| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹22.6 LAdmitted-Finance NEHRU MARKET DAKPATHAR DEHRADUN | -38.93% | ₹22.6 L | L1 | Admitted-Finance |
| 2 | L2₹26.9 LAdmitted-Finance | -27.19% | ₹26.9 L | L2 | Admitted-Finance |
| 3 | L3₹35.0 LAdmitted-Finance FIRST FLOOR FLAT NO 6 BLOCK B CLASSIC APARTMENT GANGOTRI VIHAR DEHRADUN 248001 | DEHRADUN | UTTARAKHAND | 248001 | -5.33% | ₹35.0 L | L3 | Admitted-Finance |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | - | Not Admitted-Fee/PreQual/Technical Others-Hard copy of documents (As per NIT/Tender) not submitted |
| 5 | Not Admitted-Fee/PreQual/Technical KOTI COLONY KOTI DEHRADUN | - | - | - | Not Admitted-Fee/PreQual/Technical Others-Hard copy of documents (As per NIT/Tender) not submitted |
Tender Value
₹37.0 L
EMD Value
₹92,500
Closing Date
3 Jul 2026, 5:00 pmClosed
EE Civil Maintenance Vyasi Project
Office of EE Civil Maintenance Vyasi Project
Annual Repair and Maintenance of residences allotted to officers/employees of Vyasi HEP at Dakpathar, Dehradun (Year- 2026-27).
2026_UJVN_96490_1
02/2026-27/EE(C-M)/Vyasi Project
Open Tender
Civil Works
Percentage
365 days
Dakpathar
Please refer tender document
3 documents required · 3 mandatory
₹2,360
DGM O and M Vyasi Project UJVN Limited Dakpathar
₹92,500
23 Jul 2026
12 Jun 2026
7 Jul 2026
12 Jun 2026
3 Jul 2026
22 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix). Including supply of all material labour T&P etc. required for proper completion of the work. (As per CPWD DSR 2023, Code No.- 15.2.1) | 5 | Cum | 2,062.92 | ₹10,314.6 |
| 2 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. (As per CPWD DSR 2023, Code No.- 15.3) | 3 | Cum | 3,009.53 | ₹9,028.59 |
| 3 | Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead : Of area 3 sq. metres and below. Including supply of all material labour T&P etc. required for proper completion of the work. (As per CPWD DSR 2023, Code No.- 15.12.1) | 25 | Each | 311.19 | ₹7,779.75 |
| 4 | Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. Including supply of all material labour T&P etc. required for proper completion of the work. (As per CPWD DSR 2023, Code No.- 15.56) | 40 | Sqm. | 46.31 | ₹1,852.4 |
| 5 | Demolishing brick work, manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. Including supply of all material labour T&P etc. required for proper completion of the work. (As per CPWD DSR 2023, Code No.- 15.7.4) | 3 | Cum | 1,745.93 | ₹5,237.79 |
| 6 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. (As per CPWD DSR 2023, Code No.- 2.8.1) | 20 | Cum | 220.59 | ₹4,411.8 |
| 7 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size). Including supply of all material, labour T&P etc. required for proper completion of the work. (As per CPWD DSR 2023, Code No.- 4.1.8) | 3 | Cum | 5,772.88 | ₹17,318.64 |
| 8 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 40 mm nominal size derived from natural sources) (As per CPWD DSR 2023, Code No.- 4.1.6) | 25 | Cum | 6,083.69 | ₹1,52,092.25 |
| 9 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size. Including supply of all material, labour T&P etc. required for proper completion of the work. (As per CPWD DSR 2023, Code No.- 4.1.3) | 35 | Cum | 6,676.69 | ₹2,33,684.15 |
| 10 | Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete. 40 mm thick with 20 mm nominal size stone aggregate. Including supply of all material, labour T&P etc. required for proper completion of the work. (As per CPWD DSR 2023, Code No.- 11.3.1) | 50 | Sqm. | 520.51 | ₹26,025.5 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.30 MB
BOQ_113997.xls
BOQ • 0.49 MB
tender.pdf
Tender Documents • 2.47 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].