| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.0 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹3.0 L+₹1,057 (0.35%)Admitted-Finance 675 R N GUHA ROAD KOLKATA 700028 | 24 PARAGANAS NORTH | WEST BENGAL | 700028 | L2 | Admitted-Finance | ||
| 3 | L3₹3.0 L+₹1,450 (0.48%)Admitted-Finance | L3 | Admitted-Finance | ||
| 4 | Rejected-Technical | - | Rejected-Technical Documents are not in order | ||
| 5 | Rejected-Technical | - | Rejected-Technical Documents are not in order |
Tender Value
₹3.0 L
EMD Value
₹6,041
Closing Date
25 Sept 2026, 12:00 pmClosed
ASSISTANT ENGINEER
ROOM NO 16 GROUND FLOOR PURTA BHAVAN DF BLOCK SECTOR I SALT LAKE KOLKATA 700 091
Periodical maintenance of Building works for 26 27 in the different Hospital Buildings of Dr Bidhan Chandra Roy Multispecialty Hospital under jurisdiction of Section I of NKHSD I under Kolkata North Health Division R and B Works Phase I
2026_WBPWD_5023523_5
WBPWD/AE/NKHSD-I/NIeT-06/26-27
Open Tender
CIVIL WORKS
Percentage
180 days
Dr Bidhan Chandra Roy Multispecialty Hospital
Please refer Tender documents.
4 documents required · 4 mandatory
₹6,041
12 Oct 2026
10 Sept 2026
28 Sept 2026
11 Sept 2026
25 Sept 2026
11 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared. | 153.68 | M² | 17.6 | ₹2,704.77 |
| 2 | Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared. | 281 | M² | 8.95 | ₹2,514.95 |
| 3 | Surface dressing of the ground including removing vegetation and inequalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m. All kinds of soil | 171.5 | M² | 34.15 | ₹5,856.72 |
| 4 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. Nominal concrete 1:3:6 or richer mix (including equivalent design mix) | 4.24 | M³ | 2,434.25 | ₹10,321.22 |
| 5 | Taking out doors, windows and clerestory window shutters (steel or wood) including stacking within 50 metres lead :Of area 3 sq. metres and below | 63.54 | M² | 143.5 | ₹9,117.99 |
| 6 | Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material within 50 metres lead :Of sectional area 40 square centimetres and above | 0.23 | M³ | 4,459.1 | ₹1,021.13 |
| 7 | Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. | 106.34 | M² | 54.65 | ₹5,811.48 |
| 8 | Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge. 25 mm average thickness | 48.28 | M² | 126.75 | ₹6,119.49 |
| 9 | Cleaning of reinforcement from rust from the reinforcing bars to give it a total rust free steel surface by using alkaline chemical rust remover of approved make with paint brush and removing loose particles after 24 hours of its application with wire brush and thoroughly washing with water and allowing it to dry, all complete as per direction of Engineer-In-Charge. Bars upto 12 mm diameter | 192.25 | Mtr | 8.25 | ₹1,586.06 |
| 10 | Providing, mixing and applying bonding coat of approved adhesive on chipped portion of RCC as per specifications and direction of Engineer- In-charge complete in all respect.SBR Polymer (@10% of cement weight) modified cementitious bond coat @ 2.2 kg cement per sqm of surface area mixed with specified proportion of approved polymer | 106.34 | M² | 141.2 | ₹15,015.21 |
stage.html
html • 0.08 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.14 MB
Tendernotice_2.pdf
PDF • 1.12 MB
BOQ_5107537.xls
BOQ • 0.36 MB
corrigendum1.pdf
PDF • 0.54 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .