| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹19.1 LAccepted-AOC | ₹19.1 L | L1 | Accepted-AOC L1 |
| Sl No | Description | Qty | Unit | C. H. MOHAMMED ASHARAF L1 |
|---|---|---|---|---|
| 1.001.Appendix A Construction of VCB | ||||
| 1.00 | 2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | 40 | sqm | 18.31 ₹732.40 |
| 1.00 | 60.1.2:RING BUND Type II Putting up ring bund with earth fille gunny bags of top width 1.0m bottom width 2.0m height 2.0 m side and filling in between with earth to form ring bund and maintaining the same leak proof till the completion of the work and clearing the site by dismantling the bund after completion of the work.etc.complete. | 6.8 | metre | 1,450.4 ₹9,862.72 |
| 1.00 | 60.2.2:Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete | 80 | hour | 459.93 ₹36,794.40 |
| 1.00 | 2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil | 137.68 | cum | 259.44 ₹35,719.18 |
| 1.00 | 60.7.2:DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site. | 28.21 | cum | 2,988.16 ₹84,310.93 |
| 1.01 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 107.64 | cum | 9,301.23 ₹10.0 L |
| 1.01 | 5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources) | 5.44 | cum | 10,562.89 ₹57,441 |
| 1.01 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 470.08 | kilogram | 113.21 ₹53,217.76 |
| 1.01 | 4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. | 126.14 | sqm | 845.53 ₹1.1 L |
Tender Value
₹17.7 L
EMD Value
₹44,205
Closing Date
27 Jan 2026, 6:00 pmClosed
Executive Engineer Minor Irrigation Division Kanur
Office of the Executive Engineer Minor Irrigation Division Kannur
DEPOSIT-Construction of VCB -Deposit work-Construction of Pallikkulam VCB at ward no.8 pallikkulam in Karivellur Peralam Panchayath ,Payyannur constituency in Kannur District.-General Civil Work-1
2026_Irrig_825336_2
IRR/IA/TR/783/2025_5_1_1/1
Open Tender
Civil Works - Others
180 days
Karivelloor Peralam
Please refer Tender documents.
12 documents required · 12 mandatory
₹2,760
Yes
₹44,205
Yes
12 Mar 2026
17 Jan 2026
29 Jan 2026
17 Jan 2026
27 Jan 2026
17 Jan 2026
1.Appendix A Construction of VCB
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
60.1.2:RING BUND Type II Putting up ring bund with earth fille gunny bags of top width 1.0m bottom width 2.0m height 2.0 m side and filling in between with earth to form ring bund and maintaining the same leak proof till the completion of the work and clearing the site by dismantling the bund after completion of the work.etc.complete.
60.2.2:Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil
60.7.2:DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.23:Smooth finishing of the exposed surface of RCC work with 6mm thick cement mortar 1:3 ( cement : 3 fine sand).
60.63.1:FRP SHUTTERS - Supplying and fixing FRP Channels of "C" profile and sill beam size 100x100x100 mm with flange of 50 to 75mm depth in the grooves already arranged and as per the direction of departmental .officers.
60.63.2:FRP SHUTTERS - Supplying and fixing FRP shutters of suitable size to with stand the design and max water pressure as prescribed by the departmental officer and installing the FRP channels provided in the grooves already arranged and as per the direction of departmental .officers.
60.7.4:DR PACKING FOR APRONS - Rough stone dry packing for apron with good quality blasted rubble including packing to compactness to lines levels, cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1390741.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.05 MB
viewnit.pdf
Tender Documents • 0.03 MB
epayment.pdf
Other Document • 0.01 MB
viewsbd.pdf
Tender Documents • 5.93 MB
BOQ_1390741.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid