Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹84,682Accepted-AOC | L1 | Accepted-AOC Lowest | |
| 2 | L2₹90,220.50+₹5,538.50 (6.54%)Rejected-AOC | L2 | Rejected-AOC Second |
Tender Value
₹84,706
EMD Value
₹2,118
Closing Date
25 Nov 2022, 12:00 pmClosed
Assistant Executive Engineer
Head works sub division Malampuzha
Demolishing cc 1 3 6and cc1 4 8,Earth work excavation, cc 1 4 8,centring and shuttering,cc1 3 6,cc1 2 4, plastering, etc
2022_Irrig_529526_1
IRR/PI/TR/3508/2022_5_2_1/1HW
Open Tender
Repair and Maintenance Works
Item Rate
180 days
Mankara
Please refer tender document
7 documents required · 7 mandatory
₹555
Yes
₹2,118
Yes
23 Dec 2022
15 Nov 2022
28 Nov 2022
16 Nov 2022
25 Nov 2022
16 Nov 2022
Amount
sluice work
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
2.25:Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
OD20404/2022-2023:SUPPLYING and APPLYING GREASE on SCREW ROD for CANAL GATE
OD20405/2022-2023:Painting all the exposed surfaces of the gate and embedded parts with two coats of epoxy coal tar black paint confirming to IS14948 with a minimum film thickness of 150+/-5 microns per each coat over two coats of priming coat applied with zinc primer containing not less than 85% of zinc on dry film with a film thickness of 70+/-5 microns , so that the total film thickness of all coats including priming coat at any rate is not less than 350 microns after cleaning the surface using hand and power tool cleaning including cost of all materials, labour charges , cost of testing all painting materials, all incidental charges, hire of T&P etc. complete as per the direction of department officers at site
OD21035/2022-2023:Re-Conditioning of existing EN-8 Screw rod including cost of all materials, labour charges, hire charges, energy charges, conveyance, all leads and lifts etc. complete.
V A ABDUL MUTHALIF
Bidder Name
V A ABDUL MUTHALIF
ANWAR V A
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_765356.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .