| 1 | 1₹5.8 LAccepted-AOC | 1 | Accepted-AOC AGREEMENT EXECUTED | |
| 2 | Rejected-Technical KERALA KL | KOTTAYAM | KERALA | 686001 | - | Rejected-Technical REJECTED |
| Sl No | Description | Qty | Unit | P H Zakeer L2 | SHAJI K N L1 |
|---|---|---|---|---|---|
| 1.00Road maintenance and side protectionwall | |||||
| 1.00 | 2.14.1.A:Dismantling of Flexible Pavements Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 100 m, stacking serviceable and unserviceable materials separately as per Technical Specification Clause 202 (I) By Manual Means (A) Bituminous Courses | 30 | cum | 1,539.18 ₹46,175.4 | 1,538 ₹46,140 Lowest |
| 1.00 | 2.5.2.A:Dismantling of Structures Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.(II) By Mechanical Means (A) Cement Concrete | 1.84 | cum | 700.9 ₹1,289.66 | 700 ₹1,288 Lowest |
| 1.00 | 3.14:Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. | 61.64 | cum | 461.21 ₹28,430.83 | 460 ₹28,356.24 Lowest |
| 1.00 | 4.9:Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. By Mechanical Means with 1 km lead | 61.64 | cum | 3,316.46 ₹2,04,439.86 | 3,314 ₹2,04,288.22 Lowest |
| 1.00 | OD299199/2022-2023:Providing and laying of Inter locking block pavements using 80mm m40hydraulic blocks of approved size ,design&shape laid in crushed stone chipping 6.7 mm size 100 mm passing 9.5 mm and retained on 2.36 using plate vibrator etc.as per the departmental specification. | 130 | sqm | 1,008.47 ₹1,31,101.1 | 1,007 ₹1,30,910 Lowest |
| 1.01 | OD299200/2022-2023:tacking out existing CC interlocking paver blocks from foot path /central verge, including removal of rubbish etc. disposal of unserviceable material to dumping ground. | 37.24 | sqm | 115.32 ₹4,294.52 | 115 ₹4,282.6 Lowest |
| 1.01 | OD299201/2022-2023:resetting80 mm thick inter locking concrete block pavement of M-30 grade made by block making machine with strong vibratory compaction . | 29.79 | sqm | 328.44 ₹9,784.88 | 328 ₹9,771.78 Lowest |
| 1.01 | 75.8.1:Providing Plain cement concrete for road work CC 1:2:4 (1 cement: 2 fine aggregate: 4course aggregate) laid to required slope and camber in panels (@ 3 m c/c) as requiredincluding compaction, finishing and tamping etc .complete. Max. size of courseaggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification
(i) Nominal mix (1:2:4) | 6.54 | cum | 8,306.23 ₹54,355.97 | 8,306 ₹54,354.46 Lowest |
| 1.01 | 75.8.1.1:Providing plain/reinforced concrete(1 cement:2 fine aggregate: 4 course aggregate) forsubstructure as per drawings and technical specifications Clause 802, 803, 1202 & 1203as required including compaction, finishing and tamping etc .complete. Max. size ofcourse aggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification
(i) Nominal mix (1:2:4) | 5.1 | cum | 8,296.75 ₹42,313.43 | 8,296 ₹42,309.6 Lowest |
Tender Value
₹5.8 L
EMD Value
₹14,476
Closing Date
1 Jun 2023, 3:00 pmClosed
SUPERINTENDING ENGINEER
Kochi Municipal Corporation Park Avenue Ernakulam , Kochi 682011
SYE2/008333/22-Construction of side protection wall ,tile paving,sluice at N.M.Madhavan road in Div.15
2023_LSGD_577665_2
Kochi muncipal corparationSYE2/1505/2021
Open Tender
Civil Works - Canal
Item Rate
120 days
Ernakulam
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,366
₹14,476
30 Apr 2026
24 May 2023
3 Jun 2023
24 May 2023
1 Jun 2023
24 May 2023
Amount
Road maintenance and side protectionwall
2.14.1.A:Dismantling of Flexible Pavements Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 100 m, stacking serviceable and unserviceable materials separately as per Technical Specification Clause 202 (I) By Manual Means (A) Bituminous Courses
2.5.2.A:Dismantling of Structures Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.(II) By Mechanical Means (A) Cement Concrete
3.14:Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.
4.9:Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. By Mechanical Means with 1 km lead
OD299199/2022-2023:Providing and laying of Inter locking block pavements using 80mm m40hydraulic blocks of approved size ,design&shape laid in crushed stone chipping 6.7 mm size 100 mm passing 9.5 mm and retained on 2.36 using plate vibrator etc.as per the departmental specification.
OD299200/2022-2023:tacking out existing CC interlocking paver blocks from foot path /central verge, including removal of rubbish etc. disposal of unserviceable material to dumping ground.
OD299201/2022-2023:resetting80 mm thick inter locking concrete block pavement of M-30 grade made by block making machine with strong vibratory compaction .
75.8.1:Providing Plain cement concrete for road work CC 1:2:4 (1 cement: 2 fine aggregate: 4course aggregate) laid to required slope and camber in panels (@ 3 m c/c) as requiredincluding compaction, finishing and tamping etc .complete. Max. size of courseaggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification (i) Nominal mix (1:2:4)
75.8.1.1:Providing plain/reinforced concrete(1 cement:2 fine aggregate: 4 course aggregate) forsubstructure as per drawings and technical specifications Clause 802, 803, 1202 & 1203as required including compaction, finishing and tamping etc .complete. Max. size ofcourse aggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification (i) Nominal mix (1:2:4)
11.6.3.2:Stone masonry work in cement mortar in foundation complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203.III. Random Rubble Masonry (ii) In cement mortar 1:4
OD311869/2022-2023:RING BUND Type 2 Putting up ring bund with earth fill gunny bags of top width 1 m bottom width 2 m height 2.m side and filling in between with earth to form ring bund and maintaining the same leak proof till the completion of he work and cleaning the site by dismantling the bund after comletion of the work etc.complete MODIFIED 60.1.2
OD311870/2022-2023:Bailing out water using 5HP pump-Bailing out water with 5HP engine and pump set including conveyance to site and erection cost of fuel , lubrication oil and other stores , pay of staff etc. complete. MODIFIED 60.2.2
P H Zakeer
Bidder Name
SHAJI K N
P H Zakeer
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.51 MB
Tendernotice_2.pdf
PDF • 0.06 MB
Tendernotice_3.pdf
PDF • 0.06 MB
BOQ_853350.xls
BOQ • 0.28 MB
PRI.pdf
Tender Documents • 0.07 MB
AFFDVT.pdf
Tender Documents • 0.06 MB
FOT.pdf
Tender Documents • 0.01 MB
sbd.pdf
Tender Documents • 1.70 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .