| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹57.1 LAccepted-AOC | L1 | Accepted-AOC L1 bidder | |
| 2 | L2₹57.9 L+₹85,250 (1.49%)Rejected-Finance 46 TARDEO AIR CONDITION MARKET 2ND FLOOR TARDEO MAIN ROAD MUMBAI 400 034 | MUMBAI | MUMBAI | MAHARASHTRA | 400034 | L2 | Rejected-Finance L2 bidder |
Tender Value
₹53.2 L
EMD Value
₹50,000
Closing Date
21 Feb 2024, 3:00 pmClosed
The Chief Engineer, Sports Kerala Foundation
Jimmy George Indoor Stadium, Vellayambalam, Thiruvananthapuram
Modernization of Swimming Pool at Jimmy George Sports Hub, Thiruvananthapuram- Leak Rectification of Pool-Retender
2024_SKF_652984_2
170/SKF/CE/2023-24
Open Tender
Civil Works - Others
Item Rate
60 days
Thiruvananthapuram
Please refer Tender documents.
6 documents required · 6 mandatory
₹2,950
₹50,000
6 May 2024
13 Feb 2024
23 Feb 2024
13 Feb 2024
21 Feb 2024
13 Feb 2024
Amount
Demolishing
od323115/2023_2024 : Dismantling tile work in floors and walls laid in cement mortar including stacking material within 50 metres lead.<br>For thickness of tiles 10 mm to 25 mm (Based on DSR 15.23.1)
15.2.1 : Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
Rectification
26.31.2 : Providing, mixing and applying bonding coat of approved adhesive on chipped portion of RCC as per specifications and direction of Engineer-In-charge complete in all respect.Epoxy bonding adhesive having coverage 2.20 sqm/kg of approved make
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
5.2.2 : Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.6.4.1 : Hollow block masonry using pre cast blocks (Factory made) of size 40x20x20cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth with thickness 20cm and above in: CM 1:6 ( 1 cement : 6 coarse sand ) etc complete
22.23.1 : Providing and applying integral crystalline slurry of hydrophilic in nature for waterproofing treatment to the RCC structures like retaining walls of the basement, water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels / subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts integral crystalline slurry : 1 part water) for horizontal surfaces and applying the same from negative (internal) side with the help of synthetic fiber brush. The material shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing permeability of concrete by more than 90% compared with control concrete as per DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The crystalline slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work shall be carried out all complete as per specification and the direction of the engineerin- charge. The product performance shall carry guarantee for 10 years against any leakage.For vertical surface two coats @0.70 kg per sqm
22.23.2 : Providing and applying integral crystalline slurry of hydrophilic in nature for waterproofing treatment to the RCC structures like retaining walls of the basement, water tanks, roof slabs, podiums, reservior, sewage & water treatment plant, tunnels / subway and bridge deck etc., prepared by mixing in the ratio of 5 : 2 (5 parts integral crystalline slurry : 2 parts water) for vertical surfaces and 3 : 1 (3 parts integral crystalline slurry : 1 part water) for horizontal surfaces and applying the same from negative (internal) side with the help of synthetic fiber brush. The material shall meet the requirements as specified in ACI-212-3R-2010 i.e by reducing permeability of concrete by more than 90% compared with control concrete as per DIN 1048 and resistant to 16 bar hydrostatic pressure on negative side. The crystalline slurry shall be capable of self-healing of cracks up to a width of 0.50mm. The work shall be carried out all complete as per specification and the direction of the engineerin- charge. The product performance shall carry guarantee for 10 years against any leakage.For horizontal surface one coat @1.10 kg per sqm.
od318650/2023_2024 : Providing and fixing pool tile 200x100mm in customize design as per direction of Engineer-in-charge. The tiles to be fixed on the wall surface with the help of approved adhesive applied at the rate of 2.5 kg per sqm and grouting of the same. The rate is inclusive of all operation, material and required pattern approved by Engineer-in-charge.
od318653/2023_2024 : Epoxy Grouting the joints of pool tiles having joints of 3 mm width, using stain free pool epoxy grout mix Resin(Part A), Hardener (Part B), and colored filler powder (Part C)(0.25 kg of Resin & hardener and 0.75 kg of filler per kg), including filling/grouting and finishing complete as per direction of Engineer-in-charge.
11.55.1 : Providing and laying flamed finish Granite stone flooring in required design and patterns, in linear as well as curvilinear portions of the building all complete as per the architectural drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white cement slurry admixed with pigment of matching shade including rubbing, curing and polishing etc. all complete as specified and as directed by the Engineer-in-Charge :Flamed finish granite stone slab Jet Black, Cherry Red, Elite Brown, Cat Eye or equivalent.
8.3.2 : Providing edge moulding to 18 mm thick marble stone counters, vanities etc., including machine polishing to edge to give high gloss finish etc. complete as per design approved by Engineer -in-Charge.Granite work
50.18.8.9.1 : Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes with one step PVC solvent cement and testing of joints complete as per direction of Engineer-in-Charge. Concealed work, including cutting chased and making good the wall etc. 110 mm pipe 6kgf/cm2
od319074/2023_2024 : Supply of White ABS plastic bottom inlet with S.S. screws. and regulable flow in pool as per the direction of Engineer in charge.
Chlorination Engineering
Bidder Name
M ASHARAF
Chlorination Engineering
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1017773.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .