| 1 | L1₹9.9 LAdmitted-Finance | ₹9.9 L | L1 | Admitted-Finance |
| 2 | L2₹10.2 L+₹23,806 (2.39%)Admitted-Finance | ₹10.2 L+₹23,806 (2.39%) | L2 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | Rejected-Technical Not meet TQR |
| Sl No | Description | Qty | Unit | M/S AMIT ASSOCIATES L2 | maa bhagwati engineering works L1 |
|---|---|---|---|---|---|
| 1.00 | Work of transportation of required materials and heavy T&P, generator etc. to the designated work site by head loading for executioon. After completion, all material will be shifting back to the store at 220 KV SIDCUL, Haridwar. | 8 | Job | 6,600 ₹52,800 | 6,495 ₹51,960 Lowest |
| 2.00 | Work of strengtheningof towers by providing stays on towers with the help of steel rope and turn buckle at suitable dry place near tower, including excavation of earth, grouting to stay with all necessary work required in order to ensure safety safety of next tower to prevent from any distortion. | 8 | Job | 12,450 ₹99,600 Lowest | 12,495 ₹99,960 |
| 3.00 | Earth work in excavation by mechanical means ( Hydraulic excavator) / manual means in foundation trenches or pits of any size, including dressing of sides and ramming og bottoms, including getting out the excavated soil and disposal of surplus excavated soil as directed, including all leads & lifts. | 300 | CuM | 479 ₹1,43,700 | 470 ₹1,41,000 Lowest |
| 4.00 | Work of breaking of chimney of towers as per instruction of site in-charge including all labour and T&P etc. | 8 | Job | 2,000 ₹16,000 | 1,990 ₹15,920 Lowest |
| 5.00 | Work of fabrication of tower stubs as per site requirement, including all labour and T&P for proper completion of work. | 8 | Job | 20,000 ₹1,60,000 | 14,995 ₹1,19,960 Lowest |
| 6.00 | Work of dismantling of required tower stubs, legs and tower members of towers, including all labour and T&P for proper completion of work. | 8 | Job | 18,000 ₹1,44,000 Lowest | 19,999 ₹1,59,992 |
| 7.00 | Work of erection and fixing of required stubs, leg tower members, including all labour and T&P for proper completion of work. | 8 | Job | 20,000 ₹1,60,000 | 19,999 ₹1,59,992 Lowest |
| 8.00 | Making chimney of existing tower legs by cement concrete 1:1.5:3 ratio with cement, 20 mm stone blast and core sand including cost of labour, material and T&P required for proper completion of work. | 12 | CuM | 12,000 ₹1,44,000 | 11,880 ₹1,42,560 Lowest |
| 9.00 | Supply and spreading of earth by earth work in excavation by mechanical means (Hydraulic excavation)/manual means over surface areas, in trenches, plith, sides of foundation etc. In layers not exceeding 20 cm in depth, consoldating each deposited layer by ramming and watering including all lead lifts (land of erth supply to be arranged by the contractor at his own cost). | 150 | Job | 652 ₹97,800 Lowest | 685 ₹1,02,750 |
Tender Value
Refer Docs
EMD Value
₹35,000
Closing Date
28 May 2026, 1:00 pmClosed
Superintending Engineer
O and M Circle, PTCUL ,26-Civil Lines, Roorkee.
Work for replacement of perished/ rusted tower stubs of 132 KV SIDCUL-Roorkee line and 132 KV Jwalapur-Roorkee line under 220 KV Substation SIDCUL, Haridwar.
2026_PTCUX_94806_1
T-10/SE(OandM)CR/2026-27
Open Tender
Electrical Works
Item Rate
90 days
SIDCUL
Please refer Tender documents.
3 documents required · 3 mandatory
₹590
Yes
SE O and M PTCUL Roorkee
₹35,000
Yes
20 Jun 2026
28 Apr 2026
29 May 2026
29 Apr 2026
28 May 2026
29 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0.0 | Work of transportation of required materials and heavy T&P, generator etc. to the designated work site by head loading for executioon. After completion, all material will be shifting back to the store at 220 KV SIDCUL, Haridwar. | 8 | Job | 100 | ₹800 |
| 0.0 | Work of strengtheningof towers by providing stays on towers with the help of steel rope and turn buckle at suitable dry place near tower, including excavation of earth, grouting to stay with all necessary work required in order to ensure safety safety of next tower to prevent from any distortion. | 8 | Job | 100 | ₹800 |
| 0.0 | Earth work in excavation by mechanical means ( Hydraulic excavator) / manual means in foundation trenches or pits of any size, including dressing of sides and ramming og bottoms, including getting out the excavated soil and disposal of surplus excavated soil as directed, including all leads & lifts. | 300 | CuM | 100 | ₹30,000 |
| 0.0 | Work of breaking of chimney of towers as per instruction of site in-charge including all labour and T&P etc. | 8 | Job | 100 | ₹800 |
| 0.0 | Work of fabrication of tower stubs as per site requirement, including all labour and T&P for proper completion of work. | 8 | Job | 100 | ₹800 |
| 0.0 | Work of dismantling of required tower stubs, legs and tower members of towers, including all labour and T&P for proper completion of work. | 8 | Job | 100 | ₹800 |
| 0.0 | Work of erection and fixing of required stubs, leg tower members, including all labour and T&P for proper completion of work. | 8 | Job | 100 | ₹800 |
| 0.0 | Making chimney of existing tower legs by cement concrete 1:1.5:3 ratio with cement, 20 mm stone blast and core sand including cost of labour, material and T&P required for proper completion of work. | 12 | CuM | 100 | ₹1,200 |
| 0.0 | Supply and spreading of earth by earth work in excavation by mechanical means (Hydraulic excavation)/manual means over surface areas, in trenches, plith, sides of foundation etc. In layers not exceeding 20 cm in depth, consoldating each deposited layer by ramming and watering including all lead lifts (land of erth supply to be arranged by the contractor at his own cost). | 150 | Job | 100 | ₹15,000 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.03 MB
BOQ_112159.xls
BOQ • 0.26 MB
T10DOC.pdf
Tender Documents • 0.83 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .