Tender Value
₹70.8 Cr
EMD Value
₹12 L
Closing Date
18 Jul 2026, 4:00 pmClosed
Additional Chief Engineer (P&C)
Supply, Erection, Testing and Commissioning of LILO of one circuit of the 220 kV D/C Chorania – Salejda transmission line at 220kV Khoraj Substation using AL-59 conductor, comprising 40 Rkm on D/C towers / Narrow Base Towers and 3.961 Rkm on M/C towers / Narrow Base Towers, with a total double-circuit line length of 48.616 Rkm and an overall route length of 52.577 Rkm on turnkey basis, under Limbdi Construction Division of Surendranagar Circle.
321834
ACE(P&C)/Contract/E-485/TL/220kV/S&E
Open
Electrical
Turn-key
Vadodara
35 documents required · 26 mandatory · 9 optional
₹11,800
Gujarat Energy Transmission Corporation Limited
₹12 L
8 Jul 2026
8 Jul 2026
8 Jul 2026
18 Jul 2026
8 Jul 2026
Sr. No. Description of Works - SAC Code 9954 Amount in Rs.
PART -A Supply of Materials
Erection of Line
TOTAL F.O.R. COST WITHOUT GST
Service of "Works Contracts" GST @ 18% (SAC 9954)
TOTAL END COST WITH GST
I am / we are willing to carry out this service package of works contract stated above at GST 18% (in
figure) ______ % (in words _____ %) below / above the estimated TOTAL END COST for all the items
stated there in.
The amount of tender works out with above % (in figure) for TOTAL END COST Rs. _____________ (in
I / we confirm that our above quoted rates are ON firm price basis; except price variation will be
applicable of Supply of Tower material (including bolts & nuts), Supply of Conductor, Supply of
Hardware & accessories for conductor and Erection portion.
1) Separation of the Contract into Supply of Goods, Services and Civil Work, is only for convenience and better
economical management and for the ease of Accountancy but the entire Contract, is to be assessed under GST
Law, as the Works Contract Service, which is, as per the provisions of Section 2(30), read with, Section 2(119),
further read with, Paragraph 6(a) of the Schedule II to the CGST Act, 2017 or SGST Act, 2017 and similar
provisions, applicable under the UTGST Act, 2017and the IGST Act, 2017 and the entire activity, would be
subjected to levy of Tax, at the rate of 9% CGST + 9% SGST or 18% IGST, under the GST Law. However,
Classification Codes for different segments or portions of the Works Contract, may be specified separately, in the
Supplies, with a final common Classification Code of Works Contract Service.
2) The Bidder is hereby conveyed that only SAC Code and Tax rate for supply of Service Works Contract i.e. 18%
is relavant for the purpose of contract since the contract is works contract and any separation in the works is for
better management and convenience purpose.
It is to state that bidders are however requested to fill the HSN code item by item for the knowledge and
transparency purpose which shall have no bearing on price or taxation payment.
Signature of Authorized Representative of Company / Agency
SEAL & SIGNATURE Status _________________
OF BIDDER Name of bidder Company
FOR REFERENCE ONLY
Supply, Erection, Testing and Commissioning of LILO of one circuit of the 220 kV D/C Chorania – Salejda transmission line at 220 kV Khoraj Substation using AL-59 conductor, comprising
Rkm on D/C towers/Narrow Base Towers and 3.961 Rkm on M/C towers / Narrow Base Towers, with a total double - circuit line length of 48.616 Rkm and an overall route length of 52.577 Rkm on
turnkey basis, under Limbdi Construction Division of Surendranagar Circle.
Tender no: ACE(P&C)/Contract/E-485/TL/220kV/S&E
Description of Supply with Detail Specification of Service Unit Freight, Packing FOR Total Cost
Unit Insurance FOR Unit Rate
Sr. No. Package - Works Contract (SAC Code: Unit Quantity Unit Rate & Forwarding (Excl. GST)
Charges in Rs. in Rs.
9954) charges in Rs.
A Supply of Materials
A.1 Tower Materials
A.3 Silicon Rubber Insulators
A.3.1 220kV, 90kN Suspension SRI Nos. 782 4378.00 86.00 37.00 4501.00
A.4 Insulator hardware for AL-59 Conductor (61/3.50)
A.4.1 Single Suspension Nos. 654 2447.00 18.00 8.00 2473.00
A.4.3 Double Suspension Nos. 60 5257.00 36.00 16.00 5309.00
A.4.7 Vibration Damper Nos. 3480 1243.00 12.00 5.00 1260.00
A.4.8 Repair Sleeve Nos. 32 695.00 7.00 3.00 705.00
A.5.1 48 Fibre (DWSM) OPGW fibre Optic cable kM 52.577 195533.00 2385.00 1022.00 198940.00
Description of Supply with Detail Specification of Service Unit Freight, Packing FOR Total Cost
Unit Insurance FOR Unit Rate
Sr. No. Package - Works Contract (SAC Code: Unit Quantity Unit Rate & Forwarding (Excl. GST)
Charges in Rs. in Rs.
9954) charges in Rs.
Installation Hardware set * & accessories for above OPGW
i.e. all cable fittings & accessories like suspension clamps,
tension clamps, vibration dampers, earthing clamps, down
lead clamps, in-line splice enclosures etc. including; Pigtails
a) Fibre Optic Approach Cable -
400 Mtrs - For 220KV S/S &
500 Mtrs - For 400KV S/S
(with installation hardware like ties/
clips / cleats, conduits, ducts,
supports, fittings, accessories etc).
(Any variation in quantities shall be absorbed by contractor)
TOTAL COST PART - A WITHOUT GST
Service of "Works Contracts" GST @ 18% (SAC 9954)
TOTAL COST PART - A WITH GST
1). One set of installation hardware shall contain all installation hardware fittings as may be required for 1 kM of OPGW cabling.
2). LCT (Local Craft Terminal- Laptop) with EMS software shall have to be supplied by Manufacturer free of cost for local as well as remote configuration of FOTE equipment.
3) Rates are taken from SoR 2024-25 for transmission line materials
OEM will have to submit confirmation in written for following.
1). The bidder shall furnish the copies of valid type test reports for the offered equipment from NABL accredited Laboratory or KEMA type tested.
2). The bidder should have to confirm for guarantee of 5 years from the date of receipt of equipment in store in good condition or three years from the date of commissioning of offered FOTE
(Operational for Speech+DATA+Protection + Remote SCADA over OPGW) at respective Sub-station which ever will be earlier.
3). The bidder should have to confirm the service and spares support for at least 10 years after the guarantee period.
A) SOR GETCO/1155/12/2025 Approved Date: 20-12-2025 considered.
SEAL & SIGNATURE OF BIDDER
ERECTION PORTION
FOR REFERENCE ONLY
Supply, Erection, Testing and Commissioning of LILO of one circuit of the 220 kV D/C Chorania – Salejda transmission line at
220 kV Khoraj Substation using AL-59 conductor, comprising 40.000 Rkm on D/C towers/Narrow Base Towers and 3.961 Rkm
on M/C towers / Narrow Base Towers, with a total double - circuit line length of 48.616 Rkm and an overall route length of
52.577 Rkm on turnkey basis, under Limbdi Construction Division of Surendranagar Circle.
Tender no: ACE(P&C)/Contract/E-485/TL/220kV/S&E
Sr. Description of Supply with Detail Specification of
Unit Quantity Unit Rate (Excl. GST)
No. Service Package - Works Contract (SAC Code 9954)
B ERECTION OF LINE
The work of detail survey, preparation and submission
of profiles in 6 copies (PLSCAD as well as hardcopy),
Detail scope of Work :-
(a) Fixing of tower as per actual requirement, site
condition and plotting of line on profile having
standard details i.e. span length, lat-long (co-
ordinate), chainage, weight and wind span, all
dimensions, scale, legends, tower spotting data etc. as
per requirement and along with all require details.
(c) Preparation and submission of tower schedule as
per standard require details with all the Major - Minor
crossing details in profile drawing and tower schedule,
1 along with due care of clearance as per prevailing kM 52.577 10222
standards i.e., for all electric line with pole, all type of
track, river, pond, nala, road, canal etc.
(d) Details of Right of Way in profile drawing. i.e.
Building, Temple, Well etc.
(g) Plotting line on TIKKA-MAP (Revenue Land map) -
Required TIKKA-MAP will be provided by GETCO.
Importantly, any work other than mentioned will align
with the specific requirements outlined by the Engineer-
Note : The survey report will be submit with sign and
stamp of the surveyor agency and engineer in charge.
Check Survey along with plotting of line route on
village (tika) map with Coordinates including detailed
survey, preparation of profiles and revision in original
route alignment, if any and as per instruction of EIC.
Excavation excluding back filling, but including
shoring, shuttering, dewatering, tree cutting for tower -
footings etc. for:-
a) Normal soil either dry or wet / Sandy soil Cu.m 667.44 307.00
b) Black cotton soil either dry or wet Cu.m 13279.540 614.00
3 c) Normal submerged/marine soil where dewatering is Cu.m
d) Black cotton submerged / Marine soil where Cu.m
dewatering is necessary
e) Soft Rock Cu.m 0.00 1066.00 -
f) Hard Rock Cu.m 0.00 2212.00 -
Installation of steel reinforcement in concrete
foundation including supply of GETCO Approved M.S.
bars, binding wire. Work also includes their cutting,
4 bending, shaping and binding with binding wire and MT 283.0130 99900.00
fixing in position of TMT bars as per drawing before the
concrete work and as per instruction of the EIC
Stub-setting with prop or template including back-
filling, during back filling dispose of excess soil and
levelling of site is to be done as per instructions of EIC
5 but excluding excavation and concreting etc. for all MT 245.198 8206.00
types of towers/extensions except special towers.
(Weight of stub, cleat & template with Bolt & Nuts of
stub & template shall be counted)
6 ---- Do ---- up to 9 to 25 mtr extension MT 20.383 9918.00
Concreting of foundation by M20/M15/M25 mixture
including shoring, shuttering, compaction, dewatering
etc. for normal tower / tower with extension upto 25mtr.
After completion of concrete work, curring (watering to -
7 concerte) is to be done as per instruction of EIC.
(Rates are inclusive of supply of GETCO approved
Grounding of towers with pipe type earthing including
excavation and back filling, with supply of all materials
like 32mm dia heavy duty 3 mtr. long G.I. Pipe, 50 x
mm G.I. flat, GI bolt-nuts, with GI spring washer, salt,
charcoal etc. as per drawing and as per instruction of
Grounding of towers with COUNTER POISE TYPE
including excavation and back-filling and supply of all
9 materials like GSS wire, GI lugs, GI bolt-nuts, GI Set. 0 15756.00 -
Spring Washer, salt, charcoal etc. as per drawing and
as per instruction of EIC.
Erection of super structure upto 6 meter extension
including tree cutting, fixing of tower accessories,
attachments except ACD /DP /NP /CIP /PP and
excluding tack welding of bolts as per instruction of
10 EIC. This includes taking delivery of tower materials MT 1409.192 10076.00
and bolt‑nuts from GETCO’s stores etc. for normal,
extension & special towers at destination and keeping
them in safe custody and transporting the same to
Same as above but erection of 9/12/15/18/21/25 Mtr.
extension with tower.
Fixing of Anti-climbing devices including supply of
12 barbed wire as per drawing and as per instruction of Loc. 204 3589.00
EIC. (C ) 220kV
Fixing of DP / NP / PP / CIP including supply of plates
13 and supply of G.I. bolt-nuts & tack welding as per Loc. 177 3379.00
drawings. (D/C)
Fixing of DP / NP / PP / CIP including supply of plates
14 and supply of G.I. bolts-nuts & tack welding as per Loc. 17 6758.00
drawings and as per instruction of EIC. (M/C)
Tack welding of nuts upto approx. 10 mtrs. height OR
two bottom-most panel from ground level at three
15 places on the nuts diametrically and applying zinc rich Per Bolt 718750.0 15.00
paint immediately after tack welding and as per
instruction of EIC.
Stringing of ACSR/ AAAC/AL-59 6 (Six conductors for
Double circuit including laying, jointing, tensioning,
clamping with armour rods, hoisting of insulator string
fixing of jumpers, dampers etc. & with required tree
cutting on entire length for adequate clearances / safe
charging of line, as per instruction of EIC.
Termination and connection for making LOOP-IN-
LOOP-OUT arrangement with existing line during
specified outage including restringing of existing
conductors OR dismantalling / new stringing for Job
making LILO arrangements with existing line or for Work
change over line as per approved LILO arrangement in
profile as per instruction of EIC in COLD CONDITION
and dismentalled
Complete materials
Installation to be credited
of OPGW to nearfibres)
cable (24/48 by
including laying, providing required hardwares, in line
splices to be encased in Fibre Optic Splice
Enclosures, Laying and termination of a fibre optic
approach cable required to connect Overhead Fiber
Optic Cable (OPGW) between the final iin line splice
enclosure on the gantry/tower and the Fibre Optec
Distribution panel (FODP) to be installed within the
building at both the substation ends as per technical
Link up of OPGW Cable including all related activities
as per inst. Of EIC.
For Rubble soiling work: (As per BoQ=68.970cmt
required): (Miscelleneous work)
(A) Suppliying of graded stone aggregate of following
sizes (for W.B.M. Road)(3) Crushed stone aggregate
for Hard Quality up to 63 mm stze : Rate/cmt=400Rs,
Surendranagar SoR 2024-25, Item no.26011C)
(B) Spreading the stone aggregate for rolling and
W.B.M. including filling the interstices to required
camber and gradient (excluding spreading of
lindage)(ii) 40mm to 63mm size aggreagates (H.B.):
Rate/cmt=247.28Rs (R&B, Surendranagar SoR 2024-
25, Item no.26018A), Hence: Job
(C) Sand, stone aggregate & soling stone brick/ cinder
aggregate (Lead).
3)- soling stone - RATE PER UNIT PER Km. FOR
KILOMETERAGE ABOVE 5Km.LEAD
FALLING IN TOTAL RANGE BETWEEN ABOVE
50Km: Rs 9.67/km/cmt (R&B, Surendranagar SoR
Total A+B+C= Rs.27,588.00+ Rs.17054.90+
Work of Painting of Line name, Location No., two coat
Painting Color code of desired length and telephone
no. on Tower Leg with letter of Gujarati language
using ISI marked Paint as per instruction of EIC
including Supply of paints and other require materials..
b) All four legs - For 2 Nos. of Line (D/C)
TOTAL COST PART - B, SCHEDULE - 01 WITHOUT GST
Service of "Works Contracts" GST @ 18% (SAC 9954)
TOTAL COST PART - B, SCHEDULE - 01 WITH GST
While calculating the weight of stub-setting, the weight of stub, cleat & templates shall also be added in
2 Red oxide & zinc rich paint shall be applied after tack welding of nuts.
3 The above rates are with supply of GETCO approved cement and steel by the contractor.
4 For concreting work, mixture machine is to be used as per site condition and as per inst. of EIC.
While crediting of material, agency has to submit the original gate pass copy / CR copy with required
documents as per instruction of EIC
The rate indicated above includes taking delivery of all stringing material from contractor store GETCO’s
store keeping them in safe custody and transporting the same to erection site.
For any crediting of material related work, agency has to submit the original gate pass copy / CR copy with
required documents as per inst. and as per requirement of EIC or when demanded.
Signature of Authorized Representative
of Company / Agency
SEAL & SIGNATURE Status _________________
OF BIDDER Name of bidder Company
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Part-I 4 EMD BG Format.pdf
Part-I 1 Tender Notice E-485.pdf
Part-I 2 Tender Spec E-485.pdf
Part-I 3 Amend -I E-485 LILO Khoraj.pdf
Part-I 4 EMD BG Format.pdf
Part-I 5 SD BG Format.pdf
Part-I 6 L-2 Schedule of Chorania Salejda at khoraj.pdf
Part-III Price Bid E-485.pdf
1. MS HT steel - Addendum for Tower material.pdf
9_ERECTION Circular-1.pdf
10_ Erection circular -2.pdf
11_Public Proc Circular of GOI.pdf
13_Letter for CBuD.pdf
0016 - G AL-59.MSJ-Model.pdf
16_Safety_regulation_for_TL.pdf
0017 - G AL-59.PAR-Model.pdf
28_STD FQP TR LINE JUNE-2014.pdf
0035 - G AL-59 .STN - 1-Model.pdf
0035 - G AL-59 .STN - 2-Model.pdf
0051 - G AL-59.SSN-Model.pdf
0052 - G AL-59.DSN-Model.pdf
0053 - G.AL-59 VD.-Model.pdf
0056 - G AL-59 .DTN - 2-Model.pdf
0056 - G AL-59. DTN - 1-Model.pdf
00150 - G AL-59.RS-Model.pdf
AL59 PANTHER and MOOSE_R5.pdf
Amendment- Structure weight.pdf
Ammendment for TTR validity 26.02.2026.pdf
Form of LD undertaking 1A.pdf
Form of LD undertaking 1B.pdf
HW and ACCS AL59 CONDUCTOR 220 kV line PRINT COPY R2 JULY 2022.pdf
ON - Ammendment for ROW clause Tender Copy.pdf
OPGW (48F) specs final-R2-11.09.2023 final.pdf
R1 - STEEL DRUM .pdf
R2 - SUPPLY and ERECTION OF 220KV LINES.pdf
R5 May 24- Silicon Rubber - Print Copy.pdf
Standard MQP GI Tower material for issuence to SUPPLIER COPY.PDF
SUPPLY and ERECTION OF 220KV MULTI CIRCUIT LINES.pdf
TOWER MATERIAL-220KV LINE-ZEBRA.pdf
TOWER MATERIAL-220KV MC LINE-ZEBRA.pdf
DC Tower weight E-485.pdf
FND VOL E-485.pdf
MC Tower weight E-485.pdf
NB DC Tower weight E-485.pdf
NB MC Tower weight E-485.pdf
E-485 Corrigendum no. 1 10-07-26.pdf
CORRIGENDUM
LATLONG.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .