| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.2 LAccepted-AOC | L1 | Accepted-AOC AGREEMENT EXECUTED |
Tender Value
₹4.2 L
EMD Value
₹10,554
Closing Date
27 Mar 2025, 4:00 pmClosed
Executive Engineer
O/o the Executive Engineer, LSGD Division, Kakkanad, Ernakulam.
Refer Tender Document
2025_LSGD_740187_2
ET136/DPEKM/EE/LSGD/24-25
Open Tender
Civil Works - Others
Item Rate
240 days
KAKKANAD
Please refer Tender documents.
7 documents required · 7 mandatory
₹935
Yes
₹10,554
Yes
26 May 2025
19 Mar 2025
29 Mar 2025
19 Mar 2025
27 Mar 2025
19 Mar 2025
Amount
COMPOUND WALL
15.7.4:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In cement mortar
15.9.2:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
OD328721/2024-2025:DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site
OD274206/2024-2025:60.7.1. DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.6.2.2:Solid masonry using pre cast solid blocks (factory made) of size 30x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for super structure up to floor two level with thickness 15cm in : CM 1:6 ( 1 cement : 6 coarse sand) etc complete
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
13.48.1:Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications:Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including one coat of special primer applied @ 0.75 ltr /10 sqm
Bidder Name
SABU T J
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1220698.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .