Loading…
Loading…
Tender Value
₹17.6 L
EMD Value
₹35,300
Closing Date
17 Oct 2026, 12:00 pm
Executive Engineer
Room No.48 Vikas Bhawan Rampur
Construction of a CC road and drain from the house of Padam Singh Maurya towards the house of Dr. Nirpal Maurya in Village Bijarkhata.
2026_REDUP_1191845_3
998 /RED/Tender/ Bond Clerk/2026-27 Dated - 18.09.2026
Open Tender
Civil Works
Percentage
90 days
Rampur
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
₹35,300
1 Oct 2026
1 Oct 2026
17 Oct 2026
1 Oct 2026
17 Oct 2026
1 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in foundation in ordinary soil including lift upto 1.5 mts and lead upto 30 mts &including filling ,watering and ramming of excavated earth in to the trenches or into the space between the sides of foundations.S.I. No-251 | 29.58 | Cum. | 190 | ₹5,620.2 |
| - | Concrete with 4 cm. gauge brick ballast, fine sand of 1.25 F.M. and cement in proportion of 8:4:1 in foundations including supply of all materials, labour and T & P etc. required for proper completion of work.S.I. No-275 | 22.18 | Cum. | 3,847.5 | ₹85,337.55 |
| - | M 150 brick work in 1 :4 cement and C. sand of 2.25 F.M. mortar in foundation and plinth including supply of all materials, labour and T & P etc. required for proper completion of work.S.I. No-305 | 52.8 | Cum. | 4,854.5 | ₹2,56,317.6 |
| - | PCC Cement Concrete with 2 cm gauge Stone grit (Crushed) approved coarse sand and cement in proportion of 4:2:1 including supply of all material labour and T&P etc. required for proper completion of work.S.I.No-279(a) | 10.26 | Cum. | 7,220 | ₹74,077.2 |
| - | 12mm thick plaster with one part of cement and four part of approved coarse sand over brick work minimum thickness not to be less than 1Cm. Including supply of all materials labour and T&P etc. required for proper completion of the work.S.I.No-584 | 280.5 | Sqm. | 193.8 | ₹54,360.9 |
| - | Concrete with 4 cm. gauge approved stone ballast, coarse sand and cement in proportion of 12 :6 :1 in foundations and sub base of Concrete road slab including supply of all materials, labour and T & P etc. required for proper completion of work.S.I.No-273(a) | 53.84 | Cum. | 4,697.75 | ₹2,52,926.86 |
| - | Cement Concrete with 2 cm. gauge approved stone grit, approved coarse sand and cement in proportion of 4:2:1 in pavement for c.c. road coarse sand fine aggregate confirming to IS stnadard mixed in comcrete mixture/Plant of not less then 0.2 cum capacity & appropriate weight batcher using approved mix design, laid in approved fixed form work (steel channel) laying and fixing of 125 micron thick polythene film, wedges, steel plates including leveling the form work spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continous operation including hassion cloth for curring of concrete pavements for not less then 14 days curring compound (where as specified) and water finishing to lines & grade including supply of all material, labour, tools & plants etc. required for proper completion of work and also including complete shifting of material & concrete etc.&S.I.-CH-20 NI-3 | 107.69 | Cum. | 6,745 | ₹7,26,369.05 |
| - | Making Expansion / construction joints of required width and depth using cutter machin or by any means and filling the same by suitable flexible materials required for proper completion of work.& As per S.I. -CH-20 NI-5 | 215.37 | Rmt | 36.1 | ₹7,774.86 |
| - | R.C.C work with cement, appoved coarse sand and 2 c.m. gauge approved stone grit in proportion of 1:2:4 in slabs, including supply of all meterial, T&P etc requried for proper comptetion of work .As per S.I. No.-283 | 1.85 | Cum | 7,647.5 | ₹14,147.88 |
| - | Mild steel (Tor steel) in plain work such as reinforced concrete or reinforced brick work including bending for proper shape and supply of all steel and wastage & all cost of Complete.As per S.I. No.-504 | 1.23 | Qtl | 7,790 | ₹9,581.7 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.20 MB
BOQ_2248857.xls
BOQ • 0.25 MB
T-1.pdf
Tender Documents • 1.39 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .