Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹1.1 Cr
EMD Value
₹2.2 L
Closing Date
15 Oct 2026, 3:00 pm5d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
The Executive Engineer,Amb-Division,PWD(RandB)
o/o the Executive Engineer,Amb-Division,PWD(RandB)
Development of Roads from i) KMA road to Bagmara road (L-1.20 km). ii) NH-8 to Hadukalak Para ( L-1.00 Km). iii) Kulai HS School Approach road ( L-0.30 Km), (Total Length -2.50 Km)/ SH- Grouting, WBM-III, Re-carpeting, Pucca Drain etc.
2026_CEPWD_77965_1
43/DNIT/SE-V/AMB/2026-27
Open Tender
Civil Works - Roads
Percentage
180 days
Ambassa
Please refer Tender documents.
4 documents required · 4 mandatory
₹4,000
₹2.2 L
o/o the Executive Engineer,Amb-Division,PWD(RandB)
9 Oct 2026
9 Oct 2026
15 Oct 2026
9 Oct 2026
15 Oct 2026
9 Oct 2026
9 Oct 2026 - 12 Oct 2026
13 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing Road Land Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girthupto300mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of service able material to be used or auctioned, up to a lead of 1000 m including removal and disposal of top organic soil not exceeding 150mm in thickness as per MoRD Technical Specification clause 201.
(I) By Manual Means
(A) In area of non-thorny jungle | 0.05 | Hect. | 86,289.2 | ₹4,314.46 |
| 2 | Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site , spreading, grading to required slope and compacted to meet requirement of Table 300.2 as per MoRD Technical Specification Clause 303.1. | 81 | Cum | 233.8 | ₹18,937.8 |
| 3 | Excavation for Structures (A) Without dewatering Earthwork in excavation for structures as per drawing and MoRD technical specifications Clause 305.1 including setting out, construction of shoring & bracing, removal of stumps & other deleterious material and disposal upto a lead of 50 m, dressing of sides & bottom and backfilling in trenches with excavated suitable material. I.Ordinary soil (i)Upto 3 m depth | 498 | Cum | 458.2 | ₹2,28,183.6 |
| 4 | Filling in foundation trenches as per drawing & MoRD technical specification Clause 305.3.9, 1200. (i)Sand filling | 39 | Cum | 1,392.25 | ₹54,297.75 |
| 5 | Providing concrete for plain concrete (using jhama brick aggregate) in open foundations complete including formwork as per drawings & MoRD technical specifications Clauses 802, 803, 900, 1202 and 1203. (including centering, shuttering, staging etc. but excluding reinforcement)
I.P.C.C grade M 10 ( Using Jhama Brick Aggregate ) (i)Nominal mix 1:3:6 | 39 | Cum | 9,405.5 | ₹3,66,814.5 |
| 6 | Providing concrete for plain/reinforced concrete in open foundations complete including form work as per drawings & MoRD technical specifications Clauses 802, 803, 900, 1202 and1203. (Including centering, shuttering, staging etc. but excluding reinforcement).
v) R.C.C grade M 25 | 72 | Cum | 11,969.75 | ₹8,61,822 |
| 7 | Supplying, fitting & placing Thermo-Mechanically treated bar/ Cold twisted deformed steel bar reinforcement in foundation complete as per drawings & MoRD technical specifications Clauses 1000 & 1202. | 5.76 | Ton | 91,625 | ₹5,27,760 |
| 8 | Plain/reinforced cement concrete in substructure complete including formwork as per drawings & MoRD technical specification Clauses 802, 804, 805, 806, 807, 900, 1202 & 1204. (including centering, shuttering, staging etc. but excluding reinforcement) (VI)RCC grade M25 i) Upto 5m height | 39 | Cum | 12,640.65 | ₹4,92,985.35 |
| 9 | Supplying, fitting & placing Thermo-Mechanically treated bar/ Cold twisted deformed steel bar in substructure complete as per drawings & MoRD technical specification Clauses 1002, 1005, 1010 and 1202. | 3.12 | Ton | 91,898.8 | ₹2,86,724.26 |
| 10 | Providing weepholes in brick masonry/ stone masonry, plain/ reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe or uPVC pipe (110 mm OD of 6.0 Kg/cm2 pressure) extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and MoRD technical specification clauses 614, 709, 1204.3.7. | 30 | metre | 392.2 | ₹11,766 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 4.42 MB
DNIT.pdf
Tender Documents • 2.77 MB
Integrity.pdf
Additional Documents • 0.59 MB
BOQ_79367.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .