Tender Value
Refer Docs
EMD Value
₹7,000
Closing Date
6 Mar 2023, 1:30 pmClosed
EE
CHANDRAWAL WATER WORKS
Dehydration /servicing of 2 nos. of 225 KVA transformers installed at Chandrawal Water Works .II
2023_DJB_237361_2
NIT NO. 16 (2022-23)
Open Tender
Miscellaneous Works
Works
30 days
CHANDRAWAL WATER WORKS
Please refer Tender documents.
3 documents required · 3 mandatory
₹500
DJBEMD A/c No-50448339804 THROUGH SUBPAISA GATEWAY
₹7,000
27 Mar 2023
28 Feb 2023
6 Mar 2023
28 Feb 2023
6 Mar 2023
28 Feb 2023
28 Feb 2023 - 6 Mar 2023
Renovation Of 225 KVA Transformer No.--01. The Job Includes the following:- Dismantling of complete transformer, removing of the HT connections leads and removing of top cover, oil tank, silica gel, breathers & cooling fins etc.
Lifting of core and coils with safe and sound conditions.
Cleaning the core and coils with hot oil vacuum machine & removing the moisture from the coils and core.
Cleaning the Transformer tank and removing the sludge and silt.
Tapping the connection leads with craft tape.
Replacement of 11 KV HT insulator Bushing
Replacement of 0.44 KV insulator Bushing
Addition of transformer oil
Dehydration of Complete transformer oil
Replacement of winding protection pad
Lowering the transformer core & coils with safe & sound conditions
Replacement of top cover gasket & insulator gasket oil seal for stopping the leakage.
Repairing of cooling fins. Brazing the fins for stopping the oil leakages.
Replacement of silica gel
Assembling of complete transformer & installation the same and testing on No load as well as on load with both side earthing.
Painting of complete transformer
Renovation Of 225 KVA Transformer No.--02 The Job Includes the following:- Dismantling of complete transformer, removing of the top cover, olio tank, silica gel, breathers & cooling fins etc. Lifting the core & coil from the transformer tank.
Lifting of core and coils with safe and sound conditions.
Cleaning the core and coils with hot oil vacuum machine & removing the moisture from the coils and core.
Cleaning the Transformer tank and removing the sludge and silt.
Replacement of 11 KV HT insulator Bushing
Replacement of 0.44 KV insulator Bushing
tapping the connection leads with craft tape.
Replacement of winding protection pad
Replacement of Tap Changer
Addition of transformer oil
Dehydration of Complete transformer oil
Repairing of cooling fins. Brazing the fins for stopping the oil leakages.
Replacement of silica gel
Lowering the transformer core & coils with safe & sound conditions
Replacement of top cover gasket & insulator gasket oil seal for stopping the leakage.
Assembling of complete transformer & installation the same and testing on No load as well as on load with both side earthing
Painting of complete transformer
EVERSHINE ENTERPRISES
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .