BID DOCUMENTS FOR PROPOSED PLASTARING ON OLD WALL AND THE WORK OF REMAINING WALL IN BHATT SMSHAN AT UMRETH NAGARPALIKA UNDER: SWARNIM JAYANTI MUKHYA MANTRI SHAHERI VIKAS YOJANA-UDP-88 (YEAR: 2023-24).
287346
SJMMSVY/2023-24
Open
Civil Works - Buildings
Anand
13 documents required · 13 mandatory
₹2,832
The Chief Officer, Umreth Municipality, Umreth
₹19,000
17 Mar 2026
17 Mar 2026
17 Mar 2026
24 Mar 2026
17 Mar 2026
Item Qty. Description Total Unit Amount
1 165.50 Excavation for foundation upto 1.5 m depth including
Cmt. sorting out and stacking of useful materials and
disposing off the excavated stuff upto 50 Meter lead.(A)
Loose or soft soil 122.94 Cmt.
2 30.50 Excavation for foundation for depth from 1.5 m to 3.0 m
Cmt. including sorting out and stacking of useful materials and
disposing off the excavated stuff upto 50 Meter
lead.(A) Loose or soft soil 136.30 Cmt.
3 136.00 Filling available excavated earth (excluding rock) in
Cmt. trenches. plinth, sides of foundations etc. in layers not
exceeding 20 cm. in depth consolidating each
disposited layer by ramming and watering.
4 19.00 Providing and laying cement concrete (1:4:8) (1 Cement,
Cmt. Coarse sand, 8 Crushed stone agreegate 40 mm nominal)
and curing complete excluding cost of formwork in
foundation and plinth.
5 29.50 Providing and Laying controlled cement concrete M-200 and
Cmt. curing complete, including the cost of formwork but excluding
the cost of reinforcement for reinforced concrete work in
Column footings.
6 4.00 Providing and laying controlled cement concrete M-200 and
Cmt. curing complete including the cost of formwork But Excluding
the cost of reinforcement for reinforced concrete work in
Column upto Plinth Level having any cross section area. 7524.00 Cmt.
7 6.00 Providing and Laying controlled cement concrete M-200 and
Cmt. curing complete, including the cost of formwork but excluding
the cost of reinforcement for reinforced concrete work in
Columns having any cross section area upto floor two level.
SBD SECTION-7 BILL OF QUANTITIES-147
8 8.50 Providing and laying controlled cement concrete M-200 and
Cmt. curing complete including the cost of formwork but Excluding
the cost of reinforcement for reinforced concrete work in
Ground Beam having any cross section area.
9 3.50 Providing and laying controlled cement concrete M-200 and
Cmt. curing complete including the cost of formwork and excluding
the cost of reinforcement of reinforced concrete work in
Coping 5815.58 Cmt.
3760.00 Providing TMT Bar FE 500D reinforcement for R.C.C. work
Kgs. including bending, binding and placing in position complete
upto floor two level
11 42.50 Brick work using common burnt building bricks having
Cmt. crushing strngth not less than 35 Kg./cm2 in super structure
for Ground Floor in C.M. (1:6) (1 Cement, 6 fine sand)
racking out joints curring etc. complete directed by Engineer-
12 1298.00 20 mm thick sand faced cement plaster on walls up to heinht
Smt 10 metres above ground laval cosisting of 12 mm thick
backing coat of C:M 1:3 (1-cement :3-sand) and 8mm thick
finishing coat of C:M 1:1 (1-cement :1-sand) etc. complete.
13 1298.00 Finishing wall with water proof exterior emulsion apex paint
Smt of on wall surfaces (two coats) to give an approved brand and
manufacture and of required slope evan shade after
throughly brushing the surface to remove all dirt and remains
of loose powered materials. etc completed.
14 7.83 Steel work, riveted in built up sections framed work including
Qtl. cutting, hoisting, fixing in position and applying a priming coat
of red lead paint. (A) In beams and joists, channels angles
Tees, flats, with connecting plates or angle cleats as in main
and cross beams. Hip and jack rafters, purlins conneted to
common rafters and the like.
15 1.30 16G Make Tata
Qtl. Double twisted barbed wire, gauge 16, barb spacing 4". four
horizontal lines and two diagonals of galvanised steel barbed
wire weighting 9.38 K.G. per 100 metre strained and fixed to
posts with G.I. staples, including fixing the posts in coping of
compound wall. 5820.34 Qtl.
SBD SECTION-7 BILL OF QUANTITIES-148
16 324.00 Providing and fixing M.S. grills of required pattern to wooden
Kgs. frames of windows etc. with M.S. flats at required spacings
and frame alround, square or round bars with round headed
bolts and nuts or by screws. (A) PLAIN GRILL.
17 11.00 Applying priming coat over new steel and other metel surface
Smt. after and including preparing the surface by throughly
cleaning, oil,grease, dirt and other foreign matter and scoured
with brushes fine steel wood, scrapers and sand paper with
ready mixed priming paint brushing red lead.
18 11.00 Painting three coats (excluding priming coat) on new steel
Smt. and other metal surface with enamel paint, brushing, interior
to give an even shade including cleaning the surface an even
shade including cleanicn the surface of all dirt, dust and other
foreign matter. 150.17 Smt.
Total Amount, Rs.
Total Amount, Rs.
Add :- 18% of GST, Rs.
Add :- 1% of Quality Controll, Rs.
Add :- 2% of Contingency Charges, Rs.
I / We am/are willing to carry out the work at _____________ % above / below (percent should be written in figure and
in words) of the estimated rates mentioned above. Amount of my/our tender works out as under.
( In words ) __________________________________________ Percentage above / below the estimated rate.
Estimated Amount put to tender Rs.
Deduct _______ % below Rs. Rs.
Estimated Amount put to tender Rs.
Add _______ % above Rs. Rs.
Total Amount Rs.
Total Amount Rs.
*( Please strike out whichever is not applicable)
Note :1 All work shall be carried out as per Public Works Department Hand Book and other specifications
of Division or as directed.
Note :2 Rates quoted include clearance of site (prior commencement of work and its close) in all respects
and hold good for work under.
Note :3 I/ We have read the conditions mentioned in this tender and agree to abide by the same.
Seal & Signature of Contractor President Chief Officer
Umerth Nagarpalika Umerth Nagarpalika
SBD SECTION-7 BILL OF QUANTITIES-149
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
SBD.pdf
Notes.pdf
BOQ.pdf
OTHER IMPORTANT-1.pdf
OTHER IMPORTANT-2.pdf
OTHER IMPORTANT-3.pdf
Download all tender documents and submit your bid