| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.8 CrAccepted-AOC | ₹2.8 Cr | L1 | Accepted-AOC L1 BIDDER |
| 2 | L2₹3.0 Cr+₹13.2 L (4.62%)Rejected-AOC | ₹3.0 Cr+₹13.2 L (4.62%) | L2 | Rejected-AOC L4 BIDDER |
| 3 | L3₹3.4 Cr+₹57.5 L (20.2%)Rejected-AOC | ₹3.4 Cr+₹57.5 L (20.2%) | L3 | Rejected-AOC L2 BIDDER |
| 4 | L4₹3.6 Cr+₹72.2 L (25.4%)Rejected-AOC | ₹3.6 Cr+₹72.2 L (25.4%) | L4 | Rejected-AOC L3 BIDDER |
| 5 | L5₹3.6 Cr+₹76.8 L (27.0%)Rejected-AOC | ₹3.6 Cr+₹76.8 L (27.0%) | L5 | Rejected-AOC L5 BIDDER |
Tender Value
₹2.9 Cr
EMD Value
₹1 L
Closing Date
21 Mar 2025, 3:00 pmClosed
HOUT
KMML CHAVARA
Construction of foundation, plinth and up to FFL.
2025_KMML_747784_1
KMML/TP/PROJ/C/T/06/2024-25 Dated 07/03/2025
Open Tender
Civil Works - Others
Item Rate
120 days
KMML CHAVARA
Please refer Tender documents
10 documents required · 10 mandatory
₹8,850
₹1 L
30 May 2025
10 Mar 2025
24 Mar 2025
10 Mar 2025
21 Mar 2025
10 Mar 2025
10 Mar 2025 - 21 Mar 2025
Amount
OXIDE STORAGE WARE HOUSE UPTO FINISHED FLOOR LEVEL
2.33.1 Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 30 cm girth up to and including 60 cm girth
2.33.2 Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 60 cm girth up to and including 120 cm girth
2.28.1 Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m.All kinds of soil
2.6.1 Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.26.1 Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil
15.2.1 Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
15.3 Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.
15.7.4 Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In cement mortar
2.16.2 Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete (Measurements to be taken of the face area timbered).Depth exceeding 1.5 m but not exceeding 3 m
2.25 Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
50.2.25.1 Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge
60.7.2 DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
4.1.5 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
4.1.3 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
4.1.8 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
60.2.2 Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
5.9.1 Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.6 Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
5.9.2 Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
5.9.5 Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
30.2.54 Anti termite treatment by digging holes 30 cm deep and 4 cm dia, 6 to 7 holes around the tree using chemical emulsion at the rate of 1.5 liter per hole in two time or more application to get the trees free from termite infection chemicals used Chlorpyriphos 20% EC in the ratio of 1% concentration and as per direction of officer-in-charge.
13.65.1 Painting with black anti- corrosive bitumastic paint of approved brand and manufacture to give an even shade:Two or more coats on new work
5.33.1 Providing and laying in position machine batched and machine mixed design mix M- 25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is payable or recoverable separately.All work upto plinth level
5.34.1 Extra for providing richer mixes at all floor levels. Note:- Excess/less cement over the specified cement content used is payable/ recoverable separately.Providing M-30 grade concrete instead of M-25 grade BMC/RMC. (Note:- Cement content considered in M-30 is @ 340 kg/cum).
5.35 Add for using extra cement in the items of design mix over and above the specified cement content therein
16.75 Providing and laying C.C pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator, vacuum dewatering process and finally finished by floating brooming with wire brush etc. complete as per specifications and directions of Engineer-in-charge ( The panel shuttering work shall be paid for separately)
11.4 52 mm thick cement concrete flooring with concrete hardener topping, under layer 40 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand: 4 graded stone aggregate 20 mm nominal size) and top layer 12 mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate 6mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacturer's specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete
5.22.6 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.6.1.4 Solid block masonry using pre cast solid blocks (Factory made) of size 30x20x20cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth with thickness 20cm and above in: CM 1:6 ( 1 cement : 6 coarse sand ) etc complete
13.1.1 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
5.28 Providing and fixing in position 12 mm thick bitumen impregnated fibre board conforming to IS: 1838, including cost of primer, sealing compound in expansion joints.
10.25.2 Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
OD64596/2024-2025 Providing & Grouting of dowel tubes / Shear keys / Joints of precast members with M-60 grade cementitious grout (Non Shrink) of approved make by suitable means ( Free flowing /pump),curing etc. Complete as per directions of Engineerincharge. (The payment shall be made on the basis of actual weight of approved grout injected.) 26.80.1 Stirrer mixed cementitious grout (non shrink) of approved make in dowel tubes / Shear keys / Joints of precast members.
OD64598/2024-2025 Providing and applying protective primer coating of BARGUARD TMT of Redwop or similar over steel reinforcement as per direction of Engineer-in-charge. The product shall be applied on reinforcement steel after thoroughly cleaning. painted area of steel shall be considered for payment.
OD64597/2024-2025 Fixing mild steel round holding down bolts of all diameter with nuts and washer plates in line and level complete supplied by KMML in columns & foundations as per issued drawing and direction of engineer in charge.
I SAFARUDEEN (BID ID -2166622)
KURIAN KOSHY (BID ID -2166678)
Santhi constructions (BID ID -2166513)
M ABDULSHUKKOOR (BID ID -2166720)
Bidder Name
Santhi constructions
KURIAN KOSHY
Amrita builders
I SAFARUDEEN
M ABDULSHUKKOOR
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .