| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.7 CrAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹1.8 Cr+₹10.7 L (6.44%)Admitted-Finance AT BAHARANA PO BAHARANA PS NIMAPADA DIST PURI | BAHARAPADA | PURI | ODISHA | 752120 | L2 | Admitted-Finance | ||
| 3 | L3₹1.8 Cr+₹12.4 L (7.50%)Admitted-Finance AT BADADANDA PO SIAL PS KRUSHNAPRASAD DIST PURI | KRUSHNAPRASAD | PURI | ODISHA | L3 | Admitted-Finance | ||
| 4 | Rejected-Technical | - | Rejected-Technical Not qualified | ||
| 5 | Rejected-Technical AT JHARPADA P O KANAK P S KANAK DIST PURI PIN 752017 | KANAK | PURI | ODISHA | 752017 | - | Rejected-Technical Not qualified |
Tender Value
₹2.3 Cr
EMD Value
₹2.3 L
Closing Date
22 Oct 2026, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
CCE Khordha RandB Circle Khordha
O/O CCE Khordha RandB Circle Khordha
Infrastructure development at CHC, Krushnprasad under AMA Hospital Building in the Dist. of Puri
2026_EICCL_142510_1
CCE-Khordha R and B Circle-8-26-27
Open Tender
Civil Works - Buildings
Percentage
180 days
Puri
3 documents required · 3 mandatory
₹10,000
₹2.3 L
Yes
9 Nov 2026
5 Oct 2026
23 Oct 2026
5 Oct 2026
22 Oct 2026
5 Oct 2026
5 Oct 2026 - 22 Oct 2026
90 days
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing roads and land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness. | 1,506.02 | sqm | 8.63 | ₹12,996.95 |
| 2 | Earth work in Ordinary soil with initial lead and lift including rough dressing in layers not exceeding 0.3m in depth and the Earth transported by transport vehicles as directed by the Engineer-in-charge. | 1,131.76 | cum | 282.88 | ₹3,20,152.27 |
| 3 | Filling in Foundation, Plinth and other low laying area with excavated materials including cost of all labour, T&P etc complete including watering and ramming as directed by the Engineer-in-charge . | 84.41 | cum | 157.16 | ₹13,265.88 |
| 4 | Filling at all depth with available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 15cm in depth: consolidating each deposited layer by ramming and watering complete (lead upto 100m) as directed by the Engineer-In-charge. | 57.8 | cum | 173.1 | ₹10,005.18 |
| 5 | Diluting and injecting chemical emulsion for PRE CONSTRUCTIONAL Anti-termite treatment and creating a continuous chemical barrier under and all-round the column pits, wall trenches, basement excavation, top perimeter of building, expansion joints, over the top surface of consolidated sorroundings of pipes and conduits etc. complete as per specifications (plinth area of the building at ground floor only shall be measured for payment). | 265.23 | sqm | 104.5 | ₹27,716.54 |
| 6 | Disposal of Surplus Earth/Debris staked at work site by mechanical means including loading and unloading and disposing the same within a lead of 5 km with hire running charges of all machineries, cost of all labour, labour cess, T&P required for the work etc. complete as directed by Engineer-In-Charge. | 168.82 | cum | 278.8 | ₹47,067.02 |
| 7 | Supplying and filling in foundation and plinth with sand including watering and ramming, poking and compacting including cost, conveyance, royalties, taxes of the materials and cost of all labour, labour cess, T&P etc. required for the work complete as directed by the engineer-in-charge.(a)Ground Floor | 230.3 | cum | 1,180.71 | ₹2,71,917.51 |
| 8 | Providing and laying Plain Cement Concrete of proportion (1:3:6) using 4 cm. size black hard crusher broken granite stone metal and screened and washed sharp sand for mortar of approved quality and from approved quarry including the cost of all materials, cost of labour, conveyance, taxes, royalties, loading, unloading, shuttering, centering, curing, labour cess, T&P, etc. all complete as per the direction of engineer-in-charge.Ground Floor | 117.94 | cum | 6,516.99 | ₹7,68,613.8 |
| 9 | Providing, lifting, hoisting and laying in Position Reinforced Cement Concrete of M-25 grade including cost of Centering and shuttering using 20mm and down grade size black hard granite (Crusher Broken) chips of approved quality from approved quary including the cost of all materials, cost of all labour, conveyance, taxes, loading, unloading, T&P, royalty, labour cess, all complete as per the direction of Engineer-in-charge but excluding the cost of steel reinforcement.R.C.C. Foundation and Footing Bases of Columns Mass Concrete Pre-Cast Slab etc.Ground Floor | 105.65 | cum | 6,912.5 | ₹7,30,305.63 |
| 10 | R.C.C. Grade Beams,Ground Floor | 43.66 | cum | 7,786.88 | ₹3,39,975.18 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_2.pdf
PDF • 2.20 MB
Tendernotice_1.pdf
PDF • 1.14 MB
BOQ_612037.xls
BOQ • 0.53 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .