| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹34.7 LAccepted-AOC | ₹34.7 L | L1 | Accepted-AOC Single bid |
| Sl No | Description | Qty | Unit | MUHAMMED T K L1 |
|---|---|---|---|---|
| 1.00Construction of Road | ||||
| 1.00 | 2.1:Clearing Grass and Removal of Rubbish Clearing grass and removal of rubbish up to a distance of 30m outside the periphery of the area as per Technical Specification Clause 201. By Manual Means | 0.17 | Hectare | 43,951.72 ₹7,691.55 |
| 1.00 | 3.15.2:Compacting Original Ground (ii) Compacting original ground supporting subgrade Loosening of the ground upto a level of 300 mm below the subgrade level, watered, graded and compacted in layers to meet requirement of Tables 300.1 and 300.2 for subgrade construction as per Technical Specification Clause 303.5.2. | 240 | cum | 64 ₹15,360 |
| 1.00 | 3.15.1:Compacting Original Ground <br> (i) Compacting original ground supporting embankment <br> Loosening, Levelling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Tables 300.1 and 300.2 for embankment construction as per Technical Specification Clause 301.4.1. | 90 | cum | 15.04 ₹1,353.60 |
| 1.00 | 3.5.3:Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m <br> Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3 | 225 | cum | 51.42 ₹11,569.50 |
| 1.00 | 3.3:Construction of Embankment with Material Obtained from Roadway Cutting <br> Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 | 180 | cum | 60 ₹10,800 |
| 1.01 | 3.4:Construction of Embankment with Material Obtained from Borrow Pits <br> Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 | 60 | cum | 617.78 ₹37,066.80 |
| 1.01 | 4.1.A.1:Granular Sub-base with Well Graded Material (Table 400.1) <br> (A) By Mix in Place Method <br> Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. <br> (i) For Grading I Material | 210 | cum | 3,124.47 ₹6.6 L |
| 1.01 | 4.9:Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. By Mechanical Means with 1 km lead | 210 | cum | 3,400 ₹7.1 L |
| 1.01 | 5.1.1a:Prime Coat :- Low porosity Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502 | 1,400 | sqm | 75.94 ₹1.1 L |
Updated dates
Tender Value
₹34.9 L
EMD Value
₹50,000
Closing Date
28 Feb 2026, 6:00 pmClosed
Executive Engineer
Office of the Executive Engineer Harbour Engineering Division Kannur Head Quarters Hospital (P.O) Kannur-670017
Gsb,WMM,MSS,RCC box culvert M25
2026_HED_835595_1
HED/CEHED/TR/639/2025_5_1_1/1
Open Tender
Civil Works - Roads
420 days
Ramanthali
Please refer Tender documents.
12 documents required · 12 mandatory
₹2,760
Yes
₹50,000
Yes
9 Jun 2026
11 Feb 2026
2 Mar 2026
11 Feb 2026
28 Feb 2026
11 Feb 2026
Construction of Road
2.1:Clearing Grass and Removal of Rubbish Clearing grass and removal of rubbish up to a distance of 30m outside the periphery of the area as per Technical Specification Clause 201. By Manual Means
3.15.2:Compacting Original Ground (ii) Compacting original ground supporting subgrade Loosening of the ground upto a level of 300 mm below the subgrade level, watered, graded and compacted in layers to meet requirement of Tables 300.1 and 300.2 for subgrade construction as per Technical Specification Clause 303.5.2.
3.15.1:Compacting Original Ground <br> (i) Compacting original ground supporting embankment <br> Loosening, Levelling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Tables 300.1 and 300.2 for embankment construction as per Technical Specification Clause 301.4.1.
3.5.3:Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m <br> Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3
3.3:Construction of Embankment with Material Obtained from Roadway Cutting <br> Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5
3.4:Construction of Embankment with Material Obtained from Borrow Pits <br> Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5
4.1.A.1:Granular Sub-base with Well Graded Material (Table 400.1) <br> (A) By Mix in Place Method <br> Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. <br> (i) For Grading I Material
4.9:Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. By Mechanical Means with 1 km lead
5.1.1a:Prime Coat :- Low porosity Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
5.2.3a:Tack Coat Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503.
5.11.1.A.2a:Mix Seal Surfacing - Manual Means - Type A - Bitumen S-65 Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates using penetration grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 8-10 kN static roller and finishing to required level and grades as per Technical Specification Clause 509 By Manual Means :- Type A (II) Bitumen (S-65)
11.4.1.1:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 I. P.C.C grade M 10 (i) Nominal mix 1:3:6
12.7:Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructure complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202
11.4.3.1:Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203III. P.C.C. grade M 20 (i) Nominal mix (1:2:4)
12.5.4:Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204 <br> For height upto 5 m <br> IV. R.C.C. grade M 25
13.1.2:Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5<br>R.C.C M 25
Side protection work and Culvert
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
60.7.2:DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
13.43.1:Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer
13.44.1:Finishing walls with water proofing cement paint of required shade:New work (Two or more coats applied @ 3.84 kg/10 sqm)
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1405964.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.15 MB
BOQ_1405964.xls
BOQ • 0.32 MB
ep.pdf
Tender Documents • 0.01 MB
sbd.pdf
Tender Documents • 9.31 MB
Download all tender documents and submit your bid