Tender Value
₹57.0 L
EMD Value
₹1.1 L
Closing Date
2 Sept 2026, 3:00 pm6d left
Executive Engineer, Div-II, AMC
O/O the Executive Engineer, Div-II, AMC
Construction of RCC drain with cover slab from the H.O Kanai Bihari Banik to Sitala Bari to H.O Partha Das near Saiba Sangha Club at Jagatpur, under ward no.05, AMC
2026_SAMC_76261_1
28/Div-II/AMC/2026-27
Open Tender
Civil Works
Percentage
120 days
Ward No. 05, AMC
Please refer Tender documents.
4 documents required · 4 mandatory
₹4,000
₹1.1 L
24 Aug 2026
24 Aug 2026
2 Sept 2026
24 Aug 2026
2 Sept 2026
24 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.-All kinds of soil. | - | Cum | 231.6 | - |
| 2 | Supplying and filling in plinth, under floor, foundations etc. with sand (fine) from local quarry with all lifts including spreading in horizontal layers, watering, grading to required slope, ramming, consolidating and compacting each layer by using plate compactor or by any suitable method complete. | - | Cum | 1,177.3 | - |
| 3 | Providing and laying in position cement concrete of
specified grade excluding the cost of centring and
shuttering --All work upto plinth level: 1:3:6 ( 1 Cement: 3 fine sand : 6 graded well burnt brick
aggregate 20 mm nominal size) | - | Cum | 9,938.6 | - |
| 4 | Providing and laying dry flat brick flooring in required pattern complete. | - | Sqm | 701.2 | - |
| 5 | Filling available excavated earth (excluding rock) in
trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.-All kinds of soil | - | Cum | 161.3 | - |
| 6 | Centering shuttering including struttings, propping etc. and removal of form work for: Foundations, footings, bases for columns etc. for mass
concrete with timber plank | - | Sqm | 333.9 | - |
| 7 | Centering shuttering including struttings, propping etc. and removal of form work for: Walls (any thickness) including attached pilasters,
buttresses, plinth and string courses etc. using shuttering ply | - | Sqm | 496.1 | - |
| 8 | Providing structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete as required. | - | Kg | 109 | - |
| 9 | Providing and laying in position cement concrete of
specified grade excluding the cost of centring and
shuttering --All work upto plinth level: 1:2:4 ( 1 Cement: 2 fine sand : 4 graded stone aggregate
20 mm nominal size) | - | Cum | 11,355.7 | - |
| 10 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or
more | - | Kg | 103.9 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.52 MB
DNIet28.pdf
Tender Documents • 2.91 MB
BOQ_77632.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].