Chief Engineer, CEG, GSO
Room No. 301, Dr. Homi Sethna Building (GSO Annex building), Kalpakkam
Providing and laying of Ductile Iron pipes for water supply mains at South PDPM row type houses Phase - II in Kalpakkam Township.
2026_GSO_929171_1
GSO/CTC/CEG/390/2026
Open Tender
Civil Works - Others
Item Rate
300 days
Kalpakkam
As stipulated in NIT/tender
8 documents required · 8 mandatory
₹0
₹2.9 L
9 Oct 2026
9 Oct 2026
30 Oct 2026
9 Oct 2026
29 Oct 2026
22 Oct 2026
12 Oct 2026 - 21 Oct 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavating trenches of required width by mechanical means (Hydraulic excavator) / manual means for pipes, cables etc., for depth upto 1.5m in all kinds of soil including excavation for sockets, dressing of sides, ramming of bottoms, getting out the excavated soil and then refilling the soil as required in layers not exceeding 200mm in depth, consolidating each deposited layer by ramming, watering etc., and disposing of surplus excavated soil as directed within a lead of 50m, (Disposed soil to be levelled by breaking clods, if any and neatly dressed), etc., all complete as per specification. | 3,500 | Cu.m | 1 | ₹3,500 |
| 2 | Clearing light jungle including uprooting of rank vegetation, grass, brush wood, removal of rubbish upto a distance of 100m outside the periphery of the area cleared, etc., all complete as per specification and as directed by Engineer-In-Charge. | 600 | Sq.m. | 1 | ₹600 |
| 3Cutting and felling trees of the girth (measured at a height of 1m above ground level) including cutting of trunks, branches, removing the roots, stacking of serviceable materials and disposal of unserviceable materials within a lead of 200m including filling the pits and depression with excavated earth, etc., all as directed by Engineer-In-Charge. | |||||
| 3.1 | Beyond 300mm girth upto and including 600mm girth. | 20 | Nos. | 1 | ₹20 |
| 4Disposal of surplus excavated earth / Debris by collecting, loading, transporting by mechanical means and unloading them at places as shown by the Department within a lead specified below and levelling, etc., all complete as per specifications and as directed by the Engineer-in-Charge. Note: 1) The rates in respect of this item are applicable for the NET Quantities arrived at after making deductions for voids @ 20% in respect of soil and @ 50% in respect of rock from the corresponding stack / truck measurements. 2) The earth shall be dumped well inside the dumping yard and not over approach pathway road. | |||||
| 4.1 | Exceeding 1 Km but not exceeding 2 Kms | 20 | Cu.m | 1 | ₹20 |
| 5Providing and laying in position of plain cement concrete using hard granite broken stone for all insitu levelling courses in foundations, floor, roof screeding, encasing pipes, etc., including mechanical mixing, ramming, compaction, levelling, curing, dewatering, if any including the cost of formwork etc., all complete as per specifications. | |||||
| 5.1 | 1: 4 : 8 (1 cement : 4 sand : 8 graded stone aggregate 40mm nominal size) | 5 | Cu.m | 1 | ₹5 |
| 6Providing, erecting, placing in position and removing Formwork for all insitu concrete works at all lifts and all shapes such as circular works, chamfers, splays, etc., using Steel / Plywood shuttering including centering, scaffolding, strutting, propping with necessary bracing in all areas, fixing of EPs, cutting holes and fixing pipe sleeves, applying of approved form oil over surface in contact with concrete, de-shuttering after specified curing period, etc., all complete as per drawings and specifications. Note: Measurement for the formwork shall be the area of forms in contact with concrete surfaces. Stop boards for construction joints will not be measured separately for payment. Centering and shuttering where exceeding 3.5m height in one floor shall be measured and paid for separately. | |||||
| 6.1 | For Plain Surfaces at all levels. | 70 | Sq.m. | 1 | ₹70 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 1.89 MB
CEG390FormofAgt.pdf
Tender Documents • 0.12 MB
AnnexuresII-IVCTC390.pdf
Tender Documents • 0.09 MB
CEG390TechnicalBidFormsACDFGH.xls
Tender Documents • 0.13 MB
BOQ_976432.xls
BOQ • 0.37 MB
CEG390PartIDocument.pdf
Tender Documents • 4.21 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .