Tender Value
₹43.1 L
EMD Value
₹1.3 L
Closing Date
26 May 2026, 6:00 pmClosed
CHIEF ENGINEER (G)
Repairing and augmentation of existing drainage network in CHP area at GTPS
299000
EW-278
Open
Miscellaneous Works
Works
Gandhinagar
2 documents required · 2 mandatory
₹2,950
Gujarat State Electricity Corporation Limited Payable at Gandhinagar
₹1.3 L
4 May 2026
4 May 2026
4 May 2026
26 May 2026
4 May 2026
1. SECTION-A:
ACKNOWLEDGEMENT OF TENDER FEE /EMD.
TENDER NOTICE.
2. SECTION-B:
DECLARATION FORM CUM UNDER TAKING TO BE
SIGNED BY BIDDER
RTGS DETAILS OF BIDDER
PROJECT SYNOPSIS
SCOPE OF WORK AND SITE CONDITION
SPECIAL NOTE FOR PRE-QUALIFICATION
GENERAL INSTRUCTION TO THE TENDERER
3. SECTION-C:
GENERAL CONDITIONS OF CONTRACT
4. SECTION-D:
TERMS AND CONTRACT FOR WORKS
GENERAL SAFETY RULES & LIST OF SAFETY TOOLS
5. SECTION-E :
PERFORMA FOR BANK GUARANTEE
INTEGRITY PACT
CERTIFICATE – A
ANNEXURE – I (DETAILS OF BANK FOR SOLVEANCY
6. SECTION-F:
SPECIAL CONDITIONS FOR USE OF CEMENT
APPROVED NAME OF MANUFACTURERS OF
STEEL / CEMENT
GENERAL GUIDELINES RELEVANT TO I.S.
7. SECTION-G:
GENERAL SPECIFICATIONS
TECHNICAL SPECIFICATION
DETAIL SPECIFICATION
8. SECTION-H:
SCHEDULE-B
Safe Maintenance Procedure
EW- 278 PUR-F-006 RFQ-
ACKNOWLEDGEMENT OF TENDER FEE /EMD
TENDER NOTICE
EW- 278 PUR-F-006 RFQ-
GUJARAT STATE ELECTRICITY CORPORATION LIMITED
Gandhinagar Thermal Power Station, Gandhinagar, India–382041.
Ph. 91-79-23215663 Fax: 91-79-23217673,
e-mail: [email protected] ; Website: www.gsecl.in
CIN:U40100GJ1993SGCO19988
ACKNOWLEDGMENT
E- Tender for the
Repairing and augmentation of existing drainage network in CHP area at GTPS
TENDER FEE PAID VIDE DEMAND DRAFT NO. _________________________________
DATED___________________________ RS. __________________________________
EARNEST MONEY DEPOSIT PAID VIDE D.D. NO. _______________________________
DATED ____________________ RS. _____________________
1. The undersigned reserves the right to reject any or all tenders without
assigning any reasons thereof.
2. The Tender fee will be accepted in form of Demand Draft and Earnest Money
Deposit will be accepted in form of Demand Draft or Bank Guarantee of any bank
as prescribe in ANNEXURE- I drawn in favour of “GUJARAT STATE
ELECTRICITY CORPORATION LTD.” payable at Gandhinagar TPS
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 278 PUR-F-006 RFQ-
GUJARAT STATE ELECTRICITY CORPORATION LIMITED
Gandhinagar Thermal Power Station, Gandhinagar, India–382041.
Ph. 91-79-23215663 Fax: 91-79-23217673,
e-mail: [email protected] ; Website: www.gsecl.in
CIN:U40100GJ1993SGCO19988
CE [Generation], Gandhinagar, TPS invites “On-line Tenders” (e-tendering) for the work of Repairing
and augmentation of existing drainage network in CHP area at GTPS. Tender Papers & Specifications
may be down loaded from Web site https://gsecl.nprocure.com(For view, down load and on
line submission) and GUVNL / GSECL web sites www.gsecl.in (For view only).All tender
documents are to be upload (Notarized / self-attested copies of original – as specified in tender
document) through online only (mandatory) on (n) procure portal excluding Tender fee and EMD
Tender fee and EMD are to be submitted physically by Registered Post A.D. or Speed Post addressed
to: CHIEF ENGINEER (GENERATION), GUJARAT STATE ELECTRICITY CORPORATION LTD,
THERMAL POWER STATION, GANDHINAGAR-382041, GUJARAT. “NO COURIER SERVICE OR
HAND DELIVERY” will be accepted.
Tender Estimated E.M.D.
No. Cost Rs. Rs.
Repairing and Rs. 6 (Six) Rs. 2500+ Rs.
EW-278 augmentation of 4314681.80 Months 450 = Rs.
existing from the 2950/-(Two (One Lakh
drainage date of Thousand Twenty Nine
network in CHP written Nine Thousand
area at GTPS order to hundred Four
commence Fifty only Hundred
the work. (Non Forty Rupees
Refundable) Only)
180 Days [From the opening of
1 Validity of Tender
Technical Bid].
Last Date for Online tender / offer submission through
2 As per Tender Notice
(n)Procure only up to 18:00 Hrs(This is Mandatory)
Last Date for physical receipt of cover for DD / Bank Guarantee
3 / Online payment reference for Tender Fee and EMD only up to As per Tender Notice
15:00 Hrs Through RPAD or Speed Post Only
Date of opening of online Technical Bid, all relevant documents
submitted through online process, Cover for Tender fee and
4 As per Tender Notice
EMD at 15:30 Hrs (Online technical bid will be opened for
Bidders who have submitted Cover for Tender Fee and EMD)
Tentative date of on-line opening of price bid (if possible) at Party has to be in touch with
15.30 hrs. website www.nprocure.com and
also with e-mail sent by above
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 278 PUR-F-006 RFQ-
1) Only following listed documents must be upload in n-process online only. No physical documents are to
be submitted except tender fee and EMD cover. Price Bid shall not be submitted in Hard copy.
1. Demand Draft for Tender Fee and EMD (Original) cover only to submit through RPAD/Speed post
2. The bidder shall have a separate Provident Fund Code of RPFC in the name of company. The bidder,
who does not possess such separate P.F. code, shall not be considered for acceptance of tender. The
contractor has to submit attested copy of such certificate showing P.F. code along with the tender.
3. Attested copy of PAN No.
4. Attested copy of work experience certificate for the similar works executed.
5. List of work in progress.
6. Attested copy of firm registration [Applicable only to the firms registered under Company Law]
7. Attested copy of partnership deed. [Applicable only to the partnership firms.]
8. Attested copy of power of attorney, if any, for signing the bid document.
9. Attested copy of balance sheet of profit & Loss account duly audited by Chartered Accountant of at
least 3 financial years, if work estimate is more than Rs. 50 Lacks.
10. Details of equipment, tools and plants immediately available with the tenderer for use of this work.
11. Details of technical personnel.
12. Undertaking duly Notarized as per attached Declaration Form
13. Any other documents required to verify technical, financial capability of the bidders & other Credentials
15. Attached The Copy Of GST Registration.
All such documents should be strictly uploaded in N-procure only expect Tender Fee and EMD details
cover. Otherwise the offer will not be considered and no any further communication in the matter will
be entertained.
2) In case any deviation is found in Data / Details / Documents uploaded on N-procure online offer (e-
tendering) documents then such tender will not be considered and no any further communication in
the matter will be entertained. Tenders must be un-conditional. Conditional Tenders will be rejected.
3) Further bidders are requested to submit Technical Bid documents and price – bid i.e. Schedule-B on
line only and not to submit the Technical bid and price bid in physical form expect Tender Fee and
EMD details cover. This is mandatory. If Technical bid document and price bid is submitted in physical
form expect Tender Fee and EMD details cover, same will not be opened and only on-line
Uploaded/submitted Technical bid document and price will be considered for evaluation. The bidder
is requested not to upload/submit the by online (n)procure while bid submission on in
(n)procure tender document, condition of the contract, specification & other relevant
documents, except documents as stated here above. Instead of the same, the bidder shall
upload on (n) procure scan copy of the duly Notarized Undertaking as stated below declaration form
on the stamp paper of Rs. 300/-. However, bidder may download tender document & preserve
with them in Hard Copy for their future reference. Later on, L1 bidder shall be asked to
collect the tender documents from the tender inviting authorities for the purpose of
contract agreement execution and place their signature with seal of the company.
4) It is mandatory for all the bidders to submit their tender documents viz. on-line (e-tendering) and
uploading on (n) procure in scheduled time. Tender documents submitted in physical form will not be
accepted and considered expect Tender Fee and EMD details cover. Also, all bidders shall submit
required Physical documents as stated in Tender Notice
5) GSECL reserves the rights to reject any OR all tenders without assigning any reasons thereof.
6) Tender Notice Number & name of the work shall be clearly written on the covers of containing the
Tender Fee and EMD.
7) Technical / Price Bids will be opened on the day and time indicated in the tender notice by an Officer
nominated by the Purchaser in the presence of such of the bidders who wish to be present. Any
technical questions, information and clarifications that may be required pertaining to this tender should
be referred to the CHIEF ENGINEER (GEN.) Gandhinagar TPS. Also during pre-bid meeting (if arranged)
the same may please be discussed
The exemption in payment of Tender Fee & EMD shall be given to
1. Micro & small-scale enterprises which participate directly in tendering
process for the product which they are manufacturing / service which
they are providing and have Udyam registration for items / service under
procurement.
2. Startups which participate directly in tendering process for the product
which they are manufacturing / service which they are providing and
recognised by DPIIT under the Start-up India Program and has obtained
Udyam registration.
EW- 278 PUR-F-006 RFQ-
3. Organization which has registration certificate for the manufacturing
product of the tender, from Gujarat Khadi Gramodyog Board or Khadi and
Village Industries Commission(K.V.I.C)or Commissioner of Cottage
Industries.
4. Board/Corporations/PSUs of the Central/State Government for their
own manufactured items.
5. State Government recognized organizations like(i) organizations for blinds,
dumb and deaf, disabled, mentally disabled persons;(ii)women's self-help
group recognized by Gujarat Livelihood Promotion Company; which
participate directly in tendering process for the product which they are
manufacturing / service which /they are providing.
1. Micro & Small Enterprises (MSEs) who participates directly in the
tendering process as Manufacturers or Service Providers, and holds a
valid Udyam Registration, are eligible for exemption from payment of
Earnest Money Deposit (EMD).
2. Agencies registered under Udyam in the capacity of Traders, Re-sellers, or
similar categories (i.e. other than Manufacturers/Service Providers) are
not eligible for EMD exemption.
3. Migration period for Reclassification of MSMEs: - ln case of an upward
change in terms of investment in plant and machinery or equipment or
turnover or both, and consequent re-classification, an enterprise shall
continue to avail of all non-tax benefits of the category (micro or small or
medium) it was in before the re-classification, for a period of three years
from the date of such upward change.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 278 PUR-F-006 RFQ-
DECLARATION FORM CUM UNDER TAKING
TO BE SIGNED BY BIDDER
RTGS DETAILS OF BIDDER
PROJECT SYNOPSIS
SCOPE OF WORK AND SITE CONDITION
SPECIAL NOTE FOR PRE-QUALIFICATION
GENERAL INSTRUCTION TO THE BIDDER
EW- 278 PUR-F-006 RFQ-
(To be uploaded on (n) procure online process duly notarized on Rs. 300/-
Non – Judicial Stamp Paper)
DECLARATION FORM
Tender No/ RFQ No:
1. I/We hereby declare that I/We have carefully studied the entire tender placed on
the WEB site and conditions of contract, specifications and other documents of this
work mentioned in the tender and abide by the same. Also, I/We hereby agree to
execute the same accordingly.
2. I/We hereby abide to execute the contract agreement by downloading the copies
of the conditions of contract, specifications and other documents of this work of
otherwise I/we will get copy of the same from the office of the tender inviting
authority and the same will be acceptable to me/us.
3. I/We hereby accept and confirm that any dispute on this regard shall not be
4. I/We hereby declare that I/We have visited the work site and fully acquainted
myself/ourselves with the local situations regarding materials, labour and other
factors pertaining to the work before submitting the tender.
5. I/We hereby confirm that our offer is Un-conditional and without any technical &
commercial deviations.
6. Should this tender be accepted, I /We hereby agree to abide by to fulfill all the
terms-conditions and provision of the Tender and Contract for Works as applicable
and default thereof, to forfeit and to pay to the Gujarat State Electricity
Corporation Limited the sums of money due.
7. The full value of the “Earnest Money Deposit” paid herewith should be absolutely
forfeited to the Corporation, should I/ we do not execute / commence the work
after issuance of date of commencement by GSECL.
EW- 278 PUR-F-006 RFQ-
8. If, I fail to submit all required documents with application or tender copy ( in each
tender ) then my tender will be cancelled, which is binding to me.
9. If, full or part work will be given to me, it will be accepted to me with same terms,
rate & conditions.
10. I, ______ proprietor / owner / partner / Authorized Agent of M/s. ______ do
hereby also declare and undertake as under:
a) That in capacity of independent contractor for M/s. ______ (Sub-Contractor
of M/s. ______ ) worked as contractor at GSECL, ___________Thermal Power
Station for the nature of work of ______ against work Order No. ______ Dt.
______., I have complied with the provisions of all laws as applicable. I have paid
the wages for the month/s of my contractual period which is / are not less than
the minimum rates as applicable, to all my employee/s and no other dues are
payable to my employee/s.
b) That I have covered all the eligible employee/s under the Employees‟
Provident Funds and Miscellaneous Provisions Act, 1952 and deposited the
contributions under my PF Code No. ______, place: ______ for the month/s of my
contractual period and as such no amount towards contribution whatever is
c) I further declare and undertake that in case any liability pertaining to any of
my worker, labour, employee/s is/are to be discharged by the principle employer
i.e. Gujarat State Electricity corporation Limited, ___________Thermal Power
Station due to my lapse, I undertake to reimburse the same or the principle
employer is authorized to deduct the same from my dues as payable.
d) I further declare and undertake the legal consequences which may arise in
future under the said work order awarded, and I bond myself to resolve the same
at the risk and cost of M/s. ______.
authorized signatory of M/s
______________________________________________ here by certify that M/s
_________________________________________________ and their proprietor /
any partner / any directors of the firm is not stop deal and / or banned for
business dealing and / or black listed by GUVNL and / or their any subsidiary
company viz. GSECL / GETCO / DGVCL / MGVCL / UGVCL / PGVCL as well as
Government and / or Semi Government company / department.
Seal & Signature of the Bidder
Phone / Mobile/ Fax No. & Company‟s Seal
EW- 278 PUR-F-006 RFQ-
E- Tender for the work of Repairing and augmentation of existing drainage network
in CHP area at GTPS
RTGS DETAIL OF BIDDER
Following RTGS details shall be submitted by agency along with the tender for direct deposit of
payment to the beneficiary account. Bidder has to submit the details as under:
1 Name of Bidder :-
2 Address for correspondence :-
3 E-Mail ID :-
4 Phone / Mobile No. :-
5 Name of Beneficiary :-
6 Bank Account Number of :-
beneficiary
7 Name of Bank of beneficiary :-
8 Name of Bank, branch & address :-
9 Type of account :-
10 Bank Code :-
11 RTGS Code :-
12 IFSC Code :-
EW- 278 PUR-F-006 RFQ-
Project Synopsis and Data
1) Location :- Gandhinagar Thermal power station
2) Purchaser :- GUJARAT STATE ELECTRICITY CORPORATION
3) Engineer :- Chief Engineer(Gen)
4) Site of Project :- Gandhinagar,Gujarat State
5) Nearest town :- Gandhinagar
6) Nearest Railway Station :- Gandhinagar Capital(Ahmedabad is situated at a
distance of about 30.00Km)
7) Nearest Port :-
8) Nearest Air Port :- Ahmedabad-20Km(Approx)
9) Access Road :-
10) Site Elevation from MSL :- RL 81.5 M(floor level)
11) Meteorological Data
Ambient Air temperature
1] Highest monthly mean of daily :- 35 C
Max. Temperature (
2] Maximum dry bulb :- 45 C
Temperature ( In C)
3] Minimum dry bulb :- 8.6 C
Temperature ( In C)
Rainfall
1] Average annual rainfall :- 1000 to 1200mm
2] For 01 hour ( In mm) :- 75 to 100mm
3] For 24 hour ( In mm) :- 250mm
Wind velocity
1] Maximum wind velocity :-
(In m/sec)
2] Wind direction – N,NE & SW :-
3] For 24 hour ( In mm) :-
Relative Humidity
1] Annual mean humidity ( In %) :- 50 to 60%
2] Maximum humidity (In %) :- 98%
3] Minimum humidity (In %) :- 2%
4] Type of Atmosphere :- Dry
12) DESIGN DATA
Seismic Data :-
Zone :- Zone-III as per IS 1893-1975
Intensity :-
Ambient temperature :-
Other Data :-
EW- 278 PUR-F-006 RFQ-
SCOPE OF WORK AND SITE CONDITIONS
The main scope of the work is to carryout Repairing and augmentation of existing drainage network
in CHP area at GTPS at GTPS. at GTPS.
Under the scope of this tender the agency has to carry out the subject work, various works as per all
items of Schedule B and as per detail technical specifications items. The quantities taken under
individual items are very tentative. However, the agency has to carry out the works as per the
Company’s requirements (Anywhere in PH Area).
The agency has to carry out the works as per item & specifications of the tender by providing all
materials of best quality and of standard manufactures as the samples approved by EIC and
providing best workmanship through expert manpower.
The agency has to carry out the works as per the priority & schedule given by EIC time to time even
in on or off working hours of the office. The agency will take complete care and will not damage any
other structure in premises of company.
The agency has to carry out all the works by taking all due cares of safety, security norms, with all
risks including scaffolding, strutting, shoring, etc up to any height irrespective of quantum of the
work. Anywhere in Power house premises or as directed by EIC/ as per GSECL requirement.
Contractor has to make arrangement for workable site condition with the cooperation of
departments of company and agencies, all necessary arrangement to get work permit is to be made
by contractor. Day to day cleaning is required after completion of job. The removed materials and
any other unwanted materials are to be transported and taken away as instructed by E.I.C.
All safety measures shall be taken by the contractor with his own cost.
The scope of work to be carried out by the Contractor shall also include Clearance of the site,
Disposal of debris, excavated material etc,
The major works involvement generally mentioned as here under:
Demolition of Brick work, unreinforced concrete, RCC etc.
Excavation
Brick Work
PCC , 15 mm thick plaster work
Supplying and fixing reinforced concrete heavy duty non-pressure pipes
Providing and laying controlled cement concrete M.200
Providing TMT Bar FE 415 reinforcement for R.C.C.
For & On behalf of GSECL
CHIEF ENGINEER
SIGNATURE OF CONTRACTOR GSECL: GTPS
EW- 278 PUR-F-006 RFQ-
Registration in VMS System
Additional Note: Vendor gets to register in VMS System through vms.guvnl.com. For
registration following documents are required and mail to [email protected] and
[email protected]. After registration vendor have to upload the invoice in the VMS
system for smooth functioning of payment.
Documents required for Registration:
(1) PAN Copy
(2) GST Certificate Copy
(3) Email ID
(4) Full Name of Vendor
EW- 278 PUR-F-006 RFQ-
SPECIAL NOTE FOR PRE-QUALIFICATION
area at GTPS
The tender documents are of two separate bids i.e. technical and price bids. Bidder is
requested to submit the technical bid with the following credentials for post-
qualification.
1. Bidder should produce evidence of having experience of successfully completed
similar works as defined hereunder, carried out in Central & State Government / Semi-
Government / GSECL / GETCO / DGVCL / MGVCL / UGVCL/PGVCL during the last seven
years ending last day of the month previous to the one in which tender is invited. Bidder
should submit self-attested copies of documentary evidence, preferably photo copies of
work completion certificate, certificate regarding works on hand progressing
satisfactorily along with certificate of amount of work done, work order with Schedule-
B, etc. from the respective department. The amount of completed works should be either
of the following:-
a. Three similar completed works each costing not less than the amount equal to
b. Two similar completed works each costing not less than the amount equal to
c. One similar completed works each costing not less than the amount equal to
2. Similar work means– General Civil Construction / Civil Maintenance works. The
work of housekeeping, horticulture, cleaning, anti-termite, fabrication will not be
considered in similar works.
3. Experience certificate of work executed with private firm shall not be accepted.
Experience as a joint venture or sub-contractor is not allowed and price bid of such
bidders will be rejected.
4. EMD: To pay EMD in form of DD OR in form of B.G. given by bank as
described in the Annexure – I.
5. Tender Fee: The tender fee shall be accompanied in the form of DD.
6. Separate employee’s Provident Fund code number towards registration of
firm with Regional P.F. Commissioner.
7. Financial qualification criteria:
1) The Average Annual Turnover of the bidder, shall not be less than Rs.
during the preceding three (3) financial years as one date of Techno-Commercial bid
2) Net worth of bidder shall not be less than 100% of the bidder’s paid up share capital
as on the last day of the preceding financial year. In case the Bidder meets the
requirement of Net worth based on the strength of its Subsidiary (ies) and/or
EW- 278 PUR-F-006 RFQ-
Holding company and/or Subsidiaries of its Holding Companies wherever
applicable, the Net worth of the Bidder and its Subsidiary (ies) and/or Holding
company and/or Subsidiary (ies) of the Holding Company, in combined manner
should not be less than 100% of their total paid up share capital. However
individually, their Net worth should not be less than 75% of their respective paid
share capitals.
Net worth in combined manner shall be calculated as follows:
Net worth (combined )= (x1+x2+X3)/(y1+y2+y3) X 100, where x1,x2, x3 are
individual net worth which shall not be less than 75 % of the respective paid up
share capitals and y1, y2, y3 are individual paid up share capitals.
3) In case the bidder is not able to furnish its audited financial statements on stand-
alone entity basis, the unaudited unconsolidated financial statements of the
bidder can be considered acceptable provided the bidder further furnishes the
following documents for substantiation of its qualification.
Copies of the unaudited unconsolidated financial statements of the bidder along
with copies of the Audited consolidated financial statements of its Holding
A Certificate from the CEO/CFO of the Holding Company, stating that the
unaudited unconsolidated financial statements form part of the Consolidated
Annual Report of the company.
4) In cases where audited results for the last preceding financial year as on the date
of techno-commercial bid opening are not available, the financial results certified
by a practicing Chartered Accountant shall be considered acceptable. In case,
Bidder is not able to submit the Certificate from practicing Chartered Accountant
certifying its financial parameters, the audited results of three consecutive
financial years preceding the last financial year shall be considered for evaluating
the financial parameters. Further, a Certificate would be required from the
CEO/CFO, stating that the Financial results of the Company are under audit as on
the date of Techno-commercial bid opening and the Certificate from the practicing
Chartered Accountant certifying the financial parameters is not available.
5) The bidder must submit Average Annual Turnover and Net worth Certificate in
support of Financial QR, duly certified and verified for authenticity from
Independent Statutory Auditor of their company / Practicing Charted Accountant/
C.A. Firms / TPIA (Third-Party Inspection Agency ) empaneled approved by
GSECL, along with copy of Annual Audited Accounts of last three years.
8. Attested copy of relevant document duly signed and sealed on each and every page
shall be submitted.
9. Attach copy of GST Registration
10. Details of orders for similar nature/jobs carried out along with documentary
Evidence, Performance Certificate and their organization set up for such work
executed in past there of indicating the Names of the organizations, order no and
11. Bidder shall have to submit the PAN card No for Income Tax with documentary
12. Details of the partnership deed.
EW- 278 PUR-F-006 RFQ-
13. Details of Tools, tackles, equipments and personals available with firm relevant to
the job/subject matter.
14. Copy of the updated valid labor contract license from the appropriate authorities and
updated workman group insurance policy covering labor engaged.
15. The tenderer shall have to produce the document of last three years annual account,
i.e. profit & loss account and balance sheet, if the estimated cost of tender is more
than 50 lakhs along with technical bid.
16. Details of skilled/semi-skilled persons presently employed by the contractor having
sufficient knowledge of similar jobs.
17. Declaration form in original duly notarized on stamp paper of Rs. 300/- (As referred
in Tender Notice)
The above documents will be analyzed and after satisfaction, the price bid will be
opened. GSECL may verify the documents, experience certificates from authority who
have issued such certificates / details.
On opening of Technical Bid, if any required attested documents are missing in technical
absence of these documents sufficient competition is not possible, in that case to have
to bidder/bidders to submit the missing required documents within stipulated time
limit and failing which bidder/bidders will be declared technically disqualified for not
submitting the required documents along with technical bids without any further
notice. However, document will be considered valid only if it is for the period of last day
of month previous to the one in which tenders are invited.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 278 PUR-F-006 RFQ-
GENERAL INSTRUCTIONS TO THE BIDDERS
1. SUBMISSIOIN OF TENDER
The tender should be uploaded/ submitted online on n-procure process.
Technical bid cover:- This cover shall contain all relevant attested qualifying documents as
prescribed in tender notice along with tender fee & EMD. Bidder shall have submit Tender Fee
and EMD cover only, All other require document to be upload on online (n)procure process only
Note: - If attested copies of qualifying documents stated as prescribed in tender
notice are not found in on-line Technical bid, but same should be submitted by mail
during scrutiny will be treated as final to consider the bid for pre-qualification. Any
missing documents, if required will be asked from the bidder as mentioned in this
tender elsewhere. If party has not submitted tender in online is liable to be ignored.
Technical Bid
“Please note that the Notarized / self-attested copies of original required documents
should be invariably uploaded in n-procure portal before due date and time in pdf
form (Scanned copy). This is mandatory. No physical documents are required to be
submitted except tender fee and EMD.
Price bid:-
The price bid shall have to be submitted online only. The percentage rates and price shall be
written both in words, and figures and the units in words. In case of any ambiguity or mistakes,
the unit rates and prices written in words shall be considered as final.
Offered rate shall include cost of all Materials, wastage of material , Labours for all leads and
lifts, Supervision, setting out works, Machinery and equipment with its mobilization /
demobilization, transportation charges, Clearing of the site both prior to commencement and
after completion of work. Consumables such as, but not limited to petrol, oil, diesel, lubricants,
drill bits, pipes, ropes etc. Construction facilities such as scaffolding, tarpaulins, wind break, etc.,
Overheads / profits of Contractor for due performance of the work under this contract.
Applicability of goods and service tax:-
1) The tenders shall be evaluated on firm price and cost with GST and cess as applicable unless
otherwise mentioned in the tender documents.
2) IF the supplier/contractor have opted for the composition scheme of GST, the same must be
clearly specified with valid declaration and certificate from department. In the event of
withdrawal/ cessation of the supplier from composition scheme during the tenure of the contract,
the rate(i. e. price) mentioned in the price bid shall be final and any additional GST will have to
be borne by the tenderer himself, In no case additional amount towards GST or otherwise will be
paid/reimbursed to supplier/contractor.
EW- 278 PUR-F-006 RFQ-
3) The bidder shall have to inform their GST no. of the registered place(s) where from the bidder
intends to supply the goods/services, meaning there by the bidder has to supply the
goods/services from the relevant declared/ registered place(s) of supply only.
4) The bidder shall not include GST in their quoted rates; but the bidder has to separately indicate
the GST rate, amount in the price bid schedule.
5) In-case Govt notification comes for change in GST , the same will be applicable.
6) Bidder should indicate GST no.( copy of GST registration to be enclosed) and PAN NO. (copy of
PAN to be enclosed) Tenders submitted without GSTIN No by the firms, the offer will be rejected
without entering into further correspondence.
Further information required, if any, can be had from the office of the Chief Engineer, GSECL,
GTPS. But it must be clearly noted that the tenders must be received complete in every
respect by the due date and time.
i. The bidder must clearly quote rates in figure as well as in words. In case of any discrepancy,
whatever written in words shall prevail.
ii. No deviation in terms & conditions, Schedule-B and technical specifications will be entertained.
Any ignorance for this shall not relieve the contractor from his contractual liability arising as per
tender documents and conditions contained in it.
iii. The bidders are required to quote only firm prices. No variation will be accepted on price/ raw
materials/ finished products or on any other cause.
iv. The bidders should note that the completion of above mentioned works in all respect in
accordance with the time limit given is very important and should be strictly adhered to. The
work is to be completed in time limit from the date of issue of written order to commence the
work by the Chief Engineer (Gen.), GSECL, Gandhinagar TPS.
v. The bids should be valid for a minimum period of 180 Days from the date of opening of
technical bid. During this period tenderer shall not be allowed to withdraw their tender and if
withdrawn, the Earnest Money Deposit submitted with the tender will be forfeited.
vi. The works covered under these specification shall be carried-out and governed by “Tender and
contract for Works” booklet appended herewith except where conditions specified in this
specifications.
vii. The successful bidder shall have to enter in to an agreement for contract as per G.S.E.C.L rules
on a stamp paper of Rs.300/- and necessary stamp duty charge shall be borne by the
contractor/consultant.
viii. The complete specification comprises of the following.
Bill of Quantities (Schedule-B), instructions to the bidders, Tender specifications and scope of
work, Tender and contract for Works booklet, General Conditions, Instructions to bidder &
Technical specifications. All these sections are complimentary to each other. The particulars
and requirements contained herein shall cover the execution of the works covered under these
specifications.
ix. The tenderer must visit the site of works and see for him self the site conditions regarding
availability of approach road during all seasons and other matters affecting the above works
before submitting the tender.
x. The submission of tender by a contractor implies that he has read these instructions the
conditions of contract etc. and has himself aware of the scope and specifications of the work to
be done and of conditions and local conditions and other factors bearings on the execution of
the works. GSECL will not therefore after acceptance of contractor's rate pay any extra charge
for any other reason; in case the contractor is found later on to have misjudged the site
condition.
xi. GSECL‟s authorized officers who accepts tender, shall have the right of rejecting all or any of
the tenders and will not be bound to accept the lowest offer nor to assign any reason
whatsoever for the rejection of any tender or all tenders.
xii. Bidders shall provide evidence of their continued eligibility to the satisfaction of the owner.
xiii. Bidders shall not be listed under a declaration of ineligibility for corrupt or fraudulent Practices
issued by the Govt., the list of black listed Contractors announced by GSECL (erstwhile GEB)
Govt. of Gujarat or its Public Sector undertakings or the contractors who are under stop dealing
in GUVNL and /or their any subsidiary company viz. GETCO/MGVCL/UGVCL/PGVCL/DGVCL.
xiv.The bid, and in case of a successful bid, the Form of Contract Agreement, shall be signed
EW- 278 PUR-F-006 RFQ-
with the name of Firm / company which will be legally binding on all partners / parties.
xv.If the application is made by an individual, it shall be signed by the individual above his full
typed written name and current address.
xvi.If the application is made by a proprietary firm. It shall be signed by the proprietor above
his full typed written name and the full name of his firm with its current address.
xvii.If the application is made by a partnership firm, it shall be signed by all the partners of the
firm above their full type written names and current addresses or alternatively by partner
holding power of attorney for the firm in which case a certified copy of the power of
attorney shall accompany the application. A certified copy of the partnership deed, full
names and current addresses of all the partners of the firm shall also accompany the
application.
xviii. If the application is made by a limited company or a Corporation, it shall be signed by
the authorized person holding power of attorney for signing application in which case a
certified copy of the power of attorney shall accompany the application. Such Limited
company or Corporation may be required to furnish satisfactory evidence of its existence
before the pre-qualification evaluation. They should also furnish Articles of Memorandum of
Association. If the application is made by group of companies, it shall be signed by the
authorized person. The authority letter shall be accompanied with the application.
2. SECURITY DEPOSIT
It should be mandatory to submit security deposit as per cl no.7 of Section C (i.e General
condition of contract).
3. MAINTENANCE:
i] The contractor shall be responsible to make good and remedy at his own expense any defect
which may develop or may be noticed before the period mentioned hereunder from the
certified date of completion. The same shall be attended within 15 days of receipt of the
notice. In the case of failure on the part of the contractor, the Engineer-in-charge may
rectify or remove or re-execute the work at the risk & cost of the contractor. The Engineer-
in-charge shall be entitled to appropriate the whole or any part of the amount of security
deposit towards the expenses, if any, incurred by him in rectification, removal or re-
execution. The defects liability period shall be as under:
a) For all works costing more than Rs. 50,000 and up to Rs. 1 crore (amount put to tender),
the period shall be 06 months from the certified date of completion OR one monsoon,
whichever is later.
For the purpose of deciding monsoon period, the 30 th September may be treated as the last
4. TIME LIMIT FOR WORK:
The scheduled time limit for the completion of work shall be 6 (Six) calendar months from the
date of issue of letter to commence the work. However extension in time limit will be granted
by GSECL for the genuine reasons only as per terms of the contracts.
5. TERMS OF PAYMENTS:
Contractor shall be paid RA bill after observing GSECL’s general procedure and submission
of bill by the agency. Also, 75% payment shall be made immediately within a week period on
receipt of recorded bill by Account Section without checking of detail bill and compliance of
queries & statutory requirement. However, remaining balance 25% amount shall be
released only after through checking of detail bill and compliance of various quarries,
statutory compliance etc. The above payment term is applicable to all the bills of general
civil works & ARC/BRC works, provided the bills are recorded regularly and submitted to
Account Section within Ninety [90] days. If the contractor fails to submit the bills regularly
in such a way so that the same cannot be recorded and submitted to account section within
EW- 278 PUR-F-006 RFQ-
Sixty [60] days, ad-hoc payment as stated above, may not be released and payment will be
released as per GSECL’s general procedure. The period of Sixty [60] days shall be considered
from the date of receipt of last R.A. Bill by Account Section.
6. METHOD OF PAYMENT:
a. The payment for the work done will be made by running bills every month after
taking joint measurement within 30 days.
b. Final bill will be paid within reasonable time after settlement of material account by
you and after recording of joint measurement.
7. All bidders shall submit the details/documents in support of Technical Qualification
Requirements duly certified and verified for authenticity from Specified Third-Party
inspection Agency (TPIA) or Statutory Auditor of their Company or Practicing CA,/CA
Firm along with a certificate regarding verification of authenticity of documents as per the
format placed at Annexur-1. All the documents submitted by the bidder in support of the
meeting Technical QR only shall be digitally signed by the Specified Third Party
inspection Agency (TPIA) or Statutory Auditor of their Company or Practicing CA/CA
The verification and certification of authenticity of documents is acceptable from
any of the following TPIAs:
1. M/s Competent Inspectorate and Consultants Pvt. Ltd, Hyderabad,
2. M/s Gulf Lloyds Industrial Service India Pvt. Ltd.-Ahmedabad.
3. M/s International Certifications Services.
4. M/s Intertek India Pvt. Ltd.
5. M/s SGS India Pvt. Ltd.
6. M/s Moody International (India) Pvt. Ltd.
7. M/s TUV SUD South Asia (P) Ltd.
8. M/s TUV Rheinland (India) Pvt Ltd.
9. M/s Bureau Veritas (india) Pvt. Ltd.
10. Hertz Inspection & services Pvt. Ltd.
11. IRCLASS Systems and Solutions Pvt. Ltd.
Verification for authenticity shall not be applicable in following cases.
1. Bidders having proven track record or regular suppliers/contractors (i.e.
OEM/OES/PSUS)
2. Past order copies of GSECL as these documents can be verified
internally.
Bidders shall be responsible for getting their documents/ credentials verified &
certified by the Specified Third-Party Inspection Agency (TPIA) or Statutory
Auditor of their Company or Practicing CA/CA Firm in support of Technical
QR. All the costs pertaining to third party verification and certification
(including those by statutory auditors) shall be borne by the Bidder. GSECL
shall have no liability (financial or Otherwise) towards the same and shall not
be liable for any claim/ dispute between the bidder and the Specified Third-
Party inspection Agency (TPIA) or Statutory Auditor of their Company or
Practicing CA/CA Firm
Annexure-1
Undertaking from Third Party inspection Agency/Statutory Auditor or
Practicing CA/CA Firm
(On letter head digitally signed by a person duly authorized to Sign on behalf of the firm)
Ref: Date:
EW- 278 PUR-F-006 RFQ-
Power Station ……………….
Subject: Authentication of veracity of documents submitted by M/s ........ in support
Meeting the Qualifying Requirements
Ref: Tender no. …………………..
Name of the Package/ Tender: ………………………………………
M/s. ……………… (hereinafter called Bidder) having Registered office at ……………………
intend to participate in above referred tender of GSECL.
The tender condition stipulates that the bidder shall submit supporting Documents
pertaining to Qualifying Requirement duly verified and certified by Third-Party
Inspection Agency (TPIA) or Statutory Auditor of their Company or Practicing CA/CA
Firm as per the list mentioned in the bidding documents.
In this regard, it is hereby confirmed that we have examined the following
documents, which are also attached with this letter. The same has been verified
from the Original Documents and / or Client for authenticity.
We hereby confirm that the following documents are found to be genuine and
authentic.
1. Doc ref. no. ……….. Dated …….. (Name of Documents)
2. Doc ref. no. ……….. Dated …….. (Name of Documents)
All the aforesaid documents have been digitally signed by us as a certificate of
authenticity.
We further confirm that we neither have any vested interest in aforesaid tender nor
have any conflict of interest in respect of above tender.
This certificate is issued at the request of M/s ………………. (Bidder) for the purpose of
participating in the subject tender/s
Thanking you,
8. ASSIGNMENT:
The rights and liabilities of the contractor shall not be assigned or transferred by them without
the consent in writing of the GSECL to any other person, firm or organization.
9. The successful Bidder, on receipt of letter of intent will submit within a week's time his
planning / programme of works, for scrutiny of the GSECL in a Bar Chart format, clearly
indicating GSECL's inputs also. Contractor will plan his works such that simultaneous work
should progress in such a way that entire job is completed in scheduled time limit on all
the fronts released by GSECL.
EW- 278 PUR-F-006 RFQ-
10. The successful bidder will have to depute his authorized representative to attend progress
review meetings to be held at GSECL, Gandhinagar TPS without any extra cost.
11. The Contractor will be responsible for complying with all rules and regulations and labour
laws applicable to him and the GSECL will not be responsible for any lapses committed by
them. If there is any claim from any Government authority pertaining to the contract, the
same amount will be deducted from the Contractor's bill.
12. The time limit for completion of work is stipulated as in the tender will be adhered to.
13. The Contractor's rates should be firm and no variation clause is to be quoted by the
Contractor and GSECL will not accept the same, during contractual period including
extended time limit if any.
14.BIDDER TO STUDY, ANALYSE & CONSIDER:
a) The information given in this specification is in good faith and meant to serve as a
guide to the Bidder. It is, therefore, imperative that Bidder shall obtain and examine for himself
all the data, information and particulars required for the satisfactory execution of the work
under this tender. The submission of a bid by Bidder implies that he has fully read the
specifications, bid drawings, instruction to the bidder along with Contract Document and
Conditions of Contract, applicable labour laws, safety norms etc., and has made himself aware
of the scope and the specifications for the work to be performed and local conditions and other
features which have a bearing on the cost and execution of the work. This specification is
intended as a general description of quality envisaged for materials and workmanship and of
the finished work. It is not intended to cover minute details. The work shall be executed in
accordance with the best modern practice and to the complete satisfaction of the Purchaser.
Special techniques approved by the Purchaser shall be used if and where found necessary. This
specification shall have precedence if anything contrary to this is stated elsewhere in the
contract documents. The Purchaser‟s decision shall be final and binding on the contractor on
any issue arising out of such discrepancies.
b) Inspection of site by bidder:
Before submission of his bid, Bidder shall inspect the site, examine and obtain all information
required and satisfy himself regarding matters such as:
weather characteristics,
Location of site and access, right of way, means of communication & mode of Transport to
The type and number of equipment and facilities required
The quantity of various items of the work.
The availability and rates of material.
Labours condition.
Local working conditions, obstructions and hindrances that may arise etc.
Power house, which is under running conditions.
Required GSECL‟s security checks.
All materials brought to site only after making entries in security register at Control gate
c) These factors are likely to affect the satisfactory completion of work and or cost thereof.
The submission of a bid by the Bidder will be construed as evidence that such an
examination was made and any later claims/ disputes in regard to rates quoted shall not
be entertained or considered by the GSECL.
d) The site visit shall be done by the bidder on his own responsibility and all liabilities
including cash, arising out of the site visit shall be at the bidder‟s account.
e) Contractor‟s scope of work shall also include making all necessary arrangements for
access to work sites, stores and site offices etc. from the nearest approach road to
facilitate transportation of man power, machinery and equipment duly considering the
existing site conditions. No extra claims / costs will be entertained by GSECL.
f) The bidder shall carefully study the work to be carried out & consider all the factors &
shall take into account &consider all the factors such as lead, lift haulage of materials,
sequence of construction, etc. & shall allow for all such information / data in the rates
g) The GSECL will not pay any extra charges or rate for any reason in case the contractor
EW- 278 PUR-F-006 RFQ-
claims, after acceptance of contract to have misjudged the site condition. Ignorance of
the intents and contents of the specification document and site conditions shall not be
accepted by the Owner as basis for any claims for compensation.
h) BIDDER shall inspect the site, examine and obtain all information required and satisfy
himself regarding matters such as sub-surface conditions, water records, access to site,
communication, transport, right of way, the type and number of equipment and facilities
required for the satisfactory completion of work, the quantity of various items of the
work, the availability and rates of material, local working conditions, uncertainties of
weather, obstructions and hindrances that may arise etc. which may affect the work or
cost thereof, before submission of his bid. Ignorance of site conditions shall not be
accepted by the ENGINEER IN CHARGE as basis for any claim for compensation.
i) The rates quoted by BIDDER shall be based on his own knowledge and judgment of the
conditions and hazards involved and shall not be based on any representations of the
Engineer in Charge. No claim on this account shall be admitted by the GSECL.
j) The bidders shall submit on online in n-procure with their offer without any deviations in
general terms and conditions of the contract or in technical specifications.
k) Tenders received after the time and date specified in the tender notice will not be
accepted. Once the offer is submitted by bidder before due date of submission, the bidder
shall not be allowed to submit revised/ additional/ modified offer even before due date
and time of submission of tender. However, if the date of issue and/or submission of
tender are extended by the Corporation due to any reason, the bidder may submit if their
wishes the revised/additional/modified offer before extended due date and time of
submission.
l) The Corporation reserves the right to accept any tender irrespective of whether it is
lowest or not or to reject all the tenders without assigning any reasons thereof. Tenders
deferring from the technical specifications or the method of bidding in a radical manner
may also be rejected.
m) The bidder shall be presumed to have carefully examined the drawings, conditions &
specifications of work & to have fully acquainted themselves with all details of the site
conditions, locations, materials, geological & weather characteristics, labour conditions &
in general all the necessary information and data etc. pertaining to and need for the
n) This specification is intended as a general description of quality envisaged for materials
and workmanship and of the finished work. It is not intended to cover minute details. The
work shall be executed in accordance with the best modern practice and to the complete
satisfaction of the Purchaser. Special techniques approved by the Purchaser shall be used
if and where found necessary. This specification shall have precedence if anything
contrary to this is stated elsewhere in the contract documents. The Purchaser‟s decision
shall be final and binding on the contractor on any issue arising out of such discrepancies.
o) Each bidder shall also submit a 'Declaration' to the effect that the tenderer is an
engineering construction firm or an association of firm or firm which has successfully
carried out large works of this nature and has adequate organization and experienced
personnel to handle this type and magnitude of work. Information should also be given
regarding the constitution of the firm; it‟s authorized, subscribed & paid up capital, the
date & place of registration, the place of business, the names of the directors and other
relevant information.
p) It is the intent of the ENGINEER IN CHARGE to incorporate these specification documents
in the final „Contract‟. BIDDERS are required to review these documents and clearly state
in their proposals their acceptance of the same.
q) Each page of the bid document including the bid drawings shall be signed, stamped and
dated in ink by the BIDDER as a token of having examined the same. Any correction in
price and the rates entered in the Schedule of Price shall also be signed and dated by the
BIDDER in ink, before submitting the bid. Non-compliance with this condition will make
the bid liable for rejection.
r) All safety measures as required to be adopted as per the Statutory Regulations and the
Safety Rules of the Plant shall be strictly followed by the Contractor during the execution
EW- 278 PUR-F-006 RFQ-
of the Contract. The Contractor shall set up a suitable safety organization of his own in
this regard.
s) In connection with the execution of the Contract, the Contractor shall comply with all
applicable statutory Rules & Regulations including employment of labours at site.
t) The Contractor shall carry out any and all such works, as may be required, for civil work
to be completed in all respect as per the Contract Specification.
u) If the GSECL Engineer-in-Charge is not satisfied with the progress of work at site, he shall
direct the Contractor to depute more numbers of supervisory personnel/workers to meet
the completion schedules as per the Contract. Upon receiving such direction, Contractor
shall deploy additional personnel within 7 days without any extra cost.
v) The GSECL may during the progress of work, order the removal of part or whole of the
work executed, found not in accordance with the specifications/ instructions. No extra
claims shall be entertained for re-executing or altering of such work.
15. SAFETY MEASURES:
The contractor shall ensure the safety of workers, material and structure including
existing structures during execution of the contract. Safety measures shall be followed
during operations of equipments/machinery being used. No separate payment shall be
made for the safety measures and the quoted rates shall include the cost for all safety
16. COMPLETENESS:
Any technical services as set forth here in above and which might not have been
specifically mentioned in this Contract relating to the work or in the specifications and
which are not expressly excluded therefore but which are necessary for the performance
in accordance with the specifications as an integral part of the painting and misc. Civil
works shall be rendered by the Contractor without any extra cost.
17. TOTAL RESPONSIBILITY
The Contractor shall be solely responsible for the entire technical works / services
irrespective of works / services have been made /rendered by him.
18. PAYMENT TO THE LABOURES:
(a) Contractor has to pay the CPF as well as salary to his skilled/unskilled manpower by
cheque A/c payee only, as per minimum wages & prevailing applicable rules on or
before 7th day of next month.
(b) Contractor has to produce challan of PF with list of employees.
(c) Contractor shall have to make payment to his labours in presence of Personal Officer
(Estt.) GSECL, Gandhinagar TPS.
19. CONTRACT AGGREMENT ON ACCEPTANCE:
The successful contractor will have to sign an agreement as per the Gujarat State
Electricity Corporation Ltd.'s rules on stamped paper and the necessary stamp duty
charges shall be borne by the contractor.
On acceptance of the tender the name (s) of the accredited representative (s) of the
tenderer who would be responsible for taking instructions from the Engineers of the
GSECL shall be communicated to Chief Engineer (Gen.) Gandhinagar Power Station,
Gujarat State Electricity Corporation Limited.
20. Unsatisfactory progress of the work:
If the work is found not progressing as per the requirement or found not satisfactory
then GSECL will take such action to get the work done through the other agency at
agency‟s risk and cost with 15% supervision charges and same will be recovered from
21. The EMD will be returned promptly to the unsuccessful bidder except that of L1, L2 & L3
till the successful contractor pays the Security Deposit as mentioned in tender document
or after the expiry of the validity of the offer, whichever is earlier.
The EMD will be returned to the successful tenderer after he furnishes the Security
Deposit for the tender work. If he fails to furnish the SD, his EMD shall be forfeited and
the tenderer will not be allowed to participate in the tenders invited by this office for a
period of ONE Year in respective Power Station.
EW- 278 PUR-F-006 RFQ-
The EMD in form of Bank Guarantee shall be valid for Ten Months from the
date of submission of the tender.
22. Effect and validity of Bid: The submission of bid with these documents and specification
shall constitute an agreement that bidder shall have no cause of action or claim against
the GSECL for rejection of his bid. The GSECL shall always be at liberty to reject or
accept, split any bid or bids at its sole discretion and any action will not be called into
question and the bidder shall have no claim in that regards against the GSECL.
23.Stop Deal / Banned for business dealing / Blacklisting :-
Has submitted fake, false or forged documents/certificates
Has revised/ withdrawn price bid after opening of Techno-commercial bid, until and
unless it is sought for,
Has tempered with the stipulated tendering procedure.
Has refused to accept Letter of Acceptance / Purchase order / Work Order after the
same is issued by the company within the validity period and as per agreed terms and
conditions,
Has committed breach of contract or has failed to perform a contract or has abandoned
the contract,
Has failed to provide suitable expertise for the work as per pre-scheduled program.
Has failed to submit all the necessary tests reports / documents within time scheduled /
as per company‟s time limit, as mentioned in the LOA, if the Letter of Acceptance (LOA)
is placed subject to submission of type reports / documents to the firm.
Has indulged in construction and erection of defective works.
Has supplied inferior quality / defective materials and refused to replace with stipulated
time frame, as specified by the company,
Has substituted materials in lieu of materials supplied by the company or has not
returned or has short returned or has unauthorisely disposed of materials / documents /
drawings / tools or plants or equipment supplied by the Company,
Has involved in malpractices such as bribery, corruption, fraud, canvassing and
pilferage,
Has unauthorisely obtained official company information or copies of documents, in
relation to the Tender / Contract.
Has failed to follow the stipulated mode of communication, if specified by the tendering
authority / Purchaser.
Has parted with, leaked or provided confidential / proprietary information of the
company given to the firm only for its use (in discharge of its obligations against an
order) to any third party without prior consent of the Company,
Any other ground for which in the opinion of the Company makes it undesirable to deal
with the Firm
In case the state Government directs the Company to place a firm in stop dealing /
banned for business dealing / blacklisting.
24. Conflict of Interest among Bidders / Agents
A bidder shall not have conflict of interest with other bidders for particular quoted item. Such
conflict of interest can lead to anti-competitive practices to the detriment of Procuring Entity's
interests. The bidder found to have a conflict of interest shall be disqualified. A bidder may be
considered to have a conflict of interest with one or more parties in this bidding process for
particular quoted item, if:
a) They have proprietor/partner(s)/Director(s)in common; or
b) They receive or have received any direct or indirect subsidy/financial
stake from any of them; or
c) They have the same legal representative/agent for purposes of this bid; or
d) they have relationship with each other, directly or through common third parties, that
puts them in a position to have access to information about or influence on the bid of
another bidder, or
EW- 278 PUR-F-006 RFQ-
e) bidder participates in more than one bid in this bidding process. Participation by a
bidder in more than one Bid will result in the disqualification of all bids in which the
parties are involved. However, this does not limit the inclusion of the components/
sub-assembly/ assemblies from one bidding manufacturer in more than one bid.
f) In cases of agents quoting in offshore procurements, on behalf of their principal
manufacturers, one agent cannot represent two manufacturers or quote on their
behalf in a particular tender enquiry. One manufacturer can also authorise only one
agent/ dealer. There can be only one bid from the following:
1. The principal manufacturer directly or through one Indian agent on his behalf; and
2. Indian/foreign agent on behalf of onIy one principal.
g) A Bidder or any of its affiliates participated as a consultant in the preparation of the
design or technical specifications of the contract that is the subject of the Bid;
h) in case of a holding company having more than one independently manufacturing
units, or more than one unit having common business ownership/ management, only
one unit should quote. Similar restrictions would apply to closely related sister
companies. Bidders must proactively declare such sister/common business/
management units in same/ similar line of business.
i) Bidder shall not act in contravention/violation to the provisions of competition act, as
amended from time to time.
Every bidder should, at the time of submission of bid, give a declaration, that bidder shall
not have conflict of interest with other bidders for particular quoted item, as above.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
SECTION-C:
EW- 278 PUR-F-006 RFQ-
GENERAL CONDITIONS OF CONTRACT
EW- 278 PUR-F-006 RFQ-
GENERAL CONDITIONS OF CONTRACT
1. DEFINITIONS :
(a) The Contract means the documents forming the tender and acceptance thereof,
together with the documents referred to therein or individual work order in the case of
term contract, including these conditions, schedules and/or additional conditions
attached to the form of tender or individual works, order, rate schedule, the
specifications and the drawings and all these documents, as applicable, taken together
shall be deemed to form the contract.
(b) The “Tender Document” means the form of tender, the applicable schedules and/or
additional conditions and the specifications and/or drawing as issued to the contractors
for the purpose of preparing tender.
(c) The expression “Works” or “Work” when used in the condition of contract shall, unless
there be something in the subject or context repugnant to such construction means,
the works or the work contracted to be executed under or in virtue of the contract
whether original or altered.
(d) The “Contractor” means the individual or firm or Corporation, whether incorporated or
not, undertaking the words and shall include his or its legal personal representatives,
successors and permitted assignees.
(e) “Corporation” means The Gujarat State Electricity Corporation Ltd. and the “Accepting
Officer” means the Officer who is authorized to sign and signs the contract on behalf of
the “Corporation”.
(f) The letter “EE” means Executive Engineer who in the case of measurement and lump
sum contract, direct the contract and the letters “SE” means Superintending Engineer
and “GM” means General Manager who administers and in the case of the term
contracts, directs the contract.
(g) The “Engineer-in-charge” means all officers of the Corporation appointed by the
General Manager to supervise the works or part of the works.
(h) “Approved” and “Directed” means the approval or direction of the Chief Engineer
(Gen), Gandhinagar TPS to Superintending Engineer or the person deputed by him for
the particular purpose.
(i) “BS.” means “British Standards” as issued by the British Standards Institution. “A.S.”
means the “American Standards” as issued by the American Standards Institution, and
“I.S.” means the “Indian Standards” as issued by the Indian Standards Institution.
Wherever the above-mentioned abbreviations are referred to, in the specifications
and/or work orders, they mean the addition with all amendments current at the date
of issue of tender document of work orders.
(j) In the case of measurement and terms of contract “Specifications” mean those
contained in Gujarat State Electricity Corporation Ltd. scheduled together with any
amendments etc. embodied in the tender documents. “Drawing” refers to those
incorporating the tender documents and/or any work orders referred therein.
(k) The “Contract Sum” means the sum accepted or the sum calculated in accordance
with the prices accepted in the tender and/or the contract rate as payable to the
contractor for the full and entire executing and completion of works.
(l) “The date for completion” is the date or dates of completion of the work or any part of
the works set out or ascertained in accordance with the individual work orders and the
tender documents or any subsequent agreed amendments thereto.
2. CONTRACTOR TO INFORM HIMSELF FULLY:
A. Notwithstanding anything contained to the contrary in the specifications or tenders in
subsequent exchange of correspondence, the conditions of contract shall be binding on
the Contractor and any change or variation expressed or implied, however made in the
said conditions, shall not be valid or operative unless expressly sanctioned by the
Corporation. The Contractor shall be deemed to have fully informed himself and to
EW- 278 PUR-F-006 RFQ-
have special knowledge of the provisions of the conditions of the Contract herein
contained.
B. The contractor shall be deemed to have carefully examined the work and site
conditions, the general conditions, the special conditions, specifications, schedules
and drawing and shall be deemed to have visited the site of the works and to
have fully informed himself regarding the local conditions.
C. If there shall have any doubt as to the meaning of any portion of these general
conditions or special conditions of the scope of work of the specifications or any other
matter concerning the contract, he shall in good time before submitting his tender,
send for the particulars thereof and submit them to the Engineer-in-charge in
writing in order that such doubt may be removed.
3. CONTRACT DRAWING AND SPECIFICATIONS:
The contractor will be entitled to receive one set of agreement along with one certified
copy of accepted tender.
The drawings which form part of these specifications show the work to be done in as
much detail as is possible at the present stage. They will be supplemented by such
additional detailed drawings as may be necessary as the work progresses. The
contractor shall perform the work on these features and in accordance with these
additional or revised drawings as the case may be and at the applicable rates as per
the contract.
The contractor shall check all drawings carefully and shall bring to the notice to the
Engineer-in-charge immediately of any errors or omissions discovered. The contractor
shall not take advantages of errors or omissions of any kind in the drawings supplied.
4. INPUTS BY GSECL:
The electric power supply and connection for construction / work purpose shall be given
at one mutually agreed point at work site free of cost by the GSECL. Further extension
for construction site as well as bore well site for using construction water will have to
be carried out by the contractor as per requirement at their cost. The necessary
electric charges will be paid by the contractor as per rates prevailing from time to time
in the respective DISCOM.
1. If there are any surplus quarters available after meeting the requirement of GSECL's
staff, then GSECL will consider allotment of quarters on rent as per GSECL's rule.
2. The contractor will have to make their own arrangement of water for
construction work as well as for their labourers at his own cost. If possible, water
for construction purpose only at one point as decided by EIC and recovery for
water charges shall be affected at the 2 % of the item of which water is used or
by quantity measured by meter reading of water meter installed by contractor,
rate of water supply will be charged at prevailing purchase rates of GSECL, for
water supplied by GSECL is used as certified by EIC. In case of agency is
installing bore well and pumps at his cost, after completion of work agency will
hand over the bore well in good condition with pumps to the GSECL.
5. DATA TO BE FURNISHED BY CONTRACTOR:
The contractor shall submit to the Executive Engineer for approval within one week of
the date of contract, a layout plan of construction plant and equipment for the
execution of work which the contractor proposes to adopt at site.
Prior to commencement of work, the contractor shall submit to the Executive
Engineer for approval, plans in triplicate showing the location of Major plant shop
and storage buildings, storage yards, offices, contractor's power house including its
services and housing facilities which he proposes to put up at site and also indicate the
programme of the work.
The successful bidder on receipt of letter of intent will submit within a week's time his
planning/programme of works for scrutiny of GSECL in a PERT/Bar chart format, clearly
indicating GSECL inputs also.
Contractor will plan his works such that on all the fronts released by GSECL,
simultaneous work should progress in such a way that entire job is completed in
scheduled time limit.
EW- 278 PUR-F-006 RFQ-
No change in the approved layout shall be carried out without specific written approval
of the Executive Engineer.
6. ERRORS, OMISSIONS AND DISCREPANCIES:
In all cases of errors, omissions, doubts or discrepancies in the dimensions, or
discrepancies in the drawings and items of work in specification, reference shall be
made to the Executive Engineer whose elucidation and elaboration shall be
considered as authoritative. The contractor shall be held responsible for any error
that may occur in the work thorough lack of such reference and precautions.
7. SECURITY DEPOSIT:
SECURITY DEPOSIT: In tender process for L1 bidder (lowest bidder)
security deposit will be charged as per table below:
Category of the Security Deposit
Unit Works up to Rs. 5 Works More than Rs.
Lakh Lakh
Enterprise or Exempted 3% of Order End Cost
Organization which
are exempted from
paying Tender Fee
For all other 5% of Order End 5% of Order End Cost
Enterprises Cost
is not willing to pay SD in advance, either EMD may be converted to SD or SD may be
deducted from 1st or subsequent invoices/RA bills with consent from the bidder. However,
PO/LOA should be placed before commencement of work, except in some emergency
cases where special approval must be obtained from the Executive Director (Gen.) at
Corporate Office.
After issue of Work order and Date of commencement, if successful bidder failed to start
the work then, RPAD notice will be issued to the successful bidder mentioning that on
failing to start the work within next 07 days from the date of issue of RPAD Notice the
EMD will be forfeited and he will not be allowed to participate in the tenders invited from
Gandhinagar TPS office for the period of One year.
The security deposit of the contract value shall be released on finalization of final bill /
successful completion of the work.
All damages, costs, charges, expenses and other sums which may be or may become
due or payable by the contractor to the Corporation under the terms of the contract,
may be deducted from the cash in the proceeds of sale of the securities/bank
guarantee so deposited (which the officer or person to whom the same may be
endorsed as aforesaid is hereby authorized to sell/to encase for that purpose) or from
the interest of any such securities or from any sums due or which may become due
to the contractor by the Corporation or from the whole or the balance unpaid as
aforesaid of the encase securities so deposited being repaid or transferred and
returned as the case may be, to the contractor on finalization of final bill OR after
(six) months of successful completion of the work, whichever later OR on furnishing
of the Performance Bond amounting to 5% of contract value against the defect
liability period as mentioned in this document elsewhere.
If entire security deposit is paid in approved form of Bank Guarantee should be
remain valid during the contractual period and such bank Guarantee should not be
reduced on the basis of the work actually done.
EW- 278 PUR-F-006 RFQ-
8. USE OF LAND:
The land required for office, godowns and for labour camp if not available with
GSECL, then the contractor has to arrange the same at his cost. GSECL will give the
land only if the spare land is available with the following conditions.
The contractor shall be permitted to use for the bonafide purpose of execution of this
contract free of cost. The contractor shall be permitted to use for the bonafide
purpose of execution of this contract free of cost.
1. Site required for the construction of the work.
2. Required approach road. The contractor shall make their own arrangements for the
necessary approach, road, for transport of their materials and be responsible for
the compensation on account of damage to crop etc. and shall till completion of
3. He will be charged the rent at the annual rate of rupees one hundred per every
acre or part thereof, for the construction of temporary hutments and his store
yard. However area required for such purpose may be clearly indicated in this
All areas of operation, including those for his staff and labour colonies handed over
to the contractor shall be cleared and handed over back in good condition to the
Engineer except areas under works as per this contract or those for which specific
approval has been obtained from the Engineer. The contractor shall make good to
the satisfaction of the Engineer any damage or alternation made to areas which he
has to hand over back or to other property land handed over to him for purpose
of this work.
Temporary structures may be erected by the contractor for storage sheds, offices,
residence etc. for noncommercial use on the land, handed over to him at his own
expense and with the permission of the Engineer. These structures shall comply
with the regulation that may be in force and/or specified by the Engineer with
regard, thereto. In any circumstances for constructing temporary structures for
contractor's use, GSECL's free supply materials shall not be used. If it is found that
GSECL's free supply materials are used for other than approved project drawings
work, same will be recovered at
penalized rate.
The contractor shall preserve all existing vegetation such as trees on or adjacent to
the sites which do not interfere with the construction as determined by the
The contractors shall take all possible precautions in felling trees authorized for
removal to avoid any unnecessary damage to vegetation and trees not to be felled
and to structures under construction, or to workmen, and shall be responsible for
any damage if it occurs in such operations
All produce from cutting of trees; grass etc. shall be the property of GSECL and
shall be stocked at the place specified by the Engineer. No claim shall be made for
such cutting and stacking of trees or grass etc. by the contractor
The contractors shall not unnecessarily or for use as fuel, cut any trees brush
wood, grass or other vegetation nor shall set fire there to without the written
permission of the Engineer. When such permission is given, the contractor shall
take necessary measures to prevent damage or to prevent fire spreading to
surrounding property, and shall be responsible for any such damage, if cause.
The land shall as herein before mentioned be handed back to Engineer in Charge
immediately after the completion of the work under this contract. Also no land
shall be held by the contractor longer than the Engineer shall deem necessary and
the contractor shall, on due notice by the Engineer, vacate and return the land
which the Engineer may certify as no longer required by the contractor for purpose
of the work.
9. START OF WORK:
The contractor shall not enter upon or commence any portion of work except with
the written authority or instructions of the Executive Engineer or his subordinate in
charge of the work, failing such the contractor shall have no claim to ask for
measurement or payment for work and shall be responsible for any claims or
damages that may arise due to such unauthorized commencement or entry.
EW- 278 PUR-F-006 RFQ-
10. COMPENSATION FOR THE DELAY:
The time allowed for carrying out the work as entered in the tender shall be strictly
observed by the contractor and shall be reckoned from the date on which the order
to commence work is given to the contractor. The work shall throughout the
stipulated period of contract be proceeded with all due diligence (time being deemed
to be the essence of contract) and for delay, the contractor shall pay compensation,
an amount equal to ½ (half) percent per one week for the contract amount or part
thereof, including taxes & duties ( i.e. End cost of contract amount including taxes &
duties) and maximum up to 10 % of the order value, including taxes & duties ( i.e.
End cost of contract amount including taxes & duties) or such smaller amount as per
the decision of the Competent Authority of the GSECL The penalty will be invariably
deducted from the bills of the contractor and no refund will be given unless the
competent authority approves the reduction. The reasons for delay, attributable to
GSECL as well as to party will be brought out clearly while putting the proposal for
waiver/reduction in penalty.
11. ACTION WHEN WHOLE OF SECURITY DEPOSIT IS FORFEITED:
In any case in which under any clause or clauses of this contract the contractor shall
have tendered himself to pay compensation amounting to the whole of his security
deposit (whether paid one sum) or in the case of abandonment for the work owing to
serious illness or death of the contractor or any other cause, the Executive Engineer
on behalf of the Corporation, shall have powers to adopt (a) below and any of the
following courses under (b) and (c) as he may deem best suited to the interest of the
Corporation.
(a) To rescind the contract (for which rescission notice of 10 days) in writing to the
contractor under the hand of the Executive Engineer shall be conclusive evidence and
in that case the security deposit of the contractor shall stand forfeited and absolutely
at the disposal of the Corporation. To employ labour paid by the Corporation, to
supply materials, to carry out the works or any part of the work debiting the
contractor with the cost of the labour and the price of the materials (as to the
correctness of which cost and price, the certificate of the Executive Engineer shall be
final and conclusive against the contractor) and crediting him with value of the work
done in all respects in the same manner and at the same rates as if it had been
carried out by the Contractor under the terms of this contract and in that case the
certificate of the Executive Engineer as to the value of the work shall be final and
conclusive against the contractor.
(b) To order that the work of the contractor be measured up and to take such part
thereof, as shall be unexecuted, out of his hands and to give it to another contractor
to complete, in which case, any expenses, which may be incurred in excess of the
sum, which would have been paid to the original contractor, if the whole work would
have been executed by him (as to the amount of which excess expenses, the
certificate in writing of the Engineer-in-charge shall be final, conclusive and shall be
borne and shall be paid by the original contractors and shall be deducted from any
money due to him by the Corporation under the contract or otherwise from his
security deposit of his proceeds sale thereof or a sufficient part thereof.
(c) In the event of the above courses being adopted by the Executive Engineer, the
contractor shall have no claim to compensation for any loss sustained by him by
reason of his having purchased or procured any materials or entered into any
engagements or made any advances on account of or with a view to the execution of
the work or the performance of the contract. And in case the contract shall be
rescinded under the provision aforesaid, the contractor shall not be entitled to
recovery or be paid any sum for any works thereof actually performed by him under
this contract unless and until the Executive Engineer shall have certified in writing the
performance of such work and the amount payable to him in respect thereof and he
only be entitled to be paid the amount so certified.
12. NOTICE UNDER UNSATISFACTORY PROGRESS:
EW- 278 PUR-F-006 RFQ-
If the progress of a particular portion of the work is unsatisfactory, and also if as per
the opinion/observation of the Executive Engineer (whose decision shall be final) in
charge that the general progress of work is not satisfactory, then Executive Engineer
in charge shall be entitled to take action under clause 11 (c) after giving the
contractor ten days‟ notice in writing and the contractor will have no claim for
compensation for any loss sustained by him owing to such action.
13. ACTION IN THE CASE OF DEFAULT BY THE CONTRACTOR :
In any case in which any of the powers conferred upon the Executive Engineer by
Clauses 11 and 12 hereof shall have exercisable and the same shall not have been
exercised, the non-exercised thereof shall not constitute a waiver of any of the
conditions hereof and such powers shall not withstanding be exercisable in any
further case of default by the contractor of which, by any clauses hereof, he is
declared liable to pay compensation amounting to the whole of his security deposit
and liability of the contractor for past and future compensation shall remain
unaffected in the event of the Executive Engineer taking action under sub-clause (a)
or (c) of Clause 11, he may if he so desires, take possession of all or any tools,
plants, materials, and stores in so upon the work or the site thereof belonging to the
contractor, or procured by him and intended to be used for the execution of the work
of any part thereof paying for allowing for the same in account at the contract rates,
or in the case of a contract rates not being applicable of current market rates to be
certified by the Executive Engineer whose certificate thereof shall be final. In the
alternative, the Executive Engineer may by notice in writing to contractor or his clerk
of works, foreman or other authorized agent, require him to remove such tools,
plant, materials or stores from the premises within a time to be specified in such
requisition, the decision to the contractor failing to comply with any such requisition,
the decision of the Executive Engineer as to the expense of any such removal and the
amount of the proceed and expense of any such sale, be final and conclusive against
the contractor
14. EXTENSION OF TIME LIMIT
If the contractor shall desire an extension of the time limit for completion of the work
on the ground of his having been unavoidably hindered in its execution or on any
other ground, he shall apply in writing to the Executive Engineer and the Executive
Engineer may, if in his opinion there are reasonable grounds for granting extension,
recommend such extension as he may think necessary or proper. The decision of the
competent authority in this regard shall be final, and binding to the contractor. Any
delay attributed to Corporation, shall be thus compensated only by way of extending
the limit.
15. COMPLETION CERTIFICATE
On completion of the work, the Contractor shall be furnished with Completion
Certificate by the Executive Engineer. No such certificate shall be given nor shall be
the work considered to be completed until works are taken over and/or duly tested
and put to operation as the case may be, nor until the work shall have been
measured by the Engineer-in-Charge or where the measurement have been taken by
his subordinates until they have received the approval of the Executive Engineer the
said measurement being binding and conclusive against the contractor.
16. EFFECT OF THE CERTIFICATE :
No payment shall be made for any work estimated to cost less than Rs.1,000 till after
the whole of said work shall have been completed and a certificate of completion
given. But in the case of works estimated to cost more than Rs.1,000, contractor
shall on submitting a monthly bill thereof, be entitled to receive payments.
Proportionate to the part of the work then approved and passed by the Engineer-in-
Charge, whose certificate of such approval and a passing of the sum so payable shall
be final and conclusive against the contract. All such intermediate payment shall be
regarded as payment by way of advance against the final payment only and not as
payments for work actually done or completed and shall not preclude the Engineer-
EW- 278 PUR-F-006 RFQ-
in-charge from requiring bad, unsound, imperfect or unskillful work to be removed
and taken away and reconstructed or re-erected nor shall any such payment be
considered as admission of the due performance of the contract or any part thereof
in any respect of the occurring of the claim nor shall conclude, determine or effect in
any way the powers of the Engineer-in-Charge as to the final settlement and
adjustment of the accounts otherwise or in any other way, vary or affect the
contract. The final bill shall be submitted by the contractor within one month of the
date fixed for completion of work; otherwise the certificate of the Engineer-in-charge
of the measurement and of total amount payable for the work shall be final and
of the measurement and of total amount payable for the work shall be final and
binding on all parties.
17. PAYMENT TO CONTRACTORS :
The rates for several items of works estimated to cost more than Rs.1, 000 agreed to
within shall be valid only when the item concerned is accepted, having been
completed full, in accordance with the sanctioned specification. In case, where the
items of the work, are not accepted, as so completed, the Engineer-in-charge, may
make payment on account of such items at such reduced rates, as he may consider
reasonable in the preparation of final or running accounts bills and it will be binding
to the contractor.
18. BILLS :
The Bill Shall be submitted by the contactor each month on or before the date fixed
by the Engineer-in-charge, for all works, executed in the previous month and the
Engineer-in-charge shall take or cause to be taken the requisite measurement for the
purpose or having the same verified and the claim so far as it is admissible, shall be
adjusted, if possible, within Fifteen days from the presentation of the bills. If the
contractor does not submit the bill, within the time fixed, as aforesaid, the Engineer-
in-charge may depute a subordinate to measure up the said work in the presence of
the contractor or his duly authorized agent, whose counter signature in the
measurement shall be sufficient warrant and the Engineer-in-charge may prepare a
bill from such list which shall be binding on the contractor in all respects. In case if
contractor/ representative does not remain present on specified date for taking
measurement than EIC may take the measurement one sided and the same shall be
binding to the contractor irrespective whether he has signed or not.
19. SUPPLY OF MATERIALS TO CONTRACTOR [APPLICABLE ONLY WHERE
MATERIAL IS TO BE SUPPLIED BY CORPORATION AS MENTIONED IN
SCHEDULE A ]
If the specification of the estimated work provides for use of any special description
of material to be supplied from the Corporation‟s stores or if it is required that the
contractor shall use certain stores to be provided by the Engineer-in-charge, (such
material and stores and the prices to be charged thereof as hereinafter mentioned
being so far as practicable for the convenience of contractor but not so as in any way
to control, the meaning or effect of this contract specified in the schedule or
memorandum hereto annexed). The contractors shall be supplied with such materials
and stores as may be required from time to time be used by him for the purpose of
the contract only and the value of the full quantity of materials and stores so supplied
shall be set off or deducted from any sum due or thereafter to become due to the
contractor, under the contract or otherwise or from the security deposit or the
proceeds of sale thereof if the deposit is held in government securities the same or a
sufficient portion thereof, shall be sold for the purpose. All materials supplied to the
contractor shall remain the absolute property of the Corporation and shall on account
be removed from the site of work and shall at all times be open to inspection by the
Engineer-in-charge. Any such materials unused and in perfectly good condition at
time of completion or determination of the contract shall be returned to the
Corporation‟s store if the Engineer-in-charge so requires by notice in writing given
under his hand but the contractor shall not be entitled to return any such materials
except with such consent and he shall have no claim for compensation on account of
EW- 278 PUR-F-006 RFQ-
any such materials supplied to him as aforesaid but remaining unused by him or for
any wastage in or damaged thereto. The contractor shall be responsible for the loss,
destruction or deterioration of the materials, stores or articles supplied to him by the
Corporation even if such loss, destruction or deterioration has occurred under any
circumstances whatsoever beyond his control as if the materials, stores or articles so
supplied were his property.
20. WORKS TO BE EXECUTED IN ACCORDANCE WITH SPECIFICATIONS,
DRAWING, ORDERS ETC.
The contractor shall execute the whole and every part of work in the most substantial
and workman like manner and both as regarding materials and in every other respect
in strict accordance with the specification. The contractor shall also confirm exactly,
fully and faithfully to the designs, drawings and instructions in writing relating to the
work signed by the Engineer-in-charge and lodged in his office and to which the
contractor shall be entitled to have access for the purpose of inspection at such
office, or on the site of the work during office hours and the contractor shall, if he so
requires, be entitled at his own expense to make or cause to be made copies of the
specification and of all such designs, drawings and instructions as aforesaid.
21. ALTERATIONS IN SPECIFICATIONS AND DESIGNS NOT TO INVALIDATE
The Executive Engineer shall have powers to make any alterations, or additions to
the original specification, designs and instructions that may appear to him to be
necessary or advisable during the progress of the work and the contractor shall be
bound to carry out the work in accordance with any instruction in this connection
which may be given to him in writing, signed by the Engineer-in-charge and such
alterations shall not invalidate the contract. Any additional work which the contractor
may be directed to do in the manner above specified as part of the work shall be
carried out by the contractor on same conditions in all respect on which he agreed to
do the main works and at the same rates as are specified in the tender for the main
Where, however, the work is to be executed according to the designs, drawings and
the specifications recommended by the contractor and accepted by the competent
authority, the alteration above referred to shall be within the scope of such designs,
drawings and specifications appended to the tender.
22. RATES FOR WORKS NOT ENTERED IN ESTIMATE OR SCHEDULE OF RATE OF
THE CORPORATION
If the additional and altered work includes any class of work for which no rate is
specified in this contract, then such class of work shall be carried out at the rates
entered in the Schedule of Rates of the Corporation or at the rate mutually agreed
upon between the Executive Engineer and the Contractor, whichever are lower. If the
additional or altered work for which no rate is entered in the Schedule of Rates of the
Division is ordered to be carried out before the rates agreed upon then the contractor
within seven days of date of receipt by him of the order to carry out the work should
inform the Executive Engineer for the rate which it is his intention to charge for such
class of work and if the Executive Engineer does not agree to this rate, he shall be
noticed in writing, be at liberty to cancel his order to carry out such class of work and
arrange to carry it out in such manner as he may consider advisable provided always
that if the rates shall have been determined as lastly herein before mentioned then in
such case he shall only be entitled to be paid in respect of the work carried out or
expenditure incurred by him prior to the date of the determination of the rate as
aforesaid according to such rate or rates as shall be fixed by the Executive Engineer
in the event of disputes, the decision of the General Manager of the Corporation will
23. EXTENSION OF TIME LIMIT IN CONSEQUENCE OF ADDITION OR
ALTERATION
EW- 278 PUR-F-006 RFQ-
The time limit for the work shall be extended in the proportion that the increase in its
cost occasioned by alterations or additions bears to the cost of the original contract
work and the certificate of the Engineer-in-charge as to such proportions shall be
conclusive.
24. NO COMPENSATION FOR ALTERATION IN OR RESTRICTION OF WORK TO
BE CARRIED OUT
If at any time, after the execution of the contract documents, the Engineer-in-charge
shall, for any reason whatsoever, requires the whole or any part of the work, as
specified in the tender, to be stopped for any period or shall not require the whole or
part of the work to be carried out at all or to be carried out by the contractor, he
shall give notice in writing of the fact to the contractor who shall thereupon suspend
or stop the work totally or partially as the case may be in any such case, except as
provided here under. The contractor shall have no claim to any payment or
compensation whatsoever on account of any loss in profit or advantage which he
might have derived from the execution, of the work in full but which he did not so
derive in consequence of the full amount of work not having been carried out or on
account of any loss that he may be put to on account of materials purchased or
agree to be purchased or for unemployment of labour recruited by him. He shall not
also have any claim for compensation by reason of any alterations having been made
in the original specification, drawings, designs and instructions which may involve any
curtailment of the work as originally contemplated. Where, however, materials have
already been purchased or agreed to be purchased by the contractor before receipt
by him of said notice, the Executive Engineer provided they are not in excess or
requirement and are of approved quality and/or shall be compensated for the loss, if
any, that he may put to in respect of materials agreed to be purchased by him. The
amount of such compensation to be determined by the Executive Engineer, whose
decision shall be final. If the contractor suffers any loss on account of his having to
pay, his labour charges during the period, during which the stoppage of work has
been ordered under this clause the contractor shall on application be entitled to such
compensation on account of labour charges as the Executive Engineer whose
decision shall be final, may consider reasonable provided that the contractor shall not
be entitled to any compensation on account of labour charges if, in the opinion of the
Executive Engineer, the labour could have been employed by the contractor
elsewhere for the whole or part of the period during which the stoppage of the work
has been ordered as aforesaid.
25. NO CLAIM FOR COMPENSATION ON ACCOUNT OF LOSS DUE TO DELAY IN
SUPPLY OF MATERIALS BY CORPORATION
The contractor shall not be entitled to claim any compensation from Corporation for
the loss suffered by him on account of delay by Corporation in the supply of materials
entered in Schedule A where such delay is caused by:
Difficulties relating to supply of railway wagons.
Force Majeure
Act of God
Any other reasonable cause beyond the control of Corporation, including shortage of
materials to be supplied by the Corporation and difficulties in time by reaching at the
site of any materials equipment.
In the case of such delay in the supply of materials, Corporation shall grant such
extension of time for the completion of the works as shall appear to the Executive
Engineer to be reasonable in accordance with the circumstances of the case. The
decision of the Executive Engineer as to the extension of time shall be accepted as
final by the contractor.
26. TIME LIMIT FOR COMPENSATION CLAIMS
Under no circumstances, whatsoever, shall the contractor be entitled to any
compensation from Corporation on any account unless the contractor has claimed in
writing to the Executive Engineer within one month of the cause thereof.
EW- 278 PUR-F-006 RFQ-
27. ACTION AND COMPENSATION PAYABLE IN CASE OF BAD WORK
If at any time, before the security deposit is refunded to the contractor, it shall
appear to the Executive Engineer or his subordinate in charge of the work that any
work has been executed with unsound, imperfect or unskillful workmanship or with
materials of inferior quality or that any materials or articles provided by him for the
execution of the work are unsound or of inferior quality to that contract for or are
otherwise not in accordance with the contract, it shall be lawful for Engineer-in-
charge to intimate this fact in writing to the contractor and then notwithstanding the
fact that the work, materials, or articles complained of, may have been inadvertently
passed, certified and paid for, the contractor shall be bound forthwith to rectify or
remove and reconstruct the work so specified in whole or any part, as the case may
require or if so required shall remove the materials or articles so specified and
provided other suitable materials or articles at his own charge and cost, and in the
event of his failing to do so within a period to be specified by the Engineer-in-charge
in the written intimation aforesaid the contractor shall be liable to pay compensation
at the rate of one percent on the amount of the estimate for every day not
exceeding ten days during which the failure so continues and in the event of any
such failure as aforesaid, the Engineer-in-charge may rectify or remove or re-execute
the work or remove and replace the materials or articles complained of, as the case
may be, at the risk and expense in all respects of contractor should the Engineer-in-
charge consider that any such inferior work or materials as described above may be
accepted, or made use of, it shall be within his discretion to accept the same as such
reduced rates as he may fix thereof.
Provided that in the case of any work of which visible check is not possible if the
Engineer-in-charge or his subordinate in charge of the work feels that such work has
been executed with unsound, imperfect or unskillful workmanship or with materials of
inferior quality, he shall take sample tests at random, cost of which shall have to be
borne by the contractor and if after taking such test part of such work is found to be
defective in any respect or to have been executed with materials of inferior quality
then the contractor shall pay for the whole work such amount as may be fixed by the
office of the Engineer-in-charge on the basis of the lowest quality of work found by
him in such sample tests.
28. WORK TO BE OPENED TO INSPECTION, CONTRACTOR OR RESPONSIBLE
AGENT TO BE PRESENT.
All works under execution or in pursuance of the contract shall at all times be open to
the inspection and supervision of the Executive Engineer and his subordinate and
contractor shall at all times, during the usual working hours and at all other times at
which reasonable
notice of the intention of the Executive Engineer or his subordinate to visit the works
shall have been given to the contractor, during which period either he should be
present to receive order and instruction, or have a responsible agent duly authorized
agent shall be considered to have the same force and effect as if they had been
given to the contractor himself.
29. NOTICE TO BE GIVEN BEFORE WORK IS COVERED UP
The contractor shall give not less than five days‟ notice in writing to the Executive
Engineer or his subordinate in charge of the work, before covering up or otherwise
placing beyond the reach of measurement of any work, in order that the same may
be measured and correct dimensions thereof, taken before the same is so covered up
or placed beyond the reach of measurement and shall not be covered up or placed
beyond the reach of measurement and work without the consent in writing of
Executive Engineer or his Subordinate in charge of work. If any work shall be covered
up or placed beyond the reach without such notice having been given or consent
obtained, the same shall be uncovered at the contractor‟s expense and in default
EW- 278 PUR-F-006 RFQ-
thereof no payment or allowance shall be made for such work or for the materials
with which the same was executed.
30. CONTRACTOR’S LIABILITIES
The contractor shall supply, at his own cost, all materials (except such special
materials, if any as may be supplied from the Corporation stored in accordance with
the contract). Plant, tools, appliances, implements, ladders, cordage, tackle,
scaffolding and any temporary works which may be required for the proper execution
of the work, in the original, altered or substituted form and whether included in the
specification and other document forming part of the contract or referred to in these
conditions or not and which may be necessary for the purpose of satisfying and
complying with the requirements of the Engineer-in-charge as to any matter on
which under these conditions, he is entitled to be satisfied or which he is entitled to
require together with carriage thereof to and from the work. The contractor shall also
supply without any charge the requisite number of persons of setting out works and
counting, weighting and assisting in the measurement of examination at the time and
from time to time of the work or materials, failing this the same may be provided by
the Engineer-in-charge at the expenses of the contractor and the expenses may be
deducted from any money due to the contractor under the contract or from his
security deposit or the proceeds of sale thereof or of a sufficient portion thereof, the
contractor shall provide all necessary fencing and light required to protect the public
from accident and shall also be bound to bear expenses of defense of every suit,
action or other legal proceedings of law that may be brought by any person for injury
sustained. Owing to neglecting of the above precautions and to pay any damage and
cost which may be awarded in such suit, action or proceedings to any such person or
which may with the consent of the contractor be paid in comprising any claim by any
such person.
31. CONTRACTOR LIABLE FOR ALL DAMAGE
Compensation for all damage done intentionally or unintentionally by contractor‟s
laborer, whether in or beyond the limit of Corporation‟s property, shall be estimated by
the Executive Engineer or such other office as he may appoint and the estimates of the
Executive Engineer, subject to the decision of the Superintending Engineer, on appeal,
shall be final and the contractor shall be bound to pay the amount of the assessed
compensation demand, failing which, the same will be recovered from the contractor
as damages or deducted by the Engineer-in-charge from any sums that may be due to
or become due from Corporation to the contractor under this contract or otherwise.
The contactor shall bear the expenses of defending any action or other legal
proceeding that may be brought by any person for injury sustained by him owing to
negligence of precautions for prevent the spread of fire and he shall also pay any
damage and cost that may be awarded by the court, if in consequence
32. RESCISSION OF CONTRACT AND FORFEITURE OF DEPOSIT
The contractor shall not assign or sublet, without the written approval of the Engineer-
in-charge and if the contractor assign, or sublet his contract, or attempt to do so or
become insolvent or commence any proceedings to be adjudicated as insolvent or
make any composition with creditors, attempt to do so, the Engineer-in-charge may,
by notice in writing rescind the contract. Also, if any bribe, gratuity, gift, loan,
perquisite, reward or advantage pecuniary or otherwise shall either directly or
indirectly be given, promised or offered by the contractor or any of his servants, or
agents, or any person to the employee of the Corporation in any way relating to his
office or indirectly interested in the contract, the Executive Engineer may, by ten days‟
notice in writing, rescind the contract. In the event of a contract being rescinded the
security deposit of the contractor shall there upon stand forfeited and be absolutely at
the disposal of the Corporation and the same consequences shall ensure as if the
contract has been rescinded under Clause 11 thereof and in addition the contractor
shall not be entitled to recover or be paid for any work thereof actually performed
under the contract.
EW- 278 PUR-F-006 RFQ-
33. COMPENSATION
All sums payable by a contractor by way of compensation under any of these
conditions shall be considered as a reasonable compensation to be applied to the use
of Corporation without reference to the actual loss or damage sustained and whether
any damage has not been sustained.
34. CHANGE IN THE CONSTITUTION OF FIRM TO BE NOTIFIED
In case of tender by partners of a Firm, any change in constitution of firm shall be
forthwith notified by the contractor to the Executive Engineer for his information.
35. WORKS UNDER DIRECTION OF SUPERINTENDING ENGINEER
All works to be executed under the contract shall be executed under the direction and
subject to the approval of Superintending Engineer /Engineer-in-charge for the time
being who shall be entitled to direct at what point or points and in what manner they
are to be commenced and from time to time to be carried on.
36. DECISION OF SUPERINTENDING ENGINEER TO BE FINAL
Except where otherwise specified in contract and subject to the power delegated to
him by Corporation under the Corporation‟s rules, then in force, the decision of the
Superintending Engineer/EIC for the time being shall be final, conclusive and binding
on all the specifications, designs, drawings and instructions herein before mentioned
and as to the quality of workmanship or material used on or as to any other question,
claim, right matter or thing whatsoever in any way arising out of or relating to the
contract, designs, drawings, specifications, estimates, instructions, orders or these
conditions or otherwise concerning, the works or the execution or failure to execute
the same, whether arising during the progress of the work or after the completion or
abandonment thereof.
37. Dispute Resolution Mechanism: For works contracts and composite Contracts,
the arbitration mechanism shall be governed by the Gujarat Public Works Contracts
Disputes Arbitration Tribunal Act, 1992 as per below details.
sub clause 37(1) Amicable Settlement : Any dispute, difference, controversy or
claim between the Parties arising out of or relating to this contract with reference to
the construction, interpretation, breach, termination or validity thereof (hereinafter
referred as "the Dispute") shall, upon the written request of either Party be referred
to the authorized representatives of the Disputing Parties for resolution. The
authorized representatives shall promptly meet and attempt to negotiate in good
faith a resolution of the Dispute within thirty days of the service of the request.
sub clause 37(2) Arbitration : If the Parties fail to amicably resolve the disputes
or differences or contrary claims as indicated herewith in sub clause (1) of Clause
arising under or in connection with the present works contracts, whether pertaining
to works contracts alone or works and procurement both, the same shall be referred
to arbitration under the Gujarat Public Works Contracts Disputes Arbitration Tribunal
38. STORES TO BE OBTAINED FROM CORPORATION [APPLICABLE ONLY
WHERE MATERIAL IS TO BE SUPPLIED BY CORPORATION AS MENTIONED
IN SCHEDULE A]
The contractor shall obtain from the Corporation stores, such articles as are
mentioned in schedule “A” which may be required for the work or any part of the
work or in making up any articles required therefore or in connection therewith,
unless he has obtained permission in writing from the Executive Engineer or obtained
such stores and articles from elsewhere. The value of such stores and articles as may
be supplied to the contractor by the Engineer-in-charge will be debited to the
contractor in his account at the rate shown in the schedule “A” attached to the
contract and if they are not entered in said Schedule, they shall be debited to him at
cost price which for the purpose of this contract shall include cost of carriage and all
other expenses whatsoever which may have to be incurred in obtaining delivery of
the same at the stores aforesaid and further overhead charges 15%.
EW- 278 PUR-F-006 RFQ-
The Contractor shall be responsible for the loss, destruction or deterioration of the
materials, stores or articles supplied to him by the Corporation, even if such loss,
destruction or deterioration has occurred under any circumstances whatsoever
beyond his control as if the materials, stores or articles so supplied were his property.
The contractor shall be responsible for returning the residual materials after
completion of the contract and it fails to return, the balance materials supplied to him
by the Corporation, the cost of the residual materials will be recovered from the
contractor at the market rate or stock issue rate whichever be higher at the time of
materials account plus 15%.
39. LUMP SUMS IN ESTIMATE
When the estimate on which tender is made, includes lump sums in respect of parts
of the works the contractor shall be entitled to payment in respect of the items of
works involved or the part of the work in question at the same rates as are payable
under this contract or such items or if the part of work in question is not in the
opinion of the Engineer-in-charge capable of measurement the Engineer-in-charge
may at his discretion pay the lump sum amount entered in the estimate and the
certificate in writing of the Engineer shall be final and conclusive against the
contractor with regard to any sum or sums payable to him under the provision of this
40. LUMP SUM TENDERS
Whenever lump sum tenders have been invited for buildings or other structures of
the same type, design, the contractor shall submit his bill stated in Clause No. 18 and
the Engineer-in-charge not below the rank of work, Executive Engineer shall certify
by general measurement or by other method considered suitable to him, the value of
work done and the contractor shall be paid monthly a sum equal to 90% of the total
value the work so certified, since the last payment, after deducting a part or whole of
the secured advance if not already paid for the materials utilized on the works. An
additional secured advance for any fresh materials utilized on the works. An
additional secured advance for any fresh materials brought on site will also be paid if
certified by the officer not below the rank of Executive Engineer. After the work is
completed final bill would be paid on the certification of officer not below the rank of
Executive Engineer, that the work, is done according to drawing and specifications
attached to the tender. If any additions and alterations have been carried out,
detailed measurement in respect thereof shall be recorded and extra payment or
deductions are regulated as per item rates quoted by the contractor while submitting
the tender and if there are any items in the additions and alterations for which the
contractor has not quoted a rate, the payment shall be as per Clause 39 above
41. ACTION WHERE NO SPECIFICATION
In the case of any class of work for which there is no such specification as is
mentioned, such work shall be carried out in accordance with the PWD and in the
event of there being no PWD specification, the work shall be carried out in all
respects in accordance with the instructions and requirements of the Engineer-in-
charge of the Corporation etc.
42. NO CLAIM FOR VARIATION IN QUANTITIES OR WORK
Quantities shown in the tender are approximate and no claim shall be entertained for
quantities of work actually executed, being either more or less up to any extent than
those entered in the tender or less than those entered in the tender or estimate.
43. NO CLAIM FOR COMPENSATION FOR DELAY IN STARTING WORK
No compensation shall be allowed for any delay caused into starting of work on
account of acquisition of land and in the case of clearance for works or any delay in
according sanction to estimates.
44. NO CLAIM FOR COMPENSATION FOR DELAY IN EXECUTION OF WORK
No compensation shall be allowed for any delays in execution of the work on account
of water standing in borrow pits or compartment. The rates are inclusive for hard or
cracked soil, excavation in mud, sub-soil water or water standing in borrow pits and
EW- 278 PUR-F-006 RFQ-
no claim for any extra rate shall be entertained unless otherwise expressly specified
and mentioned in the tender.
45. EMPLOYMENT OF TECHNICAL PERSONS:
The contractor shall keep one full time qualified Civil Engineer at the site, who shall
be fully authorized to receive and comply with such instructions, as given by the
Executive Engineer. The contractor shall intimate the name of such Engineer with his
qualifications and experience. The Executive Engineer shall have the right to demand
the removal of any technical personnel, skilled or unskilled workmen, who in his
opinion are considered to cause bad workmanship in the execution of works or to
cause indiscipline.
46. Terms and Conditions regarding Labour L aws
During the entire period of the contract, the Contractor and his Sub-
Contractors shall at all times comply with all applicable labour laws, rules,
regulations, notifications, and bye-laws issued by the Central Government,
State Government, or Local Authorities. This includes all existing laws as
well as any amendments or new notifications that may come into force during
the contract period.
The Contractor and his Sub-Contractors shall, at all times abide by the
following Acts/Statutes related to Human Resources:
1. Factories Act, 1948;
2. Contract Labour (Regulation & Abolition) Act, 1970;
3. EPF & MP Act, 1952;
4. Building & Other Construction Workers (Regulation of Employment &
Conditions of Service) Act, 1996;
5. ESI Act, 1948;
6. Minimum Wages Act, 1948;
7. Payment of Wages Act, 1936;
8. Payment of Bonus Act, 1965;
9. Payment of Gratuity Act, 1972;
10. Workmen‟s Compensation Act, 1923;
11. ID Act, 1947;
12. Maternity Benefit Act, 1961;
13. Inter-State Migrant Workmen (Regulation of Employment & Conditions
of Service) Act, 1979;
14. The Building And Other Construction Workers' Welfare Cess Act,
17. The Carriage by Road Act,
The above list is only indicative and not exhaustive. The Contractor shall
remain fully responsible for ensuring compliance with all other applicable
labour and welfare legislations, rules, and regulations in force during the
The following are some of the major responsibilities of the contractor, in
addition to other obligations prescribed under various labour laws, rules, and
regulations issued by statutory authorities such as the State Government or
Government of India from time to time, which the contractor shall strictly
comply with during the execution of the contract.
1) The Factories Act,
The contractor should not deploy worker below the age of 18 years
and above 60 years for the awarded work.
Earn Leave shall be paid to their bonafide contract workers as per
EW- 278 PUR-F-006 RFQ-
the provisions of the Factories Act,
Payment of Earned Leave should be made monthly together with wages for
better compliance of law. The contractor shall maintain Earn Leave
Register in Form No. 19 as per the provisions of the said Act and
submit the same on demand.
All the written registers, Performa etc. shall be maintained up to
date and kept ready for inspection at any time or submitted
on-time to the concerned authorities as per applicability of the Acts
by contractor.
2) The Contract Labour (Regulation and Abolition) Act,
The Contractor / Agency shall have to obtain the Labour License
under Contract Labour (Regulation & Abolition) Act from the
appropriate authorities before commencement of work. The contractor
shall maintain a valid labour license under the Contract Labour
(Regulation and Abolition) Act for employing necessary man power
to be required by contractor.
The contractor should not be allowed to engage fifty (50) or more
contract labourers without initiating to obtain the labour license under
the Contract Labour Act. (the said number i.e., fifty (50) or more
includes Supervisor and other staff).
3) Minimum Wages Act,
Contractor shall have to make the payment of wages to the Contract Labours
engaged by them, on or before 7th of every month through nearest
Nationalized Bank compulsory, preferably situated in the premises of TPS
area in case of all works contract. The Contractor shall supply copy of Bank
Statement duly stamped by the Concerned Bank as well as debited entry of
amount displayed in the contractors‟ own bank account as token of proof
towards payment of Wages through CLIM/prevailing system at relevant
time. Apart from Payment of wages through Bank, Contractors shall have to
make all other payments like Advances, Bonus, Leave Encashment etc. to
their labours through bank only and cash payment/entry will not be allowed.
Wages rates for contract laborers are applicable as per the terms and
conditions of the license. The contractor shall have to pay wages to workers
as notified by the Government of Gujarat from time to time.
Any default to pay the minimum wages to the engaged workers and deprived
of their right to minimum wages payment on or before 7th of each month
shall be dealt as per the provision of labour laws. Recurrence of the same
may lead to cancellation of awarded contract.
4) The Provident Fund and Miscellaneous Provisions Act,
The contractor must possess separate P.F. code on the name of the
Firm / Agency / Company itself for the subject work.
It should be ensured that all the contract labours engaged by
contractor are covered under the provident fund scheme and
employee‟s pension scheme and their contribution must be remitted
regularly to the concerned R P F C . The photocopies of challan along
with E C R in this regards should be submitted regularly to the User
Department to enable their onward billing clearance.
The contractor shall submit along with his bill (month wise)
EW- 278 PUR-F-006 RFQ-
statement regarding deductions against employees‟ provident
fund and family pension scheme in respect of each concerned
employee. Provident fund and family pension scheme at the rate of
12 % of wages (or at the rates made applicable by the
Government time to time). The contractor‟s contribution and his
workers contribution towards provident fund and family pension
scheme shall deposited by the contractor with concerned PF
Authorities.
5) Workmen’s Compensation & E mp l o y e r ’ s Liability
Insurance.
The contractors shall have to obtain Employee Compensation
Policy under the Employees Compensation Act before starting
the work. Employee Compensation Insurance shall be obtained for
all the workers engaged for the execution of awarded contract. If
any of the work is sub-letted, the contractor shall ensure that the sub-
contractor take and provide workmen's compensation and Employer's
liability insurance for the labours engaged. Contractor is liable to
pay compensation in case of accidental injury arising out of and in
the course of employment as per the said Act and shall bear medical
expenses due to on duty accident.
6) The Payment of Gratuity Act,
For better compliance, contractor shall pay amount of gratuity on a
monthly basis along with the payment of wages, calculated on a pro-rata
basis per month, which is equivalent to 15 days‟ wages for each completed
year of service for every worker. (* applicable to A R C / B R C
works contract only)
7) The Payment of Bonus Act,
Every worker shall be entitled to be paid by the contractor in an
accounting year, bonus, in accordance with the provisions of this Act,
For better compliance, the contractor should pay bonus amount
on a monthly basis along with wages calculated on a pro-rata basis
per month. Contractor has to submit the paid bonus details of its
worker in Form No. C as per the provisions of the said Act as and
when required by the Govt. Authority as well as by G S E C L .
8) The Maternity Benefit Act,
Contractor shall ensure that entitled female worker should
provide Maternity Leave and other benefits as per the provision of the
9) The Building and other Construction Workers’ Act,
For any construction work, fall under the definition of Section
2(1)(d), happening outside / inside the Factory premises the said
act will be applicable and the contractor or its sub-contractor shall be
liable to comply with the provisions framed there under.
10) The contractor shall give preference to existing or local contract
workers for engagement in the awarded contract and shall issue
appointment orders to each and every workers individually at the
time of their engagement during the period of contract and
terminate the same at the end of the each contract.
EW- 278 PUR-F-006 RFQ-
Follow the mentioned procedure at each milestone for the
execution of works contract.
11) On Commencement of Contractual Work
1. Before starting the work, the contractor may contact Labour
Welfare Officer / Industrial Relations Officer for all formalities
related to labour law compliance before commencement of the
contract and onward Labour Law compliance thereof, so that
later no dispute will arise in respect of compliance of labour
2. It is the responsibility of the contractor to ensure that
contractor‟s employees maintain strict discipline as regards
security, methods of safe working etc, and not to cause any
hindrance to smooth running of power station or in execution of
duties by G S E C L staff. Any lapse in this regard will be viewed
seriously and if lapse found, contract is liable to be terminated. If
any of contractor‟s staff is found unsuitable or not behaving
properly, the contractor shall have to remove such worker from
the work-site on demand by EIC. To maintain harmonious
industrial relations amongst contract labours is solely the
responsibility of contractor. Any breach of the same will be
viewed seriously.
3. A digital system developed at the request of the agencies
working at the premises of GSECL, is to facilitate them for easy,
efficient, effective management of data, gate passes, attendances,
medical records, Police Verification documents etc related to
their employees / workers deployed for various works and
services against work order of GSECL.
4. On receipt of LOA and before commencement of work,
authorized representatives of the agency shall login in the CLIMS
online portal / prevailing system at relevant time and apply for
registration of their employees / workers uploading all
information with required documents in digital form. Upon
completion of due verifications, clearance by EIC and HR
departments, contracting agency will obtain gate passes. GSECL
will only consider documents like wage sheet duly accepted and
signed by individual workers, as per the engagement/deployment
duration/hours of individual worker duly certified by the agency,
being the employer, for the purpose of payment of bills and HR
clearances.
Agency shall be solely responsible for maintaining accurate and
up-to-date data of their workers in the portal/ prevailing system at
relevant time. All statutory compliances under prevailing laws
shall remain the responsibility of the contracting agency. The
agency shall indemnify GSECL against any liabilities arising
from non-compliance of legal provisions or inaccuracies in the
data maintained by them in the digital portal of
CLIMS/prevailing system at relevant time.
5. The Contractor who intends to engage labours more than the
EW- 278 PUR-F-006 RFQ-
specified limit under law, then necessary - Form No. V under the
Contract Labour (R& A) Act, 1970 or Form No. VI under the
Interstate Migrant worker (employment regulation) Act 1979 as
applicable is to be obtained for the purpose of obtaining Labour
License from the Licensing Authority.
6. It shall be the duty of the Contractor or his Supervisor to
ensure Bio-Metric punching and reporting at the location of work.
7. The contractor shall employ adequate number of experienced
staff at site for daily supervision and for maintaining of various
registers and records required under the Labour laws and
contracts. No payment for such supervision shall be admissible.
8. The gate passes obtained for any specific work order will be
valid for that specific work order only and contractor should not
divert the man power for any other work order. If any work
or part thereof is desired/required to sublet, the contractor
shall obtain the necessary permission of EIC in black and white
well in advance which is mandatory for considering the statutory
documents of agency other than the agency who awarded work
12) During Contractual Work under the progress:
1. All Contractors shall have to make the payment of wages to the
Contract Labours engaged by them, on or before 7th of every
month through Nearest Nationalized Bank compulsory,
preferably situated in the premises of p o w e r s t a t i o n area.
The Contractor shall supply copy of Bank Statement duly
stamped by the Concerned Bank as a token of proof towards
payment of Wages through CLIMS / prevailing system at relevant
2. All Contractors has to comply & maintain statutory documents /
registers under the provision of labour laws & E P F Act.
3. In case the contractor having more than one contract in the same
T P S , the contractor shall have to obtain work order wise
separate Gate Passes and submit the same with the documents of
statutory compliance that too work order wise every month to the
User Department to enable their onward billing clearance.
(13) CONTRACTOR TO INDEMNIFY THE GSECL REGARDING
LABOUR LAWS
The contractor shall indemnify and keep indemnified the G S E C L , and
every member, officer and employees of the G S E C L , also Engineer-in-
charge and his staff against all actions, proceedings, claims, demands,
costs and expenses whatsoever arising out of or in connection with the
matter referred in above clauses and elsewhere and against all actions,
claims demands, cost and expenses which may be made against the
G S E C L by any workman/ employees of contractor or any sub- contractor
and or from any liability any wise to any workman/employees of the
contractor or sub-contractor under any laws, rules or regulation having in
force of law including but not limited to claims against the owner under
employee compensation Act, 1923. The Employee‟s Provident Fund
EW- 278 PUR-F-006 RFQ-
Act.1952, and/or the contract labour (Abolition and Regulation) Act,
The G S E C L shall not be liable for or in respect of or in consequence of
any accident or injury to any workmen or other person in the employment of
the contractor or his sub-contractor, and the contractor shall indemnify and
keep indemnified the G S E C L against all such damage and
compensation and against all claims, demands proceedings costs,
charges and expenses whatsoever in respect of or in relation thereto.
The contractor shall at his own expense / risk and cost to comply with all
the labour laws as above- mentioned and keep the G.S.E.C.L. indemnified
in respect thereof.
G S E C L : shall be entitled / empowered to deduct directly from the bills, the
amount to be paid to engaged bonafide contract workers or the contract
workers engaged by Sub-contractor; any sum or sums payable by main
contractor / sub-contractor and which sum/sums the Corporation is
required to pay in capacity of Principal Employer on account of the default
of contractor in respect of all liabilities incurred out of non-compliance
regarding any provisions of Labour Laws and same amount shall be
recovered from the pending dues of the contractor with 15% administrative
Any other rules and regulation, conditions, circulars etc., that are in force at
present and that may be framed by the G S E C L from time to time in
connection with contracts will be binding and acceptable to contractor.
The above are some of the major liabilities of the contractor in addition to
other liabilities prescribed under the various labour laws in force from time to
time from Statutory Authorities like State Government / Government of
India, which the contractor shall have to comply with.
The contractor shall provide the name of authorized representative, as
provided to other statutory Government authorities and will be notified to
Engineer In-Charge time to time.
14) Submission of Statutory documents to ensure the compliances:
The contractor shall upload statutory documents, work order-wise, under Labour
Laws and EPF in CLIMS / prevailing system at relevant time.
Required documents shall be u p l o a d e d by the contractor in existing
portal /prevailing system at relevant time invariably each month to
Engineer In-Charge for onward process and smooth clearance by HR
Department.
Sr. No. Description of documents attached
1 Copy of Work Order
2 Copy of P. F. Code No.
3 Insurance Policy as per subject of work order under the Workmen
EW- 278 PUR-F-006 RFQ-
Compensation Act,1923
Contract agreements/ subletting work contract documents with
approval copy
Copy of Id proof of Aadhar card or Election voting card or driving
license or Passport only
6 Copy of Police Verification in respect of each contract workers
15. The contractor whose work order value is above Rs. 5 lacs shall have to submit
“Declaration cum Indemnity Bond” on Rs. 300/- Non-Judicial stamp paper in prescribed
Performa (Annexure- “B”) with Agreement and Indemnity Bond before the commencement
of the contract.
Annexure- “B”
DECLARATION CUM INDEMNITY BOND
(On Rs.300/- Non Judicial Stamp Paper duly notarised)
THIS DECLARATION CUM INDEMNITY BOND made at ---------
---------------- (mention location) by M/S. ------------------------- having its
Reg. office at------------------------------------------------------(hereinafter
referred to as “Contractor” which expression shall unless it be
repugnant to the context or meaning thereof, be deemed to mean and
include their respective assigns, successors, executors, subcontractors and /
or administrators) of the ONE PART in favour of
M/S Gujarat State Electricity Corporation Limited having its
power Station at ……………..Ther mal Power Station (hereinafter
referred to as the “Company” ), which expression shall unless it be
repugnant to the context or meaning thereof be deemed to mean and
include its assigns, successors) of the OTHER PART.
WHEREAS the COMPANY has entered into a contract with the
Contractor for the work of”-----------------------------------------------------------
-„‟ under order No: ------------------------- dated-------------------------
“hereinafter called the “Contract”);
AND WHEREAS it is one of the essential conditions of the Contract that
the Contractor shall comply with all the provisions of the Labour &
Industrial Laws, as may be applicable from time to time for the
discharge and completion of the works and completion of the Works
and Services covered under said Contract Labour (R & A) Act
1970,Child Labour (Prohibition and Regulation) Act 1986,The
Employees Provident Funds & Miscellaneous Provisions
Act,1952,Employees State Insurance Act 1948, Minimum Wages
Act,1948,Payment of Bonus Act,1965,Payment of Wages Act,1936,
EW- 278 PUR-F-006 RFQ-
Employees Compensation Act.1923, Factories Act,1948 and other Labour
Laws, Rules, Notifications and Codes which are at present applicable to
the contractor and which may be applicable during the tenure of the contract
(hereinafter referred as the „Laws‟).
AND WHEREAS the Contractor has agreed to execute this Declaration
cum Indemnity Bond to this effect and has agreed to indemnify and
Company, it‟s Directors, Officers and employees and representatives
indemnified and hold harmless against all third party claims, charges
,penalties, fines, expenses ,losses, damages costs, suits or any other levy
against the Company and/or the management due to the failure of the
Contractor to observe or follow all applicable laws.
NOW THIS DEED WITNESSETH AS UNDER
1. The Contractor hereby declares that all acts, deeds, actions, activities,
conduct and lapse, delays, misdeeds, faults, breaches, inactions etc done
by his assigns, successors, executors, subcontractor and / or
administrators shall be construed to be have been done by the
contractor and he alone shall be liable for such acts, inactions etc.
2. In consideration of the Company awarding the Contract to the
Contractor subject to the condition of execution of this Declaration
cum Indemnity bond, the Contractor declares and represents to the
Company that the Contractor has obtained all Statutory registrations,
Certificates, licenses and approvals required under the Laws
enabling the Contractor to execute the Contract in a legal and
lawful manner.
3. That in the event of any liability arising out of non-compliance of any „Laws‟ of
the land by the Contractor in connection with the Performance of the contract,
the Contractor shall bear all the resultant liability (ies) whatsoever, if any and
that the company , its Directors, Officers and employees, representatives, shall
not be liable for any such liability(ies). The Contractor undertakes to indemnify
and keep the Company and its Directors, Officers and employees,
representatives indemnifies, defend and hold harmless, against all
losses, costs, damages, claims, penalties, interest, expenses,
demands, fines, legal liability, causes of action, injury to persons,
suits etc., which may be suffered, incurred, undergone and / sustained
by the Company including the Costs and expenses that may be
incurred in defending any such liability(ies) claim(S), Proceeding
(S) etc. that maybe made or taken or taken or arise on the
same by any Person, body, authority, government, judicial / quasi -
EW- 278 PUR-F-006 RFQ-
judicial authority due to the failure or non-compliance of any
such laws and rules there under (including any amendments in acts,
laws, statutes & rules there under) of whatsoever kind and nature
arising out of or in any way connected with, whether or not such
acts or omissions are actual or alleged, active or passive with
regard to the discharge of the said Contract.
4. The Contractor further declares that in case of any suit / claim /
right / damages / compensation / fine / levy / charges / expenses /
losses / penalties / costs raised by the third party, including
contract labours engaged by the contractor, he shall join such
proceedings in such Suit/Court/Tribunal/Authority and effectively
defend the same.
5. The Contractor hereby agree and undertakes to make good
any loss, damage, claims, suits, demands, decrees, expenses that
the Company may suffer to the fullest satisfaction of the Company
and if the Contractor fails to make good the same then the
Company shall have the right to recover the same from and or
any other loss sustained, without any restriction or limitation,
together with any other incidental expenses, costs, and all incidental
logistic expenses etc that may be suffered by the Company from
the Contractor and the Contractor hereby further confirms and
declares that this Declaration cum Indemnity Bond is irrevocable
and shall be final and binding on him, his heirs, executors,
administrators, legal representatives, successors, subcontractors and
assigns, wherever the context applies. any claims, demands, shall be
adjusted against any amount due and payable to the Contractor
and the Company shall have the right to withhold any amounts
due and payable to the Contractor, till the settlement of such
claims, disputes to the Contractor towards discharge of such claims,
obligations etc.
6. This Declaration cum indemnity bond shall be in accordance with the
laws of India and any dispute between the parties with regard to this
Declaration cum Indemnity Bond shall be resolved through the
dispute resolution process mentioned in the General Conditions of the
Contract (GCC).
IN WITNESS WHEREOF, the said Contractor has hereunto set their
hand the day and year first hereinabove written.
SIGNED S E A L E D AND DELIVERED By the within named
EW- 278 PUR-F-006 RFQ-
“CONTRACTOR”
(Authorized Signatory)
Rubber Stamp of Firm/Company
Full Name:
Designation:
In presence of Witness
Name & Address of Witness Signature
1. Full Name :
Residential Address:
Contact No. :
2. Full Name :
Residential Address:
Contact No. :
46 MATTERS RELATED TO EXECUTION OF WORK:
a) Work shall commence from the date given in letter to commence the work by EIC at
site. The Contractor shall make all necessary arrangements at site to mobilize labour,
operators, divers and materials and maintain necessary number of machinery and
equipment, barge, pontoons etc., to guarantee the agreed rate of progress of work as per
b) A detailed work schedule showing how he proposes to carry out the work, specifically
mentioning time periods as well as date of commencement and completion of each
activity and such approved schedules must be strictly adhered to by the CONTRACTOR.
After the owner has agreed with the schedule, the Contractor shall prepare detailed
program of each work front/activity breaking it down giving daily quantifiable/measure
of progress. The schedules are to be reviewed periodically with the OWNER / ENGINEER
to ensure that the completion date will be met or to institute corrective steps (at no extra
cost to the ENGINEER) to adhere to the completion dates. The OWNER reserves the right
to revise the schedule at his discretion in order to keep up to the completion date and to
suit the project requirement and such alterations shall not entitle the CONTRACTOR to
any extra payment.
c) A work schedule with PERT / Bar Chart for carrying out the work in prescribed time
limit mentioning date of commencement, activity to be carried with its time period,
starting & finishing event for each activity, completion of total project in critical path etc,
shall be jointly fixed and approved by the GSECL. Such approved schedules must be
strictly adhered by the Contractor.
EW- 278 PUR-F-006 RFQ-
d) After the GSECL has agreed with the schedule, the Contractor shall prepare detailed
program of each work front / activity breaking it down to daily quantifiable measure of
progress. The schedules are to be reviewed periodically with the Owner / E.I.C to ensure
that the completion date will be met or to institute corrective steps (at no extra cost to
the GSECL) to adhere to the completion dates. The Owner reserves the right to revise the
schedule at his discretion in order to keep up to the completion date and to suit the
project requirement and such alterations shall not entitle the Contractor to any extra
e) The GSECL reserves the right to delete any item of schedule-B for which contractor shall
not have any right to claim on this account.
f) One permanent reference bench mark and a reference base line shall be given for lay out
of work, which shall be maintained without disturbance by the CONTRACTOR during the
tenure of the contract. CONTRACTOR shall establish local bench marks as directed by the
ENGINEER IN CHARGE.
g) The contract or any part thereof shall not be subject to change without the written
permission of the Chief Engineer (Gen.) GSECL, GANDHINAGAR TPS or his authorized
representatives.
h) During the execution of the work if it is found that the work is not progressing as per the
scheduled program approved by the GSECL & planned by the contractor, due to the
reasons attributable to the contractor, suitable action shall be taken as per Clauses in this
tender elsewhere & other relevant clauses appearing in the section of “Terms & condition
of tender & works contract, Legal conditions of works contract” of tender document. And
the GSECL may also take such action as it may deem fit to ensure that the work is
completed in time at Risk and Cost of the contractor.
i) Contractor shall attend meetings at EIC's office at site or any other place as fixed by the
EIC, as and when required for review, discussion, coordination etc. Attending these
meetings shall be obligatory on the part of the Contractor, at no cost to the GSECL.
j) The Contractor shall take all requisite & necessary care to observe that no damage is
caused to the existing, pumps, existing works, service road, or any other structure etc. For
any damage to the existing structures of the GSECL, the Contractor shall be held
responsible and he will have to rectify the damage immediately up to the satisfaction of
Engineer in Charge, at his own cost.
k) The work shall be completed within the period stipulated in the contract. & site
clearance arranged according to the progress of work at site. Therefore, the contractor
has to organize & coordinate the work to suit these circumstantial conditions. In the
event of any delay due to the above or due to any other reason not attributable to the
contractor, reasonable extension in completing the work may be given at the discretion
and as decided by the GSECL but no compensation or idle charges will be payable to the
contractor on this account or any site conditions under any circumstances.
l) No idle charges shall be entertained by GSECL for any site condition or any
circumstances. The corporation will not pay any type of advances including mobilization
47. RECOVERIES:
a) In case of any damage to equipment / machinery or structure / building of GSECL or any
public property due to negligence of contractor or any other reasons attributed to
contractor, the decision of E.I.C. regarding the amount of recovery shall be final.
b) If the contractor fails to execute the work as per direction of E.I.C. within the time frame
given, the GSECL shall get the work done through any other contractor at the risk and
cost of the contractor and the cost of execution of such work along with 15% overhead
charges shall be deducted from contractor’s monthly bill over and above recovery as per
c) Recoveries due from the contractor, up to the end of the month previous to the one in
which the bill is prepared shall be made from bills approved for payment every month
or at other periods when the bills are prepared, for the various items in the following
order of priorities and extents.
d) Deduction on account of security deposit in full together with shortage, if any, to be made
e) Penalty in full, if levied.
f) Expenditure, if any, incurred by the Corporation on Contractor’s behalf in labour or
materials in full.
g) Charges for services such as water and power supply etc. in full.
h) Charge on account of supply of materials like cement and steel in case of shortages found
EW- 278 PUR-F-006 RFQ-
in balance or excess consumption than specified.
i) Hire charges for Corporation or Government machinery if any.
j) Recoveries of advance and secured payment or payments for preliminary work in full or
the installment due if and as the same as may have been allowed.
k) Rent recovery on account of allotting quarters on rent as per Corporation’s rules.
l) Income tax and sales tax in full as per Government rules.
m) Outstanding recoveries in respect of other contracts awarded by the Corporation if any.
n) Other recoveries. (If any)
48. WORK TO BE EXECUTED TO THE SATISFACTION OF THE ENGINEER -IN-CHARGE:
The contractor shall proceed with the work with diligence and expedition and the
whole of the work herein specified as well as the mode of execution shall be under
the supervision and direction and shall be carried on to the entire satisfaction of the
Engineer-in-charge, who shall have full power to order the contractor to alter, enlarge
or diminish the form, dimensions, positions, or quantities of any of the work or to make
use of material and workman-ship of different descriptions and qualities from this
herein specified.
The whole of the works, together with any temporary works, associated therewith, shall
be carried on in the most substantial proper and mannered workman like manner, with
the best materials and workmanship and to the entire satisfaction of the Engineer-in-
charge and in such order of time as he may direct. The contractor shall attend to and
execute without delay all orders and instruction which may from time to time be issued
by the Engineer-in-charge.
49. MATERIALS WORKMANSHIP etc.:
The work shall be executed in thoroughly substantial manner with material and
workmanship of best quality and strictly in accordance with the specifications and with
the drawings, or with such other drawings or written instruction as may from time to
time be furnished to the contractor, in accordance with terms of this contract and shall
be completed in every respect with all materials and workmanship implied and
necessary according to the fair interpretation and meaning of the same and should there
be any discrepancy between the drawings and specifications or any difference or
disputes as to the dimensions to be worked to or the quality of the materials to be used,
or the mode of doing periodical quantity of the work to be executed or with respect to
any subject arising out of this contract, the decision of the Engineer-in-charge shall be
final and binding on all parties. Rejected material shall be so disposed off as to obviate
any possibility of their use on works. The place, method and period of disposal shall be as
directed by the Engineer-in-charge.
50. SAMPLES OF DESCRIPTIVE DATE:
Samples of descriptive date, requiring approval, shall be submitted by contractor to the
Engineer-in-charge in good time before the use of such material for inspection and
permission of testing if required. The samples shall be properly marked to show the
name of the material, manufacture, place of origin, and place where to be used etc.
Failure of any sample to pass specified tests will be sufficient cause for the refusal to
consider any further sample from the same source.
51. FENCING AND LIGHTING AND VENTILATION
Except as herein after provided, the contractor shall unless otherwise specified, be
responsible for the proper fencing, guarding, lighting and taking of the necessary safety
measures for all works comprised in the contract and or the proper provision of
temporary roadway, footways, guards fences, caution notices etc. as far as the same
may be rendered necessary by reasons for the work for the accommodation and
protection of workman foot passenger or other traffic and of the owners and occupiers
of adjacent property and of the public and shall remain responsible for any
accidents that may occur on account of his failure to take proper and timely
precautions.
All the arrangements made for fencing, lighting and ventilation shall be maintained by
the contractor throughout the tendency of the contract till physical taking over of the
work by the department.
52. LIABILITY FOR DAMAGE TO WORKS OR PLANTS
The contractor shall during, the progress of the work, properly cover up and protect the
work, and plant, and materials placed at his disposal or acquired for him by the
Corporation, from injury by exposure to the weather, or any cause what so ever and shall
take every reasonable proper timely and useful precaution against accident or injury to
EW- 278 PUR-F-006 RFQ-
the same from any cause and shall be and remain answerable and liable for all accidents,
or injuries thereto which until the same be or be deemed to be, taken over by the
Corporation, may arise or be occasioned by the acts or omissions of the contractor or his
workmen of sub-contractors, and all losses and damages to the works or such plant or
material arising from such accidents or injuries as aforesaid shall be made good in the
most complete and substantial manner by and at the sole cost of the contractor and to the
reasonable satisfaction of the Engineer-in-charge. If the contractor fails to make good
such losses & damages within the time given by the Engineer-in-charge, the Corporation
shall be at liberty to recover the amount fixed by the Engineer-in-charge for such losses or
damages or any part thereof by deducting it from any sum due by the Corporation to the
contractor under this contract or otherwise.
Further the contractor shall, at all time, protect and preserve all materials, plant and
equipment that he may himself have procured for the execution of the work. All reasonable
requests of the Engineer-in-charge to enclose or especially protect any of the above shall be
expeditiously compiled with.
If the Engineer-in-charge considers that the work or materials or plant is not sufficiently
protected by the contractor, he shall be entitled to arrange for such protection at his
unfettered discretion and recover the cost thereof from the contractor.
Until the work shall be or be deemed to be taken, over as aforesaid, the contractor shall
also be liable for and shall be deemed to have indemnified the Corporation in respect of all
damage or injury to any person or any property of the Corporation or of others, occasioned
by the negligence of the contractor or his workmen, or his sub-contractor, or by
defective design, work or materials.
53. EXPLOSIVE PROCUREMENT AND STORAGE (IF APPLICABLE)
i) Explosives, petrol, oils, fuels and other inflammable materials shall be stored strictly in
accordance with the rule of the Explosive Department.
ii) The contractor shall at his own expense construct and maintain, proper magazines which
are required for the storage of explosive and arrange for proper storage facilities for oils,
fuels etc. for use in connection with the work.
iii) The contractor shall at his own expense obtain such license or licenses as may be
necessary for strong and using explosives, oils, fuels etc. The department shall not take any
responsibility whatsoever in connection with the storage or use of explosives on the site, or
any accident or occurrence whatsoever in connection therewith. All operation of the
contractor in which or for which Explosives are employed shall be at risk of contractor and
upon his own responsibility.
54. MATERIALS TOOLS AND PLANT BROUGHT ON THE SITE OF WORK
All materials, tools and tackle of the contractor brought to and delivered upon the site
for the purpose of the work shall from the time of their being so brought shall be
deemed to be the property of the Corporation in its possession to be used for the
purpose of the work and for that purpose only and shall not on any account be removed
or taken away by the contractor or any other person without the written permission of
the Engineer-in-charge but the contractor shall nevertheless be solely liable and
responsible for and loss destruction thereof or damage thereto. The Corporation shall
have a lien on such materials, tools and tackle for any sum of sums which may at any
time prior to the completion of the works be due or owing to the Corporation by the
contractor, under in respect of and dispose of any such materials, tools and tackle in such
manner as the Corporation may think fit and to apply the proceeding in or towards the
satisfaction of such sum or sums so due or owing as aforesaid but subject to such lien
and power of sale and disposal such surplus materials, tools and tackle shall belong to
the contractor and may be removed and disposed off by him as he may think fit.
55. ACCESS TO SITE AND WORK ON SITE
The Engineer-in-charge or his authorized representative may if he consider fit from time
to time enter upon any lands which may be in the possession of the contractor under
this contract, for the purpose of executing any work not included in this contract and
may execute such work not included in this contract by agents, or by other contractors
at his option and the contractor shall in accordance with the requirements of the
Engineer-in-charge, afford all reasonable facilities for execution of the works including
occupation of lands by structure or otherwise for any other contractor employed by
EW- 278 PUR-F-006 RFQ-
the Corporation and his workmen or for the workmen of the Corporation who may be
employed in the execution on or near the site of the work not included in the
contractor’s any contract in connection with or ancillary to the works and in default,
the contractor shall be liable to the Corporation for any delay or expense incurred by
reason of such default. Provided always that if the exercise of those power shall cause
any damage to the contractor he may within fifteen days of such damage arising make a
statement of the same to the Engineer-in-charge who shall from time to time assess the
value in his Judgment of such damage and the Corporation shall from time to time shall
pay to the contractor the amounts (if any accepted as justified) by the Engineer-in-
charge. The contractor shall not however, on account of any such modified, new or extra
work executed by or for the same of the Corporation be entitled to claim relief from the
obligation to execute other works.
56. INSPECTION OF WORKS
The Engineer-in-charge or his duly authorized agent shall have at all time full power to
inspect the works, wherever in progress, either on the site, on the contractor's premises
or at the premises wherever situated, of any firm or Corporation where work in
connection with this contract may be in hand.
Further, the contractor shall not allow, without written authorization permit entry on
site of work, any person except authorized agents of the Corporation of the Engineer-in-
charge or the contractor's staff and labour directly engaged on and in connection with
The contractor shall, during working hours, maintain supervisors having sufficient
training and experience to supervise the various items and operations of the work and
the said supervisors shall remain present during the inspections of the Engineer-in-
charge. All orders and directions given to such supervisors or other staff of the
contractor shall be deemed to have been given to contractor. Further the Engineer-in-
charge may be due notice, desire a higher ranking members of the supervisory staff of
the contractor to be present on any specified inspection and the contractor shall comply
with such direction.
57. CLEANING UP
The contractor shall at all times keep the construction area and his power house and
storage areas free from accumulation of waste, or rejected materials.
Prior to the completion of the work the contractor shall remove all rubbish from and about
the premises, and all tools, scaffolding, equipment and materials which are not part of
permanent structure. The premise will be left in a manner fully satisfactory to the
Engineer-in-charge, thereafter only the completion certificate will be issued.
58. CONTRACTOR TO KEEP INVENTORY OF MATERIALS etc.
The contractor shall prepare and maintain an inventory of all materials temporary
rolling stock, plant purchased or hired for use of employment or for any of the purposed
for this contract and such inventory or a copy thereof shall at all times be available for
inspection by the Engineer-in-charge. A complete and up to date copy of the inventory
shall be submitted to the Engineer-in-charge in the beginning and once a year; thereafter
changes in the interim period, if any shall be communicated on every three months.
59. CONTRACTOR TO RESTORE PLANT
Upon completion of the work, the contractor shall deliver to the Corporation, all
appliances, materials, and plants which may have been loaned or hired to him by the
Corporation and make good all damages which may have occurred to them, except such
as shall be caused by fair wear and tear in execution of the works.
60. PROGRESS SCHEDULE
i) The contractor shall furnish, within one week unless extended by the Engineer of the
order to start the work, a progress schedule in quadruplicate indicating the date of start
the weekly progress expected to be achieved and the anticipated completion date of each
major items of work to be done by him, also indicating dates of procurement and setting
up of materials, plant and machinery. The schedule should be such as is practicable of
achievement towards completion of the whole work in the time limit and of the particular
items on due dates specified in the contract and shall have the approval of the Engineer.
Further, the dates for the progress as in this schedule shall be kept up-to-date. In case it is
subsequently found necessary to alter this schedule, the contractor shall submit in good
EW- 278 PUR-F-006 RFQ-
time a revised schedule incorporating necessary modifications proposed and get the
same approved by the Engineer. No revised schedule shall be operative within such
acceptance in writing.
Detailed schedules for each week showing the progress proposed to achieve shall be
submitted to the Engineer and got approved. The Engineer is further empowered to ask
for more detailed schedule or schedules any week by week, for any items or items, and
the contractor shall supply the same as and when asked for.
ii) The Engineer shall have, at all times the right without in any way vitiating this
contract, or forming grounds for any claim to alter the order of the works or any part
thereof and the contractor shall after receiving such direction proceed in the order
directed. The contractors shall also revise the progress schedule accordingly and submit
four copies of the revised schedule to the Engineer within seven days of the Engineer's
direction to alter the order of works.
iii)The contractor shall furnish sufficient plant equipment and labour and shall work such
hours and shifts as may be necessary to maintain the progress on the work as per the
approved progress schedule. The working and shift hours shall comply with all GSECL's
regulations in force and shall be such as may be approved by the Engineer. They shall not
be varied without the prior approval of the Engineer.
iv)The contractor shall from time to time as may be required by the Engineer, furnish the
Engineer, with a statement in writing of the arrangement he proposes to adopt for the
execution of this contract and the Engineer may if he considers, necessary at any time
advise alteration in the same, which the contractor shall adopt on notice thereof.
v) The progress schedules shall be in the form of progress charts, forms, statement
and/or reports as may be approved by the Engineer. Further, the contractor shall submit
four copies showing the progress of work in forms and charts etc. at periodicals intervals
as may be specified by the Engineer.
61. DATE OF COMPLETION
The contractor shall supply, erect, equip and construct the whole of the works and
hand over them to the Corporation on or before the date specified in the tender
document including "Special Conditions" and save as herein provided, in no
circumstances whatever shall extend or alter the date for the completion of works.
Provided always that if in the opinion of the Engineer-in-charge the completion of the
works shall be delayed by any change of original design or by the order of the
Engineer-in-charge, of any altered, modified substituted or additional works or
materials omitted or by strikes, lock outs or stoppages of labour, or revolution, riots,
civil or political disturbance or by causes directly due to war or by the contractor not
being given possession of the site or any part there-of or by the Corporation taking
possession of and using the site or any part thereof or the works or any part thereof,
whether any nonperformance of work under the powers herein contained or otherwise
or by any nonperformance of work or non-supply of materials to be performed or
supplied by the Corporation or by the contractor not receiving any orders, drawings,
instructions or directions in time or by the suspensions of the works or by fire, flood
exceptionally bad weather tempest, storm, or by from unforeseen circumstances (and
whether the same shall be due to any act or omission of the Corporation or its agents
or those in their respective service or not) the Engineer-in-charge may, if in his
unfettered discretion, he thinks fit either forthwith or at any later time and from time
to time not withstanding that the prescribed or extended time for completion has
expired or that the work have been completed, by writing under his hand, extend the
time for the completion of the works to such date as he shall appoint. Provided always
that unless the contractor makes a written application to the Engineer-in-charge within
one month of the cause of delay and unless the time is extended by the Engineer-in-
charge, the prescribed time shall not be extended notwithstanding delays from the
aforesaid foregoing or any other causes of whatsoever kind.
62. SUBLETTING OF CONTRACT
There will be generally no objection on the component parts for the work, being given
over to responsible sub-contractors but Corporation shall under no
circumstances recognize these sub-contractors and the responsibility of executing the
work in the accordance with the conditions of contract will entirely rest on the main
EW- 278 PUR-F-006 RFQ-
contracts. The main contractors will therefore always have the very responsible
member, preferably a technical hand present on the works with power to sign all
work orders issued on the site of work and to take requisite actions in the interest of
very efficient execution of work. However, the subletting of the contract can be made
only with the prior approval of the competent authority of the Corporation.
63. OTHERCONTRACTS FOR THE WORK SUSPENSION STOPPAGEOR CURTAILMENTS OF
If during the tendency of the contract the Engineer-in-charge shall for any reasons
(which shall be unquestioned) whatsoever require the whole or any part of the work
as specified in the contract to be suspended for any period or shall not require the
whole or any part of the work as specified in the contract to be carried out at all by the
contractor, he shall give notice in writing of the fact to the contractor who shall
thereupon suspend or stop the work totally or partially as the case may be. In any,
case, except as provided hereunder, the contractor shall have no claim to any payment
or compensation whatsoever on account of any profit or advantage which he might have
derived from the execution of the work in full but which he did not so derive in
consequence of the full amount of the work not having being carried out, or on
account of any loss that he may be put to on account of materials purchased or agreed
to be purchased or for unemployment of labour recruited by him. He shall not also have
any claim for compensation by reason of any alterations having been made in the
original specifications, drawings, designs and instruction which may involve any
curtailment of the work as originally contemplated. Where, however, materials have
already been purchased or agreed to be purchased by the contractor, before receipt
by him of the aforesaid notice, the contractor shall be paid for such materials at the
rate determined by the Engineer-in-charge, provided they would have been useful for
the work curtailed or stopped are not in excess of requirements, are of approved
quality and cannot be used on other contract works or otherwise by the contractor
and/or shall be compensated for the loss if any, that he may be put to, in respect of
materials agreed to be purchased by him, the amount of such compensation to be
determined by the Engineer-in-charge, whose decision shall be final.
The Engineer-in-charge may grant extension of time for the execution of any item or
items of work affected by such suspension of work. The decision for the Engineer-in-
charge, regarding the granting of extension and the period thereof shall be final. The
Engineer-in-charge may order the contractor to suspend any work on account of bad
weather; rain or storm and such other adverse climate conditions and the contractor
shall comply with the same.
The contractor shall not be entitled to an compensation for such suspension of work,
concrete lining at the junctions of the different works under different contract shall be
done with particular care regarding forms, construction joints, interconnecting
reinforcement etc. If any and the joint planning of such work shall be with prior
approval of the Engineer-in-charge.
64. OTHER CONTRACTORS
Apart from this work, the other works connected with the power house will be
simultaneous going on either departmentally or through agencies inside or outside the
power house. Each contractor or agency shall co-operate with others to the fullest
extent and shall allow to each other every facility and co-ordination for execution of
their works simultaneously and satisfactorily, during their action of machinery or
execution of any other co-ordination works of the power house, the contractor will have
to work only at places as directed by the Engineer-in-charge. He will have some time
to suspend his work partially or totally in the interest of the work at large.
In such cases and at such time, he will be informed from time to time and directed by the
Engineer-in-charge where to work. He may also be required to remove the scaffolding or
to erect the scaffolding and shuttering in such a manner as to be of little obstruction and
inconvenience for erection of machinery. In such cases he shall not be given any
compensation on account of reduction or stoppage or labour force or removal and
reinstatement of scaffolding shuttering etc. It will be seen that contractor is not put to
unnecessary inconvenience.
EW- 278 PUR-F-006 RFQ-
In the matter of dumps, haul, roads, drainage, diversion and the like, each contractor
shall take into consideration the needs and requirements of the other constructors, if any
working in the vicinity. Further no contractor shall take or cause to be taken any
stops or action that may cause disruption, discontent or disturbance to the work,
labour of arrangements etc. or other contractors in the neighboring project localities.
Any action, by any contractor, which the Engineer-in-charge in his unquestioned
discretion may consider as infringement of the above code, would be considered as a
breach of the contract conditions and the Engineer-in-charge may take such action as he
may deem fit against the contractor and the action taken shall be considered as final
and binding.
65. SPEED OF WORK
The contractor shall at all times maintain the speed of work to confirm to the latest
operative progress schedule but the Engineer-in-charge may at any time with sufficient
notice in writing direct the contractor to slow down any part or the whole of the work
for any reason (which shall not be question whatsoever, and the contractor shall comply
with such orders of the Engineer-in-charge. The compliance of such orders shall not
entitle the contractor to any claim or compensation.
66. CONTRACT DOCUMENT AND MATTERS TO BE TREATED AS CONFIDENTIAL
All documents, correspondence, decisions and other matter concerning the contract shall
be considered as of confident and restricted nature by the contractor and he shall not
divulge or allow access there to any unauthorized persons of any kind.
67. ACCESS TO THE CONTRACTOR'S BOOK
Whenever it is considered necessary by the Engineer-in-charge to ascertain the actual
cost for execution of any particular item of work of supply of plant or material shall
direct the contractor to produce the relevant documents such as pay rolls records of
personnel, invoices of materials and any other data relevant to the item or necessary to
determine its cost etc. and the contractor to the aforesaid items in the mode and
manner that may be specified.
68. INTEREST ON MONEY DUE TO THE CONTRACTOR
The contractors shall not be entitled to get interest on any amount either of their bills or
arrears whatsoever because of delay in payment by the Corporation. Similarly they shall
not be entitled for any interest on amount of bank guarantees given by them. Non-
payment of interest by the Corporation therefore, shall not cause breach of contract.
69. MEASUREMENTS TO BE PROVISIONAL AND SUBJECT TO CORRECTION
Every measurements for running payment on account of work, done or supplies made,
shall be subject to adjustment or final measurements. In case of disagreement between
such intermediate and final measurements, the latter shall prevail. All works shall be
measured, met by standard measure and according to rules and custom and usual in the
use in Gujarat State Electricity Corporation Ltd., and no proposal to adopt alternative
method will be accepted, the Executive Engineer’s decision as to what is “the usual
method in use in the Gujarat State Electricity Corporation Ltd.” shall be final.
70. BREACH ON PART OF CORPORATION NOT TO ANNUAL CONTRACT
No breach or non-observance on the part of the Corporation of any of the agreements
contained herein, shall annul this contract or discharge the contractor from the
observance and performance thereof, or of any part thereof, but on application by the
contractor and in the unfettered discretion of the Engineer-in-charge an extension of
time may be given to the contractor in respect of such breach or non-observance by
the Corporation.
71. PROFORMA RETURNS
The contractor shall maintain Performa, charts and details regarding machinery
equipment materials, labour personnel and other matters as may be specified by the
Engineer-in-charge. He shall further, submit returns of Performa and details as may
be specified by the Engineer-in-charge from time to time.
72. LOCAL LAWS
All local laws in force at the time of entering into the contract and those enacted
thereafter shall be binding on the contractor and he shall abide by the same.
All import duties, sales tax and other local taxes shall be borne by the contractor and
they shall be deemed to have been covered by this quoted tender rate
EW- 278 PUR-F-006 RFQ-
73. WORKS IN SHIFT DUTY
Works shall be planned in shift duties, if possible in three shifts, depending on
emergency of the work with prior approval of Eng. - in- charge. 0n Sunday or any other
holidays work shall be continued in order to maintain progress with prior permission of
Eng.-in -charge. Such works shall not form any grounds for complaint, compensation or
extension of time limit.
If on the other hand, the Engineer-in-charge directs that the work shall be proceeded
with on days and during hours which are not permissible under this contract, the
contractor shall proceed with the work as directed without in any way vitiating this
contract or forming any grounds for compensation of claim.
The contractor shall in his dealing with labour, atall times, during the period of this
contract, have due regard to local festivals and religious and other customs.
A working day shall consist of two shifts each of eight hours, a working day shall
constitute any day on which in the opinion of the Engineer-in-charge, work can be
carried out in one or more shifts.
Final payment to the contractor shall not be made until the contractor shall deliver to the
purchaser or receipts in full in lieu thereof, and in either case, an affidavit that so far he
has knowledge or information the releases and receipts include all the labour and
material for which in lien could be filed. If any lien remains unsatisfied after all payments
are made, the contractor shall refund to the purchaser all moneys that the latter may be
compelled to pay in discharging such a lien, including all costs and a reasonable
attorney's.
75. MISCELLANEOUS:
1. In case of conflict / discrepancies among clauses of different specifications given in
this document, the stringent specification shall be followed and under such
circumstances, the decision of the EIC shall be final and binding to the Contractor
2. The Notice inviting tender, general instruction to bidders and all other documents of this
tender shall form part of the contract
3. No receipt for any payment alleged to have been made by a Contractor in regard to any
matter relating to tender of the contract shall be valid and binding on the Corporation
unless it is signed by the Engineer-in-Charge.
4. As per provisions of Income Tax Act, Corporation shall deduct Income Tax at the
applicable rate.
5. Agency has to note that the extension of Time limit/excess saving in the works if
required to approve, than it shall be processed as per the provision of DoP and will take
time for process the same.
6. The contract is inclusive of the cost of materials required to complete the work in
7. It will be absolutely incumbent on the contractors to have on the site of work only such
of the materials as have been duly passed by the Engineer-in-charge. Materials that have
been rejected must on no account be allowed to remain on the site, and in spite of
written order to do so, any such rejected materials is on the site beyond a period of
hours’ notice, the Engineer-in-charge shall have the right to remove it, at the risk and
cost of the contractors and even to destroy it.
8. It must be distinctly understood that conditions of contract and of claims in respect of
extra work, will not be allowed unless the works to which they relate is clearly without
the spirit and meaning of the specifications or unless such works are ordered in writing
by the Engineer-in-charge and claimed for in specified manner.
9. Contractor will be asked to present the sample of materials, and the approved samples
will be preserved at the site of work, and no change in the approved sample will be
allowed, without the written permission of the Engineer-in-charge.
10. The department reserves the right to make any change in the design and the plans of the
works. The contractor shall be bound to carry them out at the rates tendered. No claim
or compensation will be allowed on this account.
11. The contractor shall keep instruction book on site, for taking site instructions from time
to time. This book shall be made available on site whenever asked for.
12. Above construction equipment brought to site shall be allowed to be taken out only after
the work for which it has been brought is over. The equipment shall be taken out only
with the specific permission in writing from the E.I.C. Only the equipment required for
the work and in fit condition shall be brought to the site. The Contractor shall ensure
EW- 278 PUR-F-006 RFQ-
that proper documentation is followed at entry gate of GSECL's premises for such items
which shall be carried back by Contractor after completion of work.
13. The Contractor shall provide all temporary ladders, scaffolding materials, platforms,
supports and other necessary facilities required for trimming & cutting of trees. The
Contractor shall provide sufficient, strong and safe staging so as to ensure safety of the
14. The Contractor shall provide sufficient fencing, notice Corporations and lights to protect
and warn others as may be considered necessary by the GSECL and safety authority.
15. The GSECL may during the progress of work, order the removal of part or whole of the
work executed, found not in accordance with the approved drawings, specifications/
instructions. No extra claims shall be entertained for re-executing or altering of such
16. On completion of the work, the site shall be left in good order and the excess materials,
scraps, debris, if any shall be removed and dumped by the Contractor at place/places as
designated by the GSECL. The Contractor shall also dismantle and remove the staging
and other temporary facilities like stores, offices, labor camp etc. on completion of work.
17. Contractor is required to maintain proper records at site of work in addition to normal
routine requirement of own office. The records to be maintained shall include but not
limited to the following:
(a) Daily Progress Record.
(b) Work Site Order Book.
(c) Instruction by GSECL's Officers.
(d) Test Registers of other materials/fittings, fixtures, equipment as stipulated in the
(e) Register for Working Details.
(f) Log Book of Defects.
(g) Hindrance Register giving details of commencement and removal of each
hindrance.
(h) Supply and consumption registers of all materials shall be maintained.
(i) Day to day Record of used/received materials shall be entered in the register and
signed by the Site Engineer of the GSECL as well as contractors' representative at
(j) Measurement Book.
77. SALES TAX ON WORK CONTRACT
The Gujarat Government by its amendment to the Gujarat sales tax act has also
made works contract subject to Sales Tax. However works contract tax shall be
liability of the contractor and shall be born by the contractor. More ever you shall
also have to submit form No 702 as prescribed by Gujarat Sales Tax act while
submitting invoice.
More ever the purchaser will not pay any composite tax/turnover tax/works
contract tax which contractor has to pay as per act. Hence the incidence of sales
tax or such type of taxes shall not be payable by the purchaser in any case even if
such taxes are levied on the party/contractor at a future date.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 278 PUR-F-006 RFQ-
TERMS AND CONTRACT FOR WORKS
GENERAL SAFETY RULES
LIST OF SAFETY TOOLS
EW- 278 PUR-F-006 RFQ-
TENDER & CONTRACT FOR WORKS
I/We hereby tender for the Gujarat State Electricity Corporation Ltd. (herein Referred as
“Corporation”) of the work specified in the underwritten memorandum within the time specified
in Schedule B (memorandum showing items of work to be carried out) and in accordance, in all
respect, with the specifications, design, drawings and instructions in writing and as per annexed
conditions of contract and agree that when the materials for works are provided by the
Corporation, such materials and rates to be paid for them shall be as provided in Schedule A
MEMORANDUM
(a) General description of work : Repairing and augmentation of existing drainage
network in CHP area at GTPS
(b) Estimated cost : Rs. 4314681.80/-
(c) Earnest money (3%) : Rs. 129440.00/-
(d) Security deposit : As per cl no.7 of Section C (i.e General condition of
contract).
(e) Time allowed for the completion of work from date of written order to commence.:
06 (Six) Months
Should this tender be accepted, I/We hereby agree to abide by and fulfill all the terms and
provision of the conditions of contract annexed hereto as applicable and in default thereof
forfeit and pay to the Corporation, the sums of money mentioned in the said conditions.
Receipt No. Date from the Gujarat State Electricity Corporation Ltd. in respect of the sum of
Rs____________________________________. (The amount to be specified in figures and
words) is herewith forwarded representing the earnest money (the full value of which is to be
absolutely forfeited to the Corporation, should I / we do not execute / commence the work
after issuance of date of commencement by GSECL.
Signature of the Contractor:
Address of the Contractor:
Dated__________________ day of _______________year
Signature of Witness:
Address of the Witness:
Occupation:
Dated__________________ day of _______________year
The above tender is hereby accepted by me on behalf of the Gujarat State Electricity Corporation
For & On behalf of GSECL
Chief Engineer (Gen)
GSECL GANDHINAGAR TPS
his duly authorized Assistant
EW- 278 PUR-F-006 RFQ-
General Safety Rules & List of Safety Tools.
“GENERAL SAFETY RULES / NORMS” TO BE OBSERVED BY THE CONTRACTORS
All the contractors working in Gujarat State Electricity Corporation Limited Factory like
Coal/Lignite/Gas/Hydro/Pumping Station shall have to strictly observe the following Safety
Rules. Concern principle contractors are responsible for informing & observance of these rules by
their supervisors/contract workers as well as the owner/supervisors/ workers of sub-Contractors
engaged, if any, by them for the work contract awarded to them. Prior to commencement of the work,
Contractor shall have to submit a written assurance on their letterhead to the concerned Sectional
Head / Engineer-in-charge that they have thoroughly gone through these Rules, have educated their
employees / workers of their sub contractor and will strictly observe the said Rules while execution
of work under work contract awarded to them. They will have to indemnify the company for any loss
or damage / accident / injury to the company’s property / employee or employee of their own in
default of non - observing these rules.
(01) Contractor should issue photo gate pass for their workers from GSECL Factory
Manager as per Gujarat Factori es rules, 1963 & details shall be filled up in
GSECL gate pass format as per Aadhar card /Election card id proof & to follow
the gate pass issue procedure through concern department EE & SE, Security Officer,
LWO/IRO/DGM, Factory Medical Officer, Safety Officer/Dy. Safety Officer & Factory Manager.
(02) In case of emergency, temporary photo gate pass shall be issued by Security Officer only for
three days with prior permission of Factory Manager only. More than three days, Permanent
photo gate pass procedure shall be completed by contract agency for their contract workers.
(03) Certificate of Fitness of employment in hazardous process & operations in form no.33 of Gujarat
Factories rules, 1963 shall be issued by GSECL Factory Medical Officer for all contractor
workers before commencement of work & examination responsibility shall be taken by
contractor as well as concerned Head of Department .Pre-employment & Periodical medical
examination of contractor workers shall be carried out in form no.32 from GSECL Factory
Medical Officer after every six (06) months of contractor with their contractor workers.
Contractor shall be fulfilled all health requirements before commencement of work. After
completion of medical examination in form no.32/33, GSECL Factory Medical Officer shall be
signed in contract worker gate pass procedure format.
(04) Contract worker gate pass will issue after completion of safety induction 3D animation movie &
Training record is to be maintained in IMS/OHSAS training format by TK Office/LWO.
(05) As per Gate pass format of GSECL, Safety Officer/Dy. Safety Officer shall be checked the issue
PPE to contract workers as per nature of job, Form no.10 of lifting tools and tackles, Driving
license, Electrical contractor license, Electrical trade qualifications, Safety induction training,
SOP, supervisor qualifications etc. After fulfillment of all Safety compliances, Safety Officer/Dy.
Safety Officer shall be signed in Contract worker Gate pass procedure format.
(06) Work Contract shall be completed by principle contractor/agency/person who is awarded the
work order. Subletting of contract shall be allowed only if prior approval of Power station chief
before execution of work. Contractor/agency shall be submitted the entire subletting contract
documents with gate pass application through concern department EE & SE, LWO/DGM, Safety
Officer/Dy.Safety Officer & Factory Manager.
(07) Under The Conditions Framed Under Rule-45 Of The Indian Electricity Rules, 1956, Valid
Electrical contractor License shall be submitted to concern electrical department
EE/SE/Electrical Safety Officer/ Safety Officer/Factory Manager at the time of apply gate pass
by agency/party with latest renewal from Chief Electrical Inspector, Gandhinagar- Gujarat.
Electrical License photocopy shall be checked by Concerned HOD of Electrical
Department/Electrical Safety Officer/Dy.Safety Officer/ Safety Officer/Factory Manager.
(08) As per nature of job/work, qualified supervisor (Diploma (Electrical/
Mechanical/Civil/C&I) + 3 years experiences or ITI + 10 years) shall be engaged by contract
agency & qualification certificate with experience certificate shall be submitted to concern
EE/SE/LWO/IRO/DGM/ Dy.Safety Officer /Safety Officer/Factory Manager at the time of apply
gate pass.
(09) As per rule 3 of CEA regulation ,2010: Designating person(s) to operate and carry out the
work on electrical lines and Apparatus, Contract person/worker possesses a certificate of
competency or electrical work permit, issued by the Appropriate Government. That means,
EW- 278 PUR-F-006 RFQ-
Electrical trade Qualification of contract worker/person like ITI-wireman/ Electrician, Diploma
(Elect), BE/B. TECH (Elect), ME/ M. TECH (Elect) shall be submitted to concern
EE/SE/LWO/IRO/DGM, Dy.Safety Officer/ Safety Officer/Factory Manager at the time of apply
for photo gate pass procedure.
(10) As per nature of job/work & during capital overhauling work /Annual overhauling work /24X7
round the clock work/major shut down work, Qualified Safety Officer/Manager/Supervisor
(BE/Diploma (Elect/Mech/Civil) + PDIS-Post Diploma in Industrial Safety) shall be engaged by
contractor during dangerous operations/dangerous works as well as day to day dangerous
activities, safety supervision, tool box talk, Safety awareness programme, SOP preparation with
hazards & its control measures with each step , checking of lifting tools & tackles, hydra mobile
crane, Safety precautions, coordination with Safety Department etc.
(11) License of driver shall be submitted with gate pass issue application as per nature of vehicles &
to follow the Motor vehicle Act,1988, the Central Motor Vehicles (Amendment) Rules,2016 as
well as Gujarat Motor Vehicles rules,1989 & driver license shall be checked every day by
security shift in charge before entry in the Factory premises.
(12) SOP with JSA (Job Safety Analysis) shall be prepared by contractor through competent person
as per GFR, 1963 or Qualified Safety Officer as per GFR, 1963 with 05 years experiences. SOP
will review & approve by concern JE/DE/EE/SE/Elect. Safety Officer/Dy. Safety Officer /Safety
Officer/Factory Manager before execution of work.
(13) It is compulsory to use standard make Personal Protective Equipments (P.P.Es.) as per the job
requirement. Do not work without use of required P.P.Es. Contractor is responsible to provide
standard make (ISI/DGMS/CE/EN/ANSI approved) & to checked standard/make in PPE issue
format by concern JE/DE/EE/SE/Safety Officer/Factory Manager. Personal Protective
Equipments / Safety Gadgets suitable to give sufficient protection against hazards involved in
their work / job to their staff, as per the job requirement and insist / enforce their workers to
put on the same while at works.
The ongoing work is liable to be stopped at any time if your contract workers/staffs found
working without P.P.Es. Following is the list of various P.P.Es (as per ISI/DGMS/CE/ EN/ ANSI
approved only) to be used for various works / worksites.
In any work, Contractor shall be issued the minimum 05 nos. of PPEs like Safety Shoes, Safety
Helmet, Safety goggles, Mask & Reusable Ear plug to their workers/supervisor compulsory & it
will check by concern section HOD & Dy.Safety Officer /Safety Officer at the time of gate pass
procedure.
Industrial Safety Helmet For protection of head against falling objects or during fall of
person from height. Yellow Colour helmet is used for
contract worker with agency logo.
Safety Goggles/welding For protection of eyes against flying particles / dust,
goggles/chemical splash goggles chemical splash, welding spark, arc, flashover etc.
Full Face shield For protection of face against flying particles / dust,
chemical splash, spark, arc, flashover etc.
Reusable Earplug / Ear muffs. For ear / hearing system protection while working in high
noise level area.
Chemical suit/Gas tight suit For body protection against chemicals, oils, sharp edged
/Fire proximity suit/FR Boiler objects, heat, hot objects etc.
Safety Hand Gloves For protection of hands against chemicals, oils, sharp edged
objects, heat, hot metals/objects, electricity etc.
Safety shoes/ Gum Boots with For protection of leg/feet against falling objects, sharp
Oil/Chemical/water/heat/ edged objects, heat, hot metals/objects, electricity etc..
Electrical resistance etc.
Safety Belt(full body hardness For fall prevention while working at heights or in depth,
with double lanyard & shock working in vessel or in confined space.
absorber) / Rope / Life line /
Fall arrestor etc.
Dust Mask/Respirator with Protection of respiratory system against dust.
valve(FFP2)
Chemical Cartridge Respirator Protection against toxic chemical fumes /
EW- 278 PUR-F-006 RFQ-
with full face mask type gases/vapors/dust etc.
Trolley mounted Air line Working in oxygen deficient zone or confine space area
respirators with full face mask
Portable Single gas detector like Working in hazardous storage/process area
Chlorine, Ammonia, Hydrogen,
Portable Multi gas Detector (
Working in oxygen deficient zone & use in entry of confine
LEL,O2,CO,H2S,SO2, etc) space & Major fire
Automatic voltage detector To check the present voltage or induction voltage of
electrical equipments/ bus/switch gears from 01 (one)
feet distance before starting the any electrical work .
Auto darkening welding helmet The new auto darkening welding helmet combines
(EN 379 & EN 175 Level-B) with legendary Speed glass quality and auto darkening
PAPR as per EN 12941:1998, technology with an innovative wide-view grinding visor to
class TH2 and AS/NZS 1716 give welders an all-in-one solution for more flexibility,
precision, and efficiency.
Respiratory System is a combined face and breathing
protection device, for increased comfort and safety in
welding. The unit is equipped with a particle filter which
removes particles from the air. The unit provides a constant
airflow independent of filter combinations and clogging. The
unit can also be equipped with a gas filter (for example
A1B1E1). The unit supplies air to the head top via the
connecting breathing tube. The airflow creates a slight
positive pressure which together with the sealing to the face
prevents particles and other contaminants from entering the
(14) All PPEs (as per ISI/DGMS/CE/EN/ANSI approved only) Should issued by
party/agency/contractor to their contractor workers as per nature of job and allotment of PPE
list shall be submitted to Safety Officer, Dhuvaran on his letter head as per below mentioned
format by Contractor before commencement of work through concerned JE,DE,EE/SE .
Sub: Issue of PEE to Contractor workers
Sub of work Order:
Work order no.
Name of Agency:
Date of Commencement:
Time limit for work order:
Sr. Name Design Name of Name of PPE IS Make Qty Uni Date Receivin
no. of ation Section :Code of t of g
worker under work no. of PPE issue signature
s execution PPE
01 Safety Helmet No
Safety goggles No
Reusable Ear Pai
Dust Mask No
Safety Shoes Pai
(15) Shift Security Inspector/Security Officer shall be checked Safety Shoes & Safety Helmet of all
contractor workers at entry gate of Factory Premises & shall entered contractor workers with
Safety Shoes & Safety Helmet with photo ID Gate Pass.
EW- 278 PUR-F-006 RFQ-
(16) Shift Security Inspector/Security Officer shall be checked validity of Gate pass of all contractor
workers on daily basis.
(17) During the work execution, one trained & competent supervisor of agency should always
remain present at work site. Concern JE/DE of GSECL shall be supervised the contract work as
(18) Approved NABL laboratory calibration certificates of
electrical/mechanical/Civil/C&I/Environment survey/Chemical etc measuring /testing
equipments/instruments which are used during contract work shall be submitted before
starting the work & shall be checked by concern JE/DE/EE before starting work & it’s record
shall be maintained in concern section.
(19) The contractor shall take all the required safety measures prior to commencement of work on
dangerous substances, machineries or area at which cautionary notice is displayed and obtain
“Line Clear” or “Work Permit” through the concern Department / Section JE/DE and shall be
informed to concern section JE/DE for closed/ returned after completion of work.
(20) Safety talk/Safety work instructions shall be given to contractor workers by concern JE/DE
regarding hazards of specific work, risk & it’s control measure (mentioned in HIRA) before
starting the job work and records shall be maintained for each & every job works.
(21) Display Safety instructions shall be strictly followed by all workers who are working in factory
(22) Material Safety Data Sheet (MSDS) of each chemical shall be available with Chief
Chemist/Control room & work related Chemical information shall be taken by contractor &
contractor workers from Concern EE/Chief Chemist before starting of chemical handling work.
(23) The contractor shall be checked & securely covered or securely fenced any opened fixed vessel,
sump, tank, pit or opening in ground or in floor which, by reason of its depth, situation,
construction or contents ,is or may be a source of danger before starting the work each & every
days or after interval/recess. Contractor supervisor shall be informed to concerned HOD
regarding any unsafe conditions.
(24) Prohibition of smoking, fires, lights, spontaneous ignition substance, matches; fuses, mobile
phone etc are to be strictly followed by all workers who are working in factory premises.
(25) Prior to carrying out welding, gas cutting, furnace heating or any other hot work job, remove all
the inflammable material lying at or nearby worksite or cover it properly by suitable protective
covering. Also, special care shall be taken before carrying out such job & see that all possible
contributing factors to set fire shall be removed / vanished prior to commencement of the work.
Advance intimation shall be given to concerned section / fire section to commence the work in
fire prone areas. They should also keep ready all the First Aid Fire Extinguishers / equipments
& fire extinguishing media / material like sand / water buckets or other appropriate equipment
at such place.
(26) While carrying out work in confined space or inside vessel, obtain necessary “Confined Space /
Vessel Entry Permit” from concerned department prior to commencement of the work.
For lighting in such areas, only 24-volt (ISI certified & with proper guard) hand lamp shall be
used. For taking care of the persons working inside the confined space / vessel, a supervisor /
person capable to keep continuous watch on person(s) working inside, assist them in case of
emergency or arrange to get immediate outside help, shall remain present at entry point. Use
full body safety belt without failed.
While working inside sewage, trench or in-depth, a person to warn outsiders / entrants /
passers etc shall remain available near entry point or the entry point shall be cordoned by a
barricaded tape with a cautionary notice. After completion of the works, all the lids / covers /
grills / grits opened, shall be re-fixed / re-placed in the original position as it were prior to
commencement of the work and leave the work place in safe condition in all respect, so as to
prevent accident to fellow workers.
(27) The contractor shall see that he / his persons do not work on or block (by stacking material,
spare parts, tools-tackles, equipments etc), any passages / walkways / gangways / aisles /
staircases / ladders / lifts or any other approaches / roads leading to plans or its auxiliaries, on
which there is traffic movements or possible traffic movements in case of emergency. Such
passages are meant for safe escape in the event of emergency. If it is utmost necessary to carry
out work in such area with blocking of passage, prior permission of Competent Authority or the
Engineer-In-Charge shall be obtained. To demarcate / declare the area as “UNSAFE”, cordon it
EW- 278 PUR-F-006 RFQ-
using barricading tape & display suitable caution notice or keep a person to restrict / divert the
traffic on this route through other safe passage.
(28) The contractor shall see that he / his persons do not work on or block (by stacking material,
spare parts, tools-tackles, equipments etc), any passages / walkways / gangways / aisles /
staircases / ladders / lifts or any other approaches / roads leading to plans or its auxiliaries, on
which there is traffic movements or possible traffic movements in case of emergency. Such
passages are meant for safe escape in the event of emergency. If it is utmost necessary to carry
out work in such area with blocking of passage, prior permission of Competent Authority or the
Engineer-In-Charge shall be obtained. To demarcate / declare the area as “UNSAFE”, cordon it
using barricading tape & display suitable caution notice or keep a person to restrict / divert the
traffic on this route through other safe passage.
(29) Prior to use power / electrically operated hand tools / equipments / machines / gadgets like
welding machine, hand grinder, hand drill etc, ensure for its safe operation & use it only if it is
found safe to use. Do not use defective, unsafe or improperly maintained equipments.
The electrical power supply required to run such equipments shall not be taken directly at their
own but shall be obtained through concerned Electrical Maintenance Departments or their
authorized persons or under their observations / guidance only. The Electrical Section shall
provide temporary electrical connection up to contractor’s Mains Board on which it is
compulsory to install mains switch, ELCB & fuses of adequate capacity. All such equipments
shall invariably be earthed adequately to prevent electrical shock, sparking, short circuit etc.
Power cord to be used shall be of adequate capacity, without any joint & shall consist of earth
wire also. Hence, it is necessary to use adequate capacity 3-wire power cord for single & 5-wire
power cord for three phase power connections. The plugs, receptacles, pins, holders etc shall be
of adequate capacity & safe to use.
All electrical & mechanical equipments / tools-tackles viz. welding machine, cutting machine,
Grinder, Drill, Chain Pulley Blocks, Hook chooks etc required to be used during work execution
shall be of standard make & bear ISI certification mark on it. The consumables like welding
electrodes, grinding wheels / discs etc which has specific prescribed life span shall not be used
in any case if its expiry date is over.
(30) Non-Sparking Non-Magnetic electrical hand tools and tool kits shall be used by Electrical
contractor for safe use in areas where hazardous, flammable, or combustible vapors, liquids,
dusts, or residues may be present in Gas Based power plant and list of tools and tackles shall be
submitted with technical bid. Non-Sparking Non-Magnetic electrical hand tools and tool kits
shall be checked by JE/DE before commencement of Electrical work.
(31) Before using lifting machines / tackles (like C.P.Bs., Hook chooks, winch, forklift, mobile crane,
EOT crane etc) & its attachments (like D-shackles, slings, U-clamps, Eye bolts or any fixtures), it
shall be checked and used only if found safe to use. Also, ensure that these are tested, examined
& certified in form no.10 by Competent Person as per the Factory act-1948 & Gujarat Factories
Rules and its validity do not expire. Further, it shall be fixed properly and firmly prior to lifting
the weight. Valid Test certificate of all Lifting machines used by Contractor to be
submitted to Dy.Safety Officer/ Safety Officer before commencement of work through
concerned EE/SE.
(32) Metal Scaffoldings to be used for working at height shall be of adequate size & capacity. Obtain
the work permit when working at height. While climbing on such scaffolding or working on any
structure at height, use of full body safety belt /full body hardness with double lanyard & Fall
arrestor & Helmet is compulsory. It is also necessary to fasten chinstraps of the helmet.
(33) Contractor or their employee shall not interfere in day-to-day routine plant activities / works
except the work assigned to them, shall not loiter in the areas other than their work jurisdiction,
as well as shall not temper / operate / touch the machineries/equipments/auxiliaries with
which they are not concerned. Also, the contractor shall strictly instruct their staff for not to sit
or take rest at/near/below running plants, auxiliaries, systems or any place which is risky,
hazardous & prone to accident.
(34) The cylinders containing poisonous / toxic or inflammable / explosive gas like Oxygen,
Acetylene, LPG, Hydrogen, Ammonia, Chlorine, CO2 etc shall be handled safely taking due care.
To handle / shift such cylinders a special trolley /cage meant for it must be used but in no case
it should be rolled.
(35) In Gas Based Power station/Hydrogen storage area /Hydro carbon fumes-vapour generated
area, Spark arrestor (as per approved manufacturer of CCOE, Nagpur) shall be provided on each
EW- 278 PUR-F-006 RFQ-
vehicle by party/agency and it will check by shift security in charge before entry of vehicles in
the factory premises.
(36) No women or young person shall be employed or permitted to work in Lead-compound area
like battery room etc. as per schedule VI of GFR
(37) No women or young person shall be allowed to clean, lubricate or adjust any part of a prime
mover or of any transmission machinery while the prime mover or transmission machinery is in
motion. Examination or operation of motion machinery shall be made or carried out only by a
specially trained adult male worker wearing tight fitting clothing as per section 22 of factories
(38) In all risky job, before start the work, contractor should obtain General Safety Work Permit
through concerned section from Shift –in-charge well in advance.
(39) In case of noticing smoke or fire during their work execution, they shall make immediate efforts
to extinguish / control it and simultaneously inform the Fire Station Mobile No as well as
Station Fire Officer or Emergency Control room no which is displayed at prominent place of
factory like Main Security Gate, All unit control room, Canteen area, Safe Assembly points, Fire
Station, All security gates, Occupational Health Centre.
(40) In case of any injury / accident while working, it shall immediately be reported to Safety
Department through concerned Sectional Head / Engineer. The prescribed Form No. 21 &
ANNEXURE may be obtained from concerned section or Dy.Safety Officer/Safety Officer.
In case of any electrical accident, it shall immediately be reported to Electrical Safety Officer
through concern Sectional Head / Engineer. The prescribed Electrical accident form no. A as
per electricity act-2003 & Form No. 21 & ANNEXURE as per Gujarat Factories rules shall be
filled up by concern department JE/DE with written consent of contractor. The Form may be
obtained from concerned Electrical section or Electrical Safety Officer. Electrical accident
investigation shall be carried out by Electrical Safety Officer with Factory Manager.
After any reportable accident, Contract agency shall be submitted the fitness certificate of
injured person with endorsement of GSECL factory Medical Officer to LWO/Dy.Safety
Officer/Safety Officer/Electrical Safety Officer then after injured person may allow for work.
(41) For any incident occurred but have no injury to any persons should also reported as per GSECL
format and informed to Dy.Safety Officer/Safety Officer as Near Miss Incident.
(42) Safety penalty shall be imposed against violation by contract workers: if any contract worker
worked in a factory contravenes any provision of factories act or any rules or orders made there
under. Imposing any duty or liability on workers, contractors/agency shall be punishable with
fine which mentioned as under.
Sr. Description of penalty Amount
(i) Work without PPEs Rs.300/- per person
(ii) Work without work Safety permit like working at height, Rs.1000/- per day
confine space entry, hot work etc.
(iii) License of driver as per type of vehicles not registered. Rs.750/- per person
(iv) Welding work without flashback arrestor/double gauge Rs.1000/- per set
regulator set
(v) Operate Portable power tool without ELCB Rs.1000/-per
(vi) Work without qualified Supervisor as per nature of job like Rs.1000/-per day
mechanical, electrical, civil, C&I, chemical etc.
(vii) Work without SOP & JSA Rs.2000/-per day
(viii) Work without test report of lifting machines / tackles (like Rs.2000/- per
C.P.Bs., Hook chooks, winch, forklift, mobile crane, EOT crane equipment
etc) & its attachments (like D-shackles, slings, U-clamps, Eye
bolts or any fixtures) in Form No.10 of Gujarat Factories
Rules,1963
(ix) Work without Double lynyer Safety belt during working at Rs.3000/-per person
Height work, work without anchoring in hook/line line
(x) Work without 24 Volt supply in Confine space area Rs.3000/-per person
(xi) (a) Grinding machine used without safety guard/ machine Rs. 500/- per
guard equipment/ per set
EW- 278 PUR-F-006 RFQ-
(b) Unsafe welding machine like open body. Knob without
insulation. Connection without plug
(c) Damaged welding cables/gas pipelines
(d) Welding work doing without welding blanket.
(e) Electrical supply without 3 pin plug/industrial plug.
(f) Use of damaged electrical wire for lighting/equipments.
(g) Use of lighting lamp without cage.
(h) Use of open halogen tube.
(i) Use of damaged PPEs/use of non standard PPEs
(j) Unsafe lifting and handling of gas cylinders
(k) Cylinder handling without safety cap
(l) Temporary connection without ELCB. etc
During plants visit/supervision of concern JE/DE/EE,SE. Safety officer/Dy. safety officer.
Electrical safety officer , factory manager, if they will observed any safety violations as per CO
circular/statutory requirements then they must imposed safety penalty through office note
directly against contract workers/contract agency and Office Note process through proper
channel to concern sectional head and Account head for recovery purpose. Photograph/CCTV
Footage is to be put a with penalty note by imposing officer.
(43) Party will damage any fire equipments or property or machinery in factory during execution of
work, total damage cost will be recovered from party RA bill and recovery Office note put up by
concern HOD.
(44) All the relevant labour and industrial laws shall also be followed compulsorily.
(45) After completion of work, cotton waste, grease, oil, unused material, welding rod pieces, scrap
etc. are to be removed by contractor and scrap shall be deposited to scrap yard of Main Store.
(46) For performance evaluation of contractor, safety factors of work accident, fire incident & near
miss accident will be considered. Steps can be taken to review the job assignment up to
cancellation for negligence.
(47) Over & above these, contractor shall have to follow all the safety requirements /rules &
regulations / norms and legal provisions laid down in various statutes. Particularly the
provisions of The Factories Act-1948 & the Gujarat State Factories Rules-1963 (Amended up to
date), The Electricity Act-2003 & rules, BOCW Act/Rules shall be followed strictly. The
contractor shall also obey the rules / regulations / instructions of the local Competent Authority
for safety & health requirements.
(48) The above rules shall be scrupulously followed and where required, Contractor /contractor
workers may contact to the Dy.Safety Officer/Safety Officer/Electrical Safety Officer in case of
any ambiguity or needs further guidance in this regard.
(49) As per C.O circular No. GSECL/Medical/PME/O1 DTD.16.07.2019 i.e for procedure for health
cheak-up accordingly bill shall be reimbursed once during total contract period (for as & when
and AOH/COH contract) maximum up to Rs.1000 or actual cost per worker/ labour /person,
whichever is minimum after verification & recommendation by concern doctor. In case any
worker left the work in between than for replacement Worker Company will not provide any
reimbursement, however it is compulsory to submit new report of replacement worker for
fitness certificate at contractor’s own expense.
Chief Engineer (Gen.)
GSECL,GandhinagarTPS
SIGNATURE OF CONTRACTOR
(With Rubber Stamp & Date)
EW- 278 PUR-F-006 RFQ-
PERFORMA FOR BANK GUARANTEE
INTEGRITY PACT
CERTIFICATE – A
ANNEXURE - I
EW- 278 PUR-F-006 RFQ-
ON STAMP PAPER OF Rs.300/-
FORM OF BANKER’S UNERTAKING
(For Security Deposit for work period as per Terms and Conditions of Tender)
We, Bank of ______________________________________________ hereby agree
unequivocally and unconditionally to pay immediately on demand in writing from the Gujarat
State Electricity Corporation Limited, or any Officer authorized by it in this behalf any amount up
to and not exceeding Rs.__________ (in words) Rupees
to the said Gujarat State Electricity Corporation Limited on behalf of
M/s.___________________________________________________ who have entered into a
contract for the supply / works specified below :
L.O.I. No. _____________________________________________________ dated
This agreement shall be valid and binding on this Bank up to and inclusive of________________
and shall not be terminable by notice or by change in the constitution of the Bank or the firm of
Contractors / Suppliers or by any other reason whatsoever and our liability hereunder shall not
be impaired or discharged by any extension of time or variations or alterations made, given
conceded or agreed, with or without our knowledge or consent, by or between parties to the said
within written contract.
Notwithstanding anything contrary contained in any law for the time being in force or banking
practice this Guarantee shall not be assignable, transferable by the beneficiary (i.e. GSECL or
Subsidiaries). Notice or invocation by any person such as assignee, transferee or agent of
beneficiary shall not be entertained by the Bank. Any invocation of the Guarantee can be made
only by the beneficiary directly
“NOT WITHSTANDING” anything contained herein before, our liability under this guarantee is
restricted to Rs._______________ (Rupees
_______________________________________________________ only). Our guarantee shall
remain in force until _______________ (date of validity of the Guarantee). [Unless demands or
claims under this Bank Guarantee are made to us in writing on or before _____________ (date
of validity of the Guarantee), all rights of Beneficiary under this Bank Guarantee shall be forfeited
and we shall be released and discharged from all liabilities there under]:
Please Mention here Complete Postal Signature of
Address of the Bank with Branch Code, Bank‟s Authorized Signatory
Telephone and Fax Nos. with Official Round Seal
EW- 278 PUR-F-006 RFQ-
NAME OF DESIGNATED BANKS: (Annexure – I.)
A Guarantees issued by following banks will be accepted as SD/EMD on
permanent basis.
1. All Nationalized Banks.
B Guarantees issued by following Banks will be accepted as SD/EMD for
period up to March 31, 2026. The validity cut-off date in the GR is with
respect to date of issue of Bank Guarantee irrespective of date of
termination of Bank Guarantee.
1. AXIS Bank
2. A U Small Finance Bank
3. Bandhan Bank
4. Barclays Bank
5. City Union Bank
6. CSB Bank
7. DBS Bank India Limited
8. DCB Bank
9. Equitas Small Finance Bank
10. ESAF Small Finance Bank
11. Federal Bank
12. HDFC Bank
13. HSBC Bank
14. ICICI Bank
15. IDBI Bank
16. IDFC First Bank
17. Jammu and Kashmir Bank
18. Jana Small Finance Bank
19. Karnataka Bank
20. Karur Vysya Bank
21. Kotak Mahindra Bank
22. South Indian Bank
23. Standard Chartered Bank
24. Tamilnadu Mercantile Bank
25. Utkarsh Small Finance Bank
26. Yes Bank
27. Ahmedabad Mercantile Co-Operative Bank
28. Nutan Nagrik Sahakari Bank Ltd.
29. Rajkot Nagrik Sahakari Bank Limited.
30. Sarswat Co-Operative Bank Ltd.
31. SBPP Co-operative Bank LTD
32. SVC Co-Operative Bank Ltd.
33. The Cosmos Co-op Bank Ltd.
34. The Gujarat State Co-Operative Bank
35. The Mehsana Urban Co-Operative Bank Ltd.
36. The Surat District Co-operative Bank
37. The Surat Peoples Co-operative Bank Ltd.
38. The Kalupur Commercial Co-operative Bank
39. The Panchmahal District Co-operative Bank
40. The Baroda District Co-operative Bank
41. Baroda Gujarat Gramin Bank
42. Saurashtra Gramin Bank
EW- 278 PUR-F-006 RFQ-
EMD BANK GUARANTEE FORMAT
FOR TENDER /ENQ. NO. ___________________________________
(BANK GUARANTEE ON NON-JUDICIAL STAMP PAPER OF Rs.300)
WHERE AS M/s. _______________________________________________________________
(Name and Address of the Firm) having their registered Office at
_________________________________________________(Address of the Firm‟s registered
Office) (hereinafter called the Tenderer) wish to participate in the Tender
No.__________________________ for______________________________________ of (supply
/ Erection / Supply & Erection / Work) of __________________________________ (Name of the
material / equipment / work) for _________________________ Gujarat State Electricity
Corporation Limited and WHEREAS a Bank Guarantee for (hereinafter called the “Beneficiary”)
Rs. _____________ (Amount of EMD) valid till ____________ (mention here date of validity of
this Guarantee which will be 4 (FOUR) months beyond initial validity of Tender‟s offer) which is
required to be submitted by the Tenderer along with the Tender.
(Name of the Bank and address of the Branch giving the Bank Guarantee) having our registered
Office at _____________________ (Address of Bank‟s registered Office) hereby give this Bank
Guarantee No. _________________dated ____________ and hereby agree unequivocally and
unconditionally to pay immediately on demand in writing from the Gujarat State Electricity
Corporation Limited or any Officer authorized by it in this behalf any amount not exceeding
Rs.____________ (amount of EMD) (Rupees
______________________________________________________) (in words) to the said
Gujarat State Electricity Corporation Limited on behalf of the Tenderer.
We, ____________________________________________ (Name of the Bank) also agree that
withdrawal of the tender or part thereof by the Tenderer within its validity or non-submission of
Security Deposit by the Tenderer within one month from the date of tender or a part thereof has
been accepted by the Gujarat State Electricity Corporation Limited would constitute a default on
the part of the Tenderer and that this Bank Guarantee is liable to be invoked and encased within
its validity by the Beneficiary in case of any occurrence of a default on the part of the Tenderer
and that the encased amount is liable to be forfeited by the Beneficiary.
This agreement shall be valid and binding on this Bank up to and inclusive
of____________________ (mention here the date of validity of Bank Guarantee) and shall not
be terminated by notice or by Guarantor change in the constitution of the Bank or the Firm of
EW- 278 PUR-F-006 RFQ-
Tenderer or by any reason whatsoever and our liability hereunder shall not be impaired or
discharged by any extension of time or variations or alterations made, given, conceded with or
without our knowledge or consent by or between the Tenderer and the Gujarat State Electricity
Corporation Limited.
Notwithstanding anything contrary contained in any law for the time being in force or banking
practice this Guarantee shall not be assignable, transferable by the beneficiary (i.e. GSECL or
Subsidiaries). Notice or invocation by any person such as assignee, transferee or agent of
beneficiary shall not be entertained by the Bank. Any invocation of the Guarantee can be made
only by the beneficiary directly.
NOTWITHSTANDING anything contained hereinbefore our liability under this Guarantee is
restricted to Rs. ________ (amount of EMD) (Rupees
________________________________________ (in words). Our Guarantee shall remain in
force till _____________ (date of validity of the Guarantee). Unless demands or claims under
this Bank Guarantee are made to us in writing on or before ___________ (date of validity of the
Guarantee), all rights of Beneficiary under this Bank Guarantee shall be forfeited and we shall be
released and discharged from all liabilities there under.
Please mention here complete Postal Signature of the
Address of the Bank with Branch Code, Bank‟s authorized
Telephone and Fax Nos. Signatory with Official Seal.
EW- 278 PUR-F-006 RFQ-
GUJARAT STATE ELECTRICITY CORPORATION LIMITED- GTPS
INTEGRITY PACT
OUR ENDEAVOUR
To create an environment where Business Confidence is built through Best Business Practices
and is fostered in an atmosphere of trust and respect between providers of goods and services
and their users for the ultimate benefit of society and the nation.
GSECL’S COMMITMENT PARTY’S COMMITMENT
To maintain the highest ethical Not to bring pressure recommendations
standards in business and professions. from outside GSECL to influence its
decision..
Ensure maximum transparency to the Not to use intimidation, threat, inducement
satisfaction of stakeholders. or pressure of any kind on GSECL OR ANY
OF it‟s employees under any circumstances.
To ensure to fulfill the terms of To be prompt and reasonable in fulfilling
agreement/contract and to consider the contract, agreement, legal obligations.
objectively the view point.
To ensure regular and timely release of To provide goods and / or services timely
payments on due dates for work done. as per agreed quality and specifications at
minimum cost to GSECL.
To ensure that no improper demand is To abide by the general discipline to be
made by employees or by anyone on maintained in our dealings.
our behalf.
To give maximum possible assistance to To be true and honest in furnishing
all the Vendors/Suppliers/Service information.
Provider and other to enable them to
complete the contract in time
To provide all information to Not to divulge any information, business
suppliers/contractors relating to details available during the course of
contract / job which facilitate him to business relationship to others without the
complete the contract / job successfully written consent to GSECL.
To ensure minimum hurdles to vendors Not to enter into carter / syndicate
/ suppliers / contractors in completion /understanding whether formal / non
of agreement / contract / work order. formal so as to influence the price.
Seal & Signature Seal & Signature
(GSECL‟s Authorized Signatory) (Party‟s Authorized Person)
Name : Name:
Designation:
Name : Name:
Designation:
EW- 278 PUR-F-006 RFQ-
On Firm’s Letter Head
CERTIFICATE - A
I / We ________________________________________________ authorized signatory of
M/s._________________________________________________here by Certify that
M/s. _____________________________________________ is not related with other firms who
have submitted tenders for the same items under this inquiry / Tender.
Signature of the Tenderer
With Designation
Seal of the Firm
EW- 278 PUR-F-006 RFQ-
SPECIAL CONDITIONS FOR USE OF CEMENT
APPROVED NAME OF MANUFACTURERS OF
STEEL / CEMENT
GENERAL GUIDELINES RELEVANT TO I.S.
EW- 278 PUR-F-006 RFQ-
SPECIAL CONDITIONS FOR USE OF CEMENT IN WORK
1 The rates in Schedule – ‘B’ is inclusive of cement cost. Contractor has to purchase fresh
grade cement confirming to as per IS 8112 Or PPC IS 1489 (Part-I) or as per tender
condition.
2 Contractor has to construct pucca Go down at site of work so that cement bags can be
properly preserved to avoid damage due to any kind of water/Humidity.
3 Contractor has to bring sufficient quantities of cement bags to maintain progress of work.
The work should not suffer for want of cement.
4 Cement should be used to achieve required strength in cement concrete or as per item
proportion.
5 To bring sufficient & timely cement at site is full responsibility of contractor. Nothing extra will
be paid on account of any reason to maintain progress of work and to complete the work in
schedule time.
6 Contractor has to submit material A/c. For consumption of cement used with every bills. In
case of not submitting the same, bill will not be passed. Party has to submit the copy of
cement purchased bill and Challan/invoice along with each RA Bill/Final Bill.
7 No negative variation will be allowed for consumption in cement less then prescribed as per
R & B SoR OR Corporation/mix design and nothing will be paid extra for over consumption.
8 Contractor is fully responsible for safety of cement at site; nothing will be paid extra on
account of safety.
9 If Corporation’s authorized representative wants to check cement stock at site, contractor has
to allow for the same at any time.
10 Contractor has to maintain day to day cement consumption / balance account at site.
11 As far as possible, contractor has to maintain supply of cement of only one brand & grade
throughout the work and on account of closer/shortage of approved brand, cement of other
brand in accordance of condition No. (1) Will be allowed by Engineer – in – Charge.
12 Minimum cement consumption considered for cement concrete having grade of M–15 / M –
20 / M – 25 / is 290 Kgs. / 360 Kgs / 380 Kgs. Respectively as per R&B SOR. Contractor has
to use minimum cement as above. Contractor should not use less than the prescribed
quantities of cement even in the case of mix design recommends lower quality. For other
items cement consumption shall be as per provisions of SoR without any negative variation.
Nothing will be paid extra for over consumption.
13 Contractor will be allowed to carry out work only after physical verification of cement brought
14 Full cement bags brought by contractor shall be entered at IN GATE of GANDHINAGAR,
EW- 278 PUR-F-006 RFQ-
The list of adopting cement and steel of companies / suppliers /
manufacturers are shown below:
EW- 278 PUR-F-006 RFQ-
(Signature of Contractor)
Address &Seal: Chief Engineer (Gen)
GSECL, GTPS
EW- 278 PUR-F-006 RFQ-
GENERAL GUIDELINES RELEVANT TO IS
Please refer latest edition of relevant Indian Standard Specification of Code i.e.
B.I.S. General relevant I.S. of B.I.S. shall prevail for all items including materials,
measurements etc.
The Item wise detailed specifications are intended for full description of items
covered by Schedule “B”. The specifications are not however intended to cover
every detail and the works shall be executed according to the spirit of the
specifications below and the best prevailing P.W.D. practice. The clarification to any
clause in detailed specifications shall be sought from the latest edition of relevant
I.S. specification and codes. Where these specifications are at variance with the
specification laid down in the I.S. Books stated above, the former will be applicable.
As regarded matters not covered by any of the above specification, the decision of
the Engineer-in-charge shall be treated as final and shall be binding upon the
contractor. The contractor is expected to get clarified any doubt about specification,
etc. before tendering by discussing with Engineer-in-charge.
For detail technical specification, the item wise description along with above general
specifications shall hold good.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 278 PUR-F-006 RFQ-
GENERAL SPECIFICATIONS
TECHNICAL SPECIFICATION
EW- 278 PUR-F-006 RFQ-
GENERAL SPECIFICATIONS
01. In the specifications, “as directed”/”Approved” shall be taken to mean “as
directed”/”approved” by the Engineer-in-charge.
02. Wherever a reference to any Indian Standard appears in the specifications, it shall be
taken to mean as a reference to the latest edition of the same in force on the date of
agreement.
03. In “Mode of Measurement” in the specification wherever a dispute arises in the absence
of specific mention of a particular point or aspect, the provisions on these particular
points or aspects in the relevant Indian Standards shall be referred to.
04. All measurements and computations, unless otherwise specified, shall be carried out as
per Latest IS:
05. The distance which constitutes lead shall be determined along the shortest practical route
and not necessarily the route actually taken. The decision of the Engineer-in-charge in
this regard shall be taken as final.
06. Where no lead is specified, it shall mean “all leads”.
07. Lift shall be measured from plinth level.
08. Up to “floor two levels” means actual height of floor up to 6.5 Mt. Above plinth level.
09. Definite particulars covered in the items of work, though not mentioned or elucidated in
it, specification shall be deemed to be included therein.
10. Reference to specifications of materials as made in the detailed specification of the items
of work is in the form of a designation containing the number of the specification of the
material and prefix „M‟ e.g. „M-5‟.
11. Approval to the samples of various materials given by the Engineer-in-charge shall not
absolve the contractor from the responsibility of replacing defective material brought on
site or materials used in the work found defective at a later date. The contractor shall
have no claim to any payment or compensation whatsoever on account of any such
materials being rejected by the Engineer-in-charge.
12. The contract rate of the item of work shall be for the work completed in all respects.
13. No collection of materials shall be made before it is got approved from the Engineer-in-
14. Collection of approved materials shall be done at site of work in a systematic manner.
Materials shall be stored in such a manner as to prevent damage, deterioration or
intrusion of foreign matter and to ensure the preservation of their quality and fitness for
15. Cement, reinforcements bars & all other materials to be used shall be got approved from
EIC before starting of work. The cement, reinforcement steel & other materials to be
brought at site shall be entered at GANDHINAGAR, TPS main entry gate.
16. Materials, if and when rejected by the Engineer-in-charge, shall be immediately removed
from the site of work.
17. No materials shall be stored prior to, during and after execution of a structure in such a
way as to cause or lead to damage or overloading of the various components of the
structure.
18. All works shall be carried out in a workmanlike manner as per the best techniques for the
particular item.
19. All tools, templates, machinery and equipment for correct execution of the work as well
as for checking lines, levels, alignment of the works during execution shall be kept in
sufficient numbers and in good working condition on the site of the work.
20. The mode, procedure and manner of execution shall be such that it does not cause
damage or over loading of the various components of the structure during execution or
after completion of the structure.
21. Special modes of construction not adopted in general Engineering practice, if proposed to
be adopted by the Contractor, shall be considered only if the contractor provides
satisfactory evidence that such special mode of construction is safe, sound and helps in
speedy construction and completion of work to the required strength and quality.
Acceptance of the same by the Engineer-in-charge shall not, however, absolve the
EW- 278 PUR-F-006 RFQ-
contractor of the responsibility of any adverse effects and consequences of adopting the
same in the course of execution of completion of the work.
22. All installations pertaining to water supply and fixtures thereof as well as drainage lines
and sanitary fittings shall be deemed to be completed only after giving satisfactory tests
by the Contractor.
23. The contractor shall be responsible for observing the rules and regulations imposed under
„Minor Minerals Act‟ and such other laws and rules prescribed by Government from time
24. All necessary safety measures and precaution [including those laid down in the various
relevant Indian Standards shall be taken to ensure the safety of men, materials and
machinery on the works as also of the work itself.
25. The testing charge of all materials shall be borne by the Contractor unless recovery at
one percent towards using charges is separately made.
26. Approval to any of the executed items for the work does not in any way relieves the
contractor of his responsibility for the correctness, soundness and strength of the
structure as the drawings and specification.
For & On behalf of GSECL
CHIEF ENGINEER (Gen)
GSECL: GTPS
SIGNATURE OF CONTRACTOR
EW- 278 PUR-F-006 RFQ-
SPECIFICATIONS OF MATERIALS
M-1. Water:
1.1 Water shall not be salty or brackish and shall be clean, reasonably clear and free from
objectionable quantities of silt and traces of oil and injurious alkalies, salts, organic matter
and other deleterious material which will either weaken the mortar or concrete or cause
efflorescence or attack the steel in R.C.C Container for transport, storage and handling of
water shall be clean. Water shall conform to the standards specified I.S 456-1978.
1.2 If required by Engineer-in-charge it shall be tested by comparison with distilled water.
Comparison shall be made by means of standard cement tests for soundness, time of setting
and mortar strength as specified in I.S.269-1976. Any indication of unsoundness, change in
time of setting by 30 minutes or more or decrease of more than 10 per cent in strength of
mortar prepared with water sample when compared with the results obtained with mortar
prepared with distilled water shall be sufficient cause for rejection of water under test.
1.3 Water for curing mortar, concrete or masonry should not be too acidic or too alkaline. It
shall be free of elements which significantly affect the hydration reaction or otherwise
interfere with the hardening of concrete during curing or those which produce objectionable
stains or other unsightly deposits on concrete or mortar surfaces.
1.4 Hard and bitter water shall not be used for curing.
1.5 Potable water will be generally found suitable for curing mortar or concrete.
M-3. Cement: Cement shall be fresh 43 grade ordinary Portland cement confirming to IS
8112 or PPC IS 1489 (Part-I) and as per special conditions for use of cement in section-D.
6.1 Sand shall be natural sand, clean, well graded, hard strong durable and gritty particle free
from injurious amounts of dust clay, kankar nodules, soft or flaky particles shale, alkali, salts
organic matter, loam, mica or other deleterious substance and shall be got approved from
the Engineer-in-charge. The sand shall not contain more that 8 percent of silt as determined
by field test. If necessary the sand shall be washed to make it clean.
6.2 Coarse Sand: The fineness modulus of coarse sand shall not be less than 2.5 and shall not
exceed 3.0.
The sieve analysis or coarse shall be as under:
I.S. Sieve Percentage by weight I.S. Sieve Percentage by weight
Designation Passing sieve Designation Passing sieve
4.75 mm. 100 600 Micron 30-100
2.36 mm. 90 to 100 300 Micron 5-70
1.18 mm. 70-100 150 Micron 0-50
6.3 Fine Sand : The fineness modulus shall not exceed 1.0. The sieve analysis of fine sand
shall be as under :
I.S. Sieve Percentage by weight I.S. Sieve Percentage by weight
Designation Passing through Designation Passing through
4.75 mm. 100 600 Micron 40-85
2.36 mm. 100 300 Micron 5-50
1.18 mm. 70-100 150 Micron 0-10
Stone Grit
Grit shall consist of crushed or broken stone and be hard strong, dense, durable, clean,
of proper gradation and free from skin or coating likely to prevent adhesion of mortar Grit
shall generally be cubical in shape and as far as possible flaky elongated pieces shall be
avoided. It shall generality comply with the provisions of I.S. 383-1970. Unless special
stone of particular quarries is mentioned, grit shall be obtained from the best black trap or
equivalent hard stone as approved by the Engineer-in-charge. The grit shall have no
deleterious reaction with cement.
EW- 278 PUR-F-006 RFQ-
The grit shall conform to the following gradation as per sieve analysis :
I.S SievePercentage byPassing I.S. Sieve Designation
Percentage by Weight
Designation weight Passing through
The crushing strength of grit will be such as to allow the concrete in which it is used to
built up the specified strength of concrete.
The necessary tests for grit-shall carried out as per the requirements of I.S. 2386 (Parts I to
VII) 1963, as per instructions of the Engineer-in-charge. The necessity of test will be decided
by the Engineer-in-charge.
M-11. Cement Mortar:
11.1 Water shall conform to specification M-1. Cement: Cement shall conform to
specification M-3.
Sand: Sand shall conform to M-6.
11.2 Proportion of Mix: Cement and sand shall be mixed to specified proportion, sand
being measured by measuring boxes. The proportion of cement will be by volume on the
basis of 50 Kg./Bag of cement being equal to 0.0342 Cu. m. The mortar may be hand mixed
or machine mixed as directed.
11.3 Preparation of Mortar: 11.3.1 In hand mixed mortar cement and sand in the
specified proportions shall be thoroughly mixed dry on a clean impervious platform by
turning over at least 3 times or more till a homogenous mixture of uniform color is obtained.
Mixing platform shall be so arranged that no deleterious extraneous material shall get mixed
with mortar or mortar shall flow out. While mixing, the water shall be gradually added and
thoroughly mixed to form a stiff plastic mass of uniform color so that each particle of sand
shall be completely covered with a film of wet cement. The water cement ratio shall be
adopted as directed.
i. The mortar so prepared shall be used within 30 minutes of adding water. Only such
quantity of mortar shall be prepared as can be used within 30 minutes.
M-12 Stone Coarse Aggregate for Nominal Mix Concrete:
12.1 Coarse aggregate shall be machine crushed stone of black trap or equivalent and be
hard, strong, dense, durable, clean and free from skin and coating likely to prevent proper
adhesion of mortar.
12.2 The aggregate shall generally be cubical in shape. Unless special stones of particular
quarries are mentioned aggregates shall be machine crushed from the best black trap or
equivalent hard stone as approved. Aggregate shall have no deleterious reaction with
cement. The size of the coarse aggregate for plain cement concrete and ordinary reinforced
cement concrete shall generally be as per the table given below, However in case of
reinforced cement concrete the maximum limit may be restricted to 6 mm. less than the
minimum lateral clear distance between bars or 6 mm. less than the cover, whichever is
I.S. Sieve Percentage passing for I.S. Sieve Percentage passing for
Designation single sized aggregates of Designation single sized aggregates of
nominal size Nominal size
EW- 278 PUR-F-006 RFQ-
Note: This percentage may be varied somewhat by Engineer-in-charge when considered
necessary for obtaining better density and strength of concrete.
12.3 The grading test shall be taken in the beginning and at the change of source of
materials. The necessary test indicated in I. S. 383-1970 and I.S. 456-1978 shall have to be
carried out to be carried out to ensure the acceptability. The aggregates shall be stored
separately and handled in such a manner as to prevent the intermixing of different
aggregates. If the aggregates are covered with dust, they shall be washed with water to make
them clean.
M-13 Black Trap or Equivalent Hard Stone Coarse:
13.1 Aggregate for Design mix Concrete: Coarse aggregate shall be of machine crushed stone
of black trap or equivalent hard stone and be hard strong dense, durable clean and free from
skin and coating likely to prevent proper adhesion of mortar.
13.2 The aggregates shall generally be cubical in shape. Unless special stones of particular
quarries are mentioned, aggregates shall be machine crushed from the best, black trap or
equivalent hard stones as approved. Aggregate shall have no deleterious reaction with
13.3 The necessary tests indicated in I.S. 383-1970 and I.S. 456-1978 shall have to be
carried out to ensure the acceptability of the material. If aggregate is covered with dust it
shall be washed with water to make it clean
M-15. Brick
15.1. The bricks shall be hand or machine molded and made from suitable soils and kiln-
burnt. They shall be free Iron crack and nodules of free lime. They shall have smooth
rectangular faces with sharp corners and shall be of uniform colour. The bricks shall be
molded with a frog of 100mm. X 40 mm. and 10mm. to 20 mm. deep on one of its flat sides.
The bricks shall not break when thrown oft the ground from a height of 600 mm.
15.2. The size of modular bricks shall be 190 mm. x 90 mm. x 90 mm.
15.3. The size of the conventional bricks shall be as under : (9” x 4 3/8 “ X2 3/4 “) 225 x
15.4. Only bricks of one standard size shall be used on one work. The following n-.rrances
shall be Permitted in the conventional size adopted in a particular work. Length + 1/8 “(3.0
mm.) Width :
±1/16” (1.50 mm,.) Height: ± 1/6” (1.50 mm.)
15.5. The crushing strength of the bricks shall not be less than 50 Kg./Sq.Cm. The average
water Absorption shall not be more than 20 percent by weight. Necessary tests for crushing
strength and water absorption etc. shall be carried. Out as per I.S. 3495 (Part-I to IV)
M-18. Mild Steel Bars
18.1 Mild steel bars reinforcement for R.C.C. work shall conform to I.S, 432 (Part-II)
and §hail be of tested quality. It shall also comply with relevant part of I.S. 456-
18.2 All the reinforcement shall be clean and free from dirt, paint, grease, mill scale or loose
or thick rust
at the time of placing.
18.3 For the purpose of payment, the bar shall be measured correct upto 100 mm. length
and weight payable worked out at the rate specified below :
1. .6 mm. 0,22 Kg./Rmt. 8 20 mm. 2.47 Kg./Rmt.
2. 8 mm. 0.39 Kg./Rmt. 9. 22. mm. 2.98 Kg./Rmt.
EW- 278 PUR-F-006 RFQ-
3. 10mm. 0.62 Kg./Rmt. 10. 25 mm. 3.85 Kg./Rmt.
4. 12 mm. 0.89 Kg./Rmt. 11. 28 mm. 4,83 Kg./Rmt.
5. 14 mm. 1.21 Kg./Rmt. 12. 32 mm. 6.3.1 Kg./Rmt.
6. 16mm. 1 .58 Kg./Rmt, 13. 36 mm. 7.99 Kg./Rmt.
7. 18 mm. 2.00 Kg./Rmt. 14. 40 mm. 9.86 Kg/Rmt.
M-19. High Yield Strength Steel Deformed Bars
19.1. High yield strength steel deformed bars be either cold twisted or hot/rolled, shall
conform to I.S. 1739-
1966 and I.S.1139-1966 respectively.
19.2. Other provision and requirements shall conform to specification No. M-18. for Mild
steel bars.
M-22 Structural Steel:
22.1 All structural steel shall conform to I. S. 226-1965. The steel shall be free from the
defects mentioned in I. S. 226-1975 and shall have a smooth finish. The materials shall be
free from loose mill scale, rust pits or other defects affecting the strength and durability.
Rivet bars shall conform to I. S. 1148-1973.
22.2 When the steel is supplied by the Contractor test certificates of the manufactures shall
be obtained according to I. S. 226-1975 and other relevant Indian Standards.
DETAILED TECHNICAL SPECIFICATIONS
NOTE: BOOKLET FOR “GENERAL TECHNICAL SPECIFICATIONS FOR BUILDING WORKS” OF R.
& B. DEPARTMENT, GOG, GUJARAT AND BOOKLET OF “GENERAL SPECIFICATION FOR CIVIL
WORKS” OF GSECL WILL BE AVAILABLE IN CIVIL OFFICE AT GANDHINAGAR TPS FOR
REFERNCE OF RELEVANT DETAIL SPECIFICATIONS OF ITEMS. SHALL BE CONSIDERED &
ADOPTED IN WORK.
Item No.1: Demolition of Brick work and stone masonry including stacking of
serviceable materials and disposal of unserviceable materials with all lead and lift. (ii)
In Cement Mortar.
1.0. Workmanship: The relevant specifications of item No. (3) shall be followed except
demolition of brick or stone masonry in cement mortar is to be done.
2.0. Mode of measurements & payment : The relevant specification of item No.3 shall be
followed. The unserviceable materials shall be stacked as directed by Engineer-in-charge
with all leads and lifts
The rate shall be for a unit of one cubic metre.
Item No.2: Demolition and disposal of unserviceable materials with all lead and lifts.
(i) Unreinforced cement concrete
1.0. Workmanship :
1.1. The demolition shall consist of demolition of one or more parts of the building as
specified or shown in the drawings. Demolition implies taking up or down or breaking up.
This shall consist of demolishing whole or part of work including all relevant item as
specified or shown in the drawings.
1.2. The demolition shall always be planned before hand and shall be done in reverse order
of the one in which the structure was constructed. This scheme shall be got approved from
the Engineer-in-charge before starting the work. This however will not absolve the
contractor from the responsibility of proper and safe demolition.
1.3. Necessary dropping, shoring and under pinning shall be provided for the safety of the
adjoining work or property, which is to be left intact, before dismantling and demolishing is
EW- 278 PUR-F-006 RFQ-
taken up and the work shall be carried out in such a way that no damages is caused to the
adjoining property.
1.4. Wherever required, temporary enclosures or partitions shall also be provided.
Necessary precautions shall be taken to keep the dust nuisance down as and where
necessary.
1.5. Dismantling shall be commenced in a systematic manner. All materials which are likely
to be damaged by dropping from a height or demolishing, masonry etc. Shall be carefully
dismantled first. The dismantled articles shall be properly stacked as directed.
1.6. All materials obtained from demolition shall be the property of Government unless
otherwise specified and shall be kept in safe custody until handed over to the Engineer-in-
1.7. Any serviceable material, obtained during dismantling or demolition shall be separated
out and stacked properly as directed, with all lead and loft. All unserviceable materials,
rubbish etc. Shall be stacked as directed by the Engineer-in-charge.
1.8. On completion of work, the site shall be cleared of all debris rubbish and cleaned as
Mode of measurements & payment:
Measurements of all work except hidden work shall be taken before demolition or no
allowance for increase in bulk shall be allowed. The demolition of lime concrete shall be
measured under this item. Specification for deduction for voids, openings etc. Shall be on
same basis as that employed for construction of work.
The unserviceable materials shall be disposed of at all leads and lifts. The rate excludes
scraping straightening of reinforcement but includes cutting of reinforcement.
The rate shall be for a unit of one cubic meter actual work done.
Item No.3: Demolition including stacking of serviceable materilas and disposal of
unserviceable materials with all lead and lift. (i) R.C.C. Work
1.0. Workmanship: The relevant specifications of item No.(2) shall be followed except that
demolition of R.C.C. work is to be done.
2.0. Mode of measurements & payment:
2.1. The relevant specification of item No.2 shall be followed except that the demolition of
reinforced concrete structure. The unserviceable materials shall be disposed of at all leads
and lifts. The rate excludes scraping straightening of reinforcement but includes cutting of
reinforcement.
2.7.1 2.2. The rate shall be for a unit of one cubic meter
Item No. 4: Excavation for foundation upto 1.5m depth including sorting out and
stacking of useful materials and disposing excavated stuff upto 500 mt. lead. (A) Loose
or soft soil.
1.0 General:
1.1 Any soil which generally yields to the application of pickaxes and shovels, phawaras,
rakes or any such ordinary excavating implement or organic soil, gravel, silt, sand turf loam,
clay, peat etc. Fall under this category.
2.0 Clearing the site:
2.1 The site on which the structure is to be built shall be cleared and all obstructions, loose
stone, materials and rubbish of all kind, bush, wood and trees shall be removed as directed.
The materials so obtained shall be properly of the Government and be conveyed and stacked
as directed within 50 M. Lead. The roots of the trees coming in the sides shall be cut and
Coated with a hot asphalt.
EW- 278 PUR-F-006 RFQ-
2.2 The rate of site clearance is deemed to be included in the rate of earth work for which no
extra will be paid.
3.0 Setting out :
After clearing the site, the centerlines will be given by the Engineer-in-charge. The
contractor shall assume full responsibility for alignment Elevation and dimension of each
and all parts of the work. Contractor shall supply laborers, materials, etc. Required for
setting out the Reference marks and bench marks and shall maintain them as long as
required and directed.
4.0 Excavation:
The excavation in foundation shall be carried out in true line and level and shall have the
width and depth as shown in the drawings or as directed. The contractor shall do the
necessary shoring and shutting or providing necessary slopes to a safe angle, at his own cost.
The payment for such precautionary measures shall be paid separately if not specified. The
bottom of the excavated area shall be leveled both longitudinally and transversely as
directed by removing and watering as required. No earth filling will be allowed for bringing
it to level, if by mistake or any other reason excavation is made deeper or wider that shown
on the plan or directed. The extra depth or width shall be made up with concrete of same
proportion as specified for the foundation concrete at the cost of the contractor. The
excavation up to 1.5m Depth shall be measured under this item.
5.0 Disposal of the excavated stuff:
leveling the ground in layers including ramming and watering etc. The balance of the
excavated quantity shall be removed by the contractor from the site of work to a place as
directed with lead up to 500 M and all lift.
Mode of measurement and payment:
The measurement of excavation in trenches for foundation shall be made according to the
sections of trenches shown on the drawing or as per sections given by the Engineer-in-
charge. No payment shall be made for surplus excavation made in excess of above
requirements or due to slopping back as found necessary on account of conditions of soil
and requirements of safety.
The rate shall be for a unit of one cubic meter.
Item No. 5: Brick work using common burnt clay building bricks having crushing
strength not less than 50 kg./Sq.Cm. in foundation and plinth in Cement Mortar 1:6 (1-
Cement : 6 -fine sand)(C) Fly Ash Bricks
1.0 Materials:
Water shall confirm to M-1, Cement shall confirm to M-3, Sand shall confirm to M-6,. Bricks
– M 15 .Admixture is confirm to the manufacture specification
2.0 Workmanship :
Fly ash bricks (cement bonded) shall be locally made. Bricks shall have smooth rectangular
faces with sharp and square corners. Bricks shall be hand or machine moulded and shall be
made from the admixture of suitable good quality of fly ash, sand and cement as per the
composition mentioned below:
FLY ASH: 50-60%
CEMENT: 8-12%
The fly ash bricks will be as per latest relevant IS code. The bricks will be of
dimension as per standard clay brick, suitable for making 230mm thick full brick wall,
115mm thick half brick wall and 75mm thick minor partition walls, as applicable, as per
drawing/specification/BOQ. A maximum tolerance of (+/-) 2mm shall be allowed as the
manufacturing tolerance. The bricks shall have frog of 100 mm in length 40 mm in width and
10 to 20 mm deep of one of its flat sides.
EW- 278 PUR-F-006 RFQ-
The bricks when tested in accordance with the procedure laid down in IS 3495 (part
2): 1992 after immersion in cold water for 24 hrs. water absorption shall be within 13-15%
by weight. Similarly, the porosity of the fly ash bricks shall be within 12-20%. The bricks
shall have a minimum crushing strength of 50 Kg/CmSq. Bricks shall be tested in a Govt.
Approved laboratory at the cost of contractor. Bricks shall be allowed to use after
satisfactory result. Mortar that can be utilized within initial setting time of the cement shall
be mixed with water. Mortar shall be prepared on pucca platform or on steel plate’s
platform. Mortar shall be uniformly mixed dry and then required quantity of water shall be
added. If work demands mixing or mortar in mixture, same shall have to be arranged
without any extra cost
All joints vertical and horizontal shall be properly racked out to a depth of 12mm
when mortar is green and soft. The exposed faces of walls are to be provided with flush joint.
Brickwork shall be cured with water for a period of 10 days, keeping constantly moist.
During rainy season green work shall have to be protected from rain, by covering it with
suitable covering.
Work shall be measured in volume any opening more than 0.5 sq. Meter areas shall be
deducted. No payment shall be made for keeping in masonry any pipe, and sleeves etc.,
supplied by department. Thickness of brickwork shall be paid as per standard practice half
brick, full brick, 1 ½ bricks etc. as shown on drawings.
2.1 Proportion:
2.1.1 The proportion of the cement mortar shall be 1: 6 (1 cement: 6 fine sand) by volume.
2.2 Wetting of bricks: The bricks required for masonry shall be thoroughly wetted with clean
water for about two hours before use or as directed. The cessation of bubbles, when the
bricks are wetted with water is an indication of through wetting of bricks.
2.3 Laying:
2.3.1 Bricks shall be laid in English bond unless directed otherwise. Half or cut bricks shall
not be used except where necessary to complete to bond closers in such case shall be cut to
required size and used near the ends of walls.
2.3.2 A layer of mortar shall be spread on full width for suitable length of the lower course,
each brick shall first be properly bedded and set home by gently tapping lapping with handle
of trowel or wooden mallet. It side face shall be flushed with mortar before the next brick is
laid and pressed against it. On completion of course, the vertical joints shall be fully filled
from the top with mortar.
2.3.3 The walls shall be taken up truly in plumb. All courses shall be laid truly horizontal
and all vertical joint shall be truly vertical. Vertical joints in alternate course shall generally
be directly one over the other. The thickness of brick course shall be kept uniform.
2.3.4 The brick shall be laid with frog upwards. A set of tools comprising of wooden
straight edges, mason’s sprit level, square half meter rub, and pins, string and plumb, shall
be kept on the site of work for frequent checking during the progress of work.
2.3.5 Both the faces of walls of thickness greater than 23 cms. Shall be kept in proper place.
All the connected brick work shall be kept not more than one meter over the rest of the
work. Where this is not possible the work shall be raked back according to bond (and not left
toothed) at an angle not steeper than 45 degrees.
2.3.6 All fixtures, pipes, outlets of water, hold fasts of doors and windows etc. Which are
required to be built in wall shall be embedded in cement mortar.
2.4 Joints:
2.4.1 Bricks shall be so laid that all joints are quite flush with mortar. Thickness of joints
shall not exceed 12 mm. The face joints shall be raked out as directed by taking tools daily
during the progress of work, when the mortar is still green so as to provide key for plaster or
pointing to done.
2.4.2 The face of brick shall be cleaned the very day on which the brick work is laid and all
mortar dropping removed.
2.5 Curing: Green work shall be protected from rain suitably. Masonry work shall be kept
EW- 278 PUR-F-006 RFQ-
moist on all the faces for a period of seven days. The top of masonry work shall be kept well
wetted at the close of the day.
2.6 Preparation of foundation bed: If the foundation is to be laid directly on the excavated
bed the bed shall be leveled, cleared of all loose materials, cleaned and wetted before
starting masonry. If masonry is to be laid on concrete footing the top of concrete shall be
cleaned and moistened. The contractor shall obtain the engineer’s approval for the
foundation bed, before foundation masonry is started. When puccas flooring is to be
provided flush with the top to plinth the inside plinth offset shall be kept lower than the
outside plinth top by the thickness of the flooring.
3.1 Mode of measurement and payment:-
Measurement shall be made per CMT of Brickwork at site.
Rate shall be for unit of one CMT of Brickwork at site
Item NO.6: Providing and laying cement concrete 1:3:6 (1 cement: 3 coarse sand:
hand broken stone aggregates 40mm nominal size ) & curing complete excluding cost
of form work in (A) foundation & plinth.
Materials:
1.1 Water shall conform to M-1. Cement shall conform to M-3. Sand shall conform to M-6.
Stone aggregate 40 mm. Nominal size shall conform to M-12.
Workmanship:
2.1 General: before starting concrete bed of foundation trenches shall be cleared of all loose
materials, leveled, watered and rammed as directed.
2.2 Proportion of Mix: The Proportion of cement, sand and coarse aggregate shall be 1 part
of cement, 4 parts of sand, 8 parts of stone aggregates and shall so measured by volume.
2.3 Mixing: The concrete shall be mixed in a mechanical mixer at the site of work. Hand
mixing may however be allowed for smaller quantity of work if approved by the Engineer-in-
charge. When hand mixing is permitted by the Engineer-in-charge in case of break-down of
machineries and in the interest of the work, it shall be carried out on a water tight platform
and care shall be taken to ensure that mixing is continued until the mass in uniform in color
and consistency. However in such cases 10% more cement than otherwise required shall
have to be used without any extra cost. The mixing in mechanical mixer shall be done for a
period 1 to 2 minutes. The quantity of water shall be sufficient to produce a dense concrete
of required workability for the purpose.
2.4 Transporting & placing the concrete:
2.4.1 The concrete shall be handled from the place of mixing to the final position in not
more than 15 minutes by the method as Directed and shall be placed into its final position,
compacted and finished within 30 minutes of mixing with water i.e. before the setting
commences. The concrete shall be laid in layers of 15 cms. to 20 cms.
2.5 Compacting:
2.5.1 The concrete shall be rammed with heavy iron rammers and rapidly to get the required
compaction and to allow all the interstices to be filled with mortar.
2.6 Curing: 2.6.1 after the final set, the concrete shall be kept continuously wet, if
required by pounding for a period of not less than 7 days from the date of placement.
2.7 Mode of measurement and payment:
The concrete shall be measured for its length, breadth and depth, limiting dimensions to
those specified on plans or directed.
The rate shall be for a unit of one cubic meter.
Item NO.7: Providing 15mm thick Cement plaster in single coat on fair side
brick/concrete walls for interior plastering upto floor two level in finished even and
smooth in (i) cement 1:3 (1 cement: 3 sand)
1.0. Materials : 1.1. Water M-1. The cement mortar proportion 1:3 shall conform to M-11.
EW- 278 PUR-F-006 RFQ-
2.0. Workmanship :
2.1. Scaffolding: Wooden bellies, bamboos, planks, treatles and other scaffolding shall be
sound. These shall be properly examined before erection and use. Stage scaffolding shall be
provided for ceiling plaster which shall be independent of the walls.
2.2. Preparation of back ground:
2.2.1.The surface shall be cleaned of all dust, loose mortar droppings, traces of algae,
efflorescence and other foreign matter by water or by brushing. Smooth surface shall be
roughened by wire brushing if it is not hard and by racking if it is hard. In case of concrete
surface, if a chemical retarder has been applied to the form work, the surface shall be
roughened by wire brushing and all the resulting dust and loose
particles cleaned off and care shall be taken that none of the retarders is left on the surface.
Trimming of projections on brick/concrete surface where necessary shall be carried out to
get an even surface.
2.2.2. Racking of joints in case of masonry where necessary shall be allowed to dry out for
sufficient period before carrying out the plaster work.
2.2.3. The work shall not be soaked but only damped evenly before applying the plaster. If
the surface becomes dry such area shall be moistened again.
2.2.4. For external plaster, the plastering operation shall be started from top floor and
carried downwards. For internal plaster, the plastering operations may be started whenever
the building frame and cladding work are ready and the temporary supporting ceiling
resting on the wall of the floor have been removed. Ceiling plaster shall be completed before
starting plaster to walls.
2.3. Applications of plaster :
2.3.1. The plaster about 15 x 15 cms. Shall be first applied horizontally and vertically at not
more than 2 metres intervals over the entire surface to serve as gauge. The surfaces of these
gauges shall be truly inplane of the finished plastered surface. The mortar shall then be
applied in uniform surface slightly more than the specified thickness, then brought to a true
surface by working a wooden straight edge reaching across the gauges with small upward
and sideways movement at a time. Finally, the surface shall be finished off true with a
trowel or wooden float according as a smooth or a sandy granular texture is required.
Excessive trowelling or overworking the float shall be avoided. All corners, arrises, angles
and junctions be truly vertical or horizontal as the case may be and shall be carefully
finished. Rounding or chamfering corners, arrises junctions etc. Shall be carried out with
proper templates to the size required.
2.3.2. Cement plaster shall be used within half an hour after addition of water. Any mortar
or plaster which is partially set shall be rejected and removed forthwith from the size.
2.3.3. In suspending the work at the end of the day, the plaster shall be left out clean to the
line both horizontally and vertically. When recommending the plaster, the edges of the old
work shall be scraped clean and wetted with cement putty before plaster is applied to the
adjacent areas to enable the two to properly join together. Plastering work shall be closed at
the end of the day on the body of the wall and nearer than 15 cm. To any corners or arrises.
Horizontal joints in plaster work shall not also occur on parapet tops and copings as these
invariably load to leakage. No portion of the surface shall be left out initially to be packed up
2.3.4. Each coat shall be kept damp continuously till the next coat is applied or for a
minimum period of 7 days. Moistening shall commence as soon as plaster is hardened
sufficiently. Soaking of walls shall be avoided and only as much water as can be readily
absorbed shall be used, excessive evaporation on the sunny or windward side of building in
hot air or dry weather shall be prevented by handing mattings or gunny bags on the outside
of the plaster and keeping them wet.
3.0. Mode of measurements & payment :
3.1. The rate shall include the cost of all materials, labour and scaffolding etc. Involved in the
operations described under workmanship.
EW- 278 PUR-F-006 RFQ-
3.2. All plastering shall be measured in square meters unless, otherwise specified, Length,
breath or height shall be measured correct to a centimeter.
3.3. Thickness of the plaster shall be exclusive of the thickness of the key i.e. Grooves or open
joints in brick work, stone work etc. Or space between laths. Thickness of plaster shall be
average thickness with minimum 10 mm. At any point on this surface.
3.4. This item includes plastering upto floor two level.
3.5.The measurement of wall plastering shall be taken between the walls or partition
(dimensions before plastering being taken) for length and from the top of floor or skirting to
ceiling for height. Depth of cover of cornices if any shall be deducted.
3.6. Soffits of stairs shall be measured as plastering on ceilings. Flowing soffits shall be
measured separately.
3.7. For jambs, soffits, sills etc. For openings not exceeding 0.5 sq.mt. Each in area for ends of
joints, beams, posts, girders, steps, etc. Not exceeding 0.5 sq. Mt. Each in area and for
openings exceeding 0.5 sq. Mt. And not exceeding 3.00 sq. Mt. In each area deductions and
additions shall be made in the following manner :
(a) No deductions shall be made for ends of joints, beams, posts etc. And openings not
exceeding 0.5 sq.mt. Each and no addition shall be made for reveals, jambs, soffits, sills etc.
Of these opening for finish to plaster around ends of joints, beams, posts etc.
(b) Deduction for openings exceeding 0.5 sq.mt. But not exceeding 3 sq.mt. Each shall be
made as follows and no addition shall be made for reveals, jambs, soffits, sills etc. Of these
(i) When both faces of all wall are plastered with same plaster, deduction shall be made for
one face only.
(ii) When two faces of wall are plastered with different types of plaster or if one faces is
plastered and the other pointed, deductions shall be made from the plaster or pointing on
the side of frame for door, window etc. On which width of reveals is less than that on the
other side but no deductions shall be made on the outer side. Where width of reveals on
both faces of all are equal, deductions of 50% of area of opening on each face shall be made
from area of plaster and/or pointing as the case may be.
3.8. For openings having door frames equal to projecting beyond the thickness of wall, full
deduction for opening shall be made from each plastered face of the wall.
3.9. In case of openings of area above 3 sq.mt. Each, deduction shall be made for opening but
jambs, soffits and sills shall be measured.
3.10. The rate shall be for unit of one sq. Meter
Item No. 8: Supplying and fixing reinforced concrete heavy duty non-pressure pipes with
collars for culverts carrying heavy traffic as per IS 458- 1991 specifications including
setting the pipes in C.M. 1:2 watering and laying (to level or slopes) of class NP3 of
following internal daimeters.(iii) 600mm dia.
Materials: 1.1 The reinforced concrete heavy duty non-pressure pipes of specified diameter
shall conform to I.S. 458-1991.
1.0 Workmanship: 2.1 The relevant specifications for excavation is as per above item of
excavation shall be followed for work of trenches except that the excavation in trenches
shall be for reinforced concrete pipes of specified diameter.
2.2 Laying:
2.2.1 The pipes shall be lowered into the trenches carefully. Mechanical appliances may be
used. Where necessary pipe shall be laid in straight lines or with easy curves and true to line
and gradient as specified. The laying of pipe shall precede upgrade of a slope. In the pipe
with loose collars, the collars shall be slipped on before the next pipe is laid. The work is to
be carried out on main road of power house. Hence only seven days will be given for
crossing this main road. Penalty will be imposed if road crossing work is not completed
EW- 278 PUR-F-006 RFQ-
within seven days.
2.2.2 In case where the foundation conditions are unusual such as the proximity of troes
holes, under existing or proposed around in 150 mm. Thick cement concrete 1 : 5 : 10(1
cement : 5 fine sand : 10 graded stone aggregate 40 mm. Nominal size) or compacted sand or
2.2.3 In case where the natural foundation is inadequate the pipe shall be laid either in
concrete cradle, supported on proper foundation or on any other suitably designed
structure. If concrete bedding is used the depth of concrete below bottom of the pipe shall be
at least ¼th of the internal diameter of the pipe subject to a minimum of 100 mm. And
maximum 300 mm. The concrete shall be extended upto the sides of the pipe at least a
distance of ¼the of the outsided diameter for pipes and over in diameter.
2.2.4 The pipes shall be laid in the concrete bedding before the concrete has set. Pipes laid
in trenched in earth shall be bedded evenly and firmly and as far as upto the naunches of the
pipe as to safely transmit the load expected from the back fill through the pipe to the bed.
This shall be done either by excavating the bottom of the trenches to fit the curve of the pipe
or by compacting the earth under round curve of the pipe to form an even bed. Necessary
provision shall be made for joints wherever required.
2.3 Jointing: 2.3.1 The joints shall be done by slipping the collar over and clear of the end
of the pipe. The recess of the end of the pipe shall be filled with jute threading dipped in hot
bitumen. The new pipe shall then be brought forwarded until the bitumen ring in recess of
first pipe is set into the recess of the second pipe. This process shall be repeatred for two or
three pipes such shall then be jacked up so as to thoroughly compress the bitumen. The
quantity of jute and bitumen shall be just enough to fill the recess when pressed hard by
jacking, care being taken that no offset of the jute brading shall be visible either outside or
inside of pipe. The collar shall then be set up over the joints covering equally both the pipe
and leaving an even caulking space all round Cement and sand mortar 1 : 1½ shall then be
well punched or pressed home with a caulking tool within this caulking space. Care shall be
taken that the underside of the joints is properly filled with mortar.
2.4 Curing:
2.4.1 Every joint shall be kept wet for about 10 days for maturing the section of the pipe
line laid and jointed shall be covered immediately to protect from weather effects. Minimum
bore of 100 mm. Is considered adequate.
2.4.1 The joints shall be left exposed for observation.
2.0 Mode of measurements & payment :
3.1 The rate includes for laying (to level or slope in trenches etc. Measured separately)
making the joints as indicate and testing to stand the water test.
3.2 The measurements shall be net without any allowance for cutting and waste. The
length of bends, junctions and other connections (measured along the center line) shall be
including in the total length of the pipes the connections being numbered afterwards and
paid for extra over pipes.
3.3 The size of bends, junctions etc. Shall suit the size of pipe. The bore (internal diameter
of pipe) shall be the criterion for payment.
3.4 Nothing extra shall be paid separately for the use of mechanical appliances, where
necessary as described above.
The rate shall be for a unit of one running meter
Item No: 9 Providing and laying controlled cement concrete M.200 and curing complete
excluding the cost of formwork and reinforcement for reinforced concrete work in (A)
Foundations, footings, Base of columns and Mass concrete
EW- 278 PUR-F-006 RFQ-
1.0 Materials : Water shall conform to M-1 Cement shall conform to M-3 Sand shall
conform to M-6. Grit shall conform to M-8. Coarse aggregate shall conform M-12 B.
2.0 General :
2.1 The relevant specifications of item No. 5.4.1 of ordinary concrete shall be followed
except that the concrete mix shall be designed from preliminary tests, the proportioning
of cement and aggregates shall be done by weight and necessary precautions shall be
taken in the production to ensure that the required work cube strength is attained and
maintained. The controlled concrete shall be in grades of M-100, M-150, M-200, M-250,
M-300, M-350 & M-400 with prefix controlled added to it. The letter ‘M’ refers to mix and
numbers specify 28 days works cube compressive strength of 150 mm. Cubes of the mix
expressed in Kg./Cmt.
2.2 The proportion of cement sand and coarse aggregates shall be determined by weight
the weight the weight batch machine shall be used for maintaining proper control over
the proportion of aggregates as per mix design.
The strength requirements of different grades of concrete shall be as under :
Grade of Concrete Compressive strength Cubes in Kg./Cmt. At
of 15 cms. 28 days with I. S. 516-1959.
conducted in Min.
accordance Preliminary
test Work test Min.
In all cases the 28 days compressive strength specified in above table the criteria for
acceptance or rejection of the concrete. Where the strength of a concrete mix as indicated
by tests, line in between the strength of any two grades specified in the above table, such
concrete shall be classified in for all purpose as concrete belonging to the lower of the two
grades between which its strength lies.
Workmanship :
2.3 The proportions for ingredients chosen shall be such that concrete has adequate
workability for conditions prevailing on the work in question and can be properly
compacted with means available except where it can be shown to the satisfaction of the
Engineer-in-charge that the supply of properly graded aggregate of uniform quality can be
maintained till the completion of work. Grading of aggregate shall be controlled by
obtaining the coarse aggregates in different sizes and benignity hem in the right
proportions as required. Aggregate of different sizes shall be stocked in separate
stockpiles. The required quantity of material shall be stock piled several hours, preferably
a day before use. The grading of coarse and fine aggregate shall be checked as frequently
as possible the frequency for a given job being determined by the Engineer-in-charge to
ensure that the suppliers are maintaining the uniform grading as approved for samples
used in the preliminary tests.
2.4 In proportioning concrete the quantity of both cement and aggregate shall be
EW- 278 PUR-F-006 RFQ-
determined by weight. Where the weight of cement is determined by accepting the
maker’s weight per bag a reasonable number of bags shall be weighted separately to
check the net weight. Where cement is weighted from bulk stocks at site and not by bags
it shall be weighted separately from the aggregates. Water shall either be measured by
volume in calibrated tanks or weighed. All measuring equipments shall be maintained in
clean and serviceable condition. Their accuracy shall be periodically checked.
2.1 It is most important to keep the specified water cement ratio constant and at its
correct value. To this end moisture content in both fine and coarse aggregates shall be
determined by the Engineer-in-charge according to the weather conditions the amount of
mixing water shall then be adjusted to compensate for variations in the moisture content.
For the determination of moisture content in the aggregates I. S. 2389 (Part-III) shall be
referred to suitable adjustments shall also be made in the weights of aggregates due to
variation in their moisture content. Minimum quantity of cement to be used in concrete
shall not be less than 220 Kg./M3 in plain concrete and not less than 250 Kg./M3 in
reinforced concrete.
3.0 Mode of measurement and payment :
3.1 The relevant specifications item No. 5.4.1 (from detailed specification of GOG SOR )
shall be followed except that the controller concrete R.C.C. work for work as specified in
item shall be measured under this item. The rate excludes cost of form work.
The rate shall be for a unit of one cubic meter
Item No. 10: Providing TMT Bar FE 415 reinforcement for R.C.C. work including
bending, binding and placing in position complete upto floor two level
1.0 Materials : 1.1 Mild steel bars shall conform to M-18 mild steel binding wires shall
conform to M-21.
All reinforcement TMT bar specified in item shall conform to relevant IS standard 1786 for
thermo mechanical Tested bars, wherever tested brands to be used, certificate for the same
from manufacture shall be submitted. If Executive Engineer instructs it, contractor shall have
to arrange for testing of bars at the laboratory or institution, suggested by GSECL at his cost.
Bars shall be bent as per bar bending schedule supplied with drawing. If bar bending schedule
is not supplied contractor shall prepare it and get it approved at the site before cutting for
fabrication. Bars shall be clean, free form rust, dust, mud etc. if coils are there, they shall be
first straightened. Bars shall be cut according to the cutting length specified/approved by
department. Bars shall be bent gradually. Bars having crack or spits shall be rejected. Bars
shall be bent cold, unless otherwise specified in case of higher diameter bars. If bar is bended
wrongly, it should be straightened and reset such that it does not injure the materials.
Laps and splices shall be got approved. They shall be staggered and shall be at location shown/
approved. Lapping shall be avoided when full-length bars are available. All laps, hooks, bends
etc. shall be provided as per IS standards. Reinforcement bars shall be place in position as per
drawing or details given. It shall be tied with annealed black wire/G.I. wire of 18 gauges.
Blocks, spacers, chairs etc., shall be provided as per IS. 2502 at places instructed.
Bars shall be provided with clear cover as shown in drawing or as instructed on site. Cover
shall be provided with cement mortar cover block prepared of specified thickness with
binding wire embedded to fix cover in position and tie with the reinforcement so that it may
not get disturbed. Minimum clear cover shall be less than 13 mm or diameter of bars for slabs.
For beam and columns depending on size it shall be 20mm to 25mm. Cover shall be provided
depending on structure, weather condition, location of structure etc., as per ISI.
After the reinforcement is tied and checked by contractor himself it shall be got checked by
GSECL authorized representative and Okayed for pouring of concrete. Quantity of
reinforcement bars in M.T. embedded in concrete shall be paid. Weight shall be computed on
cutting length approved or given multiplied by standard weight of particular diameter of bars
EW- 278 PUR-F-006 RFQ-
as per IS standards. Work shall to be carried out at all levels. “Rate quoted shall inclusive of
wastages, cost of binding wire, etc., No separate payment will be made for binding wire.
However laps, dowels etc., shall be paid as per drawing or as approved in site.
For the purpose of payment, the bar shall be measured correct up to 100 mm length and
weight payable worked out at the rate specified below:
1 6 mm = 0.22 Kg / Rmt. 8 20mm = 2.47 Kg / Rmt.
2 8 mm = 0.39 Kg / Rmt. 9 22mm =2.98 Kg / Rmt.
3 10 mm = 0.62 Kg / Rmt. 10 25mm = 3.85 Kg / Rmt.
4 12 mm = 0.89 Kg / Rmt. 11 28mm = 4.83 Kg / Rmt.
5 14mm = 1.21 Kg / Rmt. 12 32mm = 6.31 Kg / Rmt.
6 16 mm = 1.58 Kg / Rmt. 13 36mm = 7.99 Kg / Rmt.
7 18 mm = 2.00 Kg / Rmt. 14 40mm = 9.86 Kg / Rmt.
Mode of measurement and payment :
The rate shall be for a unit of one Kg actual work done
Item No. 11: Providing formwork of ordinary timber planking so as to give a rough
finish including centering shuttering strutting and propping etc. Height of propping and
centering below supporting floor to ceiling not exceeding 4 M. and removal of the same
for in situ reinforced concrete and plain concrete work in. (A) Foundations Footings
Bases of Columns etc. and Mass concrete.
1.0 Materials :
1.1 The shuttering to be provided shall be of ordinary timber planks and shall conform to
1.2 The dimensions of scantlings and battens shall conform to the design. The strength of
the wood shall not be less than that assumed in the design.
2.0 Workmanship :
2.1 The form work shall conform to the shape lines and dimensions as shown on the plans and
be so constructed as to remain sufficiently rigid during the placing and compacting of the
concrete. Adequate arrangements shall be made by the contractor to safe-guard against any
settlement of the form work during the course of concreting and after concreting. The form
work of shuttering, centering, scaffolding bracing etc. Shall be as per design.
2.2 Cleaning & Treatment of forms : 2.2.1 All rubbish, particularly chippings shaving and
saw dust shall be removed from the interior of the form before the concrete is placed and the
form work in contact with concrete shall be cleaned and thoroughly wetted or treated. The
surface shall be then coated with soap solution applied before concreting is done. Soap
solution for the purpose shall be prepared by dissolving yellow soap in water to get
consistency of paint. Alternatively a coat of raw linseed oil or form oil of approved
manufacture may be applied in case steel shuttering us used. Soap solution or raw linseed oil
shall be applied after thoroughly cleaning the surface. Care shall be taken that the coating does
not get on construction joints surface and reinforcement bars.
2.3 Stripping time : 2.3.1 In normal circumstance and where ordinary cement is used
forms may be struck after expiry of following periods :
(a) Sites of walls columns and vertical faces of beam 24 to 48 hours.
(b) Beam soffits. (Props left under) – 7 days.
(c) Removal of props slabs.
(i) Slabs spanning upto 4.5 m. – 7 days (ii) Spanning over 4.5 mm. – 14 days.
(d) Removal of props to beams and Arches.
(i) Spanning upto 6 m. – 14 days. (ii) Spanning over 6 m. – 21 days.
2.4 Procedure when removing the form work : 2.4.1 All form work shall be removed
without such shock or vibrations as would damage the reinforced concrete surface. Before the
soffit formwork and struts are removed the soffits and the concrete surface shall be exposed
EW- 278 PUR-F-006 RFQ-
where necessary in order to ascertain that the concrete has sufficiently hardened.
2.5 Centering :
2.5.1 The centering to be provided shall be got approved. It shall be sufficiently strong to
ensure absolute safely of the formwork and concrete work before during and after pouring
concrete. Watch should be kept to see that behavior of centering and formwork is satisfactory
during concreting. Erection should also be such that it would allow removal of forms in proper
sequence without damaging either the concrete or the forms to be removed.
2.5.2 The props of centering shall be provided on firm foundation or base of sufficient
strength to carry the loads without any settlement.
2.5.3 The centering and formwork shall be inspected and approved by the Engineer-in-
charge before concreting. But this will not relive the contractor of his responsibility for
strength, adequacy and safety of form work and centering. If there is a failure of formwork or
centering, contractor shall be responsible for the damages to the work, injury to life and
damage to property.
2.6 Scaffolding :
2.6.1 All scaffolding, hoisting arrangements and ladders etc. Required for the facilitating of
concreting shall be provided and removed on completion work by contractor at his own
expense. The scaffolding, hoisting arrangements and ladders etc. Shall be strong enough to
withstand all live, dead and impact loads expected to act and shall be subject to the approval of
the Engineer-in-charge. However, contractor shall be solely responsible for the safety of the
scaffolding, hoisting arrangement, ladders, work and workman etc.
2.6.2 The scaffolding, hoisting arrangement and ladders shall allow easy approach to the
work spot and afford easy inspection.
2.6.3 The rate is applicable to all conditions of working and height upto 4 mts. The rate shall
include the cost of materials and labor for various operations involved such as :
(a) Splayed edges, notching, allowance for overlaps and passing at angles, battens centering,
shuttering, strutting, propping bolting, nailing, wedging, easing, striking and removal.
(b) Filleting to form stop chamfered edges or played external angles not exceeding 20 mm.
Width to beams, columns and the like.
(c) Temporary openings in the forms for pouring concrete, if required, removing rubbish etc.
(d) Dressing with oil to prevent adhesion of concrete with shuttering and
(e) Raking or circular cutting.
2.7 Re-Use : 2.7.1 Before re-use all forms shall be inspected by Engineer-in-charge and
their suitability ascertained. The forms shall be scarred, cleaned and joints gone over, repaired
where required. Inside surface shall be retreated to prevent adhesion of concrete.
3.0 Mode of measurements & payment :
3.1 Form work shall be measured as the area in square meters of shuttering in contract
with concrete except in the case of inclined member and portion of curved pro-file and upper
side in which case only area of underside shall be measured for payment.
3.4 Form work to secondary beams shall be measured up to the sides of main beams but no
deduction shall be made from the form work of the main beam at the inter section point. No
deduction shall be made from the form work of a column at inter section of beams.
3.5 The rate is for the completed item.
3.6 The rate shall be for a unit of one Sq. Meter.
Item No. 12: Providing formwork of ordinary timber planking so as to give a rough
finish including centering shuttering strutting and propping etc. height of propping and
centering below supporting floor to ceiling not exceeding 4 M. and removal of the same
for in situ reinforced concrete and plain concrete work in. (I) Edges of slabs and Breaks
in floors and walls.
Relevent specification item no 11 to be followed.
EW- 278 PUR-F-006 RFQ-
2.0. Mode of measurements & payment :
The rate shall be for a unit of one sq. Metre
Item No. 13: Providing formwork of ordinary timber planking so as to give a rough
finish including centering shuttering strutting and propping etc. Height of propping and
centering below supporting floor to ceiling not exceeding 4 M. and removal of the same
for in situ reinforced concrete and plain concrete work in. (B) Flat surfaces such as
soffits of supspened floors slabs Landings and the like. (1) Floors etc. upto 200 mm in
thickness.
Materials : The shuttering to be provided shall be of ordinary timber planks and shall conform
1.3 The dimensions of scantlings and battens shall conform to the design. The strength of
the wood shall not be less than that assumed in the design.
2.0 Workmanship :
2.1 The form work shall conform to the shape lines and dimensions as shown on the plans and
be so constructed as to remain sufficiently rigid during the placing and compacting of the
concrete. Adequate arrangements shall be made by the contractor to safe-guard against any
settlement of the form work during the course of concreting and after concreting. The form
work of shuttering, centering, scaffolding bracing etc. Shall be as per design.
2.2 Cleaning & Treatment of forms : 2.2.1 All rubbish, particularly chippings shaving and
saw dust shall be removed from the interior of the form before the concrete is placed and the
form work in contact with concrete shall be cleaned and thoroughly wetted or treated. The
surface shall be then coated with soap solution applied before concreting is done. Soap
solution for the purpose shall be prepared by dissolving yellow soap in water to get
consistency of paint. Alternatively a coat of raw linseed oil or form oil of approved
manufacture may be applied in case steel shuttering us used. Soap solution or raw linseed oil
shall be applied after thoroughly cleaning the surface. Care shall be taken that the coating does
not get on construction joints surface and reinforcement bars.
2.3 Stripping time : 2.3.1 In normal circumstance and where ordinary cement is used forms
may be struck after expiry of following periods :
(e) Sites of walls columns and vertical faces of beam 24 to 48 hours.
(f) Beam soffits. (Props left under) – 7 days.
(g) Removal of props slabs.
(i) Slabs spanning upto 4.5 m. – 7 days (ii) Spanning over 4.5 mm. – 14 days.
(h) Removal of props to beams and Arches.
(i) Spanning upto 6 m. – 14 days. (ii) Spanning over 6 m. – 21 days.
2.4 Procedure when removing the form work : 2.4.1 All form work shall be removed
without such shock or vibrations as would damage the reinforced concrete surface. Before the
soffit formwork and struts are removed the soffits and the concrete surface shall be exposed
where necessary in order to ascertain that the concrete has sufficiently hardened.
2.5 Centering :
2.5.1 The centering to be provided shall be got approved. It shall be sufficiently strong to
ensure absolute safely of the formwork and concrete work before during and after pouring
concrete. Watch should be kept to see that behavior of centering and formwork is satisfactory
during concreting. Erection should also be such that it would allow removal of forms in proper
sequence without damaging either the concrete or the forms to be removed.
2.5.2 The props of centering shall be provided on firm foundation or base of sufficient
strength to carry the loads without any settlement.
2.5.3 The centering and formwork shall be inspected and approved by the Engineer-in-
charge before concreting. But this will not relive the contractor of his responsibility for
strength, adequacy and safety of form work and centering. If there is a failure of formwork or
centering, contractor shall be responsible for the damages to the work, injury to life and
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
GTPS_Tender _ EW-278_25_04_2026.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .