Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.8 LAccepted-AOC | ₹4.8 L | L1 | Accepted-AOC L1 |
| 2 | L2₹5.4 L+₹53,807.34 (11.1%)Rejected-AOC | ₹5.4 L+₹53,807.34 (11.1%) | L2 | Rejected-AOC L2 |
Tender Value
₹5.4 L
EMD Value
₹13,601
Closing Date
20 Jun 2024, 11:00 amClosed
Assistant Executive Engineer
PWD Special Buildings Sub Division Thrissur-680001
General Civil Work
2024_PWD_669645_3
74/AEE/SPL/2023-24
Open Tender
Civil Works - Buildings
Item Rate
120 days
Mulamkunnathukavu
9 documents required · 9 mandatory
₹1,200
₹13,601
17 Jul 2024
12 Jun 2024
22 Jun 2024
12 Jun 2024
20 Jun 2024
12 Jun 2024
Amount
Leach pit
2.32:Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.26.2:Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.Ordinary or hard rock
OD40570/2021-2022: Dry rubble with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement:6 coarse sand :12graded stone aggregate 20mm nominal size ) up to plinth level with : cement mortar 1:6 (1 cement:6 coarse sand)
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
50.18.9.9.2:Providing and fixing PVC pipes includes joints of pipes with one step PVC solvent cement, trenching, refilling & testing of joints complete as per direction of Engineer in CHarge. 110 mm dia 4 Kg/cm2
MELVIN VINCENT
Bidder Name
K V SARATHKUMAR
MELVIN VINCENT
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1050268.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .