior to commencement of the work and
leave the work place in safe condition in all respect, so as to prevent accident to
fellow workers.
28. The contractor shall see that he / his persons do not work on or block (by
stacking material, spare parts, tools-tackles, equipments etc), any passages /
walkways / gangways / aisles / staircases / ladders / lifts or any other
approaches / roads leading to plans or its auxiliaries, on which there is traffic
movements or possible traffic movements in case of emergency. Such passages
are meant for safe escape in the event of emergency. If it is utmost necessary to
carry out work in such area with blocking of passage, prior permission of
Competent Authority or the Engineer-In-Charge shall be obtained. To demarcate
/ declare the area as “UNSAFE”, cordon it using barricading tape & display
suitable caution notice or keep a person to restrict / divert the traffic on this
route through other safe passage.
29. Prior to use power / electrically operated hand tools / equipments / machines /
gadgets like welding machine, hand grinder, hand drill etc, ensure for its safe
operation & use it only if it is found safe to use. Do not use defective, unsafe or
improperly maintained equipments.
30. The electrical power supply required to run such equipments shall not be taken
directly at their own but shall be obtained through concerned Electrical
Maintenance Departments or their authorized persons or under their
observations / guidance only. The Electrical Section shall provide temporary
electrical connection up to contractor’s Mains Board on which it is compulsory to
install mains switch, ELCB & fuses of adequate capacity. All such equipments
PUR-F-10 ET-296
shall invariably be earthed adequately to prevent electrical shock, sparking, short
circuit etc. Power cord to be used shall be of adequate capacity, without any joint
& shall consist of earth wire also. Hence, it is necessary to use adequate capacity
3-wire power cord for single & 5-wire power cord for three phase power
connections. The plugs, receptacles, pins, holders etc shall be of adequate
capacity & safe to use.
All electrical & mechanical equipments / tools-tackles viz. welding machine,
cutting machine, Grinder, Drill, Chain Pulley Blocks, Hook chooks etc required
to be used during work execution shall be of standard make & bear ISI
certification mark on it. The consumables like welding electrodes, grinding
wheels / discs etc which has specific prescribed life span shall not be used in
any case if its expiry date is over.
31. Non-Sparking Non-Magnetic electrical hand tools and tool kits shall be used by
Electrical contractor for safe use in areas where hazardous, flammable, or
combustible vapors, liquids, dusts, or residues may be present in Gas Based
power plant and list of tools and tackles shall be submitted with technical bid.
Non-Sparking Non-Magnetic electrical hand tools and tool kits shall be checked
by JE/DE before commencement of Electrical work.
32. Before using lifting machines / tackles (like C.P.Bs., Hook chooks, winch, forklift,
mobile crane, EOT crane etc) & its attachments (like D-shackles, slings, U-
clamps, Eye bolts or any fixtures), it shall be checked and used only if found safe
to use. Also, ensure that these are tested, examined & certified in form no.10 by
Competent Person as per the Factory act-1948 & Gujarat Factories Rules and its
validity do not expire. Further, it shall be fixed properly and firmly prior to lifting
the weight. Valid Test certificate of all Lifting machines used by Contractor
to be submitted to Dy.Safety Officer/ Safety Officer before commencement of
work through concerned EE/SE.
33. Metal Scaffoldings to be used for working at height shall be of adequate size &
capacity. Obtain the work permit when working at height. While climbing on
such scaffolding or working on any structure at height, use of full body safety
belt /full body hardness with double lanyard & Fall arrestor & Helmet is
compulsory. It is also necessary to fasten chinstraps of the helmet.
34. Contractor or their employee shall not interfere in day-to-day routine plant
activities / works except the work assigned to them, shall not loiter in the areas
other than their work jurisdiction, as well as shall not temper / operate / touch
the machineries/equipments/auxiliaries with which they are not concerned.
Also, the contractor shall strictly instruct their staff for not to sit or take rest
at/near/below running plants, auxiliaries, systems or any place which is risky,
hazardous & prone to accident.
35. The cylinders containing poisonous / toxic or inflammable / explosive gas like
Oxygen, Acetylene, LPG, Hydrogen, Ammonia, Chlorine, CO2etc shall be handled
safely taking due care. To handle / shift such cylinders a special trolley /cage
meant for it must be used but in no case it should be rolled.
36. In Gas Based Power station/Hydrogen storage area /Hydro carbon fumes-vapour
generated area, Spark arrestor (as per approved manufacturer of CCOE, Nagpur)
shall be provided on each vehicle by party/agency and it will check by shift
security in charge before entry of vehicles in the factory premises.
37. No women or young person shall be employed or permitted to work in Lead-
compound area like battery room etc. as per schedule VI of GFR
38. No women or young person shall be allowed to clean, lubricate or adjust any part
of a prime mover or of any transmission machinery while the prime mover or
transmission machinery is in motion. Examination or operation of motion
machinery shall be made or carried out only by a specially trained adult male
worker wearing tight fitting clothing as per section 22 of factories act
39. In all risky job, before start the work, contractor should obtain General Safety
Work Permit through concerned section from Shift –in-charge well in advance.
PUR-F-10 ET-296
40. In case of noticing smoke or fire during their work execution, they shall make
immediate efforts to extinguish / control it and simultaneously inform the Fire
Station Mobile No as well as Station Fire Officer or Emergency Control room no
which is displayed at prominent place of factory like Main Security Gate, All unit
control room, Canteen area, Safe Assembly points, Fire Station, All security
gates, Occupational Health Centre.
41. In case of any injury / accident while working, it shall immediately be reported to
Safety Department through concerned Sectional Head / Engineer. The prescribed
Form No. 21& ANNEXURE may be obtained from concerned section or
Dy.Safety Officer/Safety Officer.
In case of any electrical accident, it shall immediately be reported to Electrical
Safety Officer through concern Sectional Head / Engineer. The prescribed
Electrical accident form no. A as per electricity act-2003 & Form No. 21 &
ANNEXURE as per Gujarat Factories rules shall be filled up by concern
department JE/DE with written consent of contractor. The Form may be
obtained from concerned Electrical section or Electrical Safety Officer. Electrical
accident investigation shall be carried out by Electrical Safety Officer with
Factory Manager.
After any reportable accident, Contract agency shall be submitted the fitness
certificate of injured person with endorsement of GSECL factory Medical Officer
to LWO/Dy.Safety Officer/Safety Officer/Electrical Safety Officer then after
injured person may allow for work.
42. For any incident occurred but have no injury to any persons should also reported
as per GSECL format and informed to Dy.Safety Officer/Safety Officer as Near
43. Safety penalty shall be imposed against Offences by contract workers: If any
contract worker worked in a factory contravenes any provision of Factories act or
any rules or orders made there under, imposing any duty or liability on workers,
contractor/agency shall be punishable with fine which mentioned as under.
Sr. Description of penalty Amount
(i) Work without PPEs Rs.300/- per
(ii) Work without work Safety permit like Rs.1000/- per day
working at height, confine space entry, hot
(iii) License of driver as per type of vehicles not Rs.750/- per
registered. person
(iv) Welding work without flashback Rs.1000/- per set
arrestor/double gauge regulator set
(v) Operate Portable power tool without ELCB Rs.1000/-per
(vi) Work without qualified Supervisor as per Rs.1000/-per day
nature of job like mechanical, electrical, civil,
C&I, chemical etc.
(vii) Work without SOP & JSA Rs.2000/-per day
(viii) Work without test report of lifting machines / Rs.2000/- per
tackles (like C.P.Bs., Hook chooks, winch, equipment
forklift, mobile crane, EOT crane etc) & its
attachments (like D-shackles, slings, U-
clamps, Eye bolts or any fixtures) in Form
No.10 of Gujarat Factories Rules,1963
(ix) Work without Double lynyer Safety belt Rs.3000/-per
during working at Height work, work without person
anchoring in hook/line line
PUR-F-10 ET-296
(x) Work without 24 Volt supply in Confine Rs.3000/-per
space area person
(xi) (a) Grinding machine used without safety Rs. 500/- per
guard / machine guard equipment / per set
(b) Unsafe welding machine like open body,
Knob without insulation, connection
(c) Damaged welding cables/gas pipelines
(d) Welding work doing without welding
(e) Electrical supply without 3 pin plug/
Industrial Plug
(f) Use of damaged electrical wire for lighting
(g) Use of lighting lamp without cage
(h) Use of open halogen tube
(i) Use of damaged PPEs/use of non
(j) Unsafe lifting and handling of gas
(k) Cylinder handling without safety cap
(l) Temporary connection without ELCB etc.
During plant visit/supervision of concern JE/DE/EE, SE, Safety Officer/Safety
Officer/Electrical Safety Officer and Factory Manager/Occupier, if they will
observed any safety violations as per CO circular/statutory requirements then
they must imposed Safety Penalty through office note directly against contract
workers/ contract agency and Office note process through proper channel to
concern Section head and Account head for recovery purpose. Photograph/CCTV
camera footage is to be put up with penalty note by imposed individual officer.
44. Contractor will damage any fire equipments or property or machinery in factory
during execution of work, total damage cost will be recovered from Contractor RA
bill and recovery Office note put up by concern HOD.
45. All the relevant labour and industrial laws shall also be followed compulsorily.
46. After completion of work, cotton waste, grease, oil, unused material, welding rod
pieces, scrap etc. are to be removed by contractor and scrap shall be deposited to
scrap yard of Main Store.
47. For performance evaluation of contractor, safety factors of work accident, fire
incident & near miss accident will be considered. Steps can be taken to review
the job assignment up to cancellation for negligence.
48. Over & above these, contractor shall have to follow all the safety requirements
/rules & regulations / norms and legal provisions laid down in various statutes.
Particularly the provisions of The Factories Act-1948 & the Gujarat State
Factories Rules-1963 (Amended up to date), The Electricity Act-2003 & rules,
BOCW Act/Rules shall be followed strictly. The contractor shall also obey the
rules / regulations / instructions of the local Competent Authority for safety &
health requirements.
49. The above rules shall be scrupulously followed and where required, Contractor
/contractor workers may contact to the Dy.Safety Officer/Safety
Officer/Electrical Safety Officer in case of any ambiguity or needs further
guidance in this regard.
GENERALCONDITION AT CONTRACT
1. “Contract” means the documents forming tender and the subsequent agreement
PUR-F-10 ET-296
that may be entered in to.
2. “Work” or “Works” means the work related to the subject mentioned in tender.
3. Contractor” means a firm or an individual undertaking these works or offers the
rates for this work.
4. The general rules and regulations of the GSECL for tender and contract for works
will apply to the extent of the same and not modified herein. The contractor is
deemed to have gone through and considered to be fully aware of the conditions
mentioned therein.
5. Earnest Money Deposit:
Tender should be submitted along with Earnest Money Deposit (EMD) at the rate
of three percentage (3 %)of estimated cost of the tender, without which tender is
liable to be rejected.
The exemption in payment of EMD shall be given under following clauses.
1. Micro & small-scale enterprises which participate directly in tendering
process for the product which they are manufacturing / service which
they are providing and have Udyam registration for items / service under
2. Start-ups which participate directly in tendering process for the product
which they are manufacturing/ service which they are providing and re-
cognized by DPIIT under the Start-up India Program and has obtained
Udyam registration.
3. Organization which has registration certificate for the manufacturing
product of the tender, from Gujarat Khadi Gramodyog Board or Khadi and
Village Industries Commission (K.V.I.C) or Commissioner of Cottage
4. Board/Corporations/PSUs of the Central/ State Government for their
own manufactured items.
5. State Government recognized organizations like (i) organizations for
blinds, dumb and deaf, disabled, mentally disabled persons; (ii) women's
self-help group recognized by Gujarat Livelihood Promotion Company;
which participate directly in tendering process for the product which they
are manufacturing / service which /they are providing.
6. Security Deposit:
It is mandatory to submit security deposit before order placement. Contractor
shall have to pay security deposit of 5% of contract value within 10 days from the
date of letter of intent. Such security deposit will be payable either in D.D./ Bank
guarantee. Bank guarantees from scheduled/ nationalized banks will be
acceptable if the amount of security deposit payable exceed Rs 5000/- . The
bank guarantee will be excruciated on the standard form prescribe by the
corporation. In case of bank guarantees furnished/ submitted they should have
clear one time validity till the completion of the order in all respects and up to
the expiry of the guarantee period from the date of work completion. Bank
guarantee for interim period will not be allowed. If by any reason the work period
is extended than contractor should undertake to renew the bank guarantee at
least one month before the expiry of the validity failing which GSECL will be at
liberty to encash the same.
If the full security amount is not paid immediately after the receipt of the letter of
intent, than the order will not be placed (at the discretion of the GSECL) and
without entering to any correspondence and this will be binding on the tenderer.
If the tenderer fails to pay the security deposit or defaults in execution of the
orders place or if GSECL suffers any financial loss due to this, then GSECL will
be liberty to adjust the amount of others orders of the same firms or by encasing
the bank guarantee.
Failure to deposit the S.D. will entail for failure of EMD and the contract shall be
treated as terminated. You shall not be, allow to start the work if, S.D. is not
PUR-F-10 ET-296
paid. Any loss to the GSECL due to late start of the work because of the late
payment of S.D shall be contractor’s liability.
SD will be accepted in form of Bank guarantees issued by ….
[A] Any nationalized bank
[B] Guarantees issued by following banks will be accepted as SD/EMD for the
period up toDt:31.03.2027. The validity cut-off date In the GR is with respect to
the date of issue of Bank Guarantee irrespective of the date of termination of
Bank Guarantee.
No. Name of Banks No. Name of Banks
1 AXIS Bank 23 A U Small Finance Bank
2 Bandhan Bank 24 City Union Bank
3 CSB Bank 25 DBS Bank India Limited
4 DCB Bank 26 Dhanlaxmi Bank
5 Equitas Small Finance Bank 27 Federal Bank
6 HDFC Bank 28 HSBC Bank
7 ICICI Bank 29 IDBI Bank
8 IDFC First Bank 30 IndusInd Bank
9 Jammu and Kashmir Bank 31 Jana Small Finance Bank
10 Karnataka Bank 32 Karur Vysya Bank
11 Kotak Mahindra Bank 33 RBL Bank
12 South Indian Bank 34 Standard Charter Bank
13 Tamilnad Mercantile Bank 35 Ujjivan Small Finance Bank
14 YES Bank 36 Ahmedabad Mercantile Co-
15 Nutan Nagrik Sahakari Bank 37 Rajkot Nagrik Sahakari Bank
16 Sarswat Co-Operative Bank 38 SBPP Co-operative Bank Ltd.
17 SVC Co-Operative Bank Ltd. 39 The Cosmos Co-op Bank Ltd.
18 The Gujarat State Co- 40 The Surat District Co-operative
Operative Bank Bank
19 The Surat Peoples Co- 41 The Baroda Central Co-
operative Bank Ltd. operative Bank
20 The Panchmahal District Co- 42 The Kalupur Commercial Co-
operative Bank Op. Bank
21 The Rajkot Commercial Co- 43 The Banskantha Mercantile Co-
operative Bank operative Bank Ltd.
22 Gujarat Gramin Bank
In tender process, for L-1 Bidder Security Deposit will be charged as per table
Security Deposit
Category of the Unit Purchase Up-to Rs. Purchase of more
5 Lakhs than Rs. 5 Lakhs
Enterprises or Exempted 3% of order value
organizations which are
Exempted from paying
tender fee & EMD as per
procurement policy
For all other enterprises 5% of order value 5% of order value
7. The security Deposit/ Bank guarantee covering execution of the contract will be
released only on successful execution of contract and on receipt of the “NO
Objection Certificate” from the Engineer In charge of the work.
8. Sublet or transfer of contract without prior written approval of G.S.E.C.L., will be
PUR-F-10 ET-296
treated, as breach of contract and it will be punishable by forfeiting the Security
Deposit as well as termination of contract.
9. The G.S.E.C.L. reserves the right to forfeit the S.D. in case of any breach of
contract and in case of disputes the decision of C.E., G.S.E.C.L Gandhinagar
T.P.S. shall be final and binding and shall be acceptable to the contractor. If the
contractor fails to start the work as stipulated the EMD and the SD shall be
10. Contract agreement & indemnity Bond:
As per Corporation’s rules, Contractor will have to submit an agreement with the
Corporation on stamp paper of appropriate value Rs.300/- in the prescribed form
within one month of receipt of this A.T. or before starting the work. The cost of
the stamp fee shall be borne by you. The tender with the specification, price
schedule, drawing and the contract booklet are to be signed by you. This letter
and subsequent correspondence shall be deemed to be part of the Contract.
Contractor will have to submit an Indemnity Bond also with the corporation on
stamp paper of appropriate value Rs.300/- in the prescribed form before
commencement of the work. The cost of the stamp fee shall be borne by you.
11. The contractor must be maintaining regular labour record and should be paying
all acquired benefits to labour force and contractor should obtain certificates to
this effect from Labour Commissioner. Because of this contract, the GSECL shall
not accept any additional labour liabilities than stated above.
12. The contractor will make arrangements at his own cost to insure all men,
materials and equipment employed for this work. The GSECL will not be
responsible for any loss or damage either to the contractor’s personnel or his
13. Dispute, if any, taking place between the contractor and labourers must be
intimated to Labour Welfare Officer, Gandhinagar TPS, immediately.
14. The contractor must insure all the labourers before starting the works.
15. Any casualty will also have to be borne by the contractor for the period the
contract continues.
16. The contractor shall not engage any sub-contractor without written prior
permission of the Chief Engineer or the authorized officer of the GSECL. In no
case the GSECL will be liable in any manner regarding any liability in respect of
any contract labours engage by the sub-contractor and the liability of such
contract labours will solely rest with the principal contractor.
17. The GSECL reserves the right to terminate this contract at any time during its
currency without giving notice of termination or any reason thereof.
18. In case of default, the work will be got done through other agency / agencies at
the risk and cost of the original contractor, and the GSECL shall be entitled to
recover such expenses from defaulting contractor by such methods as deemed
fit. The contractor shall not, however, be entitled to terminate the contract or
stop works undertaken by him before expiry of the contract period / extended
period due to any reason whatsoever.
19. Under the contract, the contractor should either himself be present at the site or
should nominate persons in writing, who must be available at site and who
should be authorized to take decisions about the works and receive the
instructions from Site In charge of the work at any time. In absence of any
responsible man of contractor at the time of any emergency, adhoc decision of
Site In charge will be binding on the contractor.
20. The contractor is bound to execute the work for any item as per the instruction
of the Site In charge. On refusal to do so, the work will be carried out at the risk
and cost of contractor by using the contractor’s tools and tackles, for which no
compensation whatsoever shall be payable to the contractor.
21. If any immovable articles/tools/equipment will be found stolen from the working
place, the contractor would be held responsible and cost will be recovered from
PUR-F-10 ET-296
22. For any conflict and ambiguity, the decision of the Chief Engineer (GEN) shall be
final and binding on the contractor.
23. DISPUTE RESOLUTION MECHANISM:
(1) Amicable settlement
Any dispute, difference, controversy or claim between the Parties arising out
of or relating to this contract with reference to the construction,
interpretation, breach, termination or validity thereof (hereinafter referred as
“the Dispute”) shall, upon the written request of either Party be referred to the
authorized representatives of the Disputing Parties for resolution. The
authorized representatives shall promptly meet and attempt to negotiate in
good faith a resolution of the Dispute within thirty days of the service of the
(2) Arbitration
If the Parties fail to amicably resolve the disputes or differences or contrary
claims as indicated herewith in sub clause (1) of this Clause, arising under or
in connection with the present Works Contracts, whether pertaining to works
contracts alone or works and Procurement both, the same shall be referred to
arbitration under the Gujarat Public works Contracts Disputes Arbitration
Tribunal Act,1992”
24. “D.G.S. & D. Force Majeure Clause”
“ If, at any time during the continuance of this contract, the performance in
whole or in part by either Contractor of any obligation under this contract shall
be prevented or delayed by reason of any war, hostility, act of the public enemy,
civil commotion, sabotage fires, floods, explosion, epidemics, quarantine
restrictions, strikes lockouts or acts of God ( hereinafter referred to as event)”,
then provided notice of the happening of any such event is given by either
Contractor to the other within twenty one days from the date of occurrence there
of neither Contractor shall by reason of such event be entitled to terminate this
contract nor shall either Contractor shall have any claim for damage against the
other in respect of such non-performance of delay in performance, and deliveries
under the contract shall be resumed as soon as practicable after such event has
come to end or ceased to exist, and the decision of the Managing Director as to
whether the deliveries have been so resumed or not shall be final and conclusive.
Provided further that if the performance in whole or part of any obligation under
this contract is prevented or delayed by reasons of any such event for a period
exceeding 60 days, either Contractor may at its option terminate the contract
provided also that if the contract is terminated under this clause, the Purchaser
shall be at liberty to take over from the supplier at a price to be fixed by the
Managing Director of the GSECL, which shall be final, all unused undamaged
and acceptable materials bought out components, and stores in course of
manufacture in the possession of the supplier at the time of such termination or
such portion thereof as the Purchaser may be deem fit excepting such materials,
bought out component and stores as the supplier may with concurrence of the
Purchaser elect to retain”.
25. The contractor shall quote rate & also furnish GST, if any, as per Schedule-B.
Nothing will be paid extra as a part of contract unless & until, it is specified in
the tender documents by GSECL.
26. The rates quoted shall be firm and valid for 180 days for acceptance from the
date of opening.
27. The contractor, if desired, can see the plant and site on any working day and
during working hours with permission of the Chief Engineer.
28. Conditional tender is liable to be rejected withdrawal or insertion of conditions
unilaterally after opening of tenders will not be permitted unless it is so desired
PUR-F-10 ET-296
29. Office correspondence will be carried out in English language, and if at any time
to facilitate the contractor, Gujarati translation may be furnished, if deemed fit.
The English version will be the correct one and the same only will held good for
30. The contractor should intimate to the office the name and address of authorized
and responsible representatives, so that our field officers can contact them when
required in connection with the execution of the said works.
LABOUR LAWS TERMS AND CONDITIONS
Terms and Conditions regarding Labour Laws
During the entire period of the contract, the Contractor and his Sub Contractor
shall at all times comply with all applicable labour laws, rules, regulations,
notifications, and bye-laws issued by the Central Government, State Government,
or Local Authorities. This includes all existing laws as well as any amendments or
new notifications that may come into force during the contract period.
The Contractor and his Sub-Contractors shall, at all times abide by the following
Act/statutes related to Human Resources:
1. Factories Act, 1948;
2. Contract Labour (Regulation & Abolition) Act, 1970;
3. EPF & MP Act, 1952;
4. Building & Other Construction Workers (Regulation of Employment &
Conditions of Service) Act, 1996;
5. ESI Act, 1948;
6. Minimum Wages Act, 1948;
7. Payment of Wages Act, 1936;
8. Payment of Bonus Act, 1965;
9. Payment of Gratuity Act, 1972;
10. Workmen's Compensation Act, 1923;
12. Maternity Benefit Act, 1961;
13. Inter-State Migrant Workmen (Regulation of Employment & Conditions of
Service) Act, 1979;
14. The Building And Other Construction Workers' Welfare Cess Act, 1996;
15. The Carriage by Road Act,
The above list is only indicative and not exhaustive. The Contractor shall remain
fully responsible for ensuring compliance with all other applicable labour and
welfare legislations, rules, and regulations in force during the contract.
The following are some of the major responsibilities of the contractor, in addition
to other obligations prescribed under various labour laws, rules, and regulations
issued by statutory authorities such as the State Government or Government of
India from time to time, which the contractor shall strictly comply with during the
execution of the contract.
1) The Factories Act,
The contactor should not deploy worker below the age of 18 years and above
60 years for the awarded work.
Earn Leave shall be paid to their bonafide contract workers as per the
provisions of the Factories Act,
Payment of Earned Leave should be made monthly together with wages for
better compliance of law. The contactor shall maintain Earn Leave Register
PUR-F-10 ET-296
in Form No. 19 as per the provisions of the said Act and submit the same on
All the written registers, Performa etc. shall be maintained up to date and
kept ready for inspection at any time or submitted on-time to the concerned
authorities as per applicability of the Acts by cotractor.
2) The Contract Labour (Regulation and Abolition) Act,
The Contractor / Agency shall have to obtain the Labour License under
Contract Labour (Regulation & Abolition) Act from the appropriate
authorities before commencement of work. The contractor tor shall maintain
a valid labour license under the Contract Labour (Regulation and Abolition)
Act for employing necessary man power to be required by contractor.
The contractor should not be allowed to engage fifty (50) or more contract
labourers without initiating to obtain the labour license under the Contract
Labour Act. (the said number i.e., fifty (50) or more includes Supervisor and
3) Minimum Wages Act,
Contractor shall have to make the payment of wages to the Contract
Labours engaged by them, on or before 7th of every month through nearest
Nationalized Bank compulsory, preferably situated in the premises of TPS
area in case of all works contract. The Contractor shall supply copy of Bank
Statement duly stamped by the Concerned Bank as well as debited entry of
amount displayed in the contractors' own bank account as token of proof
towards payment of Wages through CLIM/prevailing system at relevant
time. Apart from Payment of wages through Bank, Contractors shall have to
make all other payments like Advances, Bonus, Leave Encashment etc. to
their labours through bank only and cash payment entry will not be allowed.
Wages rates for contract laborers are applicable as per the terms and
conditions of the license. The contractor shall have to pay wages to workers
as notified by the Government of Gujarat from time to time.
Any default to pay the minimum wages to the engaged workers and deprived
of their right to minimum wages payment on or before 7th of each month
shall be dealt as per the provision of labour laws. Recurrence of the same
may lead to cancellation of awarded contract.
4) The Provident Fund and Miscellaneous Provisions Act,
The contractor must possess separate P.F. code on the name of the Firm
/Agency /Company itself for the subject work.
It should be ensured that all the contract labours engaged by contractor are
covered under the provident fund scheme and employee's pension scheme
and their contribution must be remitted regularly to the concerned RPFC.
The photocopies of challan along with ECR in this regards should be
submitted regularly to the User Department to enable their onward billing
The contractor shall submit along with his bill (month wise) statement
regarding deductions against employees' provident fund and family pension
scheme in respect of each concerned employee' Provident fund and family
pension scheme at the rate of 12 %o of wages (or at the rates made
PUR-F-10 ET-296
applicable by the Government time to time). The contractor's contribution
and his workers contribution towards provident fund and family pension
scheme shall deposited by the contractor with concerned PF Authorities.
5) Workmen's Compensation & Employer's Liability Insurance.
The contractors shall have to obtain Employee Compensation Policy under
the Employees Compensation Act before starting the work. Employee
Compensation Insurance shall be obtained for all the workers engaged for
the execution of awarded contract. If any of the work is sub-letted the
contractor shall ensure that the sub-contractor take and provide workmen's
compensation and Employer's liability insurance for the labours engaged.
Contractor is liable to pay compensation in case of accidental injury arising
out of and in the course of employment as per the said Act and shall bear
medical expenses due to on duty accident.
6) The Payment of Gratuity Act,
For better compliance, contractor shall pay amount of gratuity on a monthly
basis along with the payment of wages, calculated on a pro-rata basis per
month, which is equivalent to 15 days' wages for each completed year of
service for every worker. (* applicable to ARC / BRC works contract only)
7) The Payment of Bonus Act,
Every worker shall be entitled to be paid by the contactor in an accounting
year, bonus, in accordance with the provisions of this Act, For better
compliance, the contractor should pay bonus amount on a monthly basis
along with wages calculated on a pro-rata basis per month. Contactor has to
submit the paid bonus details of its worker in Form No. C as per the
provisions of the said Act as and when required by the Govt. Authority as
well as by GSECL.
8) The Maternity Benefit Act,
Contractor shall ensure that entitled female worker should provide
Maternity Leave and other benefits as per the provision of the said Act.
9) The Building and other Construction Workers' Act,
For any construction work, fall under the definition of Section 2(1) d),
happening outside / inside the Factory premises the said act will be
applicable and the contactor or its sub-contactor shall be liable to comply
with the provisions framed there under.
10) The contractor shall give preference to existing or local contract workers for
engagement in the awarded contract and shall issue appointment orders to
each and every workers individually at the time of their engagement during
the period of contract and terminate the same at the end of the each
Follow the mentioned procedure for each milestone for the execution of
works contract.
11) On Commencement of Contractual Work
1. Before starting the work, the contractor may contact Labour Welfare
Officer / Industrial Relations Officer for all formalities related to labour
law compliance before commencement of the contract and onward
Labour Law compliance thereof,, so that later no dispute will arise in
respect of compliance of labour laws.
2. It is the responsibility of the contractor to ensure that contactor’s
employees maintain strict discipline as regards security, methods of safe
PUR-F-10 ET-296
working etc., and not to cause any hindrance to smooth running of
power station or in execution of duties by GSECL staff Any lapse in this
regard will be viewed seriously and if lapse found, contact is liable to be
terminated. If any of contractor's staff is found unsuitable or not
behaving properly, the contractor shall have to remove such worker from
the work-site on demand by EIC. To maintain harmonious industrial
relations amongst contact labours is solely the responsibility of
contractor. Any breach of the same will be viewed seriously.
3. A digital system developed at the request of the agencies working at the
premises of GSECL, is to facilitate them for easy, efficient, effective
management of data, gate passes, attendances, medical records, Police
Verification documents etc. related to their employees / workers
deployed for various works and services against work order of GSECL.
4. On receipt of LOA and before commencement of work, authorized
representatives of the agency shall login in the CLIMS online portal /
prevailing system at relevant time and apply for registration of their
employees / workers uploading all information with required documents
in digital form. Upon completion of due verifications, clearance by EIC
and HR departments, contracting agency will obtain gate passes. GSECL
will only consider documents like wage sheet duly accepted and signed
by individual workers, as per the engagement/deployment
duration/hours of individual worker duly certified by the agency, being
the employer, for the purpose of payment of bills and HR clearances.
Agency shall be solely responsible for maintaining accurate and upto-
date data of their workers in the portal/ prevailing system at relevant
time. All statutory compliances under prevailing laws shall remain the
responsibility of the contracting agency. The agency shall indemnify/
GSECL against any liabilities arising from non-compliance of legal
provisions or inaccuracies in the data maintained by them in the digital
portal of CLlMS/prevailing system at relevant time.
5. The Contractor who intends to engage labours more than the specified
limit under law, then necessary - Form No. V under the Contract Labour
(R & A) Act, 1970 or Form No. VI under the Interstate Migrant worker
(employment regulation) Act 1979 as applicable is to be obtained for the
purpose of obtaining Labour License from the Licensing Authority.
6. It shall be the duty of the Contractor or his Supervisor to ensure Bio-
Metric punching and reporting at the location of work.
7. The contractor shall employ adequate number of experienced staff at site
for daily supervision and for maintaining of various registers and
records required under the Labour laws and contracts. No payment for
such supervision shall be admissible.
8. The gate passes obtained for any specific work order will be valid for that
specific work order only and contractor should not divert the man power
for any other work order. If any work or part thereof is desired/required
to sublet, the contactor shall obtain the necessary permission of EIC in
black and white well in advance which is mandatory for considering the
statutory documents of agency other than the agency who awarded work
12) During Contractual Work under the progress:
1. All Contractors shall have to make the payment of wages to the Contract
Labours engaged by them, on or before 7th of every month through
Nearest Nationalized Bank compulsory, preferably situated in the
premises of power station area. The Contractor shall supply copy of
Bank Statement duly stamped by the Concerned Bank as a token of
proof towards payment of Wages through CLIMS / prevailing system at
2. All Contractors has to comply & maintain statutory documents /
registers under the provision of labour laws & EPF Act.
PUR-F-10 ET-296
3. In case the contractor having more than one contract in the same TPS,
the contractor shall have to obtain work order wise separate Gate Passes
and submit the same with the documents of statutory compliance that
too work order wise every month to the User Department to enable their
onward billing clearance.
13) CONTRACTORTO II\TDEMNIFY THE GSECL REGARDING LABOUR
The contractor shall indemnify and keep indemnified the GSECL, and every
member, officer and employees of the GSECL, also Engineer-in-charge and
his staff against all actions, proceedings, claims, demands, costs and
expenses whatsoever arising out of or in connection with the matter referred
in above clauses and elsewhere and against all actions, claims demands,
cost and expenses which may be made against the GSECL by any
workman/ employees of contractor or any sub-contractor and or from any
liability any wise to any workman/employees of the contractor or sub-
contractor under any laws, rules or regulation having in force of law
including but not limited to claims against the owner under employee
compensation Act, 1923. The Employee's Provident Fund Act.l952, and/or
the contract labour (Abolition and Regulation) Act,
The GSECL shall not be liable for or in respect of or in consequence of any
accident or injury to any workmen or other person in the employment of the
contractor or his sub-contractor, and the contractor shall indemnify and
keep indemnified the GSECL against all such damage and compensation
and against all claims, demands proceedings costs, charges and expenses
whatsoever in respect of or in relation thereto.
The contractor shall at his own expense / risk and cost to comply with all
the labour laws as above-mentioned and keep the G.S.E.C.L. indemnified in
respect thereof.
GSECL : shall be entitled /empowered to deduct directly from the bills, the
amount to be paid to engaged bonafide contract workers or the contract
workers engaged by Sub-contractor any sum or sums payable by main
contractor / sub-contractor and which sum/sums the Corporation is
required to pay in capacity of Principal Employer on account of the default of
contractor in respect of all liabilities incurred out of non-compliance
regarding any provisions of Labour Laws and same amount shall be
recovered from the pending dues of the contractor with 15% administrative
Any other rules and regulation, conditions, circulars etc., that are in force at
present and that may be famed by the G S E C L from time to time in
connection with contracts will be binding and acceptable to contractor. The
above are some of the major liabilities of the contractor in addition to other
liabilities prescribed under the various labour laws in force from time to time
from Statutory Authorities like State Government / Government of India,
which the contractor shall have to comply with.
The contractor shall provide the name of authorized representative, as
provided to other statutory Government authorities and will be notified to
Engineer In-Charge time to time.
14) Submission of Statutory documents to ensure the compliances:
The contractor shall upload statutory documents, work order-wise, under
Labour Laws and EPF in CLIMS / prevailing system at relevant time.
Required documents shall be uploaded by the contractor in existing portal
/prevailing system at relevant time invariably each month to Engineer In-
Charge for onward process and smooth clearance by HR Department.
PUR-F-10 ET-296
List of documents required for gate passes of contract workers through clims /
prevailing System.
Sr. Description of documents attached
1 Copy of Work Order
2 Copy of P. F. Code No.
3 insurance Policy as per subject of work order under the Workmen
Compensation Act,
4 Contract agreements/ subletting work contract documents with
5 Copy of Id proof of Aadhar card or Election voting card or driving
license or Passport only
6 Copy of Police Verification in respect of each contract workers
15). The contractor whose work order value is above Rs. 5 lacs shall have to
submit ‘Declaration cum Indemnity Bond’ on Rs. 300/- Non-Judicial stamp
paper in prescribed Performa (Annexure- ‘B’) with Agreement and Indemnity
Bond before the commencement of the contract.
DECLARATION CUM INDEMNITY BOND
(On Rs.300/- Non Judicial Stamp Paper duly notarised)
THIS DECLARATION CUM INDEMNITY BOND made at_____________________
having its Reg. office at___________________________(hereinafter referred to as
“Contractor” which expression Shall unless it be repugnant to the context or
meaning thereof, be deemed to mean and include their respective assigns,
successor, executors, subcontractors and/or administrators) of the ONE PART in
favour of M/S Gujarat State Electricity Corporation Limited having its power
Station at Gandhinagar Thermal Power Station (hereinafter referred to as the
“Company”), which expression shall unless it be repugnant to the context or
meaning thereof be deemed to mean and include its assigns, successors) of the
WHEREAS the COMPANY has entered into a contract with the Contractor for the
_____________________________________dated_____________“hereinafter called the
AND WHEREAS it is one of the essential conditions of the Contract that the
Contractor shall comply with all the provisions of the Labour& Industrial Laws,
as may be applicable from time to time for the discharge and completion of the
works and completion of the Works and Services covered under said Contract
Labour (R & A) Act 1970, Child Labour (Prohibition and Regulation) Act 1986, The
Employees Provident Funds & Miscellaneous Provisions Act, 1952, Employees
State Insurance Act 1948, Minimum Wages Act, 1948, Payment of Bonus Act,
1965, Payment of Wages Act, 1936, Employees Compensation Act,
Factories Act, 1948 and other Labour Laws, Rules, Notifications and Codes which
are at present applicable to the contractor and which may be applicable during
the tenure of the contract (hereinafter referred as the ‘Laws’).
AND WHEREAS the Contractor has agreed to execute this Declaration cum
PUR-F-10 ET-296
Indemnity Bond to this effect and has agreed to indemnify and Company, it’s
Directors, Officers and employees and representatives indemnified and hold
harmless against all third party claims, charges, penalties, fines, expenses,
losses, damages costs, suits or any other levy against the Company and/or the
management due to the failure of the Contractor to observe or follow all
applicable laws.
NOW THIS DEED WITNESSETH AS UNDER:
1. The Contractor hereby declares that all acts, deeds, actions, activities,
conduct and lapse, delays, misdeeds, faults, breaches, inactions etc done by
his assigns, successors, executors, subcontractor and/ or administrators
shall be construed to be have been done by the contractor and he alone shall
be liable for such acts, inactions etc.
2. In consideration of the Company awarding the Contract to the Contractor
subject to the condition of execution of this Declaration cum Indemnity bond,
the Contractor declares and represents to the Company that the Contractor
has obtained all Statutory registrations, Certificates, licenses and approvals
required under the Laws enabling the Contractor to execute the Contract in a
legal and lawful manner.
3. That in the event of any liability arising out of failure to observe or non-
compliance of any such „Laws‟ by the Contractor in connection with the
Performance of the contract, the Contractor shall bear all the resultant
whatsoever liability(ies), if any arising out thereof and that the company, its
Directors, Officers and employees, representatives, shall not be liable for any
such liability(ies). The Contractor agrees to indemnify and keep the Company
and its Directors, Officers and employees, representatives indemnifies, defend
and hold harmless, against all losses, costs, damages, claims, penalties,
interest, expenses, demands, fines, legal liability, causes of action, injury to
persons, suits etc., which may be suffered, incurred, undergone and /
sustained by the Company including the Costs and expenses that may be
incurred in defending any such liability(ies) claim(S), Proceeding (S) etc. that
maybe made or taken or taken or arise on the same by any Person, body,
authority, government, judicial / quasi - judicial authority due to the failure
or non-compliance of any such laws and rules there under (including any
amendments in acts, laws, statutes & rules there under) of whatsoever kind
and nature arising out of or in any way connected with, whether or not such
acts or omissions are actual or alleged, active or passive with regard to the
discharge of the said Contract.
4. The Contractor further declares that in case of any suit / claim / right /
damages / compensation / fine / levy / charges / expenses / losses /
penalties / costs raised by the third party, including contract labours
engaged by the contractor, he shall join such proceedings in such
Suit/Court/Tribunal/Authority and effectively defend the same.
5. The Contractor hereby agree and undertakes to make good any loss, damage,
claims, suits, demands, decrees, expenses that the Company may suffer to
the fullest satisfaction of the Company and if the Contractor fails to make
good the same then the Company shall have the right to recover the same and
or any other loss sustained, without any restriction or limitation, together
with any other incidental expenses, costs, and all incidental logistic expenses
etc that may be suffered by the Company from the Contractor and the
Contractor hereby further confirms and declares that this Declaration cum
Indemnity Bond is irrevocable and shall be final and binding on it / him
heirs, executors, administrators, legal representatives, successors,
subcontractors and assigns, wherever the context applies. any claims,
demands, shall be adjusted against any amount due and payable to the
Contractor and the Company shall have the right to withhold any amounts
due and payable to the Contractor, till the settlement of such claims, disputes
to the Contractor towards discharge of such claims, obligations etc.
PUR-F-10 ET-296
6. This Declaration cum indemnity bond shall be in accordance with the laws of
India and any dispute between the parties with regard to this Declaration
cum Indemnity Bond shall be resolved through the dispute resolution process
mentioned in the General Conditions of the Contract (GCC).
IN WITNESS WHEREOF, the said Contractor has hereunto set their hand the day
and year first hereinabove written.
SIGNED SEALED AND DELIVERED By the within named “CONTRACTOR”
(Authorized Signatory)
Rubber Stamp of Firm/Company
In presence of Witness
Name & Address of Witness Signature
Residential Address:
Residential Address:
SIGNATURE OF CONTRACTOR CHIEF ENGINEER (GEN),
WITH SEAL & DATE GSECL, GTPS
PUR-F-10 ET-296
Job Safety Analysis sheet
JSA for: Repair and Modification of Existing NDCT of 210MW Unit#3 through
Design, Engineering, supply, erection, testing, commissioning and
Performance guarantee testing of the Natural Draught Cooling Tower.
Section: PLANNING
Control Measures
Risk Risk assessment should
Job Step Hazard Responsibility
Level be carried out and
inform to all labours.
Removals Fall of object & High All job related PPE Contractor &
person from should be use as It’s Supervisor
height per note of works.
pipes, Area barricaded.
Safety talk to be
given before work
reducers & execution.
Close supervision
new one. Failure of lifting High Crane / Hydra
tools / tackles must be operated
crane/hydra to be
used as per load of
Form no 10 must
available for lifting
machine/ tools &
tackles is to be
Electric shock High Electric supply Contractor &
through It’s Supervisor
Industrial plug
socket should be
Three pin used
with earthing wire
Three cord cable to
Lamp guard to be
Cable cord to be
Exposure to High Use PPE, personal Contractor &
eyes care required. It’s Supervisor
Close supervision
Area barricaded.
PUR-F-10 ET-296
Exposure to hot Medium Use PPE, personal Contractor &
surfaces care required. It’s Supervisor
Close supervision
Area barricaded.
Injury to human Medium Load should be
body due to hang in vertical
unbalancing of direction only.
Hazard due to
slips/trips/falls load should be
considered before
dismantling of any
NOTE: Required check list should be filled up by Contractor at time of work
Prepared by Reviewed by Checked by Approved by
EE (Planning) Dy. Safety Officer SE (Mech) Factory Manager (GEN)
PUR-F-10 ET-296
PPE UNDERTAKING (WITH SPECIFICATION AND MAKE) ATTACHED
Name of Repair and Modification of Existing NDCT of 210MW Unit#3 through
Work: Design, Engineering, supply, erection, testing, commissioning and
Performance guarantee testing of the Natural Draught Cooling Tower
COMPULSORY UNDERTAKING OF BIDDER REGARDING QUALITY OF PPEs
(PERSONNEL PROTECTIVE EQUIPMENTS)
Authorized signatory of M/s ______________________________
Hereby certify that following mentioned PPEs (as per ISI / DGMS / CE/ EN / ANSI
approved only) must be issued to our all contract workers as per nature of hazards
before execution of work.
Sr. IS : Code no.
Name of PPE Make of PPE Qty Unit
1 Safety Helmet IS:2925-1984 Nos.
2 Safety Goggles IS:5983 Nos.
3 Reusable Ear plug IS 9167:1979 Pair
4 Dust Mask ISI Nos.
5 Safety Shoes IS:15298 Pair
If our company is not provided above mentioned good quality of PPE`s, Factory
manager and Safety Officer shall be empowered to stop the work without any notice.
SIGNATURE OF THE CONTRACTOR
WITH SEAL OF THE FIRM.
PUR-F-10 ET-296
COMPULSORY UNDERTAKING OF BIDDER REGARDING QUALITY OF PPEs
(PERSONNEL PROTECTIVE EQUIPMENTS)
Ref.: Tender no.: ____________
Authorized signatory of M/s____________________________________
Hereby certify that following mentioned PPEs (as per ISI/DGMS/CE/EN/ANSI
approved only) must be issued to our all contract workers as per nature of hazards
before execution of work.
Sr. Name of PPE IS :Code no. of Make of PPE Qty Unit
1 Safety Helmet IS:2925 Nos.
2 Safety goggles with IS:5983:1980 or Nos.
Anti fog lens EN:166
3 Reusable Ear Plug ANSI S3.19- Pair
4 Dust Mask EN149:2001 Nos.
5 Safety Shoes IS:15298 Pair
6 Cur resistance Hand EN 388:2003 Pair
gloves Cut level-1
If our company is not provided above mentioned good quality of PPE’s, Safety Officer
and Factory manager shall be empowered to stop the work without any notice.
Seal of the Firm Signature of Authorized signatory
PUR-F-10 ET-296
ANNEXURE-II: SOP/JOB SAFETY ANALYSIS
Name of Job analyzed:
Tender No. /Work order No.
Name of Agency: Mobile No.
Name of Supervisor: Mobile No.
Name of Section/Department:
Job Location/Area:
Required PPEs and Emergency equipment :(1) Safety Helmet (2) Safety Shoes (3)
Safety Goggles (4) Reusable ear plug (5) Cut resistance hand gloves (6) Dust mask
Job Step Hazard Risk Level Control Measures
Prepared Checked Reviewed
DE / EE Safety Chief
SE ( ) Factory Manager
( ) Officer Engineer
PUR-F-10 ET-296
GSECL Contractor EH&S Performance Evaluation Form
Name of Contract Agency:
Contract work order No.
Date Evaluation Completed:
Work Description:
Name of Power Station:
Status of Work/ Project: _________% completed.
No. of person engaged during work contract:
Total Exposure hours worked on work order:
This evaluation must be completed by Concern EE & SE after completion of the Work
Contract /project and at pre-determined intervals (three months) as agreed upon at
the Pre-Job Mobilization Meeting.
Statistics Number Frequency
Environmental Excursions
Traffic Violations
The following categories should be rated for the Contractor’s overall
performance on the work order/ Project.
RATING (5 = Excellent; 4=Very Good 3=Good 5 4 3 2
2=Satisfactory 1 = Poor)
A. Adherence to Requirements:
Adherence to contract provisions for new hire
Compliance to plant safety rules.
Compliance with industrial hygiene
Compliance with site contractor’s health and
safety guidelines.
Compliance with site permits.
Material Safety Data Sheets (MSDS)
Response to safety requests.
B. Housekeeping
Monthly housekeeping inspection results.
Overall site housekeeping practices.
Response to safety requests.
Chemical hazard control
Fire control measures
Flammable and explosive materials control
General waste – trash collection
C. Injury Performance:
Contractor’s timely reporting of accidents and
PUR-F-10 ET-296
Contractor’s use of modified work program.
Contractor’s participation in accident
investigations.
Number of incidents observed and reported.
D. Contractor Safety Program:
On site safety officer.
All subcontractors employed by the Contractor
have been managed effectively with reference to
EHS and Quality (meets company standards,
practices and/or procedures).
Safety training for supervisors.
Substance abuse policy compliance.
Weekly toolbox meeting and/or participation.
Updates to written safety programs.
E. Tools and Equipment:
Availability of tools and equipment furnished.
Condition of contractor’s tools and equipment by
site and provincial Labour and OH&S standards.
Maintenance of Equipment / Tools / etc.
Contractor’s knowledge and proper use of
Contractor’s equipment certification readily
Contractor’s materials inspection/acceptance
program followed.
F. Costs Within Expectations:
Contractor’s cost program.
Contractor’s reasonableness and/or
G. Execution of Work:
Contractor’s cooperation in handling change
Contractor’s efforts to eliminate nonproductive
Contractor’s planning of work.
Relationship with other site contractors.
Contractor’s cooperation with our company and
other contractor personnel.
H. Key Field Personnel:
Competence of main office staff and
Quality of first and second line supervision.
J. Labour Relations:
Contractor’s ability to anticipate problems.
Contractor’s efforts in exercising management
Contractor’s relationship with the building
K. Project management /Supervision:
Contractor’s efforts to use efficient crew size.
Control of subcontractors.
L. Quality of Craft Labour :
Contractor’s ability to obtain qualified personnel.
Quality of work.
Contractor’s adherence to schedule
PUR-F-10 ET-296
N. Quality Control/Assurance:
Contractor’s equipment certification readily
Contractor’s material inspection / acceptance
program followed.
Contractor meets expectations on quality
O. Issues and Concerns:
Advises of potential problems.
Efficiency in handling paperwork.
Readiness to accept responsibility.
Reliability in dealings.
Response to site requests for action by the
supervisor/ management.
OVERALL PERFORMANCE:
Any specific issues or concerns with the contractor:
Would you hire this contractor again to do similar work:
How can this contractor improve on its past performance:
Evaluation carried out By:
Designation Executive Engineer Superintending Safety Officer
Date Completed:
PUR-F-10 ET-296
Work Agreement Format
STAMP PAPER OF RS. 300/-
This agreement is made at Gandhinagar the ___ day of ________________in the
Christian year two thousand and fourteen between M/s
“THE CONTRACTOR” which expression shall unless excluded by or repugnant to the
context include its successors or permitted assigns)of the one part and the Gujarat
State Electricity Corporation Ltd., having their Head office at Race course Baroda -7
(hereinafter called “GSECL” which expression shall unless excluded by or repugnant
to the context include- its successors or assigns) of the other part.
WHEREAS the aforesaid GSECL has accepted the tender of the aforesaid contractors
for work ______________________________________at GTPS as per GSECL’s order
_________________________________dtd.___________ hereinafter called ”The works” and
more particularly described enumerated or referred to in the specification, terms and
conditions prescribed in the order letter, covering letter and other letters and schedule
of price which for the purpose of identification have been signed by Shri
____________________________________ On behalf of the contractors and by Chief
Engineer (Gen.) on behalf of GSECL a list where of is made out in the schedule
hereunder written and all of which said documents are deemed to form part of this
contract and included in the expression “THE WORKS” wherever herein used, upon
the terms and subject to the conditions herein after mentioned.
AND WHEREAS GSECL has accepted the tender of the contractors for the
construction/work, of the said works for the sum Rs.___________________(Rupees
___________________________only) upon the terms and subject to the conditions herein
NOW THIS AGREEMENT WITNESS AND IT IS HEREBY AGREED AND DECLARED
1. The contractors shall do and perform all works and things in this contract
mentioned and described or which are implied therein or thereof from respectively or
are reasonably necessary for the work as mentioned and at the times, in the manner
and subject to the terms condition s and stipulations contained in this contract, and
in consideration of the due provision, executions, work/ construction and completion
of the; works agreed to by the contractors as aforesaid, GSECL both hereby convenant
with the contractor to pay all the sums of moneys as and when they become due and
payable to the contractor under the provisions of the contract Such payments to be
made at such times and in such manner as is provided by the contract.
2. This conditions and convenants stipulated herein before in this contract are
subject to and without prejudice to the rights of GSECL to enforce penalty for delays
and/or any other rights what so ever including the right to reject and cancel on default
or breach by the contractors of the conditions and the covenants as stipulated in the
general conditions, specifications, forms or tender, schedule drawing etc. attached
with GSECL’s order No
3. The contract value, extent of supply delivery dates, specifications and other
relevant matters may be altered by mutual agreement and if so altered shall not be
deemed or constructed to means or apply to affect or alter other terms and conditions
of the contract and the general conditions and the contract so altered or revised shall
be and shall always be deemed to have been subject to and without prejudice to said
PUR-F-10 ET-296
List of documents forming part of the contract :-
1. Original tender
3. Tender & contract for works booklet.
4. General specifications for civil works book.
In witness whereof the parties hereto have set their hands and seals this day,
month and year first above written.
1. Signed, Sealed and delivered by (Contractor)
(Signature with Name, Designation & official seal / stamp)
(Contractor) (Complete Name, Address of the authorised person of the
Supplier with Authority letter or Board’s Resolution in case of company)
In the presence of Name, full Address & Signatures:
2. Signed, Sealed and Delivered by (Purchaser-GSECL):
PUR-F-10 ET-296
(Signature with Name, Designation & official seal / stamp)
For and on behalf of ____________________________________________ (Purchaser-
(Complete Name, Designation & Location / Address of the authorized
officer as per DOP of the Purchaser Company)
In the presence of Name, full Address & Signatures:
PUR-F-10 ET-296
Notes for Supplier:
(1) SECURITY DEPOSIT: It shall be mandatory to submit security deposit as per
below table within 10 days from the date of issue of Letter of Intent (LOI)
before order placement. Party shall have to pay Security Deposit in the form of
Demand Draft/Bank Guarantee/RTGS/NEFT only. In case when successful
bidder is not at all responding within notice period or withdraws his offer then
his EMD shall be forfeited and he will not be allowed to participate in the tenders
invited from the same office for the period of One year for that place from where
tender is invited.
Category of the Unit Security Deposit
Order End Cost Order End Cost
Up to Rs. 5 Lakh More than Rs. 5 Lakh
Enterprise or Organization Exempted 3% of Order End Cost
which are exempted from
paying Tender Fee & EMD as
mentioned on Tender Page
For all other Enterprises 5% of Order End Cost 5% of Order End Cost
(2) Guarantee: If the goods/Stores/materials and equipments are found defective
due to bad design materials or workmanship then same should be repaired or
replaced by you free of charge if reported within 12 months from the date of
commissioning or 18 months of receipt of material at site whichever is earlier.
(3) Performance Bank Guarantee (Not Applicable): The supplier/contractor/party
(i.e. tenderee) has to give --% of order end cost as a Bank Guarantee with validity
period of additional 01 (one) month i.e. more than actual Guarantee/Warranty
period of 12/18 months from the date of commissioning/receipt of material at
site to safeguard Company’s interest in case of any eventuality happening on the
last day of the Guarantee/Warrantee period after office hours of the Bank or
(4) The GSECL reserves the right to prefer overall lowest party, to reduce/enhance
the tender quantity as per GSECL’s requirement at the time of finalization of
tender. GSECL also reserves the right to close the Tender at any time, without
assigning any reasons, whatsoever. Tenderers will not be entitled for any
compensations/ damages/losses, whatsoever, on account of such cessation of
(5) GSECL reserves the right to terminate the Contract (i.e. Purchase order) at any
time, without assigning any reasons, whatsoever. Suppliers will not be entitled
for any compensations/damages/losses, whatsoever, on account of such
termination of the Contract.
(6) Delivery Period: As per Technical Bid. Bidder should accept delivery period as
per GSECL requirement and same should be confirmed in Technical bid. The
party has to submit required documents within 10 days and delivery period will
be start from the date of issue of LOI. If party does not submit the documents
within specified time, necessary action may be initiated as per GSECL rules.
(7) Penalty: as per Clause NO. (19.0) Measurement & Bill Payment Conditions of
General Terms & Conditions for Contractor of Annexure-A mentioned under
(8) Outside Gujarat material should come through RR sale at destination (i.e.
(9) Payment Term : Payment will be made by the GSECL directly to you as per
Clause NO. (18.0) Measurement & Bill Payment Conditions of General Terms
& Conditions for Contractor of Annexure-A mentioned under Technical Bid.
Amount of GST and applicable cess will be kept under retention till submission of
PUR-F-10 ET-296
documentary proof of payment of GST or till reflection of amount of GST in GST
return after due verification.
Additional Note: Vendor get to register in VMS System through vms.guvnl.com.
For registration following documents are required and mail to
[email protected] and [email protected]. After registration vendor
have to upload the invoice in the VMS system for smooth functioning of payment.
Documents required for Registration:
(2) GST Certificate Copy
(4) Full Name of Vendor
(10) Supplier shall have to submit all the necessary documents like material Test
certificate, other required test certificates, guarantee certificate, invoice etc along
with supply as per the order terms. Payment will not be processed without
required documents.
(11) REPEAT ORDER: GSECL reserves rights for the placement of repeat order @
% of the order quantity/value of A/T at the same prices, Terms and Conditions
stipulated in the original contract within 6 (Six) months of the order. In special
circumstances GSECL reserve the right to place repeat order up to 100% of the
original quantity of the A/T at the same prices, Terms and conditions stipulated
in the original Contract as mutually agreed upon.
(12) In case of submission of Bank guarantee against Earnest Money Deposit/
Security Deposit/ Performance Guarantee following changes must be look
into by supplier/ contactor and followed by bank.
(a) There should be claimed period of at least one year after expiry of the bank
(b) For lodgment of claim for invocation of bank guarantee, the clause should
specifically state that said bank guarantee can be presented by GSECL at
the local branch of the issuing bank.
(c) The invocation of BGs a written application from the GSECL should be
sufficient for lodgment of our Claim.
(d) On receipt of original bank guarantee a written confirmation should be
obtained by GSECL from the issuing bank.
(e) GSECL shall accept bank guarantee issued by the bank as per approved
bank list mentioned in tender copy.
(f) E-BG is acceptable.
(13) Purchase Agreement:
The supplier shall have to enter into a ‘Purchase Agreement’ with GSECL. This
purchase Agreement has to be executed on Non-Judicial stamp paper of Rs.
300/- duly notarized.
The cost of Non judicial stamp & Notary charges will be borne by supplier.
Format for the Agreement is attached in the tender.
The Purchase Agreement shall be signed by the authorized representative and
have to produce documents as hereunder:
1. If the authorized representative is from a partnership firm, then a certified copy
of the registered partnership deed must be attached along with the signatures of
other partners who have authorized the particular partner to execute and sign
PUR-F-10 ET-296
2. If it is a private or public limited firm, a copy of the resolution, authorizing the
person to execute & sign the agreement on behalf of the firm, passed by the
Board of Directors along with the Company’s Seal must be attached with the
3. If it is a proprietary firm, then the proprietor himself should execute & sign the
agreement and his full residential address must be available in the record
document. Statutory evidence (Aadhar Card / Voter card) of the person signing
the agreement should accompany the agreement.
Upon submission Security Deposit against LOI and signing of Agreement, GSECL
shall issue a detailed A/T /Purchase order incorporating various terms and
You have to accept all the GSECL’s terms and conditions without any deviations.
I/We agree to supply the article noted above at the rates herein tendered by
me/us subject to the condition of ‘tender and supply above given at the tender
inquiry which I/We have carefully read and which I/We have thoroughly
understood and to which I/We agree.
I /We hereby agree to keep this offer open for 120 days after the returnable date
of the tender and shall bound by communication of acceptance dispatched within
the prescribed time.
Date: Yours faithfully,
Signature of Tenderer
With Company's Round Seal
PUR-F-10 ET-296
SCHEDULE-B (PRICE BID FORMAT FOR ET-296)
(TO BE FILLED IN ONLINE / e-TENDER FORMAT ONLY)
Rate Quantity Unit Total Unit Unit END Total
Ex- Freight, GST F.O.R.
Sr. Description of materials With HSN with Tender offered Insurance FOR COST END
UOM Works P&F with COST
No. Details of Specifications Code CESS, Quantity by Charges Destination with GST COST
price in Charges CESS in Rs.
if any Tenderer in Rs. Cost in Rs. in Rs. in Rs.
UPVC PIPE CONFIRMING
TO IS: 4985, CLASS
1 RATING, PIPES ARE WITH
SOCKETED ENDS: UPVC
PIPE, SIZE : 200 MM OD
UPVC PIPE CONFIRMING
TO IS: 4985, CLASS
2 RATING, PIPES ARE WITH
SOCKETED ENDS:UPVC
PIPE, SIZE : 160 MM OD
3 THREADED FOR 160MM Numbers
4 UPVC SOCKET 160MM OD Numbers
UPVC REDUCER OF SIZE -----------------------------ONLINE SUBMISSION ONLY---------------------------
5 200 MM OD TO 160 MM Numbers
COUPLING FOR 160MM
PVC TRIANGULAR BAR Running
FRP RAILING WITH
9 ACCESSORIES & HEIGHT
Loading, unloading &
10 shifting of UPVC pipes to
PUR-F-10 ET-296
Rate Quantity Unit Total Unit Unit END Total
Ex- Freight, GST F.O.R.
Sr. Description of materials With HSN with Tender offered Insurance FOR COST END
UOM Works P&F with COST
No. Details of Specifications Code CESS, Quantity by Charges Destination with GST COST
price in Charges CESS in Rs.
if any Tenderer in Rs. Cost in Rs. in Rs. in Rs.
Removal & re-erection of
UPVC piping system with
supports and end caps. Running
Shifting of Old Pipes within Meter
the plant area as per EIC
Nozzle installation with
PVC Lath (Triangular Bar) Running
installation Meter
Two-coat Bituminous Paint
IS:158:2015, min. 100- Square
micron DFT. Coat 1: diluted Meter
(penetration); Coat 2: full
FRP Railing installation Running
with accessories Meter
Pre-shutdown baseline
performance test & Post-
intervention performance
Dewatering, cleaning,
scrapping, removal of
debris & disposal as per
Note: Overall Lowest party’s offer (for all 17 items) will be considered for placement of order i.e. considering supply &
installation work. Part/Partial offer will not be considered.
PUR-F-10 ET-296
1. Applicable GST rates needs to be mentioned in column no. 4 above and in case of tenderer opting for Composition scheme, “C” shall
be mentioned and amount (in Rs.) shall be “0” (Zero) in column no. 12. Also, such tenderer shall have to submit the copy of
Composite Registration Certificate.
2. I/We agree to supply the articles noted above at the rates herein tendered by me /us subject to the condition of Tender and supply of
the Tender inquiry which I/ We have carefully read and which I/ We have thoroughly understood and to which I/ We agree.
3. I/ We here by agree to keep this offer open for 120 days after the written date of the tender and shall be bound by communication of
acceptance dispatched within the prescribed time.
Date: Yours faithfully,
(Signature of Tenderer)
(With Company's Round Seal)
PUR-F-10 ET-296
(on Non-judicial stamp paper of Rs.300/- duly Notarized)
THIS AGREEMENT made on this …………. day of …………… Two thousand ……………
……………..……………………………… (Name of the Company), having Registered Office
at ……………………………………………. and represented by
……………………………………… …………. (Name and designation of the Authorized
Officer (herein after called “The Supplier”, which expression where the context so
requires or admits shall include his legal heir, administrators, executors, assignees
and legal representatives) of the ONE PART.
……………..……………………………… (Name of the Company), having Registered Office
at ……………………………………………. And represented by …………………………………
………………. (Name and designation of the Authorized Officer (here in after called
“The Purchaser / purchaser Company”, which expression where the context so
requires or admits shall include his administrators, executors, authorised person,
assignees and legal representatives) of the OTHER PART.
WHEREAS, the Supplier willingly submitted bids for the Tender No………………
……………… of the Purchaser company for supply of ……………………………….. [Name
of the material / items to be supplied by the Supplier] as specified and as per
delivery instructions provided in the Acceptance of Tender (AT) / Letter of Acceptance
(LOA) issued vide No………………. dtd……………. by the Purchaser company at the
accepted respective prices or rates mentioned against the said items / materials.
AND WHEREAS THE PURCHASER Company has accepted the tender of the Supplier
for the supply for the total sum of Rs. __________ (Rupees ___________________________
only) *including / excluding taxes upon the terms and subject to the conditions herein
mentioned in the agreement.
AND WHEREAS, a list is made out in the “SCHEDULE” hereunder written and all of
which said documents of the Schedule are deemed to form part of this agreement and
included in the expression “the Supply” wherever herein used, upon the terms and
subject to the conditions hereinafter mentioned.
NOW THIS AGREEMENT WITNESSES AS UNDER AND IT IS HEREBY AGREED AND
DECLARED THAT:-
(1) The Supplier has accepted the Terms and Conditions set out in the Tender Notice
No. ……………… dtd. ………….. as well as in the form of Acceptance of Tender (AT)
/Letter of Acceptance (LOA) No. .………………………...............…… dtd. …………….
which will hold good & valid during the period of this Agreement.
(2) The supplier shall do and perform for all supplies and things mentioned and
described in this agreement or which are implied therein or therefrom respectively
or are reasonably necessary for the in-time and in manner supplies as mentioned
and subject to the general / commercial terms & conditions and stipulations
contained in this agreement.
PUR-F-10 ET-296
(3) In consideration of the due provision, executions, completion of the Supply, as
agreed to by the Supplier as aforesaid, the Purchaser company hereby agrees to pay
all the sums of money as and when they become due and payable to the supplier
under the provisions of the agreement and such payment to be made at such times
and in such manner as provided in the agreement.
(4) In respect of the said Tender as per the terms & conditions of this Agreement, the
Supplier has deposited amount in Cash or DD or has provided valid Bank
Guarantee of Rs. …........……. (Rupees.……………….............…………………….. only)
with the Purchaser Company towards performance guarantee of execution period
i.e. for security deposit of the supply material / items.
(5) Upon breach by the Supplier of any of the conditions of this Agreement, the
Purchaser Company may give a notice in writing to rescind, determine and put to
an end to the A/T without prejudice to the right of the Purchaser company to claim
damages for antecedent breaches thereof on the part of the Supplier and also to
claim reasonable compensation /risk & cost purchase for the loss occasioned by the
Purchaser Company due to failure of the Supplier to fulfill the Order as certified in
writing by the Purchaser for which Certificate shall be conclusive evidence of the
amount of such compensation payable by the Supplier to the Purchaser.
(6) The Purchaser Company shall not be bound to take the whole or any part of the
ordered quantity herein or therein mentioned in the LOA / AT and may cancel the
contract at any time after giving ONE MONTH’S NOTICE IN WRITING without
compensating the Supplier.
(7) This Agreement shall remain in force till the expiry of satisfactory performance of the
Supply during Guarantee /Warranty period including for the quantity mentioned in
the repeat order, if any as per the terms & conditions of the LOA / AT.
(8) Any Notice in connection with the Supply including the Notice for termination may
be given by the Purchaser or any Authorized Officer for the said purpose as per the
Commercial Terms & Conditions of the LOA / AT.
(9) If subject to the circumstances beyond control i.e. Force Majeure conditions, the
Supplier fails to deliver the materials, the same shall be governed as per the Tender
(10) The agreed value, extent of supply, delivery dates,specifications, and other relevant
matters may be altered by mutual agreement as per the policy of the purchaser
Company and if so altered shall not be deemed or construed to mean or apply to
affect or alter other general /commercial terms & conditions of the agreement and
the agreement so altered or revised shall be and shall always be deemed to have
been adhered subject to and without prejudice to said stipulation.
(11) The following is the Schedule forming part of this agreement as provided herein
PUR-F-10 ET-296
List of documents:
In witness whereof the parties hereto have set their hands and seals this day,
month and year first above written.
3. Signed, Sealed and delivered by (Supplier):
(Signature with Name, Designation & official seal / stamp)
For and on behalf of M/s. _________________________________________ (Supplier)
(Complete Name, Address of the authorised person of the Supplier with
Authority letter or Board’s Resolution in case of company)
In the presence of Name, full Address & Signatures:
4. Signed, Sealed and Delivered by (Purchaser):
(Signature with Name, Designation & official seal / stamp)
For and on behalf of ____________________________________________ (Purchaser),
(Complete Name, Designation & Location / Address of the authorized officer
as per DOP of the Purchaser Company)
In the presence of Name, full Address & Signatures:
PUR-F-10 ET-296
EMD BANK GUARANTEE FORMAT
(BANK GUARANTEE ON NON-JUDICIAL STAMP PAPER OF Rs.300/-)
FOR TENDER No.: …………….. (Gujarat State Electricity Corporation Limited).
WHEREAS M/s. ____________________________________________ (Name and Address of the
Firm) having their registered Office at _______________________________________
__________________ (Address of the Firm’s registered Office) (hereinafter called the
“Tenderer”) wish to participate in the Tender No. ______________ for _______________work
____________________________________ of (Supply / Erection / Supply & Erection/Work) of
_____________________ (Name of material / equipment / work) for Gandhinagar TPS,
Gujarat State Electricity Corporation Limited (hereinafter called the “Beneficiary”)
and WHEREAS a Bank Guarantee for Rs. _______________ (Amount of EMD) valid till
______________ (mention here date of validity of this Guarantee which will be
months beyond initial validity of Tender’s offer) which is required to be submitted
by the Tenderer along with the Tender.
address of the Branch giving the Bank Guarantee) having our registered Office at
_____________________ (Address of Bank’s registered Office) hereby give this Bank
Guarantee No. _________________ dated ____________ and hereby agree unequivocally
and unconditionally to pay immediately on demand in writing from the Gujarat
State Electricity Corporation Limited or any Officer authorized by it in this behalf
any amount not exceeding Rs.____________ (amount of E.M.D.), (Rupees
Gujarat State Electricity Corporation Limited on behalf of the Tenderer.
agree that withdrawal of the tender /Bid / EOI or part thereof by the Tenderer within its
validity or non-submission of Performance Guarantee towards execution/supply
period by the Tenderer within 15 days from the date of issue of Letter of Acceptance
by Gujarat State Electricity Corporation Limited would constitute a default on the
part of the Tenderer and that this Bank Guarantee is liable to be invoked and encashed
within its validity by the Beneficiary in case of any occurrence of a default on the part of
the Tenderer and that the encashed amount is liable to be forfeited by the Beneficiary.
This agreement shall be valid and binding on this Bank upto and inclusive of
____________________ (mention here the date of validity of Bank Guarantee) and shall not
be terminable by notice or by Guarantor change in the constitution of the Bank or the
Firm of Tenderer or by any reason whatsoever and our liability hereunder shall not
be impaired or discharged by any extension of time or variations or alterations made,
given, conceded with or without our knowledge or consent by or between the
Tenderer and the Gujarat State Electricity Corporation Limited.
Notwithstanding anything contrary contained in any law for the time being in force or
banking practice, this Guarantee shall not be assignable, transferable by the beneficiary
(i.e. Gujarat State Electricity Corporation Limited) Notice or invocation by any person
such as assignee, transferee or agent of beneficiary shall not be entertained by the Bank.
Any invocation of the Guarantee can be made only by the beneficiary directly.
NOTWITHSTANDING anything contained hereinbefore our liability under this
Guarantee is restricted to Rs. _______________ (amount of EMD) (Rupees
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Tender Document_ET-296.pdf
Commercial Terms and Conditions.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].