Tender Value
₹48.7 L
EMD Value
₹49,000
Closing Date
22 May 2026, 6:00 pmClosed
Executive Engineer, Panchayat Irrigation Division, Amreli
Cleaning and Strengthening of Banks of Rivers at Village Ghoba Ta.Savarkundla Di.Amreli
300645
01 of 2026-27
Open
Miscellaneous Works
Amreli
8 documents required · 5 mandatory · 3 optional
₹1,500
Executive Engineer Panchayat Irrigation DIvision Amreli
₹49,000
2 May 2026
2 May 2026
2 May 2026
22 May 2026
2 May 2026
• BILL OF QUANTITIES
1. The bill of Quantities shall be read in conjunction with the Instructions to Bidder,
Conditions of Contract, Technical Specifications and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional, and
are given to provide a common basis for bidding. The basis of payment will be the
actual quantities of work ordered and carried out, as measured by the Contractor
and verified by the Engineer and valued at the rates and prices tendered in the
priced Bill of Quantities, where applicable, and otherwise at such rates and prices
as the Engineer may fix within the terms of the Contract.
3. The rates and prices tendered in the priced Bill of Quantities shall, except in so
far as it is otherwise provided under the Contract, include all constructional
plant, layout, supervision, materials, erection, maintenance, insurance, profit,
taxes and duties, together with all general risks, liabilities and obligations set out
or implied in the Contract.
4. The rates and prices shall be quoted entirely in Indian Currency.
5. A rate or prices shall be entered against each item in the Bill Quantities, whether
quantities are stated or not. The cost of Items against which Contractor has failed
to enter a rate or price shall be deemed to be covered by other rates and prices
entered in the Bill of Quantities (in case of Item rate contract).
6. The whole cost of complying with the provisions of the Contract shall be included
in the items provided in the priced Bill of Quantities, and where no Items are
provided the cost shall be deemed to be distributed among the rates and prices
entered for the related items of Work.
7. General direction and descriptions of work and materials are not necessarily
repeated or summarized in the Bill of Quantities. References to the relevant
sections of the contract documentation shall be made before entering rates or
prices against each item in the Bill of Quantities.
8. The method of completed work of payment shall be in accordance with the
specification for Road and Bridge works. For building works specifications for
building are to be followed.
9. Errors will be corrected by the Employer for any arithmetic errors pursuant to
Clause 29 of the Instructions to Bidder.
10. Rock is defined as all materials which, in the opinion of the Engineer, required
blasting, or the use of metal wedges and sledgehammers, or the use of
compressed air drilling for its removal, and which cannot be extracted by ripping
with a tractor of at least 150 kw with a single rear mounted heavy duty ripper.
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr.)
Item Description of Item Quantity Unit Rate In Amount
No (with brief specification and reference to book of specifications) figures
Jungle Clearance (Ganda Baval etc) of Light/heavy dence (work done by manually or by
machinery) including grabbing of & removing the roots & girth completely from the
ground & backfill with earth & making surface good as directed including depositing &
1 removing the material away from the site of work at own risk and cost as and where 52000.00 SQMT 3.80
directed etc completed for following.
A) Light density
(R.SOR 2024-25 Pg.No.43 Item.32)
Excavation for deepening of pond/checkdam including depositing excavated material
lead upto 1 km with all lift. Etc completed as per instruction of engineer in charge.
I/We am/are willing to carry out the work at… ............... % above/below percent (Should be written in figures and words) of the estimated rate
mentioned above. Amount of my /our tender works out as under.
Estimated amount put to tender Rs. Estimated amount put to tender Rs.
Deduct………………………. % below Rs. Add……………………………% Above Rs.
Net Rs. Net Rs.
In words :: In words ::
* (Please strike out whichever is not applicable)
NOTE 1: All work shall be carried out as per Public Works Department Handbook and other specifications of division or as directed.
NOTE 2: All the columns in schedule should be filled in ink and the total of the entries in the last column should be struck by the contractor
under his signature. Site, moisture, weather etc.
NOTE 3: Rates quoted include clearance of site (Prior to commencement of work and at tis close) in all respects and hold good for work under
all conditions.
NOTE 4: To be on additional sheets, if found necessary.
Deputy Executive Engineer Divisional Accounts Officer Executive Engineer
C.S.I. Sub Division Panchayat Irrigation Division Panchayat Irrigation Division
Savarkundla Amreli Amreli
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
BOQ.pdf
Raate.pdf
Section 10 - Documents to be submitted.pdf
SBD.pdf
NOtice 01.pdf
Download all tender documents and submit your bid