Tender Value
₹21.8 L
EMD Value
₹22,000
Closing Date
16 Sept 2026, 6:00 pm
Executive Engineer, Petlad Irrigation Division Petlad
Construction Box Type V.R.B. in place of damaged Pipe V.R.B at Ch.690 m on Changada Sub lateral Drain.
339057
06 of 2026-27
Open
Miscellaneous Works
Works
Anand
12 documents required · 9 mandatory · 3 optional
₹900
Executive Engineer Petlad Irrigation Division Petlad
₹22,000
29 Aug 2026
29 Aug 2026
29 Aug 2026
16 Sept 2026
29 Aug 2026
Bill Of Quantities
Memorandum showing items of works to be carried out
NAME OF Construction Box Type V.R.B. in place of damaged Pipe V.R.B at Ch.690 m on
WORK : Changada Sub lateral Drain.
Quantit Estimated rate
SR. estimat accoarding to
Item of work Rs. in Rs. in Unit
No. ed but estimated
may be figs. words quantities
ITEM NO :- 1 Dismantling the existing R.C.C.
Pipes including sorting out and stacking of the Rs. Eight
useful materials of the following diameters Hundred
1 10.00 including refilling the trenches etc. complete as 866.40 Sixty Six & RMT
directed. NP_2 pipes. 600 mm. to 900 mm. Forty Paise
ITEM NO :- 2 Dismantling the existing brick Rs. Seven
masonry including sorting out and stacking the Hundred
2 12.00 useful material and removing the debris and 750.90 Fifty & CM
making good the damages etc. complete as Ninety Paise
directed. In Cement Mortar Only
ITEM NO :- 3 Excavation for foundation in all
sorts of soil including yellow sandy gravelly soils
,soft & hard murrum etc. in dry condition Rs. One
including depositing the excavated stuff in Hundred
3 315.00 uniform layers in banks or as and where directed 107.80 Seven & CM
etc. complete for lead upto 500 m and all lift.(BY Eighty Paise
MACHINERY) Including dewatering. Only
ITEM NO :- 4(A) Providing & Laying in position
"DESIGN MIX" cement concrete using cement
sand and crushed aggregate for C.C./ R.C.C
work by "FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator, Rs. Four
curing as directed with all lead & lift etc complete Thousand
4 34.00 without dewatering and excluding the cost of 4012.50 Twelve & CM
steel reinforcement. (A) For Footing of column / Fifty Paise
Abutment / Pier / Bottom slab of barrel / Plinth Only
course / Coping/Approach slab etc. (b) Concrete
grade M-15 and MSA-40 mm
ITEM NO :- 4(B) Providing & Laying in position
"DESIGN MIX" cement concrete using cement
sand and crushed aggregate for C.C./ R.C.C
work by "FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator, Rs. Four
curing as directed with all lead & lift etc complete Thousand
4 27.00 without dewatering and excluding the cost of 4190.00 One CM
steel reinforcement. (A) For Footing of column / Hundred
Abutment / Pier / Bottom slab of barrel / Plinth Ninety Only
course / Coping/Approach slab etc. (a)
Concrete grade M-15 and MSA-20 mm
ITEM NO :- 4(C) Providing & Laying in position
"DESIGN MIX" cement concrete using cement
sand and crushed aggregate for C.C./ R.C.C
work by "FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator, Rs. Four
curing as directed with all lead & lift etc complete Thousand
5 44.00 without dewatering and excluding the cost of 4651.00 Six Hundred CM
steel reinforcement. (A) For Footing of column / Fifty One
Abutment / Pier / Bottom slab of barrel / Plinth Only
course / Coping/Approach slab etc. (e)
Concrete grade M-25 and MSA-20 mm
ITEM NO :- 4(D) Providing & Laying in position
"DESIGN MIX" cement concrete using cement
sand and crushed aggregate for C.C./ R.C.C
work by "FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator, Rs. Four
curing as directed with all lead & lift etc complete Thousand
without dewatering and excluding the cost of Three
steel reinforcement. (B) For Pier and Abutments Hundred
/ Wing wall / Head wall / Return wal/Dowel wall Forty Four
etc. (e)Concrete grade M-15 and MSA-40 mm Only
ITEM NO :- 4(E) Providing & Laying in position
"DESIGN MIX" cement concrete using cement
sand and crushed aggregate for C.C./ R.C.C
work by "FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator, Rs. Five
curing as directed with all lead & lift etc complete Thousand
7 51.00 without dewatering and excluding the cost of 5642.00 Six Hundred CM
steel reinforcement. (E) For Column / Beam / Forty Two
Solid Slab of Road Bridge / Barrel / Cutoff wall Only
etc.(q) Concrete grade M-25 and MSA-20 mm
ITEM NO :- 4(F) Providing & Laying in position
"DESIGN MIX" cement concrete using cement
sand and crushed aggregate for C.C./ R.C.C
work by "FLORI" including necessary formwork, Rs. Five
centering, scaffolding, compaction by vibrator, Thousand
curing as directed with all lead & lift etc complete Four
8 10.00 without dewatering and excluding the cost of 5481.00 CM
steel reinforcement. (D) For Kerb / Wearing Eighty One
coat.(n) Concrete grade M-25 and MSA -10 to Only
ITEM NO :- 4(G) Providing & Laying in position
"DESIGN MIX" cement concrete using cement
sand and crushed aggregate for C.C./ R.C.C
work by "FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator, Rs. Eight
curing as directed with all lead & lift etc complete Thousand
9 2.00 without dewatering and excluding the cost of 8023.00 CM
steel reinforcement. (F) For Perapet wall of Road Three Only
Bridge / Structure (t)Concrete grade M-25 and
MSA -10 to 20 mm
ITEM NO :- 5 Providing & Placing in position
reinforcement bars including cutting, bending,
welding joints where necessary, hooking etc.
10 92.95 complete as per drawing for all lead and lifts.TMT 7194.00 Qtl
/ CRS (FE 500 D)
ITEM NO :- 6 Providing and fixing 110 mm Rs. Three
diameter P.V.C.Pipe (6 kgf / sqcm) Water spout Hundred
11 4.00 with necessary iron gratting as per design 369.20 Sixty Nine & RMT
ITEM NO :- 7 Providing and laying in position
110 mm dia (6 kgf/sqcm) P.V.C. Pipe for weep Rs. Two
holes with non corroding jali in abutments, wing Hundred
12 12.00 walls, retaining walls etc. complete. 262.50 Sixty Two & RMT
ITEM NO :- 8 Providing & Laying in position
"NOMINAL MIX" cement concrete using cement,
sand and crushed aggregate by mass and
machine mix for C.C./R.C.C work incl. necessary Rs. Three
formworks centering, scaffolding, compaction by Thousand
vibrator, curing as directed with all lead & lift etc Three
13 62.00 complete Without Dewatering and excluding cost 3346.00 CM
of steel reinforcement.(A) For Foundation Forty Six
concrete / General purpose. (a) C. C. Nominal Only
Mix, M-10 and MSA-40 mm
ITEM NO :- 9 Providing temporary all weather
and fair weather drain diversion suitable for Rs. Two
drain water during the construction period of the Thousand
14 20.00 structure including all safty measures including 2012.89 Twelve & RMT
red lamps/ signals at night for traffic etc. comp. Eighty Nine
ITEM NO :- 10 Providing temporary all weather
and fair weather diversion suitable for traffic Rs. Five
during the construction period of the structure Hundred
including all safty measures including red Seventy
lamps/ signals at night for traffic etc. comp Eight &
ITEM NO :- 11 Back filling the foundation
trenches around the structures etc with selected Rs. Thirty
16 63.00 excavated stuff including watering, ramming, 36.90 Six & Ninety CM
compacting etc. complete. (By Machinery) Paise Only
ITEM NO :- 12 Providing drone videography on
the occaion of function or for before/on
going/after completion of construction work
including dubbing , titeling etc. complete Rs. Four
17 1.00 including cost of cassette/CD 4000.00 Thousand
Rs. Twenty One Lacs Sevety Five Thousand Seven Hundred Seventy Six and Thirty Nine Paise
I / We am / are willing to carry out the work at………………..% above / below precent.
(Should be written in figure and words) of the estimate reates mentioned above.
Amount of my / our tender works out as under.
Estimated amount put Estimated amout put
to tender Rs……………. to tender RS
Deduct …………..% Add………………%
below Rs………… Above Rs……………
Net Rs……………….. Total Rs…………….
In words…………………………….. In words………………
Notes 1 - The Contractor shall exhibit a board with detailed specification and details of work as directed by the Engineer-In-Charge for
which no extra payment shall be made.
Notes 2 - The labour cess will be deducted as per prevailing rules i.e.1% of the work done.
Notes 3 - GST and Income tax TDS will be deducted at a source while making payments of bills
Note 4 - In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt.G.R.:PRC-10/2017 Cement
Consumption / 16 / CDate: 11/05/2017asstated in S.O.R. there fore in R.C.C. items where there is a change as per actual mix design the
cost of difference of cement consumption have been deducted from the rate of original item at the rate of input rate mentioned in all the
Signeture of Contractor Deputy Executive Engineer
Drain Sub Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1 Front Page.pdf
2 Notice Inviting online Tender.pdf
3.SBD-Documen .pdf
4 Item Technical Specification-.pdf
5. except item wise specification.pdf
9.1 Cemenr Consumption.pdf
9.2 BOQ.pdf
9.3 PE.pdf
1. Tender Notice 06 of 2026-27 pdf.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].