Loading…
Loading…
Tender Value
₹64.7 L
EMD Value
₹97,500
Closing Date
1 Oct 2026, 10:30 am4d left
Chief Executive Officer HPAFMS
Directorate of Fisheries Matsya Bhawan Bilaspur HP
Infrastructure facilities for Establishment of Rainbow Trout Brood Bank at Trout Fish Farm Patlikuhal Distt. Kullu HP SH Civil work for construction of trout hatchery building shed including water supply and stands for trough tray and indoor fitting.
2026_HAFMS_143540_1
2026_HPAFMS_1962_1
Open Tender
Civil Works
Item Rate
180 days
Patlikuhal Distt. Kullu H.P.
Please refer Tender documents.
6 documents required · 6 mandatory
₹2,000
Chief Executive Officer HPAFMS
₹97,500
16 Sept 2026
16 Sept 2026
1 Oct 2026
16 Sept 2026
1 Oct 2026
16 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Infrastructure facilities for Establishment of Rainbow Trout Brood Bank at Trout Fish Farm Patlikuhal Distt. Kullu H.P. (SH:- Civil work for construction of trout hatchery building shed including water supply and stands for trough tray and indoor fitting .) | |||||
| 1.01 | Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains , including dressing of sides and ramming of bottoms, lift upto all depth, including getting out the excavated soil and disposal of surplus excavated soils as directed, within all lead .including de-watering and carriage of materials , within all leads and lifts as per direction of Engineer-in-Charge .Any loss to the public and private property during the course of execution and disposal of unserviceable materials shall be absolute responsibility of the contractor which shall have to be duly compensated by the contractor to full extent in all respects in all cases as per direction of the Engineer-in-charge. | 84.81 | Cubic Metre | - | - |
| 1.02 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited\ layer by ramming and watering, lead up to 50 m and lift upto 1.5 m Any loss to the public and private property during the course of execution and disposal of unserviceable materials shall be absolute responsibility of the contractor which shall have to be duly compensated by the contractor to full extent in all respects in all cases as per direction of the Engineer-in-charge. | 45 | Cubic Metre | - | - |
| 1.03 | Centering and shuttering including strutting, propping etc. and removal of form for all heights Foundations, footings, bases of columns, etc. for mass concrete .including dewatering,river training works and carriage of material with in all leads and lifts as directed by the Engineer-in-Charge and other incidentals. | 82.8 | Square metre | - | - |
| 1.04 | Centering and shuttering including strutting, propping etc. and removal of form for all heights Columns, Pillars, Piers, Abutments, Posts and Struts as per the directions of the Engineer-in-charge including carriage of material within all leads and lifts and other incidentals. | 105.84 | Square metre | - | - |
| 1.05 | Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers on slab long beam as per the directions of the Engineer-in-charge including carriage of material within all leads and lifts and other incidentals. | 274.33 | Square metre | - | - |
| 1.06 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:4:8 (one cement : four coarse sand :eight graded stone aggregate 40 mm (forty millimetre) nominal size as per the directions of the Engineer-in-charge including dewatering works and carriage of materials , within all leads and lifts as per direction of Engineer-in-Charge and other incidentals. | 46.92 | Cubic Metre | - | - |
| 1.07 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:1.5:3 (1 cement : 1.5 coarse sand) : 3 graded stone aggregate 20 mm nominal size) as per the directions of the Engineer-in-charge including carriage of material within all leads and lifts and other incidentals. | 22.23 | Cubic Metre | - | - |
| 1.08 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level , excluding cost of centering, shuttering, finishing and reinforcement 1:1.5:3 (one cement : one and half coarse sand): three graded stone aggregate 20 mm (twenty millimetre) nominal size as per the directions of the Engineer-in-charge including carriage of material within all leads and lifts and other incidentals. | 10.98 | Cubic Metre | - | - |
| 1.09 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand) : 3 graded stone aggregate 20 mm nominal size) as per the directions of the Engineer-in-charge including carriage of material within all leads and lifts and other incidentals.. | 31.55 | Cubic Metre | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.19 MB
Tendernotice_2.pdf
PDF • 2.13 MB
Tendernotice_3.pdf
PDF • 36.80 MB
BOQ_213285.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .