Loading…
India Infra Updates on WhatsApp
Join the Tenderkart WhatsApp channel for India Tender Updates
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.0 CrAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹1.1 Cr+₹11.4 L (11.1%)Rejected-AOC | L2 | Rejected-AOC L2 |
Tender Value
₹1.1 Cr
EMD Value
₹2.2 L
Closing Date
6 Sept 2023, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Chief Engineer, BARC(V)
Chief Engineer, BARC(V), Anu Vihar, Mekarasi Hill, Gajuwaka -Yellamanchili Road, Maduturu Sub Post Office,Visakhapatnam-531 011
Construction of a shallow underground tunnel at BARC main campus, Atchutapuram, Near Visakhapatnam, Andhra Pradesh
2023_BARC_767979_1
BARC (V)/CES/Tunnel/128 Dated 18.08.2023
Open Tender
Civil Works
Item Rate
150 days
Atchutapuram, Visakhapatnam
Please refer Tender documents.
6 documents required · 6 mandatory
₹0
₹2.2 L
Atchutapuram,Visakhapatnam
8 Nov 2023
23 Aug 2023
11 Sept 2023
23 Aug 2023
6 Sept 2023
1 Sept 2023
23 Aug 2023 - 30 Aug 2023
30 Aug 2023
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1General Notes Applicable to all BOQ Items | |||||
| 21) The make/model/brand for all the BOQ items shall be as per suggestive makes of Annexure-B of Section-VII of the tender document. The make/model/brand mentioned in Annexure-B of Section-VII of the tender document is merely for guidance and bidders can prefer any other make which is meeting technical specifications given under Section-V and Schedule of Quantities of Tender document and shall confirm to the relevant BIS codes and other relevant codes. However, the bidder may suggest any equivelent make/ model/brand meeting technical parameters on or before pre-bid conference for approval of BARC(V). 2) Only sieved river sand/crushed stone sand confirming to Zone-II from Godavari river or Varaha river or Vamsadhara river or Sarada river or Nagavali river / Crushed stone sand shall be used as fine aggregate and Graded hard broken granite metal of 3 stage (VSI) material shall be used as coarse aggregate in relevant items. Specification for fine and coarse aggregate shall confirm to IS:383 (latest revision) 3) In view of limit on water-cement ratio for durability requirements in design mix concrete, concrete admixtures (Carboxylate based superplasticizers) can be used after taking prior approval of Engineer-in-Charge and the rates quoted for concrete items shall be inclusive of the cost of admixtures, Design mix, trial mixes, testing (at site & at approved labs), etc. complete. 4) The contractor shall set up sufficient number of self loading mobile concrete mixers inside the project area for the production of concrete. | |||||
| 35) Contractor may also be allowed to procure concrete from prior approved RMC plants on prior approval of the BARC subject to maintain required slump at site during pouring.To that extent suitable Mix Design should be carried out with required retention period. No extra payment will be made if concrete is brought from RMC plants outside the project area. 6) Manufacturer's Test certificate of cement which is procured from dealer/company is to be submitted for all cement related works by the contractor. 7) The Scope of works which are not included in any specific items but indicated in the document "General Scope of all works" shall be within the scope of overall contract works. The cost of work/item/material indicated in this document shall be deemed to be included in the quoted rates of all individual items. 8) The quoted rates shall include necessary royalties, seigneiorage charges,etc. and all other charges to supply all the required construction materials. | |||||
| 49) For all standards and code of practices, specifications, like Indian Standard, MORT&H, ASTM, etc. refer only latest revisions including all applicable amendments, revisions and additional publications (during contract period) and these have to be followed. 10)Prior approval for source of all construction materials by submission of relavent test certificates, documents, invoices etc. have to be taken from BARC. 11) All the tests mentioned in Quality Assurance Plan(QAP) should be carried out without any extra cost. 12) The contractor has to submit all royalty /seigneiorage slips,etc for all the naturally available construction materials before submitting the RA bills. | |||||
| 5General Notes for Earth Work Excavation: Note : The rate quoted for earth work excavation by contractor is deemed to have included the following points (a) to (j) a) removal of all kinds of vegetation, small shrubs, light/heavy jungle, trees etc., alongwith roots, including disposal/stack in the identified location. b) shoring, strutting, stepping, dressing, grading required for keeping the earth in position on sides of trenches with approved timber/steel accessories wherever necessary to prevent sides from falling including bailing or pumping out of water if necessary including removal of debris/unserviceable materials and excavated excess soil, if any. c) dewatering of both ground and surface water, including removal of slurry generated while excavation and keeping the area free from water, to be let out of the building area through proper pipes & channels if required by suitable pumps, d) watering, ramming and thoroughly consolidate the bottom of all excavations & ground before the construction of foundation/footing/plinth beam, filling in basement or other work is commenced. | |||||
| 5.1 | e) the loose pockets shall be excavated and compacted after back filling as directed by Engineer-in-charge, as per detailed specification and conforming to safety rules during progress of the work.
f) Contour levels to be taken jointly with the Engineer-in-charge and prior written approval be taken before starting any excavation/ filling at every 3 m grids for arriving at the actual quantity,
g) Backfilling will be done in layers of thickness as specified below.
h) Cost inclusive of necessary royalties, seigneiorage charges and other charges to supply all the required construction materials,
i) cost of items shall include all labour charges, hire charges of machinery, lubricants, fuels and tests etc.
j) Measurement/Payment will be reststicted to PCC/drawing dimensions only. | - | - | - | - |
| 5.2 | Earth work excavation by mechanical means (Hydraulic excavator) / manual means in all types of soil other than soft and hard rock, dressing the sides of foundation, ramming of bottom etc. including shoring and dewatering (if necessary) and refilling with selected excavated earth in layers of not more than 500 mm thick, each layer well rammed and consolidated including disposing the surplus earth within a distance of 200 m all as per specifications including clearing Jungle, uprooting of vegetation, grass, etc.complete and as directed by the Engineer-in-charge | - | - | - | - |
| 5.21 | 0 to 1.50 m depth from Average Ground Level | 550 | Cum | - | - |
| 5.22 | 1.5 to 3.0 m depth from Average Ground Level | 400 | Cum | - | - |
| 5.23 | 3 to 4.50 m depth from Average Ground Level | 300 | Cum | - | - |
stage.html
html • 0.04 MB
techsummary_807305.pdf
PDF • 0.50 MB
BOQ Comparative Chart
xlsx • 0.01 MB
finsummary_807305.pdf
PDF • 0.45 MB
wo-tunnel.pdf
PDF • 4.28 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
Tender Document • 0.60 MB
TENDERDOCTUNNEL2023.pdf
Tender Document • 5.53 MB
BOQ_807305.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .