| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.4 CrAccepted-AOC | ₹5.4 Cr Quoted ₹5.8 Cr | L1 | Accepted-AOC The Loewst Negotiated tender of M/s Sekar Constructions Thiruvannamalai has been approved by the Commissionerate of Tenders,Chennai |
| 2 | L2₹6.0 Cr+₹22.0 L (3.81%)Rejected-AOC | ₹6.0 Cr+₹22.0 L (3.81%) | L2 | Rejected-AOC Highest Bid |
| 3 | Rejected-Technical 21 A 2ND STREET ARULANANDA AMMAL NAGAR THANJAVUR 613007 | THANJAVUR | TAMIL NADU | 613007 | - | - | Rejected-Technical not fulfil the technica qualication |
Tender Value
₹5.2 Cr
EMD Value
₹2.7 L
Closing Date
13 Jul 2020, 11:00 amClosed
Superintending Engineer (H) Proj Circle, Thanjavur
Superintending Engineer (H) - Projects Circle, No1 South Street, Ganapathy Nagar, MC Road, Thanjavur 613001
Construction of Bridge at KM 4.10 of Kalagam-Avudaiyar Koil road (MDR 603) across Poonaikuthi River
2020_HWAY_168028_2
Tn.No. 01 2020-21
Open Tender
Civil Works - Bridges
Item Rate
456 days
Trichy
As Per PQ Document
7 documents required · 7 mandatory
₹0
₹2.7 L
Thanjavur
7 Nov 2020
12 Jun 2020
15 Jul 2020
12 Jun 2020
13 Jul 2020
23 Jun 2020
18 Jun 2020
Amount
MAINBRIDGE
Earthwork excavation in all classes of soil, except rock, not requiring blasting and depositing on bank with all leads and lifts as per SS20B, including all other incidential charges such as bailing out water, shoring, walling & forming protective bunds wherever necessary etc., complete as per relevant standard specification for DRESSING THE BED UPTO SILL LEVEL
Earthwork excavation in all classes of soil, rock not requiring blasting and depositing on bank, with all leads and lifts as per SS20B, including cost of all labour, equipments and all other incidential charges such as bailing out water, providing and maintaining necessary cofferdams sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps and other deleterious matter and obstructions, trimming bottom of excavation backfilling and clearing the site and disposal of all surplus materials etc., complete for PILE CAP UNDER PIERS AND ABUTMENTS FOR FOUNDATION as per Section 300 of MORT & H specifications (V revision)
Providing and driving in position permanent M.S steel liners 6mm thickness for piles from bottom of pile cap as per cl. 709.1.4 of IRC 78 2014 (upto the maximum scour level for estimate purpose) including cost of liners and fabricating, welded construction with consumable, labour and plants and driving M.S liners 6mm thick to be left peramnently with the pile shaft as per the requirement and as per the requirement and as per standard specifications, and placing them in position with all leads and lifts etc., complete as per section 1100 & 1000 of MORT&H specification (V revision)
providing Reinforced cement concrete cast-in-situ bored piles of 1200 mm diameter in RCC M-35 (Design mix) using 20mm ISS HBG metal with minimum cement content of 400kg per cu.m maximum water cement ratio of 0.4 and slump of 150 - 200mm by tremie concreting including cost and conveyance of all materials to site and cost of cement at site but excluding cost and fabrication of steel and placing it in position before concreting setting up of piling equipment, shifting the same from one pile location to another pile location dismantling and including all labour for boring through rock leading the excavated material to a distance 200m including forming of working plaltform over the river bed for accommodating piling equipment forming approaches to the working platform, mixing concrete, filling it in position by tremie pipe, cutting of pile head to cut off level for casting pilecap, including diversion of water course if necessary and all other incidental charges tec., complete as per standard specifications, forming and maintaining protective bunds and all other incidental charges etc., complete for PILES BELOW PIERS AND ABUTMENTS as per section 1100 & 1700 of MORT&H specification (V revision)
Plain Cement Concrete M15 using 40mm ISS metal including cost and conveyance of all materials to site and cost of cement at site including soft water, labour charges for mixing, transporting, laying compacting curing concrete, Tools and Plants and incidental charges such as bailing out water, maintaining of protective bunds, cofferdams, shoring, strutting etc; complete for LEVELLING COURSE BELOW PILECAPS OF PIERS AND ABUTMENTS as per section 1100 of MORT&H specification (V revision)
Vibrated Reinforced cement concrete of grade M35 (Design Mix) using 20 mm ISS HBG graded metal including cost and conveyance of all materials to site excluding cost of steel including cost of form work, soft water labour charges for mixing, transporting, laying and curing concrete, working at depths, Tools and plants, incidental charges such as bailing out water, maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for PILE CAPS UNDER PIERS AND ABUTMENTS as per section 1100, 1500 & 1700 of MORT & H specification (V Revision)
Vibrated Reinforced cement concrete of grade M35 (Design Mix) using 20 mm graded ISS HBG metal including cost and conveyance of all materials to site excluding cost of steel including cost of form work, soft water labour charges for mixing, transporting, laying and curing concrete, working at depths, Tools and plants, incidental charges such as bailing out water, maintaining of protective bunds, cofferdams, shoring, strutting etc., complete for SUBSTRUCTURE OF ABUTMENTS AND RETURNS as per section 1500, 1700 & 2200 of MORT&H specification (V Revision)
Vibrated Reinforced cement concrete of grade M35 (Design Mix) using 20 mm ISS graded metal including cost and conveyance of all materials and cost of cement to site but excluding cost and fabrication of steel but including soft water labour charges for mixing, transporting, laying and curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges etc., complete for BED BLOCK CUM DIRT WALL as per 1500, 1700 & 2200 of MORT&H SPECIFICATIONS (V Revision)
Vibrated Reinforced cement concrete of grade M-35 (Design Mix) using 20 mm ISS HBG graded metal including cost and conveyance of all materials and cost of cement to site but excluding cost and fabrication of steel but including soft water, labour charges for mixing, transporting, laying and curing concrete. working at heights, hire charges for tools and plants, including all other incidental charges, etc., complete for CIRCULAR PIERS (1800 mm dia) as per section 1500, 1700 & 2200 of MORT&H specification (V revision)
Vibrated Reinforced cement concrete of grade M35 (Design Mix) using 20 mm ISS HBG graded metal including cost and conveyance of all materials and cost of cement to site but excluding cost and fabrication of steel but including soft water, labour charges for mixing, transporting, laying and curing concrete. working at heights, hire charges for tools and plants, including all other incidental charges, etc., complete for CAPPING BEAM OVER PIERS as per section 1500, 1700 & 2200 of MORT&H specification (V revision)
Vibrated Reinforced cement concrete of grade M35 (Design Mix) using 20 mm ISS HBG graded metal including cost and conveyance of all materials and cost of cement to site but excluding cost and fabrication of steel but including soft water, labour charges for mixing, transporting, laying and curing concrete. working at heights, hire charges for tools and plants, including all other incidental charges, etc., complete for PEDESTAL OVER ABUTMENT AND PIERS as per section 1500, 1700 & 2200 of MORT&H specification (V revision)
Supply and fixing of ELASTOMERIC BEARING of size 400x300x80mm including cost and conveyance to work site, labour for fixing the bearing in position and all other incidental charges etc., complete as per section 2000 of MORT&H specifications (V Revision) and IRC: 83 - 2015 (part - II)
Vibrated Reinforced cement concrete of grade M35 (Design Mix) using 20 mm ISS HBG graded metal including cost and conveyance of all materials to site and cost of cement at site, but excluding cost and fabrication of steel but including cost of form work, labour charges for mixing, transporting, laying curing concrete. working at heights, potable water, hire charges for tools and plants, including all other incidental charges, etc., complete for T-BEAMS and CROSS BEAMS as per section 1500, 1700 & 2300 of MORT&H specification (V revision)
Vibrated Reinforced cement concrete M35 (Design Mix) using 20 mm ISS HBG graded metal including cost and conveyance of all materials to site and cost of cement at site, but excluding cost and fabrication of steel but including cost of formwork, labour charges for mixing, transporting, laying curing concrete. working at heights, soft water, hire charges for tools and plants, including all other incidental charges, etc., complete for DECK SLAB, KERB & SAFETY KERB as per cl 1500, 1700 & 2300 of MORT&H specification (V revision)
Vibrated Reinforced Cement Concrete M40 (Design Mix) using 20mm ISS HBG metal as the max. size of coarse aggregate, as including cost and conveyance of all materials to site and cost of cement at site but excluding cost and fabrication of steel but including cost of formwork, labour charges for mixing, transporting, laying, curing concrete. working at heights, potable water, hire charges, for tools and plants, including all other incidental charges, etc.,complete for CRASH BARRIERS as per 811,1700 & 2703.3 of MORT&H Specifications (V Revision).
Supplying and installation of STRIP SEAL EXPANSION joint system conforming to specifications for Road and Bridge Works_Published by Ministry of Roads Transport and Highways in the 40mm wide expansion gap provided in between decks over piers and in between deck and dirt wall over abutment with fatigue tested structural steel section at the nosing and anchorage assembly, including cost and conveyance of all materials, cost of testing as per the MOST specifications, including labour, equipment and incidental charges for fixing the joints complete in all respects, as per section 2600 of MORT&H specifications (V Revision).
Providing and fixing of G.I. Drainage spouts 100mm dia as per GOI drawing SD/205 with grating arrangements at top as shown in the drawing 100mm dia drainage spout projecting atleast 300mm beyond the bottom of deck slab as shown in the drawing including cost and conveyance of Galvanised Iron pipes and flats and fixing them in position etc., complete as per cl 2705 of MORT&H specification (V revision)
Vibrated Cement Concrete M15 (Nominal Mix) using 40mm ISS HBG metal including cost and conveyance of all materials to site and cost of cement at site including all labour charges for mixing concrete, laying, hire charges for tools and plants, compacting, curing with all leads for soft water, including all other incidental charges, form work etc., complete for SAFETY KERB RAMP ADJACENT TO APPROACH SLAB, BASE COURSE BELOW APPROACH SLAB AND KERB RAMP as per cl 1500, 1700 & 2704 of MORT&H specification (V Revision)
Vibrated Reinforced Cement Concrete M30 (Design Mix) using 20mmISS HBG metal including cost and conveyance of all materials to site and cost of cement at site but excluding cost and fabrication of steel but including labour charges for mixing, laying, curing concrete, working at heights, soft water, hire charges for tools and plants, including all other incidental chages etc., complete for APPROACH SLABS as per section 1500, 1700 & 2704 of MORT&H specification (V revision)
Vibrated Cement Concrete M30 (Design Mix) using 75mm uniform thick with surface reinforcement conforming to section 2702.2 of MORTH 5th revision, using ISS HBG graded metal, including cost and conveyance of all materials to work site including cement at site, including all labour charges for mixing concrete, laying, hire charges for tools and plants, compacting, curing with all leads for potable water, including all other incidental charges, formwork, complete for WEARING COAT over DECK SLAB AND APPROACH SLAB as per cl 2702.2 of MORT&H specification (V Revision)
Vibrated Cement Concrete M15 (Nominal Mix) using 40mm ISS metal, including cost and conveyance of all materials to site and cost of cement at site including cost of formwork, labour charges for mixing, transporting, laying, and curing concrete, soft water, tools and plants, and incidental charges,etc.,complete as per relevant standard specification for PARAPET OVER RETURN WALLS as per section 1500 & 1700 of MORT&H Specifications (V Revision).
Providing and fixing CLASS 1 PVC SEEPAGE PIPES of 100mm dia. of required lengths for abutments and returns including costs and conveyanace of all materials to work site and labour charges for fixing etc., complete to drain of the backfill as per section 2706 of MORT&H specifications (V revision)
Providing FILTER MEDIA behind the abutments and returns for 600mm thickness using filter material conforming to clause 309.3.2.B of MORTH well packed with smaller size towards the soil and bigger size towards the wall including cost and conveyance to work site including all labours and other incidental charges. etc., complete as per Cl. 710.1.4 & Appendix 6 of IRC: 78-2014.
Filling behind Abutments and Returns as per Appendix 6 of IRC: 78-2014 with clean gritty free draining material including cost and draining material having Phi value more than 35° conveyance of material to worksite, laying, handling charges and filling in layers tamping under optimum moisture content to get the maximum density, including watering, with all leads for water and all other incidental charges, etc., complete as per cl 710.1.4 & Appendix 6 of IRC 78-2014.
Supply and Fabrication of Fe-500 steel required for all RCC items of works involved in the schedule including cost of steel at site and cost of fabrication, Anticorrosive treatment with fusion bonded epoxy coating, labour charges for cleaning the rods straightening, cutting, bending, tying grills, including overlaping to the required length wherever necessary and providing reinforcement placing the reinforcement in position as specified in the drawings, including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc, complete as per sec 1800 of MORT&H specification (V revision)
Supply and fabrication of Fe-240 steel required in the schedule including cost of steel at site cost of providing and cost of fabrication, providing Anticorrosive treatment with fusion bonded epoxy coatingfor steel, labour charges for cleaning the rods straightening, cutting, bending, tying grills, including overlapping to the required length whenever necessary and providing to the reinforcement, placing the reinforcement in position as specified in the drawings including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc,complete, as per cl 1600 of MORT & H specification (V revision)
Supply and fixing of High Quality of PVC pipes of 150mm dia. Including cost and conveyance of pipes to the site and fixing in position to prpoer grade and level, including labour charages for fixing and including all other incidental charges etc complete., for providng utility services in footpaths.
SUB WORK-Box culvert on Kalagam side Earth work excavation in all classes of soils such as hard rock requiring blasting and depositing on bank with all leads and lifts as per SS 20B including cost of all labour materials, tools, equipments and all incidental charges and sheeting, shoring and bracing and their subsequent removal, removal of all logs, stumps and other deleterious matter and obstructions, trimming of bottom of excavaion back filling, clearing up the site and disposal of all surplus materials etc., complete as per standard specification FOR BOX CULVERT.
Vibrated plain cement concrete M15 using ISS graded hard granite broken metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but transporting, placing in position vibrating and compacting finishing and curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges etc., complete as per standard specification for LEVELLING COURSE BELOW BOX CULVERT.
Vibrated reinforced cement concrete M25(Design mix) using ISS graded hard granite broken metal including cost and conveyance of all materials to site and cement at site excluding cost and fabrication of steel but transporting, placing in position vibrating and compacting finishing and curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges etc., complete as per standard specification for BOX CULVERT.
Vibrated reinforced cement Concrete M-40, Grade, Design Mix, using 20mm & 12mm ISS size hard granite broken graded metal including cost and conveyance of all materials to site including cement at site including labour charges for mixing, transporting, laying, and curing concrete,working at heights,hire charges for tools and plants,including all other incidental charges,etc, complete for RCC CRASH BARRIER over Box culvert.
Supply and fabrication of S-500 steel required for all RCC items of works involved in the schedule cost of steel at site fabrication, providing Anticorrosive treatment with fusion bonded epoxy coating for steel , labour charges for cleaning the rods straightening, cutting, bending, tying grills, including overlapping to the required length whenever necessary and placing the reinforcement in position as specified in the drawings, including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc,complete, as per section 2706 of MORT&H Specifications (Fifth Revision-2013).
Sub work of (a) Approach Road and (b) DiversionRoad Work Earth work excavating and depositing on bank with initial lead of 10 m & initial lift of 2m in Hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS20B.(a) Approach Road 320.00cum
Filling with Carted earth within an average lead of 5 km from available source for forming embankment including conveyance of earth to site, spreading the earth uniformly to the entire embankment formation in layers of not exceeding 250 mm thick as directed by the department officers including compacting each layer to the required density in accordance with IS 2720 part VII at 95% Proctor density upto sub grade level and shoulders keeping the moisture content of earth at the time of compaction within the range of 1% above and 2% below the OMC determined and plasticity index value of not more than 20 and liquid limit not greater than 40 in accordance with IS 2720 using required capacity rollers to achieve the required density in each layer including watering with all leads for water and finishing the surface to the lines and grades ,sections as directed by the departmental officers and including hire charges and running charges for the roller and all other tools and plants employed for the work and all labour charges widening of embankment including compacting the original ground with power roller etc., complete. (a) Approach Road Work-1080.00cum (b) Diversion Road -545.00cum.
Providing and laying Carted earth within an average lead of 5 km from available source, including cost and conveyance of earth to worksite,seniorage charges, laying, handling charges and filling in layers, including all leads for water and all other incidental charges etc.complete as directed by the Engineer for forming the shoulders as per MORTH No.111,112,305,900 for Forming approach road for 97% Compaction. (b) Diversion Road -992.00.cum
Filling with Gravel having CBR not less than 8 for forming embankment including conveyance of earth to site, spreading the earth uniformly to the entire embankment formation in layers of not exceeding 250 mm thick as directed by the department officers including compacting each layer to the required density in accordance with IS 2720 part VII at 97% Proctor density upto sub grade level and shoulders keeping the moisture content of earth at the time of compaction within the range of 1% above and 2% below the OMC determined and plasticity index value of not more than 20 and liquid limit not greater than 40 in accordance with IS 2720 using required capacity rollers to achieve the required density in each layer including watering with all leads for water and finishing the surface to the lines and grades ,sections as directed by the departmental officers and including hire charges and running charges for the roller and all other tools and plants employed for the work and all labour charges widening of embankment including compacting the original ground with power roller etc., complete (a) Approach Road Work-1076.00cum
Supply of NP 3 class RCC 1000 mm dia. pipes supplied by the Contractor at his own cost specified below confirming to IS 458 / 1989 cost of pipe as a finished work including all other incidental charges, testing charges including loading and unloading transport and delivery in good condition at work site as directed by the departmental officers etc., complete. (b) Diversion Road -340.00 rm
Hoisting and Fixing of 1000 mm dia. NP 3 pipes and collars to proper gradient including all Labour charges and all other incidental charges etc., Complete. (b) Diversion Road -340. 00 Rm
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401(a) Approach Road Work-357.50cum (b) Diversion Road -216.50cum
Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 250 mm thick specification including premixing the materials with water at OMC in mechnanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5 (a) Approach Road Work-430.00 cum(b) Diversion Road -200.00cum
Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion Bitumen (SS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as perClause 502 of MORTH Rev-5. (a) Approach Road Work-1665.00sqm (b) Diversion Road -1238.00sqm
Providing and laying Tack Coat over WBM/ WMM surface (treated with primer) using 2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as perClause 503 of MORTH Rev-5 (a) Approach Road Work-1665.00sqm (b) Diversion Road -1238.00sqm
Providing and laying Tack Coat over Existing BT surface using 2 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as perClause 503 of MORTH Rev-5 (a) Approach Road Work-550.00sqm
Providing and laying 70mm consolidated thick Dense Bituminous Macadam using 0.24 cum of 26.50-13.20mm, 0..25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20 Kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the mix to uniform thickness of 70mm with paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 505 MORTH Rev-5 (a) Approach Road Work-119.00cum.
Providing and laying 50mm consolidated thick bituminous macadam using 0.20 cum fo 26.50-13.20mm, 0.43 cum of 13.20-2.36mm and 0.08 cum of 2.36mm & below size IRC metal with 37 Kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5 (b) Diversion Road -62.00cum
Providing and laying Bituminous Concrete to30/ 40 mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30 kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 (a) Approach Road Work-67.50cum (b) Diversion Road -37.50cum
Providing and laying of Gravel including cost and conveyance of the same to work site from approved quarry including stacking the same to departemental gauge for premeasurement including all labour charges for laying, spreading etc., complete and as directed by the departmental engineers for making up of low berms. (a) Approach Road Work-47.50 cum(b) Diversion Road -89.50cum
Sub Work -DISMANTLING EXISTING PIPED CAUSEWAY. -Dismantling salvaging and removal and disposing of resulting materials and back filling the resulting trenches and pits etc.,For Stone masonry in cement mortar.
Dismantling salvaging and removal and disposing of resulting materials and back filling the resulting trenches and pits etc.,For Plain Cement Concrete.
Dismantling salvaging and removal and disposing of resulting materials etc.,For RCC pipe 900mm and 600mm dia.
SUB WORK Providing Colour washing and Painting Painitng two coats with ready mix plastic emulsion paint with approved colour including priming coat over the cement surface complete including scrapping clean removal of dirt of parts including cost and conveyance of all materials to site, all labour for cleaning the surface,painting including form work for working in heights and all other incidental charges etc.,complete.
Painitng two coats with ready mix plastic enamel paint with approved colour including priming coat over the cement surface complete including scrapping clean removal of dirt of parts including cost and conveyance of all materials to site, all labour for cleaning the surface,painting including form work for working in heights and all other incidental charges etc.,complete.
Sub work Road Furniture Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes (Road Marking with hot applied thermoplastic compound with Reflectorising Glass beads on bituminous surface) etc complete as per MORTH specification 803
Providing and fixing reflective road studs of category A raised pavement markers made out of polycarbonate/methyl methercrylate/ABS moulded body confirming to ASTM D 788 and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face with retro-reflectance and chromaticity values conforming to ASTM D4280. The reflective raised pavement markers shall also confirm to the MORTH circular No RW/NH.33023/10/97-DO.III dt.11.06.97 and the length, height and width of the body shall not be less than 100 mm, 15 mm and 90 mm and with minimum reflective area of 13Sq.cm on each side and the slope to the base shall be 35+5 degree. Each reflector shall have a CIL not less than values specified in table 2 of said MORTH circular. The strength of detachment of the integrated cylindrical shanks, (of diameter not less than 19+/-2mm and height not less than 30+/-2 mm) from the body is to be a minimum value of 500kgf. Fixing will be drilling holes on the road for the shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturer's recommendation and complete as directed by the engineer. The marker shall support a load of 13635kg tested in accordance with ASTM D4280 and confirming to IRC 35- 2015 guidelines and MoRT&H specification 804 etc., complete
Providing and erecting of direction and place identification Retro -Reflectorised sign made out of High Intensity Prismatic Grade Sheeting conforming to type-IV standards of IRC 67:2012 and ASTM D 4956-09, Specification and fixed over 2mm thick Aluminium sheet fixed over a back supporting frame of 25mm x 25mm x 3mm Mild steel angle and supported on a mild steel angle post 75mm x 75mm x6mm with a clear height of not less than 2.10m from the ground level to bottom of sign board and 0.60m below ground level. The sign post should be painted as per IRC67-2012 and firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45cm x 45cm x 60cm size including cost and conveyance of all materials, equipment, machinery and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. High intensity Retro Reflectro sheet shall consis of minimum coefficient of retro reflection as per table 6.6 of IRC67-2012. The Retro-reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC67:2012. (as per MORT & H Specification No.801)
Providing and erecting of Retro -Reflectorised Cautionary, mandatory and Informatory signs(without definition board) made out of High Intensity Prismatic Grade Sheeting conforming to type-IV standards of IRC 67:2012 and ASTM D 4956-09, Specification and fixed over 2mm thick Aluminium sheet fixed over a back supporting frame of 25mm x 25mm x 3mm Mild steel angle and supported on a mild steel angle post 75mm x 75mm x6mm with a clear height of not less than 2.10m from the ground level to bottom of sign board and 0.60m below ground level. The sign post should be painted as per IRC67-2012 and firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45cm x 45cm x 60cm size including cost and conveyance of all materials, equipment, machinery and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. High intensity Retro Reflectro sheet shall consist of minimum coefficient of retro reflection as per table 6.6 of IRC67-2012. The Retro-reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC67:2012. (as per MORT & H Specification No.801) (60 cm circular board without definition board)
Providing and erecting of Retro -Reflectorised Cautionary, mandatory and Informatory signs(without definition board) made out of High Intensity Prismatic Grade Sheeting conforming to type-IV standards of IRC 67:2012 and ASTM D 4956-09, Specification and fixed over 2mm thick Aluminium sheet fixed over a back supporting frame of 25mm x 25mm x 3mm Mild steel angle and supported on a mild steel angle post 75mm x 75mm x6mm with a clear height of not less than 2.10m from the ground level to bottom of sign board and 0.60m below ground level. The sign post should be painted as per IRC67-2012 and firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45cm x 45cm x 60cm size including cost and conveyance of all materials, equipment, machinery and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. High intensity Retro Reflectro sheet shall consis of minimum coefficient of retro reflection as per table 6.6 of IRC67-2012. The Retro-reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC67:2012. (as per MORT & H Specification No.801) (90 cm equilateral triangular board without definition board)
Providing and Fixing of Retro - Reflectorised Hazard Marker Traffic Sign made made out of High Intensity Prismatic Grade Sheeting confirming to Type-IV standards of IRC-67: 2012 and ASTM D 4956 -09, specification and fixed over 2mm thick Aluminium sheet fixed over a back supporting frame of 25mmx25mmx3mm Mild Steel angle and supported on a mild steel angle post 75x75x6mm and 0.60m below ground level. The sign post should be painted as per IRC 67-2012 and firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45cmx45cmx60cm size including cost and conveyance of all materials, equipment, Machinery and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. High intensity Retro - Reflectro sheet shall consist of minimum coefficient of Retro - reflection as per Table 6.6 of IRC 67-2012. The retro - reflective sheeting shall be covered under 7 year warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC 67:2012. ( as per MORT&H Specification No.801)
Providing and Fixing of Rigid Median Marker double sided made of tough, high impact resistant, injection-molded, thermoplastic body with an isosceles trapezoidal structure of length, width and height not less than 15cm, 10cm and lOcm respectively and thickness not less than 1.8mm, the body structure shall be rounded at its acute angle, all the corners and edges. The plastic used for moulding the Median Marker shall have a minimum Notched lzod Impact strength value of 600 Jfm at room temperature, when tested in accordance with ASTM 0256 a nd shall retain at least 70% of this value when subjected to accelerated weathering for 1000hrs as per ASTM 0155 or UL746C. The logo of the manufacturer shall be embossed on either side of the body in the injection molding process. The Median Marker shall have rectangular-shaped, fluorescent yellow color retro-reflective sheeting of size not less than 8.5cm*8.5cm and with fully reflective micro prismatic cube corners as its retroreflective elements as per IRC 67 2012 and ASTM 04956-09 type xr specifications reflectivity values. The retro-reflective sheeting shall be both sides of the Median Marker and shall be edge protected with no exposed edges which will prevent edge lifting, vandalism, sheeting damage, etc. The Median Marker shall be flxed by a combination of epoxy grouting.
Calculation of SubTotal, GST and Total carried out by system automatically
Sub Total Amount for above all items
GST 12% for the above SubTotal Amount
APU CONSTRUCTIONS
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .