Tender Value
₹46.8 L
EMD Value
₹47,000
Closing Date
30 Sept 2026, 6:00 pmClosed
Assistant Municipal Commissioner
Maintenance And Repairing Work Of Surat Castle Located At Chowk Bazaar, Surat.
344250
AMC/HR/01/2026-27
Open
Repair and Maintenance
Works
Surat
3 documents required · 3 mandatory
₹1,770
Commissioner, Surat Municipal Corporation
₹47,000
11 Sept 2026
11 Sept 2026
11 Sept 2026
30 Sept 2026
11 Sept 2026
BIDDING DOCUMENT – PERCENTAGE RATE CONTRACT
LAST DATE FOR ON LINE SUBMISSION OF TENDERS: 30/09/2026 UP TO 18.00 hrs. (IST)
LAST DATE & TIME OF PHYSICAL SUBMISSION: 09/10/2026 UP TO 18.00 hrs. (IST)
SEPTEMBER -2026
VOL -1 Technical Bid | SURAT MUNICIPAL CORPORATION
SURAT MUNICIPAL CORPORATION
Tender Notice (On line) No: AMC/HR/01/2026-27
Name of work : Maintenance And Repairing Work Of Surat Castle
Located At Chowk Bazaar, Surat.
BIDDING DOCUMENTS FOR PERCENTAGE RATE CONTRACT BID DOCUMENT
SECTION DESCRIPTION PAGE
- TENDER NOTICE
- INVITATION FOR BID (IFB)
I INSTRUCTIONS TO BIDDERS (ITB)
II(A) CONDITION OF PARTICULAR APPLICATION
II(B) MEMORANDUM
III QUALIFICATION INFORMATION FORMS
IV(A) GENERAL CONDITIONS OF CONTRACT
IV(B) SPECIAL CONDITIONS OF CONTRACT
V TECHNICAL SPECIFICATIONS
VI BILL OF QUANTITIES
VII STANDARD FORMSOF SECURITIES, FORMS OF
ACCEPTANCE AND FORM OF AGREEMENT
VIII CHECK LIST
VOL -1 Technical Bid | SURAT MUNICIPAL CORPORATION
Tender Notice (On line) No: AMC/HR/01/2026-27
On line tender consisting of Post-Qualification, Technical & Price Bid duly super scribed are
invited on https://smctender.nprocure.com and by Regd. Post/Speed Post through postal
authority only, so as to reach “Chief Accountant, Surat Municipal Corporation, Surat-395003.” on
or before the date mentioned below.
Tender Notice No. DMC/HR/01/2026-27
Organization Name Surat Municipal Corporation (SMC) Surat,Gujarat
Department Name Heritage Cell
Name of Work Maintenance And Repairing Work Of Surat Castle Located At Chowk Bazaar,
Tender Type On line Open – Percentage rate basis.
Bidder Nationality National Competitive Bidding (NCB)
Type of Contract Single Work
Bidding Currency Single- Indian National Rupees.
Joint Venture/ Not Allowed.
Schedule of E- Tender Downloading of Tender Documents Upto Dt.30/09/2026 up to 18:00 hrs. (IST).
Pre-Bid Queries Bidder shall have to post queries on Email
address [email protected] on
or before 22/09/2026 up to 18.00 hrs.
Last date and time of online Dt. 30/09/2026 Up to 18.00 hrs. (IST)
Physical submission of Tender fee, On all working days from 01/10/2026 to
EMD, affidavit, and Addenda 09/10/2026 From 11.00 Hrs. to 18.00 Hrs, at
Corrigendum if any. the office of “The Chief Accountant, Surat
Municipal Corporation, Tapi Bhawan, Tapi
pura, Surat by Speed Post/ RPAD only.” In
sealed cover duly super scribed with name of
work and tender notice no.
Opening of Technical Bid (Online) Dt.01/10/2026 after 11.00 Hrs (IST) onwards.
Tentative along with Eligibility and
Qualification Submissions documents.
Opening of Price Bid, (Online) INTIMATED LATER
Bid validity period 120 days. (After Price Bid Opening)
Project Completion 12 Months. (Excluding Monsoon)
Payment Details Document Fee Rs.1500/-+@18%GST = Rs.1770/- In form of
Account Payee Demand Draft payable in favour
VOL -1 Technical Bid |
of The Commissioner, Surat Municipal
Estimated Value Rs.
EMD (BID SECURITY) Rs.47,000.00
100 % in the form of Demand Draft or pay order
of nationalized / Scheduled bank only in favour
of Commissioner , Surat Municipal Corporation,
General Terms & Bidders who wish to participate in this E-Tender will have to procure valid digital
Conditions certificate as per information Technology Act 2000. Bidders can procure this certificate
from any of the Government approved certifying agency i.e. (n) Code Solution. Bidders
shall upload the tender documents after submitting the DD details for tender fees and
EMD details online. The Demand Draft toward Tender Document fees can be submitted
along with Earnest Money Deposit before the due date as specified above. This should be
as per details given online and it should be drawn before last date of the uploading of the
tender. The intending bidders shall have to submit the following documents along with
the EMD (BID SECURITY). The Bidder should submit all the forms electronically only.
I. The CD containing technical & financial details required for evaluation dully
digitally signed.
II. Power of attorney.
III. Company’s profile and certificate of registration of company under the law.
DOWNLOAD OF TENDER DOCUMENT :
The tender document for these work are available only in Electronic format which can be
downloaded free of cost by the bidder.
SUBMISSION OF TENDER
Bidder shall submit their offer in electronic format on above mentioned website on or
before the scheduled date and time as mentioned, after Digitally Signing the same. No
Price bid in physical form will be accepted and any such offer if received by SURAT
MUNICIPAL CORPORATION will be out rightly rejected. Bidders need not to submit
Technical Bid , P.Q. (i.e. Eligibility and Qualification Submission specified in clause
2&3 of ITB) documents in Hard Copy. Bidder shall have to submit separate account
payee DD for Tender Fee & EMD drawn in favour of Commissioner, Surat Municipal
Corporation, Surat.
OPENING OF TENDER:
The Technical Bid will be opened on the specified date online on website
https://smctender.nprocure.com. Bidders or their representative who wish to participate
in online tender opening can log on to https://smctender.nprocure.com on the due date
and time, mark their presence and participate in online tender opening. Bidders who wish
to remain present at Surat Municipal Corporation, Heritage Cell at the time of tender
opening can do so. Only one representative of each firm will be allowed to remain
Information for online 1. Internet site address for e-Tendering activities will be
participation https://smctender.nprocure.com
2. Interested bidders can view detailed tender notice and download tender document
from the above mentioned website.
3. Bidders who wish to participate in online tender have to register with the website
through the ‘’New User Registration’’ link provided on the home page. Bidder will
create login id &password on the own in registration process.
4. Bidders who wish to participate in this tender need to procure Digital Certificate as
per Information Technology Act-2000 using that they can digitally sign their
electronic bids. Bidders can procure the same from any of the CCA approved
certifying agencies, or they may contact (n) code Solution at below mentioned address
and they will assist them in procuring the same. Bidders who already have a valid
Digital Certificate need not to procure the same. In case bidders need any clarification
VOL -1 Technical Bid |
regarding online participation, they can contact –
(n)code solution (Adivision of GNFC Ltd.)
14th Floor,Tower one Road,5C,Zone5,
Gujarat International Finance,
Tech City (Gift City)
Gandhinagar-382355.
Toll Free No:-1800-419-4455.
URL:https://smctender.nprocure.com
5. Bidders who wish to participate in e-Tender need to fill data in predefined forms of
tender fee, EMD, and Price bid only.
6. Bidder shall have to upload scanned copies of reference documents support of their
eligibility of the bid withVolume-1 of tender i.e. PQ (Technical) or experience details
and tender fee & EMD Demand Draft in Electronic format through online (By
scanning) system.
7. All documents must be colored scanned to be seen as original. Scanning in
black and white or gray shall not be acceptable.
8. All the documents must be notarized with clearly displaying stamp, number
and name of the notary.
9. After filling data in predefined forms, bidders need to click on final submission link
to submit their encrypted bid. Bidder must submit Tender Fees & EMD (D.D/ Pay
order),Affidavit ( Form No.08), Anti blacklisted Ceritificate Affidavit ( Form
No.09), Site Visit Affidavit ( Form No.11) , Annexure-B on non-judicial stamp
paper of Rs.300/- with Notorized submit, and Annexure-C (SPECIMEN
SIGNATURE AND PHOTOGRAPHS OF THE BIDDER) in electronic format as
well in hardcopy.
10. For the purpose of realization of tender fee and EMD
(A)The bidder should submit the Demand Draft for E.M.D. &Tender (Bid) fee shall be
submitted in electronic format through online mode (by scanning) while uploading the
bid. This submission shall mean that E.M.D. & tender fee are received for purpose of
opening of the bid. Accordingly offer of those shall be opened whose E.M.D. & tender
(bid) fee is received electronically. However, for the purpose of realization of D.D. bidder
shall send the D.D. in original through RPAD / Speed post so as to reach to Chief
Accountant, SMC upto Dt.09/10/2026 up to 18:00 Hrs. as per schedule from the last
date of online submission of the bid as per tender notice.
VOL -1 Technical Bid |
Following Penalty based actions for not submitting D.D. in original shall be initiated by
Biding If Situation arises Relaxation / Punitive action
Tenderer's First If bidder fails to submit the Relaxation: Bidder shall pay Penalty as per below
Time original D.D. (For tender fee mentioned table within 10 Days from the last date of the
and E.M.D.) within stipulated Hard Copy Submission as mentioned in published tender
time mentioned in published notice.
tender notice for this work, in If bidder fails to deposit the penalty amount (as per
this situation. following table) Punitive action will be taken as below.
Punitive action : Abeyance of registration for 06 (six)
months with cancelation of E-tendering code for 06 (six)
Tenderer's If bidder fails to submit the Punitive action :Abeyance of registration for 06 (six)
Second Time original D.D. (For tender fee months with cancelation of E-tendering code for 06 (six)
and E.M.D.) within stipulated months
time mentioned in published
tender notice for this work, in
this situation.
Table for Penalty
Sr.No. Tender Amount in Rs. Penalty Amount in Rs.
2 More Than 1.00 Cr. And Up to 10.00 Cr 20,000/-
3 More Than 10.00 Cr. And Up to 50.00 Cr 30,000/-
4 More Than 50.00 Cr. And Up to 100.00 Cr 70,000/-
5 More Than 100.00 Cr 1,00,000/-
Any documents in supporting of bid shall be in electronic format only through online
(by scanning) & hard copy will not be accepted separately.
Assistant Municipal Commissioner
Surat Municipal Corporation
VOL -1 Technical Bid |
SURAT MUNICIPAL CORPORATION
DOMESTIC COMPETITIVE BIDDING
INVITATION FOR BID (IFB)
1. The Deputy Commissioner, Surat Municipal Corporation, Surat on behalf of Surat Municipal
Corporation invites bids for the works detailed in Table-1 given here.
Approximate value of Bid Completion
Sr. No. Name of Works works(Estimated Security/
Project Cost) (Rs.) EMD (Rs.)
1 Maintenance And Repairing Rs. 46,77,019.50 Ps. Rs. 47,000/- 12 Months.
Work Of Surat Castle Located (Excluding
At Chowk Bazaar, Surat. Monsoon)
The above work shall be executed on Percentage rate contract. The Contractor is also required
to maintain the above works for a Defect Liability Period after construction. The Project site for
the work is on the plot specified in Table-1.
2. Bidding is open to all eligible and qualified bidders meeting the eligibility and qualification
criteria as specified in clause no.2 and 3 of Instructions to Bidders. Bidders should, however,
be registered with the “E-1” class registration with Various Department of State
Government, CPWD & Surat Municipal Corporation.
3. Bidding documents can be downloaded from the website https://smctender.nprocure.com
upto 30/09/2026 up to 18:00 hrs. (IST). The Bidders are required to submit a non refundable
Tender fee and EMD as specified in Tender Notice from any Approved Banks to SMC. Any bid
without Tender Fee and EMD shall be rejected.
4. While Duly filled and signed copies of form no 1 to 11 specified in section III (Qualification of
Information Forms) shall be submitted online along with Eligibility and Qualification
5. Price Bid shall be submitted online.
6. Details required in hardcopy (i.e Tender fee,E.M.D, Affidavit and addenda/Corrigendum if
any) must be delivered to The Chief Accountant, Surat Municipal Corporation, Mugalisarai
Surat 395003 by R.P.A.D/ Speed Post, on or before 09/10/2026 up to 18:00 hours (IST)
through Registered Post/speed post of Indian postal department (Hand delivery or delivery
through courier is not allowed). Technical Bid (online) along with Eligibility and Qualification
Submissions will be opened on Dt.01/10/2026 after 11:00 (IST) onwards if possible, in the
presence of the bidders who wish to attend. If the office happens to be closed on the date of
receipt of the bids as specified, the bids will be received and opened on the next working day at
7. Bids must be accompanied by the earnest moneydeposit (Bid Security) of the amount specified
for the work in the Table-1 of the IFB. The earnest money will have to be in the form as
specified in Tender Notice and Tender Document from any of the Approved Banks to SMC.
VOL -1 Technical Bid |
8. Bid document consists of Instruction to Bidders, BOQs, General Conditions of Contract,
Technical Specifications can be seen in the Bidding documents.
9. No Physical Pre bid meeting shall be held. Bidders shall have to send their queries on email
address: [email protected] on or before 22/09/2026 and Time: up to 18:00
Hrs (IST). Answers to the queries shall be circulated electronically.
10. If SMC is convinced that the Bidder has resorted to material misrepresentation or provided
fraudulent information / statement, the said Bidder will be liable for disqualification / rejection
11. Surat Municipal Corporation, Surat reserves the rights to reduce/ increase the scope of work
and contract without assigning any reason thereof.
12. The Price Bids of those bidders who are shortlisted and qualified as per the eligibility and
qualification criteria will be opened on the date to be intimated to them later.
13. A bidder shall not be permitted to bid for works in the division responsible for award and
execution of contracts in which his or his spouse’s near relative (defined as first blood relations,
and their spouses) is posted as an officer in any capacity between the grades of Deputy
Commissioner and Technical Supervisor (both inclusive) or equivalent post.
14. No Engineer of officer rank or other officer employed in Engineering or Administrative
duties in an Engineering Department of the Surat Municipal Corporation is allowed to work as a
Contractor for a period of two years after his retirement from Surat Municipal Corporation service,
without Surat Municipal Corporation’s permission. This contract is liable to be cancelled if either
the Contractor or any of his employees is found any time to be such a person who had not obtained
the permission of the Government as aforesaid before submission of the tender or engagement in
the Contractor’sservice.
15. Conditional Bid shall not be accepted and liable for rejection.
16. SMC’s decision for selection or rejection of the offers shall be final and binding to all.
17. Tender Fee DD and EMD DD details (Bank Name, DD Number, Date of issue etc.) are to be
filed in the provided online form on https://smctender.nprocure.com Scanned copy of these
Tender Fee DD and EMD DD are to uploaded as a part of Technical Bid document submission.
These Tender Fee DD and EMD DD to be dispatch physically by RPAD/ Speed Post so as reach
to The Chief Accountant, Surat Municipal Corporation (main Office) up to Dt: 09/10/2026 up to
18:00 Hrs. Punitive action shall be initiated for non-submission of EMD & tender fees in original
to Account Department (Main Office) by bidder including abeyance of registration and
cancellation of E-tendering code for 06 months. All documents in supporting of bid shall be in
electronic format only through online (by scanning) during the bidding period & hard copy will not
be accepted separately. (Refer. page no.5 & 6 of this volume for details of punitive action)
All documents must be colored scanned to be seen as original. Scanning in black
and white or gray shall not be acceptable.
If photo copies are to be uploaded, all these documents must be attested and
notarized with clearly displaying stamp, number and name of notary.
Please verify before Online submission that Necessary Documents, Certificates etc.
are signed, Sealed and Attested wherever required in each and every respect.
VOL -1 Technical Bid |
18. It is to be noted that "Following Documents shall only be submitted in HARD
COPY to Surat Municipal Corporation by all bidders as Per ANNEXURE-A"
i Earnest Money Deposit as mentioned in tender.(i.e. D.D./Pay order)
ii Tender Fees as mentioned in the tender
iii Affidavit onRs.300 Non Judicial Stamp Paper stating that Bidder has provided true
information (As per the Form NO:-8 Page No:-49).
iv. Affidavit onRs.300 Non Judicial Stamp PaperAnti-Blacklisting Certificate(As per the
Form NO:-9 .PageNo:-50).
v. Affidavit onRs.300 Non Judicial Stamp Paper for Site Visit.(As per the Form NO:-11
vi. ANNEXURE-BAffidavit on Non Judicial stamp Paper of Rs.300/-(As per ,PageNO:-122).
vii. ANNEXURE-C SPECIMEN SIGNATURE AND PHOTOGRAPHS OF THE BIDDER
with duly Signed.(As per Page NO:-123).
viii. Addenda/corrigendum to this tender document, if issued must be signed and submitted.
Executive Engineer
Surat Municipal Corporation
VOL -1 Technical Bid |
SURAT MUNICIPAL CORPORATION
SECTION I – INSTRUCTIONS TO BIDDERS (ITB)
Table of Contents
Clause A. General Clause D. Submission of Bids
1 Scope of work 18 Sealing and Marking of Bids
2 Eligibility of Bidders 19 Deadline for Submission of Bids
3 Qualification of the Bidders 20 Late Bids
4 Cost of Bidding 21 Modification and Withdrawal of Bids
5 Site Visit E. Bid Opening
Eligible Material, Equipment and Opening of Eligibility and Qualification
Services Submissions
Examination of Eligibility and Qualification
B. Bidding Documents and Evaluation 23 Submissions and Determination of
Eligibility and Qualifications
7 Content of Bidding Documents 24 Opening of Price Bids
Prebid Meeting and Clarification of Examination of Price Bids and Determination
Bidding Documents of Responsiveness of Price Bid.
9 Amendment of Bidding Documents 26 Correction of Errors
Evaluation and Comparison of Price
C. Preparation of Bids
10 Language of Bid 28 Rate Analysis
11 Documents Comprising the Bid 29 Clarification of Bids
12 Bid Prices 30 Process to be Confidential
13 Currencies of Bid and Payment F. Award of Contract
14 Bid Validity 31 Award
Employer's Right to Accept any Bid and to
15 Bid Security
Reject any or all Bids
16 Alternative Proposals by Bidders 33 Notification of Award
17 Format and Signing of Bid 34 Signing of Agreement
35 Initial Security &Performance Security
36 Corrupt or Fraudulent Practices
38 Change in Quantity
39 New Equipment and Material
40 Rights Reserved
41 Royalty Pass
VOL -1 Technical Bid |
1. Scope of Work
1.1 Surat Municipal Corporation hereinafter called "Employer" or “SMC” invites bids forthe
construction of works (as defined in these documents, hereinafter referred to as "the Works")
detailed in the table given in the Notice Inviting Tenders.
1.2 The Scope of Works comprising followings:
(a) Repair/Restoration,Re-use and development work: as per the as per the BoQs specified in
Section VI, Drawings specified in section VIII and Technical Specification specified in
section V. The Works also includes following as well as other works specified elsewhere in
the bidding document.
i. Site clearance, removal of tree stumps and dismantling of obstructions, encroachments
etc. if any before commencement of the Works.
ii. The scope of work includes construction of all the items specified in BoQ, drawings &
specifications along with incidental work to complete the project as per conditions laid
in the contract document.
iii. True and proper setting out and layout of the Works, setting of benchmarks, preparation
of working drawings where required and provisions of all necessary labour,
instruments, and appliances;
iv. Any other item of work as may be required to be carried out for completing the Project
in all respects in accordance with the provisions of the Contract.
(b) Repair and Maintenance: The Contractor is required to carry out Repair/ Maintenance/
Improvement Work during the Defect Liability Period.
.(c) Restoration /Improvement and Repair Work to be done in accordance with the Indent
i. Employer shall issue Indent/Maintenance Notice during the Defect Liability Period cum
Maintenance Period specifying the need for repair & maintenance work (the“Indent”). Such
Indent shall be in writing and shall also specify the types of Works to be carried out and also
Intended Completion Date of all such Work. It will also specify work that arise owing
Vandalism and Accident or regular defects in initial work, manufacturing defect or
requirement of regular maintenance. The decision of Engineer in charge shall be final. All
such Work shall be completed in an Intended Completion Date specified in the Indent after
consulting the contractor. However, the decision of Employer/Engineer in Charge shall be
final in this regard. Any breach or delay in work shall be resulted in to damages. Damages
shall be commensurate with types of breach.
ii. The cost any repair and maintenance work required to be carried out owing to defection
works/manufacturing, wear and tear, damages attributable to the Contractor’s or to accident/
vandalism by the employee or people hired by Contractor shall be borne bythe contractor
iii. The Contractor shall ensure quality assurance of various components of the repair and
maintenance Works as per the Technical Specification and relevant standards of BIS.
iv. The Contractor is required to maintain adequate inventory of major Items.
v. Upon completion of repair/ maintenance work, Contractor is required to clear the project Site
from the debris and additional non-consumables immediately.
VOL -1 Technical Bid |
d) The Contractor is required to take appropriate safety measures and ensure the safety of its
employee and users of the Project Site during the Construction and Repair& Maintenance Period
as per the relevant clause of GCC and Technical Specification.
e) The works under this Contract shall be carried out in accordance with the bidding documents
constituting the contract.
f) The Works shall also include followings
i The contractor shall in accordance with the requirement of the Engineer-in-chargeaccord all
reasonable facilities for any other contractors or piece workers engaged by the
Owner/Employer and their work in and of any other properly authorized authorities or
statutory bodies who may be employed on the execution on or near the site of any work not
included in the contract or of any contract which the Owner/Employer may enter into, in
connection with ancillary works if any.
ii The Contractor shall conduct his work so as not to interfere with or hinder the progress or
completion of the work being performed by other contractor or piece workers or by the
Owner/Employer and shall as far as possible arrange his work and shall place and dispose of
the materials being used or removed so as not to interfere with the operations of the other
contractors, piece workers or the Owner/Employer.He shall co-ordinate his work with that of
the other in an acceptable manner and shall perform it in proper sequence to that of others.
iii Ensuring quality assurance of various components of the Works as per Technical
specifications and relevant standards of BIS and other restoration works related standards.
iv Providing and maintaining fully equipped laboratory for testing and site office, including the
supply of testing equipment and consumables; all as prescribed in the relevant
specifications. If an in-house laboratory is not maintained, then testing shall be done at a
laboratory directed/ approved by Engineer-in-charge.
V Submission of Completion Drawings/as built drawings and other related documents as
directed by Engineer in charge.
vi Any other item as directed by the Engineer including insurance cover.
vii All stipulated measures regarding labour employment and their welfare are to be complied
with as per prevailing laws. Provide appropriate bath and toilet facilities.Providing mosquito
nets for workers staying overnight at the site. Ensuring no stagnant water remains at the site
that could lead to mosquito breeding at the site or around the site.Co-operate with VBDC
staff that might inspect the site periodically for the same.
Viii Clearing of site from debris and contractor’s equipment’s before handing over of the Works;
Availability of the Project Area: The Employer shall provide the right-of-way for Works to the
contractor. However, the Contractor shall have to make his own arrangements for the land
required by him for borrow areas, quarries, site offices, fabrication yard, testing laboratories,
labour camps, other camps, etc.
i. The successful bidder is required to complete the work within the period stipulated in table
given in the Notice Inviting Tenders from the Date of Site Handover Date.
ii. The Employer may engage a Supervision Consultant or any other person to act as Engineer
for the project. There may be a Project Director of the Employer acting as the Employer’s
representative.
VOL -1 Technical Bid |
h) All type application contractors are required to have their own employer's code number under
EPF Act. 1952 and are required to comply the applicable provisions of said statuted regularly
i) Further the contractors for services are required to produce the certified copies of paid chalans in
respect of employees / workers employed by said contractor in respect of work allotted by Surat
Municipal Corporation, along with copies of pay roll and muster roll. If the same are not
produced, the bills will not be released.
j) The contractor shall take utmost care during excavation to protect existing underground utilities.
All water main lines / water connections, storm / sewage main / house connection, electricity
cable, telephone cable, gas pipeline or any other utilities and structures shall be protected by the
contractor. However, if met during excavation, any damage caused shall be rectified by the
contractor at the earliest and all the rectification cost shall be borne by the contractor. If the bill
for rectification work (if carried out by the concerned agencies / departments) is put by such
agencies / department, the same shall be payable by the contractor, if not so it will be deducted
and recovered from the running bills to be paid to contractor.
k) Before starting execution, the contractor shall take all existing levels, demarcation of plot
boundaries for total area, boundaries of independent structures and landscape profiles, marking of
co-ordinates of different structures, various other components, lineing out and levelling with total
station instruments including constructing necessary grit pillars for line and levels with
establishing necessary bench marks, also take levels once again after the completion of each task
at his own cost and get it approved from the engineer-in-charge or PMC. The quantity of
excavated earth will be measured on the basis of R.L. before excavation and R.L of final
excavation only.
l) The variation in quantity may be increased or decreased up-to any extent as per progress and
specific requirement for Client (SMC) / Consultant (PHC) and contractor shall not entitle to carry
any sorts of compensation.
M) The contractor shall make all arrangements necessary for execution as per site condition (like
dewatering, making of bund/retaining of earth including soaring / strutting etc ) at his own cost and
no extra cost shall be paid for the same.
N) All material shall have to be
a) Approved by engineer/ consultant before execution
b) All natural material like stone / Kota stone/marble/granite/wood etc. has to be approved by
engineer/PMC/ TPI/consultant before execution.
C) For all cement concrete work, the contractor will comply with all obligations
imposed/requested by the consultant i.e. he may readily agree to provide RMC if required and
asked by the consultant
2. Eligibility of Bidders
2.1 Bidders shall not be under a declaration of ineligibility for corrupt and fraudulent practices by the
Central Government, the State Government, Local Self Government body or any public
undertaking, autonomous body, authority by whatever name called under the Central, the State
Government or local self Government body in India and any Government body abroad.
2.2 Invitation for Bids is open to all the contractors having experience of similar work as indicated in
clause 3.1(B) of this section.
VOL -1 Technical Bid |
2.3 Bidder should not be blacklisted by any government organization/ company/ institution/body.
2.4 A bidder shall not be affiliated with a firm or entity which;
i) Has provided consulting services during the preparatory stages of the Works or of the project
of which the Works form a part, or
ii) Has been hired (or is proposed to be hired) by the Employer as Engineer for the Contract.
2.5 Only bidders which are An Individuals, Proprietorships, constituted as Companies under the
Indian Companies Act, 1956, or are Partnerships under the Indian Partnership Act, shall be
eligible to participate in bidding as single bidder only.
2.6 Bidders are not allowed to Bid by forming Consortium or Joint Venture. Only Single bidder is
allowed to participate in bidding.
2.7 The Bidder should be profit making firm (As per last audited financial statement of the year
2025-26) and its Net worth of last audited three financial years should be positive.
3. Qualification criteria of Bidders
3.1 The applicant, who is not capable of meeting the requirements listed below, shall not be qualified
for the work. Qualification shall be based on the Applicant satisfying all of the following
minimum criteria regarding their particular experience, financial position, personnel and
equipment capabilities and other relevant information as demonstrated by the applicant’s
responses in the statements. The qualifications, capacity and resources of proposed sub-
contractors shall not be taken into account in determining the applicant’s compliance with the
qualifying criteria.
A. The contractor shall have an active experience of at least 07 (Seven) years in similar
B. Experience of having successfully completed similar works during the last 07 years, in similar
works., ending on the last day of the month previous to the one in which bids are invited,
should be either of the following:
(i) 03 similar completed work costing not less than the amount equal 40% of the
estimated cost,
(ii) 02 similar completed work costing not less than the amount equal 50% of the
estimated cost,
(iii) 01 similar completed work costing not less than the amount equal 80% of the
estimated cost.
Note: (1) Evidence in terms of necessary supporting documents and client certificates (i.e.Completion
Certificate) for similar work executed (Form no:-4).
(2) Work completion certificates shall be in form of 3-A issued by Government / semi
Government/Local Government authorities. Only work order copies shall not be considered
for work experience.
C. Definition of similar type of works:
Similar Works means ''Conservation, Restoration, Strengthening, Repair and Maintenance
ofa Heritage structure "during the last 7 years ending on the last day of the month /previous
to the one in which bids are invited. Bidder having working experience of Lime work and
Wood work shall be preferable. ( Note- if required site visit of completed work will be visted
to evaluated the bidder.)
VOL -1 Technical Bid |
D. Average Annual Financial Turnover during the last 03 years, ending on 31st of March of the
previous financial year , should be at least 30% of total estimated amount of the tender.
E. Fresh solvency certificate from bankers of scheduled bank/ nationalized bank. Minimum value
of solvency shall be atleast 20% of the estimated cost of the tender.
F. The contractor shall have a valid PAN registration .
G. The contractor shall have a valid GST registration certificate.
H. The bidders shall have Registration certificate of appropriate class either
with Various Department of State Government, CPWD, PWD, MES &
Surat Municipal Corporation for civil construction works. The Bidder is
required to submit the valid registration certificate.
I. Any other documents /certificates/Annexure/Statements/Declaration/Affidavits etc. mentioned
elsewhere in proposed tender.
J. Experience as joint venture or as sub contractor shall not be considered.
K. Following enhancement factors will be used for the cost of works executed and financial
figures to common base for the value of the works completed in India.Cut of month shall be
considered from month of tender submission
Financial Year Multiplying factor
* Here assessment year shall be reckon from year and month in which tender is submitted.
L Bidder should not be blacklisted by any government organization / company / institution
M (i) The Contractor shall employ adequate numbers of full time technically qualified engineers
during the execution of this work. The Engineers so employed for the work must have
sufficient experience to handle the work independently. Such Engineers shall have to stay at
the site of work and they shall not be entrusted with any other duty except of this work. Even
if the contractor or a partner of the Contractor, firm is a Graduate Civil Engineer, employment
of adequate number of engineers will however be necessary for the execution of the work on
site as may be decided by the Engineer-In-Charge.
(ii) The bidder should provide for- (i) One Team leader (B.E.Civil / B. Arch /Conservation
Architect) of Minimum Five years relevant experience
(i) One Site Engineer for civil works (B.E. Civil)) with minimum 3 years of specific
experience in conservation works.
VOL -1 Technical Bid |
(iii) One project manager to co-ordinate and smoothly execute the project, with five (05) years or
more experience in the management of conservation - execution sites.
3.2 Bidder shall submit following documents/ information as a part of Eligibility
and Qualification submissions Online.
(a) The Bid Security/EMD and Tender Fees as required under the Tender Notice section of
thisTender. (colored scanned).
(b) Letter of Bid as per Form No: - 1(Page NO-43). (Colored scanned).
(c) General information, Legal Status including Memorandum of Associations(MOA), Articles of
Associations (AOA)& Partnership Deed; as the case may be; as per Form no 2.(PageNO-44)
(colored scanned & Attested).
(d) Average Annual Financial Turnover during the last 03 years, ending on 31st of Marchof the
previous financial year, should be at least 30% of total estimated amount of the tenderas per Form
no 3.(Page NO-45) (colored scanned & Attested).
(e) Summary of Similar nature of projects (as defined in clause 3.1( A to C)) completed in last seven
years as per Form No:-4 (Page No:-46) (colored scanned & Attested).
(f) Summary of Current Contract Commitments/ Works in Progress as per FormNo: -5 (PAGE No:-
47) (colored scanned & Attested)
(g) Provide signed CVs of key personnel and supporting educational certificate as specified in clause
3.1(M) and as per theFormNo:- 6 (Page no:-48) in section III. (Colored scanned & attested)
(h) Power of Attorney to authorized signatory of Bidder (As per the Form no:-7 Page NO:-49).
(Colored scanned & notarized)
(i) Affidavit onRs.300 Non-Judicial Stamp Paper stating that Bidder has provided true information
(As per the FormNO:-8 Page No:-50). (Colored scanned & notarized).
(j) Affidavit onRs.300 Non Judicial Stamp Paper Anti-Blacklisting Certificate (As per the Form NO:-
9 .PageNo:-51). (Colored scanned & notarized).
(k) Availability of Equipment’s (As per the FormNO:-10 PageNo:-52). (Colored scanned)
(l) Affidavit onRs.300 Non Judicial Stamp Paper for Site Visit.(As per the Form NO:-11.PageNo:-53).
(Colored scanned & notarized).
(m) The bidders shall have “E-1” class registration with with Various Department of State
Government, CPWD, PWD, MES & Surat Municipal Corporation for civil
construction works. (Colored scanned &attested).
(n) Balance Sheet for the last 3 years. (Colored scanned & attested).
(o) ANNEXURE-B Affidavit on Non Judicial stamp Paper of Rs.300/-(As per,PageNO:-131).
(Colored scanned & notarized).
(p)ANNEXURE-C SPECIMEN SIGNATURE AND PHOTOGRAPHS OF THE BIDDER (As per
PageNO: -132). (Colored scanned & attested).
VOL -1 Technical Bid |
(q) Fresh solvency certificate from bankers of scheduled bank/ nationalized bank. Minimum value of
solvency shall be atleast 20% (Rs.9,35,405.00) of the estimated cost of the tender. (colored
scanned & attested)
(r) A valid PAN, and GST registration certificates. (Colored scanned & attested).
(s) Provident Fund Registration Certification. (Colored scanned & attested).
(t) Additional information regarding litigation, debarment, arbitration, etc. (colored scanned &
(u) Signed Copy of Addenda and corrigendum if any. (Colored scanned & Attested).
Please note that submission of all above essential documents are
mandatory, else bidder may be liable for rejection and no communication
shall be made thereof.
Please verify before Online submission all the Original document must be colored
scanned,that Necessary Documents, Certificates etc. are signed,Sealed ,Attested and
notarized with clearly displaying stamp, number and name of notary wherever required
in each and every respect.
Scanning in black and white or gray shall not be acceptable
All the documents comprising the Eligibility and Qualification submission shall be signed by
Authorized Signatories of Bidder.
Please note that non-submission of Prequalification documents, forms, schedules and other
supporting documents as well as price bid does not absolve the bidders from any liability created
from the bid conditions and bidding process..
Technical Bid & Schedule-B (duly signed & stamped) in Hard copy shall be
submitted by successful bidder upon intimation from SMC.
3.3 Disqualification
Even though the Bidders may meet the above criteria, they are subject to be disqualified for any of
the following reasons:
a) Misleading or false representation in the forms, statements and attachments submitted under
b) Record of poor performance such as abandoning the work, rescinding of contract for which
the reasons are attributable to the non-performance of the contractor, consistent history of
litigation awarded against the applicant or financial failure due to bankruptcy.
c) Has been identified by the Employer as poor performer in implementation of ongoing Surat
Municipal Corporation’s/ or other Government department or Local Body’s works.
3.4 Debarment/ Black listing
Notwithstanding the above, the Employer may debar or blacklist any of the bidder(s) for their
misleadingor false representations in the forms statements, etc. for the period to be decided by
VOL -1 Technical Bid |
4. Cost of Bidding
The bidder shall bear all costs associated with the preparation and submission of his bid and the
Employer will in no case be responsible or liable for those costs.
5.1 The bidder is advised to visit and examine the Project Site of Works and its surroundings
and obtain for itself on its own responsibility all information that may be necessary for
preparing the bid and entering into a contract for construction of the Works. The costs of
visiting the Site shall be at the bidder's own expense.
5.2 The bidder and any of its personnel or agents will be granted permission by the Employer to
enter its premises and lands for the purpose of such inspection, but only upon the express
conditions that the bidder, its personnel and agents, will release and indemnify the Employer
and its personnel and agents from and against all liability in respect thereof and will be
responsible for death or personal injury, loss of or damage to property and any other loss,
damage, costs and expenses incurred as a result of the inspection.
5.3 The bidder shall provide an affidavit on a Rs 300/- government stamp paper in the format as
attached FORM-11 in the Tender copy.
6 Eligible Material, Equipment and Services
At the Employer's request, the bidder having offered the lowest evaluated Price Bid may be
required to provide evidence of the origin of materials, equipment, and services to the satisfaction
of the Employer.
B. Bidding Documents
7 Contents of Bidding Documents
7.1 The set of bidding documents comprises the documents listed below and should be read in
conjunction with any Addenda issued in accordance with Clause 9 ITB.
7.2 The bidder is expected to examine carefully the contents of all the above bid documents. Failure
to comply with the requirements of bid documents will be at the bidder's own risk. Pursuant to
Clause 24 and 26 of ITB, bids which are not substantially responsive to the requirements of the
bidding documents will be rejected.
7.3 Employer may ask, at its sole discretion, for additional information from bidders at any stage of
the bidding process.
8. Pre Bid Meeting and Clarification of Bidding Documents
8.1 No Physical Pre bid meeting shall be held. Bidders shall have to send their queries on email
address: [email protected] on or before Dt. 22/09/2026 and Time: up to 18:00
hrs. Answers to the queries shall be uploaded on the website https://smctender.nprocure.com
possible circulated electronically.
8.2 Any modification of the bid document, which may become necessary as a result of the pre bid
meeting, shall be made by the Employer exclusively through the issue of an Addendum pursuant to
9 Amendment of Bidding Documents
9.1 Before the deadline for submission of bids, the Employer may modify the bidding documents by
VOL -1 Technical Bid |
9.2 Any addendum thus issued shall be part of the bidding documents. The addendums shall be posted
on https://smctendr.nprocure.com. Bidders are required to regularly check the website for such
9.3 To give prospective bidders reasonable time in which to take an addendum into account in
preparing their bids, the Employer may its sole discretion, extend as necessary the deadline for
submission of bids.
C. Preparation of Bids
10. Language of Bid
The bid, and all correspondence and documents related to the bid exchanged between the bidder
and the Employer shall be written in the English language. Supporting documents and printed
literature furnished by the bidder may be in another language provided they are accompanied by
an accurate translationof the relevant passages in the English language, in which case, for
purposes of interpretation of the bid, the English translation shall prevail.
11. Documents comprising the Bid
Eligibility and Qualification submissions specified in Clause 2 &3 and defined hereunder
shall be submitted through online only.all the original document must be colored
scanned, that Necessary Documents, Certificates etc.) are signed,Sealed ,Attested and
notarized with clearly displaying stamp, number and name of notary wherever
required in each and every respect.
a) Eligibility and Qualification Submissions
The following shall constitute the “Eligibility and Qualification Submissions” which are to be
submitted in online:
i) Tender Fees and Bid Security/EMD for an amount as specified in the Tender Notice and in the
form specified in Clause 15 of ITB.
ii) Eligibility and Qualification Information as specified in Clause2, Clause 3 in sub clause 3.1 and
Clause 3.2 of ITB. These are detailed information lists which the bidder may carefully review
and provide as specified.
iii) Any other material/ information required to be submitted in accordance with the Instructions to
b) Price Bid (Volume-II of this Tender Document)
(Can be seen online and to be submitted online through https://smctender.nprocure.com)
The Price Bid shall consisting of Form of Price Bid which can be seen online as per Volume-II
of this Tender document and duly filled by filling percentage rates of above/below than estimated
cost mentioned in BoQ both in words and figures online through
https://smctender.nprocure.com .
The bidder shall submit the Price Bid online through e-tendering only. No Price bid in physical
form will be accepted and any such offer if received by SURAT MUNICIPAL CORPORATION
will be out rightly rejected.
11. The above Price Bid shall be submitted as per Volume-II of this Tender (can be seen online)
before the Bid submission Date and time specified in Tender Notice section online through
https://smctender.nprocure.com
The Price Bid shall not be submitted in hard copy and shall be submitted online as mentioned
VOL -1 Technical Bid |
12.1 Unless stated otherwise in the bidding documents, the Contract shall be for the whole Works
as described in bidding documents, based on the percentage rate amount in the Bill of
Quantities submitted by the bidder.
12.2 The bidder shall fill in percentage rate above and below and total amount (Both in figures and
12.2 The bidder shall fill in percentage rate above and below and total amount (Both in figures and
words) for overall items of the works provided in the Bill of Quantities (the “Total Price
12.3 GST (Goods and Service Tax) has come in existence from 1st July, 2017. Contractor /
Successful Bidder is bound to pay any amount of GST prescribed by the Govt. of India as per
the Term of Contract agreed upon during the course of execution of this Contract.
During the course of execution of Contract if there is any change in Rate of GST (Goods and
Service Tax) by the Government, the same shall be reimbursed / recovered separately by
SMC, subject to submission of Original Receipt / Proof for the amount actually remitted by
the Successful Tender / Contractor to the Competent Authority along with a Certificate from
Chartered Accountant of Contractor/ Successful Bidder certifying that the amount of GST
paid to the Government and the same shall be intimated / submitted / claimed within
(Thirty) Days from the date of payment. Remittance of GST within stipulated period shall be
the sole responsibility of the Successful Bidder / Contractor, failing which, SMC may recover
the amount due, from any other payable dues with SMC and decision of Municipal
Commissioner shall be final and binding on the Contractor / Successful Bidder in this regard.
Further, the non-payment of GST to the Government may lead to the termination of contract
and forfeiture of Security Deposit / Performance Guarantee Amount.
If imposition of any other new Taxes / Duties / Levies / Cess or any other incidentals etc. or
any increase in the existing Taxes / Duties / Levies / Cess or any other incidentals etc.
(Excluding GST) are imposed during the course of the contract, the same shall be borne by the
Contractor / Successful Bidder only in no case SMC shall be liable for the same and obliged
to reimbursed and no dispute regarding same shall be entertained by SMC. Bidder / firm
should have to produce attested copy of sale tax certificate with proof of residence.
The contractor will submit the invoice to the SMC having GSTIN of SMC mentioned therein
and the taxes shall be shown separately on the face of the invoice so as to claim as ITC by
The Construction labour welfare cess shall be deducted from R.A. bill of the contractor at the
prevailing rate. The current rate of labourcess is 1% of the capital amount.
As per the central goods and Service Tax Act-2017 Any Goverment department, local bodies
and government undertaking public adventures published tenders amounting more then Rs.
2,50,000 & which commodities/ servies are comes under taxation than 2% TDS (1% for
SGST & 1% for CGST) should be deducted. And if commodities/Servies are provided from
interstate then 2% TDS should be deducted of IGST.
NOTE:-The Rates mentioned in BOQ are excluding GST. GST will be reimbursed separately (if
applicable as per the opinion of Account department of SMC / GST Consultant of SMC)
as per the prevailing GST Rates decided by the Government.The contractor is
invariably bound to any changes in GST Rates made during the course of the work. The
payment (if applicable) for GST will be only released only after the applicable Amount
reflects on Government portal. Decision of Account Department of SMC regarding
applicable GST Rates will befinal.
VOL -1 Technical Bid |
13 Currencies of Bid and Payment
13.1 The rates and the prices shall be quoted by the bidder in Indian Rupees only. In no circumstances
shall the price bid be quoted in any other currency except the INR.
14 Bid Validity
14.1 Bids shall remain valid for a period of 120 days (one hundred and twenty days) from the date
of opening of Price Bid.
14.2 In exceptional circumstances, prior to expiry of the original bid validity period, the Employer
may request the bidders to extend the period of validity for a specified additional period. The
request and the responses thereto shall be made in writing. A bidder may refuse the request
without forfeiting his Bid Security. A bidder agreeing to the request will not be required or
permitted to modify his bid but will be required to extend the validity of his Bid Security for the
period of the extension, and in compliance with Clause 15 of ITB in all respects.
15 Bid Security
15.1 The value of EMD/Bid Security is Rs.47,000.00/- 100 % in the form of Demand Draft or pay
order of nationalized / scheduled bank only in favour of Commissioner, Surat Municipal
Corporation, Surat through Approved Bank to SMC only and payable at Surat only.
15.2 The earnest money deposit in the form of FDR or Cheque shall not be accepted. Demand Draft/
Pay Order for the purpose of this tender shall be from Approved Bank only (See Form no. 5 of
Section VII). The List of Approved Banks is specified in Form no 5 of Section VII (Page N0:-
15.3 Any bid not accompanied by Tender Fee and an acceptable Bid security and not secured as
indicated in Sub Clause 15.1 and 15.2 of ITB above shall be out rightly rejected by the
Employer as non–responsive and Bid Shall be considered as not in compliance with
requirement of Bid Documents.
15.4 The earnest money/Bid Security of the unsuccessful bidders shall be returned as promptly as
possible, on finalization of acceptance/rejection of the tenders received or as decided by the
15.5 The Bid Security of the successful bidder, along with second lowest tenders, will be returned/
discharged when the bidder has furnished the required Performance Security and signed the
15.6 Bid Security is non interest bearing deposit.
15.7 The Bid Security may be forfeited-
a) if the bidder withdraws or modifies his bid during the period of bid validity;
b) if the bidder does not accept the correction of his bid price, pursuant to Clause 27;
c) in the case of a successful bidder, if bidder fails within the specified time limit to:
Furnish the required Performance Security or
ii) Sign the Agreement.
15.8 The Bid Security of bidders other than first (L1), second and third lowest (L2 & L3) will be
returned within 30 days of opening of financial bids.
16 Alternative Proposals by Bidders
VOL -1 Technical Bid |
Bidders shall submit offers, which comply with the requirements of the bidding documents,
including the conditions of contract, basic technical design as indicated in the Drawings and
Specifications. Conditional offer or alternative offers will not be considered further in the process
of bid evaluation. Bids based on alternative designs shall not be considered.
17 Format and Signing of Bid
17.1 The Price Bid shall be dully signed and submitted in online format only. While form No. 1 to
dully filled and signed as specified in section III of ITB shall be submitted online and
mentioned in as per. IFB-18 (Page N0-9) document Submited in Hard Copy.
17.2 Eligibility and Qualification Information as specified in Clause2, Clause 3 in sub clause 3.1 and
Clause 3.2 of ITB Shall be submitted online. Please verify before Online submission all the
original document must be colored scanned ,that Necessary Documents, Certificates
etc.) are signed,Sealed, Attested and notarized with clearly displaying stamp, number
and name of notary wherever required in each and every respect.
17.3 The bid shall contain no alterations, omissions or additions, except those to comply with
instructions issued by the Employer, or as necessary to correct errors made by the bidder, in
which case all such corrections shall be initialed by the person or persons signing the bid.
17.4 All witnesses and sureties shall be persons of status and probity and their full names, occupations
and addresses shall be printed below their signatures. All signatures shall be dated.
VOL -1 Technical Bid |
D. Submission of Bids
18 Sealing and Marking of Bids
The bidder shall submit the Bid in two parts, the Eligibility and Qualification Submissions and
the Price Bid pursuant to clause 11 of this ITB. The Eligibility and Qualification Submissions
shall be submitted online through e- tendering process only (through n- procure).
18.1 The Hardcopy Submissions Envelope shall contain following Document..
Maintenance And Repairing Work Of Surat Castle Located At Chowk Bazaar, Surat.
Eligibility and Qualification Submissions –
The details are to be submitted online on https://smctender.nprocure.com as per Clause
Page No:- : 13 &
It is to be noted that "Following Documents shall only be submitted in HARD
COPY to Surat Municipal Corporation by all bidders as Per ANNEXURE-
i Earnest Money Deposit as mentioned in tender. (i.e. D.D. / Pay Order)
ii Tender Fees as mentioned in the tender
iii Affidavit on Rs.300 Non-Judicial Stamp Paper stating that Bidder has provided
true information. (As per the Form No: -8 Page No: -50).
iv Affidavit on Rs.300 Non-Judicial Stamp PaperAnti-Blacklisting Certificate (As per the
Form NO: -9 Page No:-51).
v Affidavit on Rs.300 Non Judicial Stamp Paper for Site Visit. (As per the Form NO:-11.
Page No: - 53).
vi ANNEXURE-B Affidavit on Non Judicial stamp Paper of Rs.300/-(As per,PageNO:-
vii ANNEXURE-C SPECIMEN SIGNATURE AND PHOTOGRAPHS OF THE BIDDER
with duly Signed. (As per Page No:-132).
viii. Addenda/corrigenda to these tender documents, if issue must be signed and
submitted.Please note that price bid shall not be submitted in hard copy under any
circumstances. This will hold the tender liable for rejection.
18.2 Hard Copy documents specified above clause no 18.1 shall be placedunder envelope. The
envelope shall:
a) Be addressed to the Employer at the following address and shall be sent through Speed
Post/RPAD only.
Chief Accountant,
Surat Municipal Corporation,
Mugalisarai, Surat-395003. Gujarat.
b) Bear the following identification:
1. Tender notice no.: AMC/HR/01/2026-27
2. Department :Heritage Cell
VOL -1 Technical Bid |
18.3 Name of work: Maintenance and Repairing Work of Surat Castle Located at Chowk
If the outer envelope is not sealed and marked as above, the Employer will assume no
responsibility for themisplacement or premature opening of the bid.
18.4 The Price Bid (Volume 2 of this Tender Document) shall be submitted online in the format
specified in Volume 2 of this Tender (can be seen online) by filling rates of each item of BoQ
through e-tendering only. No Price bid in physical form will be accepted and any such offer if
received by SURAT MUNICIPAL CORPORATION will be out rightly rejected.
The above Price Bid shall be submitted as per Volume-II of this Tender (can be seen online)
before the Bid submission Date and time specified in Tender Notice section online through
https://smctender.nprocure.com. The Price Bid shall not be submitted in hard copy and shall be
submitted online as mentioned above only.
18.4 The Technical Bid as specified in clause no 11 of ITB shall be submitted online.
19 Deadline for Submission of Bids
19.1 Refer “schedule of E tender” & “General terms & conditions” mentioned in E tender invitation
notice. Bidder shall quote their offer in electronic format only on website https://
smctender.nprocure.com on or before Dt.30/09/2026 up to 18.00 hrs (IST).
19.2 The Employer may, at his discretion, extend the deadline for submission of bids by issuing an
amendment in accordance with Clause 9 of ITB, in which case all rights and obligations of the
Employer and the bidders previously subject to the original deadline will thereafter be subject to
the deadline as extended.
20.1 Any bid received by the Employer after the deadline for submission of bids prescribed in
Clause19 above will be rejected returned unopened to the bidder.
20.2 No bid may be modified or withdrawn after the deadline for on line submission of bids
20.3 Withdrawal or modification of a bid between the deadline for on line submission of bids and the
expiry of the original period of bid validity specified in Clause 14 above or as extended pursuant
to Clause 14 above shall result in the forfeiture of the bid security pursuant to Clause 15 above.
21 Modification and Withdrawal of Bids
21.1 Only Price Bid can be modified by bidder at any time before online submission uptolast
E. Bid Opening and Evaluation
22 Opening of Eligibility and Qualification Submissions
22.1 The Employer will open the Technical Bid online and Eligibility and Qualification Submissions
(submitted online) on the date, time and place specified in Tender Notice and IFB section.. In the
event of specified date of bid opening being declared as a holiday for the Employer, then if
possible, Technical Bid (Online) and Eligibility and Qualification Submissions will be opened at
the appointed time and location on the next working day.
After opening of the Qualification bid, Surat Municipal Corporation. will examine verify the
details & submission by the bidders thoroughly. The Qualification bid not fulfulling the
requirement as per the qualification criteria will be rejected outrightly. And price-bid of the
unsuccessful tenderers will not be opened.
VOL -1 Technical Bid |
22.2 If any Bid contains any deviation from the Bids documents and /or if the same does not contain
Bid security and Tender Fee in the manner prescribed in the Bid documents, then that Bid will be
rejected andthe Bidder informed accordingly.The Price Bid shall not be opened at this stage.
23 Examination of Eligibility and Qualification Submissions and Determination of Eligibility
and Qualifications
23.1 Prior to evaluation of Eligibility and Qualification Submissions, the Employer will determine
whether the bid is accompanied by the required Bid Security and Tender Fee.
23.2 If the Bid Security furnished does not conform to the amount and validity period as specified
in the Invitation for Bids and has not been furnished in the form specified in Clause 15 and
not from the list of Approved Banks, the bid shall be rejected by the Employer as
nonresponsive and the Bids will be returned to the bidder.
232.3 Subject to confirmation of the Bid Security by the issuing bank, the Eligibility and
Qualification Submissions accompanied with valid Bid Security will be taken up for further
evaluation. In case, the Bank does not confirm the Bid Security, the bid shall be rejected as
non-responsive and no further evaluation carried out for that particular bidder.
23.4 The Eligibility and Qualification Submissions will further be examined to determine whether
the bid has been properly signed and meets the eligibility and qualification criteria as per
clause 2 and clause 3 of Instruction to Bidders section, has the required available bid capacity
and is accompanied by the requisite certificates/ documents, undertaking and other relevant
information specified in the bid documents and is substantially complied with the requirement
of the bidding documents and provides any clarification for ascertaining the correctness of the
information/ details that the Employer may require pursuant to Bid Evaluation.
23.5 If the Eligibility and Qualification Submissions is not complied with eligibility and
qualification requirements of bidding documents, it will be termed as non responsive and
rejected by the Employer. It will not subsequently be made in compliance with bidding
documents by correction or modification or withdrawal of the non-conforming deviation or
reservation. The Employer at its sole discretion, reserves the right to ask for further
information/ documents from the bidder/s.
23.6 Bidders whose bids meet eligibility and qualification requirements of bidding documents
specified in Clause 2 and 3 of ITB and submitted required Tender Fees and Bid Security in
accordance with clause 15 shall be termed as technically responsive bids.
23.7 The Price Bid of those bidders whose Eligibility and Qualification Submissions is determined
to benon responsive and not in compliance with the requirement of bidding documents
pursuant to this Clause23 shall not be opened.
24 Opening of Price Bids
24.1 Price Bids of the bidders whose bid capacity has already been exhausted shall not be opened
on the bid opening date.
24.2 Price Bids of those bidders whose Eligibility and Qualification Submission has been
determined to be in compliance with bidding document and responsive in accordance with
Clause 23 (i.e. meeting eligibility criteria specified in clause 2, qualification criteria specified
in clause 3,submitted all necessary documents specified in clause no 3.2, and submitted
required Tender Fee and Bid Security also provided online) shall be opened in presence of the
bidders or their representatives who choose to attend on the date intimated to such bidders. In
the event of specified date of Price Bid opening being declared a holiday for Employer, the
‘Price Bids’ shall be opened at the appointed time and location, if possible, on the next
VOL -1 Technical Bid |
24.3 The prices quoted by the bidders meeting the bid capacity criteria will be compared (i.e. Total
Bid Price quoted by the bidders shall not exceed their respective Bid Capacity) and would be
consideredfor determination of responsiveness of Price Bids pursuant to clause
24.4 The names of the bidders whose Eligibility and Qualification Submission is found to be
substantially responsive (as per clause no 23 and 24.1, 24.2,24.3) the bid prices, the total
amount of each bid, any discount, and such other details, as the Employer may consider
appropriate will be announced by the Employer at the opening of the Price Bid. Any bid price,
which is not read out and recorded at the bid opening, will not be taken into account in Bid
24.5 Bidders or their representatives who are present shall sign attendance sheet evidencing their
24.6 The Employer shall prepare besides the record of bid opening, minutes of the Price Bid
opening including the information disclosed to those in accordance with Sub-Clause 24.4.
25 Examination of Price Bids and Determination of Responsiveness of Price Bid
25.1 The Employer will determine responsiveness of each Price Bid with respect to filled amount
for each item of Bill of Quantities, Technical Specifications, Drawings and other relevant
requirement of bidding documents.
25.2 A substantially responsive Price Bid is one which conforms to all the terms, conditions and
specifications of the bidding documents, without material deviation or reservation. A material
deviation or reservation is one (i) which affects in any substantial way the scope, quality or
performance of the Works; (ii) which limits in any substantial way, inconsistent with the
bidding documents, the Employer's rights or the bidder's obligations under the Contract; or
(iii) whose rectification would affect unfairly the competitive position of other bidders
presenting substantially responsive Price Bids.
25.3 If the Price Bid is not substantially responsive pursuant to this Clause 25.1 and 25.2, it will be
rejected by the Employer.
26. Correction Error
26.1 Price Bids determined to be substantially responsive will be checked by the Employer for any
arithmetic errors. Arithmetic errors will be rectified on the following basis:
(i) Where there is a discrepancy between the rates in figures and in words, the rate in words will
(ii) Where there is a discrepancy between the unit rate and the line-item total resulting from
multiplying the unit rate by the quantity, the unit rate as quoted will govern.
26.2 The amount stated in the Price Bid will be adjusted by the Employer in accordance with the
above procedure for the correction of errors and shall be considered as binding upon the bidder. If
the bidderdoes not accept the corrected amount of bid, his bid will be rejected, and his Bid
Security may be forfeited in accordance with Clause
27 Evaluation and Comparison of Price Bids
27.1 The Employer will evaluate and compare only those Price Bids which are determined to be
substantially responsive in accordance with Clause 25 and qualified for award of Contract in
accordance with Clause 2 and 3 of ITB.
VOL -1 Technical Bid |
27.2 In evaluating the Price Bids, the Employer will determine for each Price Bid the evaluated Bid
Price by adjusting the Bid Price as follows:-
a) Making any correction for errors pursuant to Clause 26 of ITB;
b) Making an appropriate adjustment for any other acceptable variations, deviations; and
c) Making appropriate adjustments to reflect discounts or other price modifications offered in
accordance with relevant clause.
27.3 After adjusting the bid prices as stated above, final bid evaluation will be done as follows:
a) Bidder needs to quote in percentage of rates (above /below as indicated in BOQ) for each
part/section of BOQ. It is mandatory for further evaluation of bids & payment. Payment of
items of each part/section of BOQ shall be made as per quoted percentage for each
part/section of BOQ.
b) Successful bidder- will be decided based on overall percentage quoted above/below of Total
estimated amount as indicated in Vol-II for the complete project.
27.4 If the Bid of the successful Bidder is seriously unbalanced in relation to the Employer’s
estimate of the cost of the items of the Works to be performed under the Contract, the Employer
may require the bidder to produce detailed price analysis for any or all items of the Bill of
Quantities, to demonstrate the internal consistency of those prices with the construction
methods and schedule proposed. After evaluation of the price analysis, the Employer may
require that the amount of the performance security set forth in Clause 35 be increased up to an
additional 4 (four) per cent at the expense of the successful bidder to protect the Employer
against financial loss in the event of default of the successful bidder under the Contract.
27.5 The Employer reserves the right to accept or reject any variation, deviation, or alternative offer
except in case of structures where alternative offers are called for. Variations, deviations and
alternative offersand other factors which are in excess of the requirements of the bidding
documents or otherwise result in unsolicited benefits for the Employer shall not be taken into
account in bid evaluation.
27.6 A bid, which is unrealistically lower then estimate and which could not be substantiated
satisfactorily by the bidder, may be rejected as non-responsive.
28 Rate Analysis
28.1 Requirement of submission of analysis by the contractor shall be complied and submitted to the
Employer or his nominee within the stipulated time fixed by the Employer or his nominee failing
which the bid shall be treated as non responsive. After evaluation of the price analysis, the
Employer may require that the amount of the performance security set forth in clause 35 may be
increased at the expense of the successful bidder to a level sufficient to protect the Employer
against financial loss in the event of default of the successful bidder under the Contract.
29 Clarification of Bids
29.1 To assist in the examination, evaluation and comparison of bids, the Employer may, at his
discretion, ask any bidder for authentication the correctness of the information/ details furnished
by him in his bid. Such request by the Employer and the response by bidder shall be in writing or
by cable/ fax, but no change in the price or substance of the bid shall be sought, offered or
permitted except as required toconfirm the correction of arithmetical errors discovered by the
Employer in the evaluation of the bids in accordance with Clause
VOL -1 Technical Bid |
29.2 Subject to Sub Clause 29.1, no bidders shall contact the Employer on any matter relating to his
bid from the time of bid opening to the time contract is awarded.
29.3 Any effort by the bidder to influence the Employer in the Employer’s bid evaluation, bid
comparison or contract award decisions may result in the rejection of his bid.
Information relating to the examination, clarification, evaluation and comparison of bids and
recommendations for the award of a contract shall not be disclosed to bidders or any other persons
not officiallyconcerned with such process until the award to the successful bidder has been
announced. Any effort by a bidder to influence the Employer's processing of bids or award
decisions may result in the rejection of his bid.
F. Award of Contract
31.1 Subject to Clause 32, the Employer will award the Contract to the bidder whose bid has been
determined to be substantially responsive to the bidding documents and who has offered the
lowest Evaluated Bid Price pursuant to Clause 27, provided that such bidder has been
determined to be (i) eligible in accordance with the provisions of Clause 2; and (ii) qualified in
accordance with the provisions of Clause 3 of ITB.
31.2 In case of overall bidder’s offer is less than 90% of the Engineer’s estimate of the cost of work,
additional security in the form as specified in Clause 35 for a period equal to the period of
contract and for an amount equal to the difference of the bidder’s offer and 90% of Engineer’s
estimate of the cost of work shall be delivered as per clause 35thereof.
31.3 The employer reserves the right to award the whole package and/or only any section of tender
to a bidder with the lowest Evaluated Bid Price provided that such bidder satisfies the eligibility
criteria specified elsewhere in the Bid documents
32 Employer's Right to accept any Bid and Reject any or all Bids
32.1 Notwithstanding Clause 31, the Employer reserves the right to accept or reject any bid and to
annul the bidding process and reject all bids, at any time prior to award of Contract, without
thereby incurring any liability to the affected bidder or bidders or any obligation to inform the
affected bidder or bidders of the grounds for the Employer's action.
33 Notification of Award
33.1 Prior to expiration of the period of bid validity prescribed by the Employer, the Employer will
notify the successful bidder by cable/ fax/ and confirmed by registered letter that his bid has been
accepted. This letter (hereinafter and in the Conditions of Contract called "the Letter of
Acceptance") shall name the sum which the Employer will pay the Contractor in consideration of
the execution, completion and maintenance of the Works by the Contractor as prescribed by the
Contract (hereinafter and in the Conditions of Contract termed "the Bid Price/Contract Price").
33.2 The notification of award will constitute the formation of the Contract subject only to the
furnishing of a performance security in accordance with the provisions of Clause
34 Signing of Agreement
34.1 At the same time that the Employer notifies the successful bidder that his bid has been accepted,
the Employer will direct him to submit the Performance Security and attend the Employer's office
VOL -1 Technical Bid |
on a date determined by the Employer for signing the Form of Agreementspecified in section VII
of this document.
34.2 Within 28 (twenty eight) days of the date of signing the Form of Agreement, the successful bidder
shall, if required, have the same engrossed, have the correct amount of stamp duty adjudicated by
the Inspector General of Registrations and return the same duly signed and executed on behalf of
the successful bidder to the Employer.
34.3 Upon the furnishing by the successful Bidder of the Performance Security, the Employer will
promptly notify the other Bidders that their Bids have been unsuccessful and release their Bid
35 Initial Security and Performance Security
The total Security Deposit is 4% (Four) percent of contract value and shall be as under:
The successful tenderer shall have to payinitial security deposit at 2% (two) percent of the
tendered amount.
Initial Security Deposit (2%) shall be paid in form of Cash or Demand Draft/Pay Order if the
Tender Amount of work is less than Rs. 2.00 crore.
Initial Security Deposit ( 2%) Shall be paid in form of Cash or Demand Draft /PayOrder/
Bank Guarantee (encashable at Surat City)/ F.D.R. if the tender amount of the work is more
than Rs. 2.00 Crore& above 2.00 Crore.
The person/persons whose tender may be accepted [here-in after called the Contractor,
which expression shall unless excluded by or repugnant to the context include his heirs,
executors, administrators and assignees shall (within 15 days of the receipt by him of the
notification of the acceptance of his tender) deposit with Municipal Commissioner cash or
Government securities endorsedto the Commissioner sum sufficient which will make up the
full security deposit specified in the tender.
If the amount of the security deposit to be paid in lumpsum within the period specified
above is not paid the tender contract already accepted shall be considered as cancelled.The
security deposit lodged by Contractor shall be refunded after the expiry of the Defect
Liability period as shown in the attached Memorandum after deducting dues, if any, which
become liable to be recovered from the Contractor under the terms and conditions of this
Regarding remittance and release of Security Deposit (SD), Retention money deposit (RMD)
following clause will supersede over and above all the clauses depicted in the tender
(a) Remittance of SD/RMD
(i) The total security deposit shall be recovered at the rate of 4% from contractor. Out of which,
50% of amount as Initial Security Deposit shall be payable at the rate of 2%of approved
tender cost in form of Cash or Demand Draft/ Pay Order/FDR/ Bank Guarantee of any
Nationalised Bank (encashable at Surat city).
(ii) The remaining amount of the Security Deposit i.e. 2% to be deducted from each running
(iii) 5% Retention money deposit (RMD)to be released along with final bill.
(b1) Release of SD/RMD
VOL -1 Technical Bid |
(iv) The 2% Initial security deposit in form Demand Draft /Pay order / FDRshall be released after
clearance of Final bill by Audit Dept & completion of defect liability period.
(v) Whereas, the 2% security deposit recovered from the each running account bills shall be
released along with Final Bills according to Work Quality.
(vi) 5% Retention money deposit (RMD) to be released along with final bill.
b2) Release of SD/RMD
(i) The 2% Initial security deposit in form Bank Guarantee shall be released along with Final
Bills according to Work Quality.
(ii) Whereas, the 2% security deposit recovered from the each running account bills shall be
released after clearance of Final bill byAudit Dept & completion of defect liability period.
(iii) 5%Retention money deposit (RMD) to be released along with final bill.
The amount recovered from the running bills as security deposit shall not be allowed to the
transferred in the form of Bank Guarantee. However, the remaining 50%(2% of Security
Deposit) of the amount so, deducted from running bills will be allowed for conversion in the
form of interest bearing fixed deposit receipt,(FDR)issued in favour of the Municipal
Commissioner, Surat Municipal Corporation, Surat by a Nationalized Bank located at Surat
only. Additional stamp duty payable as per government prevailing rule shall be paid by
contractor for remittance of this FDR.It is clarified that the amount of security deposit shall
be collected on the basis of contract price and not on the basis of Estimated Amount put to
tender As initial Security Depositas mentioned above, accepted by the competent Authority
shall have to be paid toward Security Deposit at the time of execution of agreement.
Interest will be payable on FDR (that is deducted from Running Bill and converted in to FDR for
initial SD) for One year, after completion of work. After that no further interest shall be paid for
any extended period what so ever.
If the Security Deposit is not paid within 15 days from the date of L.O.I. / Work Order than
penalty at the rate of 0.065% per day of the amount of Security Deposit will charged. If the
Security Deposit is not paid within one month with interest, necessary actions as per condition of
contract will be taken.
Initial Security Deposit ( i.e. 2% Of Tender Amount) in form of Bank Guarantee may be
accepted as per relevant tender provision, However BG shall be valid till final date of completion
of work+1year (Whether final bill is audited and paid or not). It shall be contractor's
responsibility to extent the BG On Or Before expiry of time limit of BG. In case of late renewal
of BG, penalty of security deposit shall be levied interest at the rate of 4.00% per year of BG
amount.(As per City Engineer note No.626,Dt.04/07/2022)
The successful tenderer shall have to enter into an agreement on a non judicial stamp paper of
Rs. 300/- if initial Security Deposite paid in form Bank Guarantee or Demand draft as per the
VOL -1 Technical Bid |
form of the agreement approved by the Municipal Corporation, Surat. If initial Security deposit
is paid in form of Fixed Deposit, additional stamp paper amounting As per government’s
prevailing rule of Security Deposit shall be used to execute the agreement.
The undertaking shall be executed on stamp paper worth Rs. 300/-.
The Surety shall be executed on stamp paper worth Rs. 300/-.
The undertaking shall be executed on stamp paper as per prevailing norms of Government. The Surety
shall be executed on stamp paper as per prevailing norms of Government Within 15 days of receipt of
the Letter of Acceptance, the Successful Bidder is required to pay Initial Security to the extent of 2%
of Tender Amount plus Additional Security (if required) in the form of Bank Guarantee or in form of
D.D or pay order Nationalized Approved Banks only in favour of Commissioner, Surat Municipal
Corporation Surat .
In case of overall bidder’s offer is less than 90% of the Engineer’s estimate of the cost of work,
Additional Security for the period equal to contract period and for the amount equal to the difference
of 90% of Engineer’s estimate and bidder’s offer for unbalanced bids as per sub clause 31.2 above in
accordance with the condition of contract. The List of Approved Banks is specified in Form no 5 of
Performance Security: The 2% of the Performance Security is to be deposited through deduction
from the Running bills (2% of work done shall be deducted from every running bills and final bills).
36 Corrupt or Fraudulent Practices
36.1 The Employer requires that Bidders/Suppliers/Contractors under this contract, observe the highest
standard of ethics during the procurement and execution of this contract. In pursuance of this
policy, the Employer.
(a) Defines, for the purpose of these provisions, the terms set forth below as follows:
i.. corrupt practice: means the offering, giving, receiving or soliciting of anything of value to
influence the action of a public official in the procurement process or in contract execution; and
ii fraudulent practice means a misrepresentation of facts in order to influence a procurement
process or the execution of a contract to the detriment of the Employer, and includes collusive
practice among Bidders (prior to or after bid submission) designed to establish bid prices at
artificial non-competitive levels and to deprive the Employer of the benefits of free and open
(b) Will reject a proposal for award of work if Employer determines that the Bidder recommended for
award has engaged in corrupt or fraudulent practices in competing for the contract in question.
VOL -1 Technical Bid |
(c) Will declare a Bidder ineligible, either indefinitely or for a stated period of time, to be awarded a
SMC contract/contracts if he at any time determines that the Bidder has engaged in corrupt or
fraudulent practices in competing for, or in executing, the contract.
36.2 The Employer will reject a proposal for award if he determines that the Bidder recommended for
award has engaged in corrupt or fraudulent practices in competing for the contract in question. The
Employer will declare the firm ineligible, either indefinitely or for a stated period of time, to be
awarded a contract by Surat Municipal Corporation if it at any time determines that the firm has
engaged in corrupt or fraudulent practices in competing for the contract, or during execution.
37 STAMP DUTY :
The successful tenderer shall have to enter into an agreement on a non-judicial stamp paper of
Rs.4.90% of S.D. Amount, if S.D. Amount in FDR and otherwise as per the form of the agreement
approved by the Municipal Corporation, Surat. The agreement shall be executed on stamp paper worth
Rs.4.90% of S.D. Amount. The Undertaking and Surety shall be executed on stamp paper worth
Specific references in the specifications to any materials by tender's name, or catalogue number shall
be construed as establishing a standard or quality and performance and not as limiting competition and
the tenderer in such cases, may at their option freely use any other product, provided that it ensures
and equal or higher quality than the standard mentioned and meets Municipal Corporation approval.
All Stamp Duty consider as per Urban Development & Urban Housing Development Dept,
Gandhinagar Letter no.PRC/802021/567/P, Dt. 27/05/2021.
38 CHANGE IN A QUANTITY: The Surat Municipal Corporation reserves the right to waive any
informality in any tender and to reject one or all tenders without assigning any reasons for such
rejections and also to very to quantities of items or group as specified in the Schedule of price as may
be necessary. Claim what so ever by the contractor on the basis of variation of quantities shall not be
The quantities against each item given in Bills of Quantities may change and/or be totally omitted due
to any reason, however, the Contractor shall execute the same with the rates quoted and shall not ask
for revision of rates due to any variations and/or omission of Quantities.
The items mentioned above can be altered/ changed as per the conditions prevalent on site on that
moment. The contractor is adhered to shift arrangements in accordance and comply to the client and
architect for smooth progress of the site.
39. NEW EQUIPMENT AND MATERIAL; All materials, equipment and spare parts thereof shall be
new, unused and originally coming from manufacturer's plant to the Corporation. The rebuilt or
overhauled equipment/materials will not be allowed to be used on work.
40 RIGHTS RESERVED;
VOL -1 Technical Bid |
40.1 The SMC reserves the right to reject any or all tenders, to waive any informality or irregularity in any
tender without assigning any reasons. The SMC further reserves the right to withhold issuance of the
notice to proceed, after execution of the contract agreement, for the period of time stated in the notice
inviting tenders and no additional payment will be made to the successful tenderer on account of such
withholding. The SMC is not obliged to give reasons for any such action.
40.2. Municipal Commissioner reserves the right to reduce the scope of work and split the tender in two or
more parts without assigning any reason even after the award of contract. No mobilization advance or
advance on machinery will be given.
40.3. The scope of work is clearly mentioned in the tender documents. The contractor shall have to carry
out the work in accordance with the details specifications. No conditions will be accepted. The
conditional tender will be liable to be rejected.
41. Contractor Must submit royalty pass(photocopy) of important materials whenever asked to
submit by the authority.
Date & Signature of the Contractor Executive Engineer
Surat Municipal Corporation
VOL -1 Technical Bid |
SECTION II (A)-CONDITIONS OF PARTICULAR APPLICATION
1. The selection process will lay high emphasis on the ability and competency of contractors to
do high quality work within the given time schedule.
2. The onus of providing, all necessary company / project related information, in appropriate
manner and medium, so as to demonstrate the competency of the bidder and to allow proper
evaluation, will rest entirely on the Bidder.
3. Eligibility and Qualification submissions specified in Clause 2 &3 and defined hereunder
shall be submitted through online only.all the original document must be colored
scanned, that Necessary Documents, Certificates etc.) are signed, Sealed ,Attested
and notarized with clearly displaying stamp, number and name of notary wherever
required in each and every respect.
4. Price Bid Submitted online only.
5. ALL INFORMATION HAS TO BE SUBMITTED IN THE PRESCRIBED FORMAT ONLY
Projects for which incomplete information has been provided will not be considered for
6. The scope of work, project description mentioned in the document is indicative and may
change during detail design.
7. There is no option of submitting any conditional bid .All participating bidders are assumed to
agreed 100% on all clauses.
8. SMC’s decision for selection or rejection of the bidder shall be final and binding to all.
9. Bidder should provide information as mentioned in the prescribed forms for projects.
Information other than that related to similar projects shall not be considered for evaluation.
10. If Surat Municipal Corporation is convinced that the Bidder has resorted to material
misrepresentation or provided fraudulent information/ statement, the said Bidder will be liable
for disqualification/ rejection at any stage.
11. Proof for fulfillment of eligibility criteria should be submitted along with Eligibility and
Qualification Submission. If the Eligibility and Qualification Submission is submitted without
valid documents and without proof of eligibility criteria will be rejected.
12. Those who do not meet with the eligibility criteria need not submit the Bid.
13. Bids, which do not fulfill all or any of condition or are submitted incomplete in any respect or
are conditional tenders, will be rejected.
14. Engineer In-charge reserves the rights to reduce/ increase the scope of work and contract
without assigning any reason thereof.
15. All the expenses regarding the plant and its installation shall be borne by the contractor. The
contractor shall at his own expenses, provide erect, operate and maintain in sound and through
working condition all constructional plants and temporary works to complete the work within
the time prescribed in the contract. He shall also at his own expense when so directed by the
Engineer-in-charge in writing shall,
a. Add, extend or improve the plants and ion works already on site.
b. Remove and replace any time of plant or temporary work which in the opinion of the
Engineer-in-charge is unsafe, inadequate or unsuitable.The issuing of any directions by the
VOL -1 Technical Bid |
Engineer-in-charge as mentioned in the preceding sub-para shall not however relieve the
contractor of any of his duties and representatives under the contract in procurement by him
plants / machines in working conditions.
15 Explosive and Inflammable Materials:
The Owner/Employer does not anticipate use of any explosive or any inflammable material on
this work, however in the event, explosives of inflammable materials are to be used for the
execution of the works, the contractor shall at his own expense, obtain such license or licenses
as may be required for storing and using explosives and or inflammable materials and locate,
construct and maintain magazines if such and its required for storage in accordance with the
requirements of the relevant Government Rules in force. Such magazines shall be in the care
of competent watchman all the time. All these shall be done under intimation and after getting
assurance from Engineer in charge.
16. The contractor shall exercise utmost care while using explosives and or inflammable materials
not to endanger life or property and shall be solely responsible for any and all damages
resulting from their storage and use, and shall indemnify absolutely Owner/Employer and its
Officers and employees against any claim or liability arising out of any accident or violation
of any law, rules, orders etc.
17. Contractor shall have to make his own arrangements for water and electricity for the purpose
of construction work at site at his own expense.
18. If the contractor fails to execute the said works within prescribed time limit, the said work will
be carried out at the risk and cost by other contractors with 15 % supervision charges as may
be decided by the Engineer In-charge.
19. Availability of Drawings
The drawing and related details for the work prepared by the consultant and approved by
SMC shall be made available from the office of Engineer In-charge, Surat.
20. Office set up at site:
Contractor has to set up a site office at a centrally located area making it accessible from all
the work area, which shall be mutually agreed upon with SMC. The office shall have
computer facilities with printers and Internet connection for Email Correspondence ensuring
faster communication. Digital Camera with Data Transfer capabilities. The contractor shall
take photographs of site prior to commencement of work, during construction and after
completion of work as suggested and shall submit the photographs in soft and hard copies to
SMC. The Contractor is also required to provide office space for Project Management
Consultant/ Employer’s representative as directed by Engineer In-charge.
21. Safety and Signage
Contactor has to arrange for the complete safety of the persons working for project, users of
the road i.e. public and vehicles also. All the arrangements of traffic drums, metal / fiber
cones, traffic blinkers, traffic signs as per design, safety tapes etc. to be arranged at site.
Necessary florescent marking on traffic signs to be provided so that it should be visible at
night. During night working hours safety in charge personnel’s shall be provided with
florescent jackets
. GENERAL: SAFETY CODE: Contractor shall adhere to safe construction practice and guard
against hazardous and unsafe working conditions and shall comply with owner's safety rules
and set fourth herein.
VOL -1 Technical Bid |
21.1. First Aid and Industrial Injuries:
21.1.1 Contractor shall maintain first aid facilities for its employees and chose of his sub contractor.
21.1.2 Contractor shall make outside arrangements for ambulance service and for the treatment of
industrial injuries. Name of those providing these services shall be 66 furnished to Engineer-
in-charge prior to start of construction, and their telephone numbers shall be prominently
posted in contractor's field office.
21.1.3 All injuries shall be reported promptly to Engineer- in-charge, and a copy of Contractor's
report covering each personal injury requiring the attention of a physician shall be furnished to
21. 2. General Rules:
21.2.1 Carrying, striking, matches, lighters inside the project area & smoking within the job site is
strictly prohibited Violators of smoking rules shall be discharged immediately. Within the
operation area, not hot work shall be permitted without valid gas safety, fire permits. The
Contractor shall also be held liable and responsible for all lapses of his sub-contractors/
employees in this regards.
21.3. Scaffolding:
21.3.1 Suitable scaffolding shall be provided for workmen for all works that can not safely be done
from the ground or from solid construction except such short period work as can be done
safely from ladders. When a ladder is used, an extra mazdoor shall be engaged for holding the
ladder and if the latter is used for carrying materials as well, suitable foothold sand handholds
shall be provided on the ladder and the same shall be given inclination not steeper than 1 to
(1 horizontal and 4 vertical).
21.3.2 Scaffolding or staging more than 3.6 M (12') above the ground or floor, swing or suspended
from an overhead support or erected with stationary support shall have a guard rail properly
attached, bolted, braced and otherwise fixed at least 1.0 M (3') high above the floor or
platform of scaffolding or staging and extending along the entire length of the outside ends
thereof with only such openings as may be necessary for the delivery of materials. Such
scaffolding or staging shall be so fastened as to prevent it from swaying from the building or
21.4. Maintenance of Safety Devices:
21.4.1 All scaffolds, ladders and other safety devices mentioned or described herein shall be
maintained in some conditions and no scaffold, ladder or equipment shall be altered or
removed while it is in use. Adequate washing facilities should be provided at or near place or
21.5. Display or Safety Instructions:
VOL -1 Technical Bid |
21.5.1 These safety provisions should be brought to the notice of all concerned by display on a
notice board at a prominent place at the work-spot. The person responsible for compliance of
the safety code shall be named therein by the Contractor.
21.6. Enforcement of Safety Regulations:
21.6.1 To ensure effective enforcement of the rules and regulations relating safety precautions, the
arrangements made by the contractor shall be open to inspection by the welfare Officer,
Engineer-in-charge of safety Engineer of the owner or their representatives.
21.7. No Exemption:
21.7.1 Notwithstanding the above clause 1.0 to 7.0 there is nothing to exempt the contractor from
the operations of any other Act or rules in force in the Republic of India. 7.2 In addition to the
above, the Contractor shall abide by the safety code provision as per C.P.W.D. Safety Code
framed from time to time.
22. Convenience of Traffic:
The contractor shall notify in writing to the Engineer in charge or representative of SMC of
the starting of any construction or other operation that may in any way to inconvenience or
endanger traffic, at the earliest possible date and minimum a week in advance to enable the
Engineer in charge to take action as per rules. Under no circumstances the contractor shall
close any road traffic without the written permission of the Engineer in charge.
Whenever necessary, temporary detours or diversions shall be made at service road also and
maintained for traffic by the contractor at his cost. Such diversions shall have a width of not
less than 6 meters throughout and shall be provided with necessary road signs clearly visible
at a distance by day or night. There shall be a preliminary warning by red flags by day and red
lamps/ blinkers by night at a distance of 150meter from the ends of diversion. All diversions
shall be clearly demarcated by white washed stones or other such means.
All operations necessary for the execution of works and for the construction of any temporary
works as shall be carried out so as not to interfere unnecessarily or improperly with public
convenience or with the access to the and occupation of public or private roads and foot paths.
Least possible obstruction shall be caused to traffic.
23. Tax, Duties on Materials
GST (Goods & Service Tax) has come in existence from 1st July, 2017. Contractor/ Successful
Bidder is bound to pay any amount of GST proscribed by the govt. of India as per the Terms of
Contract agreed upon during the course of execution of this contract.During the course of
execution of Contract, if the reisany change in Rate of GST (Goods & Service Tax) by the
Government, the same shall be reimbursed/ recovered separately by SMC, subject to the
submission of Original Receipt/ Proof for the amounts actually remitted by the successful
Tenderer/ Contractor to the competent Authority along with a Certificate from Chartered
Accountant of Contactor/ Successful Bidder certifying that the amount of GST paid to the
Government and the same shallbe intimated/ submitted/ claimed within 30 (thirty) Days from
the date of payment Remittance of GST within stipulated period shall be the sole responsibility
of the successful Bidder/ Contractor, failing which, SMC may recover the amount due, from
any other payable dues with SMC and decision of Municipal Commissioner shall be final and
binding on the Contractor / Successful Bidder in this regard Further, non- payment of GST to
VOL -1 Technical Bid |
the Government may lead to the termination of contract and forfeiture of Security Deposit/
Performance Guarantee Amount.
If imposition of any other new Taxes/ Duties/ Levies/ Cess or any other incidentals etc.or any
increase in the existingTaxes/Duties/Levies/Cessoranyother incidentalsetc.(Excluding GST)
are imposed during the course of the contract, the same shall be borne by the Contractor/
Successful Bidder only,in no case SMC shall be liable for the same.
As per the central goods and Service Tax Act-2017 Any Government department, local bodies
and government undertaking public adventures published tenders amounting more than
Rs.2,50,000 & which commodities/ services are comes under taxation more than 2% TDS (1%
for SGST & 1% for CGST) should be deducted. And if commodities/ Services are provided
from inter state then 2% TDS should be deducted of IGST.
NOTE:-The Rates mentioned in BOQ are excluding GST. GST will be reimbursed
separately (if applicable as per the opinion of Account department of SMC / GST
Consultant of SMC) as per the prevailing GST Rates decided by the Government.The
contractor is invariably bound to any changes in GST Rates made during the course of
the work. The payment (if applicable) for GST will be only released only after the
applicable Amount reflecton Government portal. Decisionof Account Department of
SMC regarding applicable GST Rates will be final.
1% Construction Cess will be deducted from respective R.A. Bill and Final bill in
accordance withthe prevailing norms of Govt. of Gujarat.
24. Submission of project schedule
Contractor shall submit the detailed Project schedule showing break up for the various tasks to
be performed in order of their occurrence during the project in Microsoft Project/Prima Vera
25. Water Supply: The contractor shall arrange at his own cost, a suitable supply of potable
water for the construction of the works. The Contractor is required to provide Test
certification of Water quality from approved laboratory to Engineer for its approval prior to its
use for Construction Work. All cost related to water supply shall be borne by the Contractor.
26. Electricity: The Contractor is required to make its own arrangement, at its cost, for obtaining
electricity connection. Payment of all costs in this regard will be the responsibility of the
contractors. In case if there is any delay in supply of power at site or any interruption or fault
in the power during the work. No compensation shall be paid for idle labor staff,
machineries and for use of diesel operating sets etc. as the case may be and no extra time
limit shall be granted. In case of failure of the non-payment of power consumption charges,
SMC reserves the right to deduct thesame from the RA/ Final Bills of the contractor.
27. The contractor will be required to arrange for total station survey for carrying out the work
and for measurements wherever needed as per the instruction of the Engineer in-charge. No
extra payment shall be made towards this.
28. Contractor shall have to deploy adequate plant, machinery, manpower, equipment, DG set,
supervisorystaff etc. to carry out simultaneous work on all locations.
29. Accident liabilities:The contractor shall be responsible for all liabilities under workman
compensation act, and other relevant acts as under:
VOL -1 Technical Bid |
a. Contractor shall take all necessary safety precautions during execution of work to
avoid any type of accident at project site & plant site. No work shall continue at site in
absence of necessary and adequate safety measures.
i. Any accidents occurring at project & plant site during the contract period shall be the sole
responsibility of the contractor.
b. Contractor shall inform the owner regarding any accidents occurring at site within
Date & Signature of the Contractor Executive Engineer
Surat Municipal Corporation
VOL -1 Technical Bid |
SECTION II (B) – MEMORANDUM
Sr.No Items Particulars/ Conditions for this Contract
1 Name of Work Maintenance And Repairing Work Of Surat Castle
Located At Chowk Bazaar, Surat.
2 Estimated Value of the Work Rs.
3 Earnest Money Deposit The amount of EMD is Rs. 47,000.00/-
100 % in the form of Demand Draft or pay order of
nationalized / Scheduled bank only in favour of
Commissioner, SuratMunicipal Corporation, Surat.
4 Tender Fee Rs. 1500/- + 270 (18% GST ) = Rs. 1770/- In form of
Demand Draft or Pay order of Nationalized/ Scheduled
Bank only in favour of Commissioner, Surat Municipal
Corporation, Surat.
5 (i) Initial Security Deposit :- @ 2% of the Sanctioned Tendered Amount(Shall be
(D.D. / Payorder / F.D.R.orIn form released after clearance of Final bill by Audit Dept.)
of In form of Bank guarantee of • @ 2% of the work done amount which will be deducted
any from each running and final bill. 2% (Shall be released only
NationalisedBank) after clearance of Final bill by Audit Dept. & completion of
(ii) Performance security : defect liability period)
To be deducted from each running
bills as (As per Clause ITB-35).
6 Deduction of Retention Money from @ 5% of total amount of work done from each interim
6 Deduction of Retention Money from @ 5% of total amount of work done from each interim
each RA Bill (running) bill. Which will be released at the time of final bill.
7 Time allowed for the completion of 12 Months (Excluding Monsoon)
work from date fix in written order to
8 Tender validity period 120 days from the date of opening of price bid.
9 Address 1. The Employer is: Surat Municipal Corporation, Tapi
Bhawan, Tapi pura, Surat- 395 003, Gujarat.
2. Tender Fee, EMD, Affidiviate, Annexure-B & C shall be
submitted to: Chief Accountant, Surat Municipal
Corporation, Mugalisara Surat
3. Eligibility and Qualification & Price Bid shall be
submitted online through https://smctender.nprocure.com
before time and date specified in List of Important Dates.
10 The progress of work should (% of Work to be Completed) Period
confirm the following schedule. 25% of work to be done in 25% of time
(as per section IV (A) clause 50% of work to be done in 50% of time
38 of GCC page no:73)
75% of work to be done in 75% of time
100% of work to be done in 100% of time
11 Penalty for delay 0.2 % (Zero point Two percent) of the contract price per
day& maximum upto 10% (Ten Percent) of the Tender
VOL -1 Technical Bid |
12 Advance Payment There will not be any kind of Advance Payment from the
13 Defect Liability Period The Defect Liability Period for whole work shall be 1 years
from date of issue of Completion Certificate.Water proofing
items Defect Liability Period shall be 10 years from date of
issue of Completion Certificate. Contractor will furnish
Guarantee Bond for water proofing items for the duration of
14 Joint Venture/ Consortium Joint Venture/ Consortium is not allowed.
15 Whether water charge shall have to Contractor shall have to arrange water for execution,
be paid by the contractor curingetc. at his own cost.
16 Amount of water charges As per Clause no. 19.6 (General)
17 Construction Cess 1% of Total work done & to be deducted in every bill.
Date & Signature of the Contractor Executive Engineer
Surat Municipal Corporation
VOL -1 Technical Bid |
SECTION III – QUALIFICATION INFORMATION FORMS
Form Number Particulars
1. Letter of Bid
2. General Information
Turnover, Profit and Net worth of last three years from civil construction
contractual activities only duly audited.
4. Summary of similar projects completed in last Seven years
5. Summary of Current Contract Commitments/Works in Progress
6. Details of availabilityof key personnel
7. Power of Attorney
8. Affidavit on stamp paper stating that Bidder has provided true information
9. Anti Blacklisting Information
10 Availability of equipment’s
11 Affidavit for site visit
Date & Signature of the Contractor Executive Engineer
Surat Municipal Corporation
VOL -1 Technical Bid |
(On the letterhead of the bidder)
Assistant municipal Commissioner, on behalf of
Surat Municipal
Corporation (The Employer) Surat.
Subject: With respect to tender for
Maintenance And Repairing Work Of Surat Castle Located At Chowk Bazaar, Surat.
With respect to above mentioned subject, we are pleased to submit the bid. This offer is subject
to all terms and conditions contained in the tender document. We have not made any changes
either directly or indirectly in terms and conditions of the Tender. In additions to terms and
conditions of this tender, we are not given any written or oral promise from the Employer.
The EMD details are as follows:
Amount: __________, DD No. / Pay Order No. /Bank Gurantee No ____________ Dated:
Payable at Surat on Bank: _____________________
The Tender Fee Draft details are as follows:
Payable at Surat on Bank: _______________________
We are pleased to submit the following towards the same.
1. Eligibility and Qualification Information as specified in Clause2, Clause 3 in sub clause 3.1 and
Clause 3.2 of ITB is submitted online.
2. Online Submitted form No. 1 to 11 dully filled and signed (specified in section III of ITB) and
Price bid through e-tendering and mentioned Documents as per. IFB-18 (Page N0-9) in Hard
We are fully aware that the Employer has a right to accept any tender or reject any/ all tenders
without giving any reason and upon rejection of tender/ tenders we shall not be entitled to any
right with related to the Employer.
We have thoroughly read and understand all the terms and conditions of this tender and promise
to observe all the terms and conditions of this tender. We have signed and sealed each and every
page of this tender document.
(Signature and stamp of the Bidder with date)
VOL -1 Technical Bid |
General Information
All Bidders are required to furnish the information in this format.
1 Type of the Bidder (Company/Partnership):
2 Name of firm/s
3 Head office address
4 Year of incorporation/ registration
5 Local office address (if any)
6 Telephone & Contact Details of Concerned person/s
8 Place of incorporation/ registration
9 Main lines of business
All Bidders are required to furnish the documents such as MOA, AOA, Partnership Deed,
Sales tax registration, GST Number, Factory and Shop & Establishment registration as
may be applicable.
(Signature and stamp of the Authorized signatory of Bidder with date)
VOL -1 Technical Bid |
Turnover, Profit and Net worth of last three years from civil construction
contractual activities only duly audited.
Name of Bidder:
A Annual Turnover
All Bidders individually must complete the information in this form. The information
supplied shall be the annual turnover of the Bidder from Civil Construction Contractual
work only in term of the amounts billed to clients for each year for work in progress or
Annual turnover (Civil Construction Contractual Work only) for the
following years
Year Turnover (in Rs.)
Average of last three years
(Such turnover certificate as certified by Statutory Auditor/ Registered Chartered Accountant shall
have to be provided)
B Profit and Net worth
Year Profit (in Rs.) Net worth (in Rs.)*
Networth*: = Equity Capital + Reserve and Surplus - Revaluation Reserve - Accumulated losses -
Intangible assets
(Above statement /certificate as certified by Statutory Auditor/ Registered Chartered Accountant shall
have to be provided)
Seal and Signature of Statutory Auditor / Registered Chartered Accountant with Registration
(Also provide copied of audited financial statements for last three years)
Seal and Signature of Statutory Auditor / Registered Chartered Accountant with Registration
VOL -1 Technical Bid |
Summary of Similar nature of projects (as defined in clause 3.1(b) of ITB)
completed in last seven years.
Bidders shall provide information on such similar projects executed during last
years in the form of a table as given below:
Name of Bidder:
Name of Name of contract Name of consulting Contract Value of work Actual Actual Evidence
Employer location and Engineer or agency amount in completed and date of date of provided
nature of their responsible for Indian certified in start work from
work supervision Rupees & Indian Rupees work completion client
Bidder shall provide evidences in terms of Work Orders AND project completion
certificates from client for all mentioned projects from clients. Contractor should be
the Sole bidder of the projects listed/mentioned above. Projects executed as a Joint-
venture shall not be mentioned.
VOL -1 Technical Bid |
Summary of Current Contract Commitments/ Works in Progress
Bidders must provide information on its current commitments on all similar civil contracts that
have been awarded or for which a letter of intent or acceptance has been received, or for contracts
approaching completion, but for which full completion certificate has yet to be issued.
Name of Name of Name of Contract Value Value Actual Estimated
Employer the contract consulting g amount in of work of date of completion
location and Engineer or Indian completed and outstanding start date
nature of agency Rupees & certified in work
their work* responsiblefor date of Indian Rupees (in Indian
supervision contract Rupees)
Bidder shall provide evidences in terms of Work Orders, Letter of Acceptance, etc. for all
such projects mentioned in the table. Contractor should be the Sole bidder of the projects
listed/mentioned above. Projects executed as a Joint-venture shall not be mentioned.
Performa for declaration regarding works on hand with the tenderer:
Sr. N. Name of Estimated Date of issue Stipulated period of Amount of Brief Name Litigation
work with Cost of work order completion work done details of of /dispute if any
place delay, if Client
ALL PROJECTS BIDDED LIST OF PROJECTS BIDDED BUT NOT AWARDED.
Employer of Consultant Location and Value of Date of bid Expected date of Staff connected on Position in
Employer Supervising, description of Contract in award the project Bid if known
if any Company Indian
NOTE: - A Certificate from Qualified Chartered Accountant shall be attached. Contractor should be the Sole bidder of the
projects listed/mentioned above. Projects executed as a Joint-venture shall not be mentioned.
VOL -1 Technical Bid |
Details of Project Manager and Key Personnel
The Bidder shall provide the details and information of availability of key personnel in table
provided below. (See Clause 3.1 (L) of Instructions to Bidders section):
Sr. Name of the Total Expertise/
Designation Qualifications
No. Employee Experience Skill set
Bidder is also required to provide the CVs along with qualification certificates of all personnel as
mentioned in the table above in the following format:
Sr. Particulars
2 Qualification
3 Project details on which Name of the Project:
personnel has working Details of the Project:
Experience Tenure for which the personnel worked on that Project:
4 Any other important information
5 Signature of the personnel
NOTE:-Contractor shall submit all Documents related to the employment of the staff within 15 days
of allotment of work.
VOL -1 Technical Bid |
Power of Attorney
(On a Stamp Paper of appropriate value also notarized)
(Applicable in case of bid not being signed by the person directly authorized by the firm)
Deputy Commissioner,
Surat Municipal Corporation,
REF: Your Tender Ref.: <Name of the tender, tender no., Issue date, etc.>
<Bidder’s name> hereby authorizes <Designated Representative’s name> to act as a
representative of <Bidder’s name> for the following activities vide its Board Resolution/ Power
of Attorney attached herewith.
To attend all meetings with Surat Municipal Corporation or other entities associated with tender
for Maintenance And Repairing Work Of Surat Castle Located At Chowk Bazaar, Surat.
and to discuss, negotiate, finalize and sign any bid or agreement and subsequent Contract.
Yours faithfully,
<Signature of appropriate authority of the Bidder >Name of
appropriate authority of the Bidder:
<Signature and name of the Designated Representative of the Bidder for acceptance of this Power
<Name of Bidder >
Encl: Board Authorization
VOL -1 Technical Bid |
Affidavit on Rs.300 Non Judicial Stamp Paper
(To be provided by Bidder)
It is certified that the information furnished here in and as per the document submitted is true and
correct and nothing has been concealed or tampered with. We have gone through all the conditions
of tender and are liable to any punitive action for furnishing false information/ documents.
Dated this ____ day of _______ Year _________
In the capacity of duly authorized to sign bids for and on behalf of:
To be signed by:
Authorized Signatory with name and designation
VOL -1 Technical Bid |
Anti-Blacklisting Certificate
(On a Stamp Paper of Rs.300)
(To be provided by Bidder)
I/We M/s. _______________ (Name of the Bidder along with name and address of registered
office) hereby certify and confirm that we or any of our promoter/ s/ director/s are not barred by
Government of Gujarat (GoG)/ any other entity of GoG or blacklisted by any state government
or central government/ department/ agency/local self Government/Surat Municipal Corporation
in India from participating in Project/s, either individually or as member of a Consortium as on
_______ (Bid Submission Date).
We further confirm that we are aware that our Bid for the captioned Project would be liable for
rejection in case any material misrepresentation is made or discovered with regard to the
requirements of this Tender at any stage of the Bidding Process or thereafter during the
agreement period. Dated this ____ day of Year _________
To be signed by:
Authorized Signatory with name & designation
Name of the Bidder
VOL -1 Technical Bid |
Availability of Equipment’s (Clause 3.1 (i))
Sr. No. Equipment Year of Current Ownership detail Remarks
Name purchase status
VOL -1 Technical Bid |
AFFIDAVIT FOR SITE VISIT
(On Rs 300/- government stamp paper)
I hereby assure that, I/my authorized representative have visited and examined the site fully and
have considered all the parameters including visible/hidden hindrances which may or may not
be affect quoting of bid as well as execution.
Yours faithfully,
Authorized Signature
Name and Title of Signatory
Name of Agency.
VOL -1 Technical Bid |
SECTION IV (A)-GENERAL CONDITIONS OF CONTRACT
Table of Contents
A. General B. Time Control
1. Definitions 38. Progress Schedule
2. Interpretation 39.Approval by the Engineer for Temporary
3. Scope of Work 40. Extension of the Intended Completion Date
4. Language and Law 41. Delays Ordered by the Engineer
5. Engineer-In-Charge 42. Management Meetings
6. Delegation 43.Liquidated Damages
7. Communication C. Quality Control
8. Joint Venture 44. Accuracy
9. Assignment 45. Works to be under direction of Employer
10. Sub-letting 46. Quality Checks Register
11. Documents mutually explanatory and 47. Identifying Defects
12.Subcontracting 48. Tests
13.Programme of works 49. Correction of defects or unsatisfactory &poor
14. Disposal of surplus excavated materials D. Cost Control
15.Patented Devices, materials and processes 50. Bills of Quantities
16. Trespass 51. Variations in Quantities
17. Police protection 52. Payment for Variations
18.Office set up at the site 53. Payment Certificates and Payment
19.Obligations of Contractor 54. Tax
19.1 General Obligations of Contractor 55. Currencies
19.2 Cooperation with Other Contractors 56. Retention
19.3 No Advertisement on Corridor by 57. Performance Security
19.4 Employment of competent Personnel 58. Price Variation
19.5 Contractor to carry out the Works 59. Cost of Repairs
19.6 Electricity, Water and other services 60. Events Leading to Extension of Intended
Completion Date
19.7 The Works are to Be Completed by 61. Damages by storms, fire, rain or accidents.
theIntended Completion Date
19.8 Safety 62. Cooperation with other construction agencies.
19.9 Liability in case of Damage done in
63. Price Escalation
surrounding areas
19.10 Obligations regarding labour laws E. Finishing the Contract
19.11 Contractor to Execute the Works 64. Completion Certificate/ Final Certificate
19.12 Obligations relating to Ownership 64.1Test on Completion
ofContractor Company
19.13 Contractor’s Risk 64.2 Completion Certificate
VOL -1 Technical Bid |
19.14 Approval of temporary work 64.3 Rescheduling of Tests
20. Obligations of Employer 64.4 Clearance of Site
21. Liability of accidents to persons 64.5 Taking Over
22. Residential accommodation and sanitary and 65.Defect Liability Period
medical arrangements to be provided to the
labours employed by the contractor.
23. Change in prices, rates, wages & taxes etc. 66. Remedy of Defects or Poor Quality Work
Subsequent to the acceptance of the tender. During the Defect Liability Period
24. Permits licences, priorities, certificates etc. 67. Certificate of Performance
25.Insurance during the Construction Period and 68. Maintenance during Defect Liability Period
Defect Liability Period
25.1 Application of Insurance Proceeds 69. Maintenance Manual and Drawings
25.2 Insurance by Sub Contractors
25.3 Validity of the Insurance Cover 70. Final Account
26. Discoveries 71. Termination in Event of Default of Contractor
27. Possession of the Site 72. Termination Payment for Event of Default
28. Supervision of Works 73. Property
29. Instructions and Actions where no 74. Indemnity
30. Dispute Redressal System 74 75.Force Majeure
31.Claim for compensation for delay in the 76 Survival
starting of work
32.Claim for compensation for delay in the F. Schedule – A
execution of work
33. Entering Upon and Commencement of work 77. Cement, steel & other materials
34. Fair Wages to Contractor’s workers 78.Responsibility of contractor under construction
and demolition waste (c & d waste) rules
35 Severability and Waiver 79 .Monsoon
36.Representation and Warranties of Contractor
37.Representation and Warranties of Employer
Date & Signature of the Contractor Executive Engineer
Surat Municipal Corporation
VOL -1 Technical Bid |
Terms which are defined in the Technical Specifications are not defined in the Conditions of
Contract but have their defined meanings. Capital initials are used to identify defined terms.
"Client" shall mean "The Commissioner, Surat Municipal Corporation, Surat or his authorized
City Engineer/Deputy Commissioner/equivalent" who is the authority vested with all powers in
implementing the project in execution through his Engineer-in-charge or any other authorized
“Employer” means The Surat Municipal Corporation and is the party who will employ the
Contractor to carry out the Works.
“Engineer” shall mean the officer of CLIENT who is designated as such for the time being in
whose jurisdiction the work lies.
“Contractor” shall have the meaning attributed thereto in the array of Parties here in above as set
forth in the Recitals.
Accounting Year means the financial year commencing from the first day of April of any
calendaryear and ending on the thirty-first day of March of the next calendar year.
Applicable Laws means all statutes and laws promulgated or brought into force and effect by the
Central Government of India or any State Government(s) or Local Government(s), including
regulations and rules made by them, and judgments, decrees, injunctions, writs and orders of any
court of record, as may be in force and effect during the subsistence of this Agreement or
Applicable Permits means all clearances, permits, authorizations, consents and approvals required
to be obtained or maintained under Applicable Laws in connection with the constructions,
operations and maintenance of the Works/Project during the subsistence of this Agreement.
Bid shall mean all necessary submission pursuant to Eligibility and Qualification requirement as
per the Tender document (hereunder called “Eligibility and Qualification Submission”), Price Bid
submission online through www.smctender.nprocure.com.
Bill of Quantities means the priced and completed Bill of Quantities as specified in Section VI of
this Tender and forming part of the Bid.
Completion Date is the date of completion of the Works as certified by the Engineer and
Completion Certificate issue accordance with Clause 64.2 of General Conditions of Contract.
Completion Period shall be 12 (Twelve) Months (Excluding monsoon) from date of issue of
Notice of Award.
Contract or Agreement is the Contract between the Employer and the Contractor to execute,
complete, and maintain the Works. It consists of the documents listed in Clause 2.2 of General
Conditions of Contract.
Contractor is a person or corporate body whose Bid to carry out the Works, including routine
maintenance, has been accepted by the Employer.
Contractor's Bid is the completed bidding document submitted by the Contractor to the Employer.
Contract Price/Bid Price is the price stated in the Letter of Acceptance and thereafter as adjusted
in accordance with the provisions of the Contract.
VOL -1 Technical Bid |
Contract Period shall start from the date of issue of Notice to Proceed and end at end of Defect
Liability Period.
Days are calendar days; months are calendar months.
Defect is any part of the Works not completed in accordance with the Contract.
Defects Liability Period: The Defect Liability Period for whole work shall be 1 years from
date of issue of Completion Certificate. Water proofing items Defect Liability Period shall be
10 years from date of issue of Completion Certificate. Contractor will furnish Guarantee Bond
for water proofing items for the duration of 10 years.
Drawings include drawing specified in section VIII and calculations and other information
provided or approved by the Engineer for the execution of the Contract.
Estimated Project Cost means Engineer’s estimates of value of Works as specified in point 1 of
Invitation for Bidder (IFB) section.
Eligibility and Qualification Submissions is defined in clause no 11 of Instruction to Bidder
section. It comprises all necessary PQ supporting documents specified in clause 3.2 of ITB,
Tender Fee and EMD as per relevant clauses of ITB and addenda, corrigendum if any. Eligibility
and Qualification Submission shall be submitted online.
The Price Bid shall be dully signed and submitted in online format only. While form No. 1 to
dully filled and signed as specified in section III of ITB shall be submitted online and mentioned
in as per. IFB-18(Page N0-9) document Submited in Hard Copy at the time, mode, address and
place specified in Tender Notice.
Employer is the party (Surat Municipal Corporation or SMC), who employs the Contractor to
carry out the Works, including routine maintenance during the Defect Liability Period, Employer,
may delegate any or all functions to a person or body nominated by him for specified functions.
The Engineer is the Deputy Commissioner or Construction Supervision Consultant as appointed
by the Employer (or any other competent person appointed by the Employer and notified to the
Contractor, to act in replacement of the Engineer) who is responsible for supervising the
execution of the Works and administering the Contract. He is also known as Engineer in Charge
or Engineer-in-Charge.
Engineer In Charge, The “Engineer in charge” or the “Engineer” shall mean the technical person
designated as such by the owner from time to time and shall include those who are expressly
authorized by the Municipal Corporation to act for and in its behalf for the operation of this
contract viz, Executive Engineer of concerned department.
Equipment is the Contractor's machinery and vehicles brought temporarily to the Site to construct
Force Majeure Event shall have the meaning set forth in Clause 75 of this GCC.
Good Industry Practice shall mean the exercise of that degree of skill, diligence, prudence and
foresight in compliance with the undertakings and obligations under this Contract which would
reasonably and ordinarily be expected of a skilled and an experienced person engaged in the
implementation, operation and maintenance or supervision or monitoring thereof of any of them
of a project similar to that of the Project.
Initial Contract Price is the Contract Price listed in the Employer's Letter of Acceptance.
VOL -1 Technical Bid |
Intended Completion Date is the date on which it is intended that the Contractor shall complete
the Works. The Intended Completion date shall be 12 Months (Excluding monsoon) from the
date of issue of Notice to Proceed. The Intended Completion Date may be revised only by the
Engineer by issuing an extension of time.
Materials are all supplies, including consumables, used by the Contractor for incorporation in the
Material Adverse Effect means any act or event of either Party which causes a material financial
burden or loss to the counter party.
Parties shall mean the parties to this Agreement and “Party” shall mean either of them, as the
context may admit or require.
Performance Certificate is the certificate issued by Engineer, after the Defect Liability Period has
ended and upon correction of Defects by the Contractor to the satisfaction of Engineer.
Plant is any integral part of the Works that shall have a mechanical, electrical, electronic,
chemical, or biological function as may be required for execution of this Contract.
Routine Maintenance is the maintenance of corridors for the Defect Liability Period.
Site/ Project Site is the area defined in which project is executed.
Site Investigation Reports are those that were included in the bidding documents and are reports
about the surface and subsurface conditions at the Site.
Start Date the start date shall be date of issue of notice to proceed with the work and possession
of site given to the Contractor.
Tender Document shall comprise signed copy of Volume-I( Technical Bid) ,Volume-II(Price
Bid),Volume-III (Technical Specification Civil) ,Volume-IV( Technical Specification Electrical),
Volume-V(Drawings). All Such Document (duly signed & stamped) in Hard copy shall be
submitted by successful bidder upon intimation from SMC.
Technical Specifications means the Specifications of the Works as mentioned in Section V and
included in the Contract and any modification or addition made or approved by the Engineer.
The Owner/Employer shall mean Surat Municipal Corporation, Surat represented by Municipal
Commissioner/City Engineer/Deputy Commissioner or any officer authorized by the Surat
Municipal Corporation
Termination shall mean early termination of this Agreement pursuant to Termination Notice or
otherwise in accordance with the provisions of this Agreement but shall not, unless the context
otherwise requires, include expiry of this Agreement due to efflux of time in the normal course.
Termination Date shall mean the date specified in the Termination Notice or Notice of
Termination as the date on which Termination occurs.
Termination Notice means communication issued in accordance with this Agreement by one
Party to the other Party terminating this Agreement.
Temporary Works are works designed, constructed, installed, and removed by the Contractor that
are needed for construction or installation of the Works.
Quantity Variation means difference in quantities of items from estimated and actual, which is
required to complete the Work as per the Technical Specification.
VOL -1 Technical Bid |
Vandalism means destroying or damaging project property, deliberately and for no good reason
by the persons other than the employee or sub contractor of the Contractor.
Works or Project is defined as the scope of works defined in clause 1 of Instructions to Bidders
and clause 3 of GCC or elsewhere specified in this Bidding documents, which contractors shall
be required to perform (construct, install, maintain, and give back to the Employer).
2 Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male also means
female or neuter, and the other way around. Headings have no significance. Words have their
normal meaning under the language of the Contract unless specifically defined. The Engineer
will provide instructions clarifying queries about these Conditions of Contract.
2.2 Thefollowing documents shall be deemed to form and be read and construed as part of
Agreement/Contract, and shall be interpreted in the following order of priority:
1) Agreement signed between two parties
2) Any correspondence between the two parties that the signatories have agreed to include as
part of the Agreement for validating and clarifying any points in the Agreement, or by way
of revised or improved understanding of any terms of the Agreement
3) Notice to Proceed with the Work.
4) Letter of Acceptance.
5) Special Conditions of Contract
6) General Conditions of Contract and any other terms specified elsewhere in the Tender.
7) Technical Specifications as mentioned in this tender document.
8) Technical Specifications - Revised Clauses
9) Technical Specifications - Additional Special Specifications.
10) Scope of work
11) Performance Security
13) Bill of Quantities.
14) Contractor's Bid.
15) Any modification/amendments issued by Employer prior to bid submission date.
It is clarified that in case of conflict between the documents mentioned above, the detailed
terms specified in the Agreement, the Agreement shall have overriding effect.
2.3 Priority of Contract Documents
In case of any ambiguities or discrepancies, the priority shall be as under:
1. Letter of Acceptance
2. Priced Bill of Quantities, Correspondence after submitting bid and before letter of
acceptance / modification/ addenda.
3. Additional Technical Specifications.
5. Special Conditions of Contract; contract data.
6. General Conditions of Contract
7. Additional/General Conditions of Contract
3 Scope of Work
The Scope of the Work of this Project shall mean and includes followings.
VOL -1 Technical Bid |
1. The scope of work is defined broadly in the special conditions of Contract and
specifications. The Contractor shall provide all necessary materials equipment and labour
etc. for the execution of the maintenance work till completion. All materials that go with the
work tests as required and provision of standard specification and furnish test report from
acceptable testing laboratories shall be approved by the Engineer-in-charge prior to
procurement and use.
2. Performance and fulfillment of all obligations of the Contractors in accordance with
the provisions of Contract Conditions and matters incidental thereto or necessary for the
performance of any or all of the obligations of the Contractor under this Contract.
4 Language and Law
The language of the Contract documents is English and the law, which applies to the
Contract, is the law of Union of India and applicable State laws of Gujarat State.
5 Engineer – In-charge
5.1 Authority of the Engineer-in-charge:
Save in so, as it is legally or physically impossible, the contractor shall execute, complete and
maintain the works in strict accordance with the contract under the directions and to the entire
satisfaction of the Owner/Employer / Engineer-in-charge and shall comply with and adhere
strictly to the Owner/Employer/Engineer-in-charge’s instructions and directions on any matter
(whether mentioned in the contract or not).
Subject to over all control of Owner/Employer / Engineer-in-charge, he shall decide all issues
which may arise as to quality and acceptability of materials furnished and work executed,
manner of execution, rate of progress of the works, interpretation of the plans and
specifications and acceptable fulfillment of the contract on the part of the contractor etc. He
shall determine the amount and quality of work performed and materials furnished and his
decision and measurements shall be final. In all such matters and in any technical questions
which may arise touching the contract, his decision shall be binding on the contractor.
The Owner/Employer / Engineer-in-charge shall have the power to force such decisions and
orders if the contractor fails to carry them out promptly. If the contractor fails to execute
work ordered by the Owner/Employer / Engineer-in-charge, he may give notice to the
contractor specifying a reasonable period therein and on the expiry of that period, proceed to
execute such work as may be deemed necessary and recover the cost thereof from the
The Engineer-in-charge shall have no authority to alter or waive the provision of plans and
estimates and specifications or to relieve the contractor of any of his duties or obligations
under the contract except with the full concurrence of competent authority of the
Owner/Employer. He shall however have the authority to inform the contractor in writing to
replace any materials considered defective and to suspend, re-do or rectify any work
improperly performed or not according to plans and estimates or specifications in his
judgment and the contractor shall comply with all these requirements forthwith.
5.2 Authorized Representative of Engineer-in-charge:
The owner may employ supervision consultants who will act in the capacity of
authorizerepresentative of the Engineer–in-Charge. The supervision consultants will be
responsible for day to day supervision of works, to test and examine any materials to be used
or workmanship employed to ensure that the works are performed in conformity with the
plans, estimates and specifications in all respects and to keep the Engineer-in-charge informed
as to the progress of the works and the manner in which they are done. The powers which may
VOL -1 Technical Bid |
be delegated to the supervision consultants by the Owner/Employer shall be binding on the
5.3 Limitations of Engineer-in-charge and his Representative:
Failure of the Owner/Employer’s supervision consultant to disapprove any work or materials
shall not prejudice the power of the Engineer-in-charge thereafter to disapprove such work or
materials or to order pulling down, removal or breaking up thereof. If the contractor shall be
dis-satisfied by any reason on decision of the Engineer-in-charge or his representative, he
shall be entitled to refer the matter to the higher authority in Owner/Employer who shall
there upon confirm reverse or vary such decision, if considered necessary in terms of contract
5.4 Except where otherwise specifically stated, the Engineer-in-charge will decide contractual
matters between the Employer and the Contractor in the role representing the
Employer.However, if the Engineer is required under the rules and regulations and orders of
the Employer to obtain approval of some other authorities for specific actions, he will so
obtain the approval.
5.5 Except as expressly stated in the Contract, the Engineer shall not have any authority to
relieve the Contractor of any of his obligations under the contract.
The Engineer, with the approval of the Employer, may delegate any of his duties and
responsibilities to other people, after notifying the Contractor, and may cancel any
delegation after notifying the Contractor.
7. Communications
Communications between parties that are referred to in the Conditions shall be effective
only when in writing. A notice shall be effective only when it is delivered.
8. Joint Ventures
Consortium/Joint Venture is not allowed to participate in Bid. The Contract shall be
terminated if Single Contractor forms Joint Venture/Consortium after award of Work.
The contractor shall not assign, transfer or otherwise dispose of the contract or any part
or share thereof, in respect of any right, title, benefit or interest thereof or there under,
without the written consent of the Engineer-in-charge. No installment or other sum of
money become payable under the contract shall be payable to any person other than the
contractor, unless the written consent of the Engineer-in-charge to the assignment or
transfer of such money to such person, be produced when such payment is claimed as
10. Sub-letting
The contractor shall not sublet the whole or part of the works except where otherwise
provided by the contractor for any of the works, with the written consent of the client not
withstanding such consent, the contractor shall not be relieved of any of his liabilities or
obligations under the contract and he will stand responsible for all the acts, defaults and
neglects if any, by such sub contractor, his agents, servants or workmen as if they were
the acts, defaults and neglects of the contractor himself, provided always that the
provision of labour on a piece work basis shall not be deemed to be a subletting under
VOL -1 Technical Bid |
When asking consent from the client, the contractor shall submit names of sub-contractors
and of the actual makers in case the sub-contractors are not the actual makers. If and when
the client has consented in writing, the contractor shall send two copies of the sub contract
to the engineer-in charge.
The sub contract or sublet order shall contain all necessary information’s given in the
specifications of the contract to enable sub-contractor supply the materials or execute the
work in accordance therewith and adhere to the time in which the sub-contractor is to
procure the materials and complete the works.
11 Documents mutually explanatory and complementary:
The several documents forming the contract are essential part of the contract and a
requirement occurring in one is as binding as though occurring in all. They are intended to
be mutually explanatory and complementary and to describe and provide for a complete
In the event of any discrepancy between the several documents forming the contract in any
one document, the following order of precedence shall apply.
11.1 Dimensions and quantities.
ii. Bill of Quantities.
iii. Broad specifications given in the tender, on drawings.
Figured dimensions unless obviously incorrect will be followed in performance to scaled
11.2 Description:
i) Bill of Quantities.
iii) Broad specifications given in the tender
In case of defective description or ambiguity, the Engineer-in-charge shall issue further
instructions directing in what manner the work is to be carried out, it being understood that
the best modern practice is to be followed and the contractor shall forthwith comply with
such instructions without any extra cost.
The contractor shall take no advantage of any apparent error or omission in drawings or
specifications or in Bill of Quantities and the Engineer-in-charge shall be permitted to
make such corrections and interpretations as necessary to fulfill the intent of the plans and
specifications.
12 Subcontracting
12.1 The contractor may subcontract with the approval of the engineer but may not assign the
contract without the approval of the employer in writing. Subcontracting does not alter the
contract’s obligations and it shall not absolve Contractor from its obligations.
12.2 Any default of the sub-contractor shall not absolve the Contractor from its obligations.
13 Programme of works:
The contractor shall furnish detail programme of work with CPM/PERT chart and cash flow
chart in writing for approval of the Owner/Employer / Engineer-in-charge, within 30 days
after the work order to commence execution of the work contract is given and wherever
VOL -1 Technical Bid |
required thereafter, a programme of construction and no change shall be made, except with the
approval of or at the instance of the Owner/Employer / Engineer-in-charge.
The approval of a programme shall not relieve the contractor of any of his duties and
responsibilities under the contract. The adoption of any modification in the programme
required by the Owner/Employer /Engineer-in-charge to make good deficiency in progress
shall not entitle the contractor to any extra payments etc.
14 Disposal of Surplus Excavation Materials:
The surplus excavated earth, after back-filling the trenches shall have to be removed from
the site as directed. after compaction and consolidation, if any short fall of earth is found
then contractor has to bring the same to the required quantity in order to meet shortfall at his
own cost. More over, if any settlement of road after reinstatement is observed during the
defect liability period of the work.Contractor shall be fully responsible for the defective
work and patches/ depression / settlement shall be repaired with quarry spoil or metal at
contractor's own cost. If contractor fails to repair the patches / depression / settlement in
time, corporation will repair it at all risk and cost of contractor.Surplusearthshall not be
disposed off in a way that leads to nuisance to the public or SMC.
15 Patented Devices, materials and Processes:
Whenever the contractor desires to use any design device, drawing information’s, materials
or process covered by a patent or copyright, he shall procure the rights for such use by
suitable legal agreement with the patentee or owner at his own expenses and a copy of the
agreement shall be filed with the Engineer-in-charge.
The contractor shall indemnify the Owner/Employer from and against all claims,
proceedings damages, costs and expenses which may be brought or made against the
Owner/Employer or to which they may be put by reason of the contract infringing or being
held to have infringed any patent rights or copyright in relation to any design, device
drawing, materials or process at anytime during the prosecution or after the completion of
the work and in the event of any injunction being obtained against the use of the same, the
contractor shall replace the same with other materials design, drawing, device, process
etc. which do not infringe any such patent right or copy right, to the satisfaction of the
Engineer-in-charge.
The contractor shall at all times be responsible for any damages due to trespass committed
by his agents and work people in carrying out the work, unless authorized by the Engineer-
in-charge in writing in which case, all repair work shall be done by the contractor at his own
cost to restore the original condition.
17 Police protection:
If the police is asked for by the contractor for special protection of his camp of work, the
Owner/Employer may issue recommendation letter for such protection so far as possible with
the authorities concerned and the full cost of such protection shall be paid by the contractor
directly to the concerned police station.
18 Office set up at site:
The Contractor has to set up a site office at a centrally located area making it accessible from
all the work area, which shall be mutually agreed upon with SMC/Employer. The office shall
have computer facilities with printers and Internet connection for Email Correspondence
VOL -1 Technical Bid |
ensuring faster communication. The contractor should also have Digital Camera with Data
Transfer capabilities at the site. The contractor shall take photographs of site prior to
commencement of work, during construction and after completion of work as suggested and
shall submit the photographs in soft and hard copies to SMC. The Contractor is also required
to provide office space for ProjectConsultant/ Employer’s representative as directed by
Engineer In charge.
19 Obligations of the Contractor
19.1 General Obligations of Contractor
a) Subject to and terms and conditions of this Contract, the Contractor at its cost and
expense shall undertake survey, engineering, procurement, construction and
maintenance of the Project and fulfill, comply with all obligations set out in the
Contract Conditions, Scope of Work, Technical Specifications and Drawings.
b) Comply with applicable laws and permits in performance of its obligations during
Construction and Maintenance Period.
c) Performance of all obligations under this Contract in accordance with the Good
Industry Practice and as a reasonable and prudent person.
d) The Contractor shall remedy all loss or damage to the Project or Material to be
incorporated in the Project from the Start Date till the end of the Defect Liability Period
at Contractor’s cost if such loss or damage is attributable to the Contractor’s acts or
e) Make efforts to maintain harmony and good industrial relations among the personnel
employed in connection with the performance of the Contractor’s obligations under this
f) Contractor shall not do or omit to do any act, deed or thing which may in any manner
be violate any of the provisions of the Contract/Agreement.
g) Contractor shall support, cooperate with and facilitate the Employer in the
implementation and operation of the Project in accordance with the provisions of this
h) The Contractor should take up the Works as decided by the Engineer to ensure there is
least hindrance to the smooth flow of traffic including movement of vehicles and
equipment of other Contractors till the completion of the Works.
i) Contractor shall take insurance policies of Works, Plant& Materials, its employees and
Third party insurance as per the provision of this Contract.
j) The Contractors shall also give a list of machineries in his possession and that he
proposes to use the work.
k) The Contractor is responsible for safety of its people deployed on Project. He shall
have to arrange for the supply of gumboots, Hand gloves, mask etc. invariably to the
labourers/workers engaged by the contractor on work.
l) The Contractor shall have to deploy adequate plant, machinery, manpower, equipment,
DG set, supervisory staff etc to carry out simultaneous work on all locations.
VOL -1 Technical Bid |
m) The Contractor shall deploy adequate and good quality of Equipments required for
maintenance of the Project. It also has to abide by the direction Engineer during the
n) The Contractor shall not have any legal rights on the Site and the Contractor is required
to use Project site to carry out the Project Works only.
o) No waiving of legal rights and powers:
The Owner/Employer shall not be precluded or stopped by any measurement, estimates
or certificate made either before or after the completion and acceptance of the work and
payment therefore, from showing the true amount and character of the work
performed and materials furnished by the contractor and from showing that any
measurements, estimate or certificate is untrue or incorrectly made, and that the
Owner/Employer shall not be precluded or stopped from recovering from the contractor
such damages as it may sustain by reason of his failure to comply with the terms of the
contract. Neither the acceptance by the Owner/Employer or any representative of the
Owner/Employer nor any payment for or acceptance of the whole or any part of the work
nor any extension of time nor any possession taken by the Owner/Employer shall operate
as a waiver of any portion of the contractor any power herein reserved or of any right to
damages. A waiver of any breach of the contract shall not be held to be a waiver of any
other or subsequent breach.
p) The Contractor is required to provide the colour photograph displaying the date and
time of Completed Work along with the Bill as and when demanded by Engineer In
19.2 Cooperation with Other Contractors
The Contractor shall cooperate and share the Site with other Contractors, public
authorities, utilities and the Employer if Employer so demands or as referred in
Technical Specifications. The Contractor shall also co-operate with them or provide any
facilities as demanded by Employer.
19.3 No Advertisement on Project Corridor by Contractor
Project or any part thereof shall not be used in any manner to advertise any commercial
product or services by Contractor. It is agreed that Contractor can only display diversion
or safety related displays during the execution of Works only.
19.4 Employment of competent Personnel
a) The Contractor shall employ competent technical personnel or other technical persons
approved by the Engineer for the construction work and maintenance works of the
Project. The Engineer willapprove any proposed replacement of technical personnel only
if their relevant qualifications and abilities are substantially equal to or better than
existing competent technical personnel.
b) If the Engineer asks the Contractor to remove a person who is a member of the
Contractor's staff or work force, stating the reasons, the Contractor shall ensure that the
person leaves the Site within seven days and has no further connection with the Works in
c) The Contractor shall not employ any retired officer who has worked in the Engineering
Department of the Surat Municipal Corporation and has either not completed two years
VOL -1 Technical Bid |
after the date of retirement or has not obtained Surat Municipal Corporation’s permission
to employment with the Contractor.
19.5 Contractor to carry out the Works
a) The Contractor shall carry out engineering, survey, construction, repair and maintain
the Works in accordance with the Technical Specifications, Scope of Work, Drawings
and Good Industry Practice at Project Site as per the direction of Engineer-in -charge.
Any breach or deviation from the Technical Specifications, quality, and Safety
aspects leads to Damages and Penalties. The Damages and Penalties shall be
commensurate with the type and nature of the Default or breach. The deviation from
the Technical Specifications shall only be permitted to the extent permitted by
b) Contractor shall bear full risk in and take full responsibility for the care of the
Works/Project and Materials, equipment’s for incorporation therein from Start Date
until the end of Defect Liability Period except to the extent that any loss of or damage
to the same shall arise out of any default or neglect of Employer.
19.6 Electricity, Water and other services
a) Water Supply: The contractor shall arrange at his own cost, a suitable supply of potable
water for the construction of the works. The Contractor is required to provide Test
certification of Water quality from approved laboratory to Engineer for its approval
prior to its use for Construction Work. All cost related to water supply shall be borne
by the Contractor.
b) Electricity: The Contractor is required to make its own arrangement, at its cost, for
obtaining electricity connection. Payment of all costs in this regard will be the
responsibility of the contractors. In case if there is any delay in supply of power at site
or any interruption or fault in the power during the work. No compensation shall be
paid for idle labour staff, machineries and for use of diesel operating sets etc. as the
case may be and no extra time limit shall be granted. In case of failure of the non-
payment of power consumption charges, SMC reserves the right to deduct the same
from the RA/ Final Bills of the contractor.
c) The contractor will be required to arrange for total station survey for carrying out the
work and for measurements wherever needed as per the instruction of the Engineer-in-
Charge. No extra payment shall be made towards this.
d) Contractor will be required to establish a laboratory, fully equipped with test apparatus
as mentioned in Technical Specification.
e) The Contractor is also required to set up material storage area.
VOL -1 Technical Bid |
CONDITION FOR THE WATER SUPPLY & ELECTRIC SUPPLY
FOR WATER CHARGE (As per City Engineer Note No.386, dtd.30/7/2012) In case of
Municipal Network or distribution center available or not at nearby area
Contractor has to make his own arrangement for construction work whether from private
boring or tankers. Contractor has to submit test report of water weather it is of good quality
for construction work or not and contractor has to inform about it within 30 days of
starting the work. Contractor shall have to inform in writing in the case of using or making
own arrangement of water for the purpose of this work before starting the work.
If contractor wants to use Municipal Water, he has to follow procedure within below:
1. Contractor has to apply for water connection by Municipal Licensed plumber in prescribed
2. Contractor has followed all procedure with his own expenses.
3. According to rule of Surat Municipal Corporation issued bill to contractor for consumption
of water, contractor has to pay it within stipulated time and to submit one copy of bill and
payment receipt to concern department. If contractor fail to pay the amount of bill/paid
receipt, it can be recovered from contractor's bill.
4. If Municipal Corporation network is not available then Contractor can make arrangement of
water tanker from nearby distribution center after depositing required amount.
5. After completion of work contractor has to cancel the water connection and inform the
concerned department.
6. If network and distribution center/network are both not available in that case contractor has
to make his own arrangement for good quality construction water and has to follow the
7. The contractorshall makehis own arrangement at his cost for electric supplyrequired
foroperating various plants and machineries required for the works and for general
lighting purpose for site, office labour colony etc. The energy bills shall also be paid
by the contractor.
19.7 The Works are to Be Completed by the Intended Completion Date
The Contractor may commence execution of the Works on the Start Date and shall carry out
the Works in accordance with the Programme submitted by the Contractor, as updated with
the approvalof the Engineer, and complete them by the Intended Completion Date. Any delay
leads to the Liquidated Damages as specified under clause 43 of this General Conditions of
a) The Contractor shall be responsible for the safety in all activities on the Site and
safety of adjoining properties and adjoining property dwellers to the extent it (safety
of adjoining properties and adjoining property dwellers) is affected by construction
activities. The contractor is responsible to follow all the safety measures stated in BIS
throughout the ongoing work. He shall be responsible for any of damage, causalities,
and inconvenience due to lacking of safety on site and hence liable to compensate
VOL -1 Technical Bid |
/penalized for all such damage, causalities and inconvenience in terms of money as
decided by the engineer and such amount shall be deducted from his running
bill for that month or other deposits of contractor.
b) The contractor shall, unless otherwise specified, be responsible for the proper fencing,
lighting grading and taking of the necessary safety measures for all works comprised
in the contract and for the proper provision of temporary road, way, foot way, guards,
fences, caution notices etc., as far as the same may be rendered necessary by reasons
of the work for the accommodation of workmen, foot passengers or other traffic and
of owners and occupiers of adjacent property and the public and shall remain
responsible for any accidents that may occur on account of his failure to take proper
& timely precautions.
c) The contractor shall take all necessary precautions to prevent any nuisance or
inconvenience to the owners, tenants or occupations of adjacent properties and to the
public generally and to prevent any damage to such properties and any pollution. He
shall make immediately good at his own expense and the satisfaction of the Engineer-
in-charge, any damage to roads, paths, cross-drainage works, underground utilities
like water line, drainage network, cables of electric line, telephone line etc. or
public or private property when-so-ever and whatsoever caused due to the execution
of the work or by traffic brought thereon by the contractor. All waste or superfluous
materials shall be cleaned away by the contractor.
d) All the arrangements made for fencing and lighting shall be maintained by the
contactor throughout the contract till the physical taking over of the work by the
e) The Contractor shall provide all necessary personal safety equipment and first aid
apparatus available for the use of persons employed on the site and shall maintain
them in the same conditions suitable for immediate use at any time and shall comply
with the following regulations in connection there with :
f) The workers shall be required to use the equipment so provided by the Contractor and
the Contractor shall take adequate stops to ensure proper use of the equipment by
those concerned.
a) When work is carried on in proximity to any place where there is a risk of drawing all
necessary equipment shall be provided and kept ready for use and necessary steps
shall be taken for the prompt rescue of any person in danger.
b) Adequate provision shall be made for prompt first aid treatment or injuries likely to
be sustained during the course of the work.
c) The Contractor shall be responsible for and shall pay the expense of providing
medical to any workmen or any personnel who may suffer a bodily injury as a result
of an accident. If such expenses are incurred by the Employer the same shall be
recoverable from the Contractor forthwith and be deducted without prejudice to any
other remedy of Employer from any amount due to that may become due to the
19.9 Liability in case of Damage done in surrounding areas
a) Compensation for all damage done intentionally or unintentionally by Contractor's labourers
whether in or beyond limits of Municipal Corporation properties, Service Provider’s
properties, Any Government Agencies properties, all Third party properties whether
VOL -1 Technical Bid |
underground or above ground shall be estimated by the Engineer, or such other officer as he
may appoint and the estimates of the Engineer, subject to the decision of the Deputy
Commissioner, on appeal, shall be final and the contractor shall be bound to pay the amount
of the assessed compensation on demand, failing which the same will be recovered from the
Contractor as damages from Performance Security or deducted by the Engineer from any
sums that may be due or become due from Municipal Corporation to the contractor under
this contract or otherwise.
b) The Contractor shall bear the expenses of defending any action or other legal proceeding that
may be brought by any person for injury sustained by him owing to neglect of precautions to
prevent the spread of the fire and he shall also pay the damages and cost that may be
awarded by the court in consequence.
19.10 Obligations regardinglabour laws
The Contractor shall have to adhere to the applicable labour laws including for wages during
LABOUR LICENCE:-
Before starting the work, the Contractor will have to obtain the license from the District
Assistant Labour Commissioner under the Contract labour (Regulation and abolition) Act
1970 as contract labour (Regulation and abolition) Gujarat Rules 1972 after paying necessary
fees and deposit on the basis of the number of labourers to be employed on the work and will
have to supply two true copies of the said license to the Executive Engineer before starting the
19.11 Contractor to Execute the Works
i. The contractor shall execute the whole and every part of the work in the most substantial and
workman-like manner and both as regards materials and in other respects in strict accordance
with Technical Specifications, Drawings and Good Industry Practice.
ii. The contractor shall also conform exactly, fully and faithfully to the design, drawings and
instructions in writing for the work signed by the Engineer-in-charge. The design and the
drawings shall be lodged in the office of the Engineer-in-charge to which the contractor shall
be entitled to have access for the purpose of inspection at such office during office hours.
iii. Where the instructions referred to above are not contained in separate letters addressed to the
contractor the same shall be recorded in the work order book, which shall be maintained and
kept on the site of the work. The contractor shall be required to sign such entries in the work-
order book, which shall be maintained and kept on the site of the work. The contractor shall
be required to sign such entries in the work-order book in token of having noted the
instructions. However, if the contractor fails to sign the work-order book for any reason
whatsoever, the entry of the instructions in the work-order book shall be deemed to be the due
notice to him of the said instructions. The work-order book shall be open for inspections to the
contractor on the site of the work during office hours.
19.12 Obligations relating to Ownership of Contractor Company
Contractor shall not undertake or permit any changes in its ownership, except with the prior
approval of the Authority during the Construction Period.
19.13 Contractor’s Risk
VOL -1 Technical Bid |
a) All risks of loss of or damage to physical property and of personal injury and death which
arise during and in consequence of the performance of the Contract on any default or neglect
of Contractor is the responsibility of the Contractor.
19.14 Approval of Temporary Work
(i) The Contractor shall submit Specifications and Drawings showing the proposed Temporary
Works to the Engineer, who is to approve them if they comply with the specifications and
(ii) The Contractor shall be responsible for design of Temporary Works.
(iii) The Engineer’s approval shall not alter the Contractor’s responsibility for design of the
Temporary Works.
(iv) All Drawings prepared by the Contractor for the execution of the temporary or permanent
Works, are subject to prior approval by the Engineer before their use.
20 Obligations of the Employer
20.1General Obligations of Employer
(i) Employer is responsible for correctness and completeness of the Scope of the Project.
(ii) Employer shall provide Site to Contractor for carry out its obligations under this Contract and
(iii) Procure all applicable permits relating to the environment protection and site conservation if
(iv) Upon written request from the Contractor, subject to Contractor complying with applicable
law, provide reasonable support to Contractor for obtaining applicable permits.
21 Liability of accidents to persons
21.1 Responsibilities and liabilities of the Contractor under Workmen's Compensation Act
following shall also apply:
a) On the occurrence of an accident, which result in death of workmen employed by the
contractor or which is so serious as is likely to result in death of any such workmen, the
Contractor, shall within 24 hours of happening of such accident(s) intimate, in writing to the
Engineer in charge the fact of such accident(s). The contractor shall indemnify Surat
Municipal Corporation (SMC) against, all loss or damage sustained by the SMC resulting
directly or indirectly from his failure to give intimation in the manner aforesaid including the
penalties or fines, if any, payable by the SMC as a consequence of SMC failure to give notice
under the Workmen's Compensation Act or otherwise to conform to the provisions of the said
act in regard to such accident(s).
b) In the case of an accident, in respect of which compensation may become payable under
Workmen's Compensation Act, whether by the contractor or by the Government as principal
Employer, it shall be lawful for the Engineer in charge to retain cut of money due and payable to
the contractor, such sum or sum of money as, may, in the opinion of the Engineer in charge, be
sufficient to meet such a liability. The opinion of the Engineer in charge shall be final in regard to
all matters arising under this clause.
c) In any event of death of the worker or employee of the bidder, SMC will not held responsible
in any case . If Police case occurs then it will be sole responsibility /liabilities of the successful
bidder and SMC will not held responsible for any case.
VOL -1 Technical Bid |
22 Residential accommodation and sanitary and medical arrangements to be provided to the
labour employed by the contractor:
a. Before opening a labour camp, the contractor shall obtain and follow the advice of the
Medical Officer of the City regarding the campsite, accommodation, water and food supply,
sanitary arrangement, etc.
b. The contractor shall build a sufficient number of huts for the labour on a suitable plot of land
according to the following specifications.
(i) A good site shall be selected; High ground removed from jungle but well provided with
trees shall be chosen wherever it is available. The neighborhood of heavily built up
areas should be particularly avoided. Camps should not be established closed to
railways, highways, and canals. When a good natural site cannot be procured, particular
attention should be given to drainage.
(ii) The lines of huts shall have open space of at least 5 meters between rows.
(iii) Huts of bamboos and grass may be considered.
(iv) There should be no overcrowding. Floor space on a scale of 30 sq. ft. per head shall be
(v) Care shall be taken to see that the huts are kept clean and in good order.
(vi) The contractor must find of his own the land for the purpose. If he wants
Owner/Employer’s hand, he should apply for it and pay assessment for it.
c. The contractor shall provide at his own cost an adequate supply of pure and potable water for
the labourers at a rate of not less than forty liter per head per day. No provision needs to be
made if there is well or adequate tap water arrangement within a half kilometer of the camp.
d. The contractor shall construct at his own cost trench or semi-permanent latrines for the
labourers on a scale of not less than five for every 50 persons or part thereof. Separate
latrines shall be provided for men and for women. The labourers may at their option be
allowed to use either the trench system or the latrine system.
e. The contractor shall construct at his own cost.
(i) Screened bathing places on a scale of not less than one for every 20 persons or part
thereof. Separate bathing place shall be provided for men and women.
(ii) Washing places for washing clothes on a scale of not less than one for every
persons or part thereof.
(iii) Efficient drainage arrangement for removing sludge water from bathing and washing
places and for its disposal without causing nuisance.
f. The contractor shall provide at his own cost necessary staff for effecting conservancy.
Sanitation and cleanliness to the satisfaction of the Engineer in charge. Sweepers shall be
employed on a scale of not less than one sweeper for every 200 persons or part thereof.
g. The contractor shall arrange at his own cost for all anti-malaria measures for the labour
employed on the work as directed by the medical officer health department.
h. The contractor shall provide at site, suitable measures for fire protection and control to the
satisfaction of the Engineer in charge. The land required for the erection / construction of
labour camp will have to be arranged by the contractor at his own cost. With land owners on
such terms as may be mutually agreed between the contractor and the owner. The SMC will
VOL -1 Technical Bid |
however give assistance within its competence to enable him to obtain the land without
accepting any responsibility for delay if any.
i. The land required for the erection / construction of labour camp will have to be arranged by
the contractor at his own cost. With land owners on such terms as may be mutually agreed
between the contractor and the owner. The SMC will however give assistance within its
competence to enable him to obtain the land without accepting any responsibility for delay if
23 Change in prices, rates, wages & taxes etc. subsequent to the acceptance of the tender:
The contractor shall not be entitled to claim or any compensation on the ground that
subsequent to the acceptance of the tender, there was change in prices, rates & wages etc.
However, any new direct taxes imposed by Government during contract period should be
suitably reimbursed after verifying satisfactory production of documentary evidence. No
indirect taxes and /or any price variation on petroleum products and transportation will be
considered for payment.
24 Permits licensees, priorities, certificates etc:
The contractor shall make his own arrangements at his own cost, if required.
(a) To obtain permits, licensees, quota certificates, foreign exchange etc. for any materials or
items of work etc. if required by him.
(b) To obtain rail and other priorities for transport of his plants, tools equipment’s, stores,
machinery, materials, labour staff etc.
(c) To arrange with civil supply authorities for release of controlled goods if so, for his labour
The Owner/Employer will not undertake to arrange for these but will tender reasonable help
within its competence without accepting any responsibility for delay if any.
25 Insurance during the Construction Period and Defect Liability Period (Contractor’s All
Risk Policy (CAR Policy)
The Contractor shall, at its cost and expense, purchase and maintain during the Construction
Period and Defect Liability Period, such insurances as are necessary including but not
limited to the following:
(a) Fire and allied natural calamities for the Project;
(b) Contractor’s all risk insurance.
(c) Comprehensive third party liability insurance including injury or death to such thirdparties
who may enter or are in the vicinity of the Project Site;
(d) Workmen’s compensation insurance;
(e) Loss of or damage to property (except the Works, Plant, Materials, and Equipment) in
connection with the Contract; and
(f) Loss or damage to the plant, material and equipment.
(g) Personal injury or death of employee of Contractor/ Employer.
The contractor shall take “all contract risk insurance policy” for the estimated cost of the
work.“Workmen's compensation policy” for all workers and labourers of contractor and
Owner/Employer working at site and “Third Party Insurance Policy” to fully cover all
thirdpartytype risk. The insurance policy so taken by the contractor for such purposes shall
be in the joint name of the contractor and the Owner/Employer and the policy shall be
deposited with the Owner/Employer.
VOL -1 Technical Bid |
Any other insurance that may be necessary to protect the Contractor, its employees and the
Project against loss, damage or destruction at replacement value including all Force Majeure
Events that are insurable and not otherwise covered in items (a) to (g).
Insurance policies and certificates for insurance shall be delivered by the Contractor to the
Engineer for the Engineer's approval before the Start Date and all such insurance shall
provide for compensation to rectify the loss or damage incurred or injury of death as
specified in clause 25.1 of GCC.
25.1 Application of Insurance Proceeds
(a) All money received under insurance policies shall be promptly applied by the Contractor
towards repair or renovation or restoration or substitution of the Project or any part thereof
which may have been damaged or destroyed.
(b) Contractor shall carry out such repair or renovation or restoration or substitution to the extent
possible in such manner that the Project, or any part thereof, shall, after such repair or
renovation or restoration or substitution is as far as possible in the same conditions as they
were before such damage or destruction, normal wear and tear excepted.
25.2 Insurance by Sub-Contractors
The Contractor shall ensure that similar insurance policies are taken out by his Subcontractor (if
any) and shall be responsible for any claims or losses to Employer resulting from their failure
toobtain adequate insurance protection in connection thereof. The Contractor shall procure or
cause to be produced by his SubContractors (if any) as the case may be relevant policy or
policies and premium receipts as and when required by the Engineer.
25.3 Validity of the Insurance Cover
The Contractor shall pay the premium payable on such insurance Policy/Policies so as to keep
the insurance in force and valid throughout the Construction and Defect Liability Period and
furnish copies of the same to the Employer for each year/policy period. If at any time
Contractor fails to purchase and maintain in full force and effect any and all of the Insurances
required under this Contract, the Employer may at its option purchase and maintain such
insurance and all sums incurred by the Employer therefore shall be reimbursed by the
Contractor forthwith on demand, failing which the same shall be recovered by the Contractor by
encashment of performance security or deduct from the remaining bills of the Contractor.
Anything of historical or other interest or of significant value unexpectedly discovered on the
Site shall be the property of the Employer. The Contractor shall notify the Engineer of such
discoveries and carry out the Engineer's instructions for dealing with them.
27 Possession of the Site
27.1 Contractor shall have to make their own arrangement for the land required for Plant, Casting
yardetc.Surat Municipal Corporation, upon written request of contractor, may arrange the land
for establishing the Batching Plant, Casting yard etc. as with charge of Rs. 10/Sq. Mt./month or
as per practice by SMC and which shall be deducted from R.A. bill generated by contractor. It
shall be clearly noted that SMC does not give any guarantee for providing such land. Delay in
providing land by SMC shall not alter or delay the overall project duration and time limit. Also
the same shall not be entertained for any sort of compensation and claim regarding the delay in
providing land for the same. The rental charges & taxes at prevailing policies shall be
applicable in case of land provided by SMC.
VOL -1 Technical Bid |
28 Supervision of Work
All works under or in course of execution or executed in pursuance of the contract shall, at all
times be open to the inspection and supervision of the Engineer-in-charge and his subordinates
or its authorized representatives, the Contractor shall, at all times during the usual working
hours, and all other times for which reasonable notice of the intimation of the Engineer-In-
charge or his subordinate or its authorized representatives to visit the works shall have been
given to the Contractor, either himself be present to receive orders and instructions or have a
responsible agent duly accredited in writing present, for that purpose. Orders given to the
contractor's duly authorized agent shall be considered to have the same force and effect as if
they had been given to the Contractor himself.
29 Instructions and Actions where no specification is given
29.1 The Contractor shall carry out all instructions of the Engineer in Charge, which comply with
the applicable laws where the Site is located.
29.2 In the case of any class of work for which there is no such specification such work shall be
carried out in accordance with the event of there being no specification then in such case the
work shall be carried out in all respect in accordance with the instructions and requirements of
the Engineer-in-Charge.
30 Dispute Redressal System
30.1 Settlement of disputes
a) Except or otherwise specifically provided in the contract, all the disputes concerning
questions of fact arising under the contract shall be decided by the Engineer-in-charge,
subject to a written appeal by the Contractor to the Engineer-in-charge, and these decisions
shall be final and binding on the parties hereto. Any dispute or differences including those
considered as such by only one of the parties arising out of or in connection with this
contract shall be to the extent possible settled amicably between the parties. If amicable
settlement cannot be reached then all disputed issues shall be settled as provided in (b).
b) Dispute or difference to be referred to:
If at any time, any question, disputes or differences of any kind what so ever shall arises
between the Engineer and the Contractor upon or in relation to or in connection with this
contract, either party may forthwith give to the other, notice in writing of the existence of
such questions, disputes or differences as to any decision, opinion, instruction, direction
certificate or evaluation of the Engineer.
The question or difference shall be settled by the Municipal Commissioner, who shall state
his decision in writing and give notice of the same to the Engineer and to the Contractor and
such decisions shall be final and binding upon both parties to the contract and work on
contact if not already breached or abandoned shall proceed normally unless and until the
same shall be revised (or upheld) due to any judicial proceeding.
Should the Municipal Commissioner fail to give a decision within two (2) calendar months
after issuance of notice of a question, dispute or difference or if the Contractor is dissatisfied
with any such decision of the Municipal Commissioner, then the matter may be referred to
standing committeeofSuratMunicipal Corporation. Then also if the question or difference
remains unsettled and if the Contractor is dissatisfied with any such decision of standing
committee of SMC the question or dispute or matter may be referred to the court of law
subject to Surat Jurisdiction.
VOL -1 Technical Bid |
31 Claim for compensation for delay in the starting of work
31.1 No compensation shall be allowed for any delay caused in the starting of the work on account
of clearance to be obtained by the Contractor or on account of any delay in according sanction to
32 Claim for compensation for delay in the execution of work
32.1 No compensation shall be allowed for any delay in execution of the work on account of delay
attributable to Contractor’s fault/breach.
33 Entering upon or commencing any portion of work
33.1 The Contractor shall not enter upon or commence any portion or work except with written
authority and instruction of the Engineer-in-Charge or of his subordinate in charge of the work
failing such authority, the Contractor shall have no claim to ask for measurements of or
payment for work.
34 Fair Wages to Contractor’s workers
34.1 If a contractor fails to pay within "7' (seven) days to its labourer(s) employed for this
Project, the minimum wages prescribed by the Government under the Minimum wages. Act
1948 as in force time to time the Engineer-in-Charge shall be at liberty of deduct the amount
payable to the labourer(s) worker(s) from his Contractor's bill or deposit(s) payable by the
contractor after making due inquiries and establishing the claim(s) of the labour(s)
Worker(s) The Contractor shall not be entitled to any payment or compensation on account
of loss that he contractor may have to incur on account of the action as forced a notice in
writing to be Contractor shall be issued by the Engineer-in-Charge to the wages as per
Minimum wages Act in force at the relevant time. If the Contractor does not be as aforesaid
within seven days the action contemplated as above shall be taken against him.
35 Severability and Waiver
35.10 If any provision of this Contract, or any part thereof, shall be found by any court or
administrative body of competent jurisdiction to be illegal, invalid or unenforceable the
illegibility, invalidity or unenforceability of such provision or part provision shall not affect the
other provisions of this Contract or the remainder of the provisions in question which shall
remain in full force and effect. The relevant Parties shall negotiate in good faith in order to
agree to substitute for any illegal, invalid or unenforceable provision a valid and enforceable
provision, which achieves to the greatest extent possible the economic, legal and commercial
objectives of the illegal, invalid or unenforceable provision or part provision. No failure to
exercise or enforce and no delay in exercising or enforcing on the part of either Party to this
Contract of any right, remedy or provision of this Contract shall operate as a waiver of such
right, remedy or provision in any future application nor shall any single or partial exercise or
enforcement of any right, remedy or provision preclude any other or further such right, remedy
or provision or the exercise or enforcement of any other right, remedy or provision.
36 Representation and Warranties of Contractor
The Contractor represents and warrants to the Employer that:
i) It is duly organized and validly existing under the laws of India (and their respective countries
in case of foreign bidders), and has full power and authority to execute and perform its
obligations and carry out the work as per the terms of contract.
ii) It has taken all necessary actions under the Applicable Laws to authorize execution and
delivery of this contract and to validly exercise its rights and perform its obligations under
VOL -1 Technical Bid |
iii) This Contract constitutes its legal, valid and binding obligations, enforceable against it in
accordance with terms hereof, and its obligations under this Contact will be legally valid,
binding and enforceable obligations against it in accordance with the terms hereof.
iv) It is subject to civil and commercial laws of India with respect to the Tender and this
Contract/ Agreement and it hereby expressly and irrevocably waives any immunity in any
jurisdiction in respect thereof.
v) The information furnished in the Bid and as updated on or before the date of this
agreement/contract is true and accurate in all respects as on the date of this Contract.
vi) The execution, delivery and performance of this Tender and Contract thereof will not
conflict with, result in the breach of, constitute a default under or accelerate performance
required by any of the terms of the Contractor’s Memorandum and Articles of Association
or any Applicable Laws or any covenant, agreement, understanding, decree or order to
which it is a party or by which it or any of its properties or assets is bound or affected.
vii) There are no actions, suits, proceedings, or investigations pending or, to the Contractor’s
knowledge, threatened against it at law or in equity before any court or before any other
judicial, quasi judicial or other authority, the outcome of which may result in the breach of
or constitute a default of the Contractor under the Tender or which individually or in the
aggregate may result in any Material Adverse Effect.
viii) It has no knowledge of any violation or default with respect to any order, writ, injunction
or any decree of any court or any legally binding order of any Government Agency which
may result in any material adverse effect or impairment of the Contractor’s ability to
perform its obligations and duties under this Tender and Agreement.
ix) It has complied with all Applicable Laws and has not been subject to any fines, penalties,
injunctive relief or any other Civil or criminal liabilities which in the aggregate have or
may have Material Adverse Effect.
x) No representation or warranty by the Contractor contained herein or in any other document
furnished by it to Authority or to any Government Agency in relation to Applicable
Permits contains or will contain any untrue statement of material fact or omits or will omit
to state a material fact necessary to make such representation or warranty not misleading;
xi) No sums, in cash or kind, have been paid or will be paid, by or on behalf of the Contractor,
to any person by way of fees, commission or otherwise for securing the Tender or entering
into of the Agreement or for influencing or attempting to influence any officer or employee
of Employer inconnection therewith.
37 Representation and Warranties of Employer
The Employer represents and warrants to the Contractor that:
i) It has full power and authority to grant the Tender and enter into Agreement with the
ii) It has taken all necessary action under Applicable Law to authorize the execution, delivery
and performance of this tender.
iii) The tender constitutes its legal, valid and binding obligation enforceable against it in
accordance with the terms hereof.
iv) It has good and valid rights for Site.
VOL -1 Technical Bid |
v) It has no knowledge of any violation or default with respect to any order, writ, injunction or
any decree of any court or any legally binding order of any Government Agency which may
result in any material adverse effect or impairment of the Contractor’s ability to perform its
obligations and duties under this Tender.
B. Time Control
38 Progress Schedule (Detailed Programmer of Implementation of Works)
(i) The Contractor shall furnish within 15 (Fifteen) days (Unless extended by Engineer-In
Charge) from LOA to the Engineer in Charge for approval a Progress Schedule showing date
of starting, general methods, arrangements, order, and timing for all the activities (i.e
procurement of materials, setting up of plant and materials, construction activities etc.) in the
Works including monthly progress schedule, anticipated completion date of each major item.
The Progress Schedule submitted by the Contractor shall be adhering to the milestone
specified below.
Sr.No. Milestone of Work Completion Period
(% of Work to be Completed)
1. 25% of work to be done in 25% of time
2. 50% of work to be done in 50% of time
3. 75% of work to be done in 75% of time
4. 100% of work to be done in 100% of time
(ii) In case it is found necessary, at any stage to alter the schedule, the contractor shall submit in
good, time a revised schedule incorporating necessary modification proposed by
Engineer/Employer and get the same approved from the Engineer in charge. No revised
schedule shall be operative without such acceptance in writing. The Engineer in charge is
further empowered to ask for more detailed schedule or schedules, any week by week, for any
item or items and the contractor shall supply the same as and when asked for.
(iii) The Engineer in charge shall have, at all times, the right, without in any way vitiating this
contract forming grounds for any claim, to alter the order of the work of any part thereof and the
contractor shall after receiving such direction, proceed in the order directed. The contractor
shall also revise the progress, schedules accordingly and submit four copies of the revised
schedule to the Engineer in charge within seven days of the said Engineer's direction to alter the
order of works.
(iv) The contractor shall furnish sufficient plant, equipment and labour and shall work such hours
and shifts as may be necessary to maintain the progress of the work as per approved progress
schedule. The working and shift hours shall comply with all the Government regulations in
force and shall be such, as may be approved by the Engineer in charge and the same not be
varied without the prior approval of Engineer in charge.
(v) The contractor shall from time to time, as may be required by the Engineer in charge, furnish
the Engineer in charge with a statement in writing of the arrangements he proposes to adopt
for the execution of this contract and the Engineer in charge may, if he considers necessary
at any time advise alternation in the same, which the contractor shall adopt on notice thereof.
(vi) The progress schedule(s) shall be in the form of progress chart, forms, statements and/or
reports as may be approved by the Engineer in charge.
(vii) The contractor shall submit four copies showing the progress of the work in the form of a
chart etc., at periodical intervals as may be specified by Engineer in charge.
VOL -1 Technical Bid |
38.2 Reports regarding labour:
i. A daily report in a form as may be prescribed of the strength of labour, both skilled and
unskilled, employed by him on the works. The contractor shall increase or decrease the
strength either skilled or unskilled if directed by the Engineer in charge. The submission
of such reports shall not, however relieve the contractor of his responsibilities and duties
regarding progress or any other obligations under the contractor.
ii. A classified weekly return in the prescribed form the number of persons employed on the
works during the preceding week.
iii. A weekly medical report in the prescribed form showing the health of the contractor’s
camp, the number of persons ill or incapacitated and the nature of their illness.
iv. A report of any accident which may have occurred to be sent within 24 hours of the
v. Such other reports as may be prescribed.
vi. The contractor shall be responsible to arrange for insurance of all labourers, skilled,
unskilled workers, supervisions employed by him as per labour regulation of the state.
38.3 The approval of the progress schedules by the Engineer in charge shall not relieve the contractor
of schedule required by the Engineer in charge and it shall not entitle the contractor to any
38.4 The Contractor is also required to submit updated programme every month (30 days from
previous submission of updated programme). An update of the Program shall be a program
showing the actual progress achieved on each activity and the effect of the progress achieved
on the timing of the remaining work including any changes to the sequence of the activities.
38.5 If the Contractor does not submit an updated Program within the period specified above in
clause 38.3, the Engineer may at its sole discretion withhold the amount of Rs 2Lakh from the
next payment certificate and continue to withhold this amount until the next payment after the
date on which the overdue Program has been submitted. The Engineer’s approval of the
Program shall not alter the Contractor’s obligations. The Contractor may revise the Program
and submit it to the Engineer again at any time.
38.6 Notice to be given before work is covered up.
The contractor shall give not less than five days’ notice in writing to the Engineer-in-charge or
his subordinate in charge of the work before covering up or otherwise placing beyond the
reach of measurementany work in order that the same may be measured and correct
dimensions there of taken before the same is so covered up or placed beyond the reach of
measurement and if any work shall be covered up or placed beyond the reach of
measurement without such notice having been given or consent obtained, the same shall be
uncovered at the contractor's expense and in default thereof, no payment or allowance shall be
made for such work or for the materials with which the same was executed.
39 Approval by the Engineer for Temporary Works
39.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary
Works to the Engineer for approval, which is expected to be implemented by Contractor. The
Temporary Works shall be as specified in either Technical Specifications section or as
specified by Engineer.
VOL -1 Technical Bid |
39.2 A copy of the Auto Cad Drawings shall be provided to the Engineer on a periodic basis for
approval and to record all details relating to progress and developments. On the basis of all
Drawings relating to the Works the Contractor shall prepare ‘As-Built’ drawings using the
computing software Auto Cad Version 14 or latest version to record the precise details of the
Works complete.
The final copy of the Auto-Cad Drawings shall be provided at the time of issue of the
Statement of Completion. The Contractor shall also arrange to take photographs and video
graphs as directed by the Engineer, depicting various details and stages of progress of works
and submit them in duplicate in proper albums for records.
In case the contractor fails to submit ‘As-Built’ drawings within 30 days of project
completion, amount as stated in the contract data shall be withheld from the dues payable to
the contractor.
39.3 The Contractor shall be responsible for design of Temporary Works.
39.4 The Engineer's approval shall not alter the Contractor's responsibility for design of the
Temporary Works.
39.5 The Contractor shall obtain approval of third parties to the design of the Temporary Works,
where required.
39.6 All Drawings prepared by the Contractor for the execution of the temporary or
permanent Works, are subject to prior approval by the Engineer before their use.
40 Extension of the Intended Completion Date
40.2 The Engineer shall extend the Intended Completion Date if a Compensation Event occurs or a
Variation is issued which makes it impossible for Completion to be achieved by the Intended
CompletionDate without the Contractor taking steps to accelerate the remaining Works, which
would cause the Contractor to incur the additional cost.
40.3 The Engineer shall decide whether and by how much time to extend the Intended Completion
Date within 15 days of the Contractor asking the Engineer for a decision upon the effect of a
Compensation Event or Variation and submitting full supporting information. If the
Contractor has failed to cooperate in dealing with a delay, the delay by this failure shall not be
considered in assessing the new Intended Completion Date.
40.4 If the Contractor shall desire an extension of the time for completion of the work on the
ground of his having been unavoidably hindered in its execution or any other ground, he shall
apply in writing to the Deputy Commissioner before the expiration of the period stipulated in
the tender or before the expiration of 30 days from the date on which he was hindered as
aforesaid or on which the cause for asking for extension occurred, whichever is earlier and the
Deputy Commissionermay, if in his opinion, believe that there are reasonable grounds for
granting an extension, grant such extension as he thinks necessary or proper. The decision of
the City Engineer/Deputy Commissioner/Divisional Head or Equivalent post in this matter
shall be final.
41 Delays Ordered by the Engineer
41.1 The Engineer may instruct the Contractor to delay the start or progress of any activity within
the Works. Delay/delays totalling more than 30 days will require prior written approval of the
Employer. In such case Intended Completion Date shall be extended for a period delay has
42 Management Meetings
VOL -1 Technical Bid |
42.1 The Engineer may require the Contractor to attend a management meeting. The business of a
management meeting shall be to review the progress and plans for the Works.
42.2 The contractor shall depute his representative not below the rank of Project Manager to attend
periodic review meetings notified by the Engineer. The Engineer shall record the business of
management meetings and provide copies of the record to those attending the meeting. The
responsibility of the parties for actions to be taken shall be decided by the Engineer either at
the management meeting or after the management meeting and stated in writing to all those
who attended the meeting.
43 Liquidated Damages
43.1 The Contractor shall pay liquidated damages to the Employer at the rate of 0.2% of Contract
Price for per day delay for the period that the Completion Date is later than the Intended
Completion Date (for the whole work or the milestone as specified in approved Progress
Schedule). Liquidated Damages at the same rate shall be withheld if the Contractor fails to
achieve the milestones specified in approved Progress Schedule. The total amount of
achieve the milestones specified in approved Progress Schedule. The total amount of
Liquidated Damages shall not exceed the 10% of the Contract Price quoted by the Contractor
and agreed for this Works. In case Liquidated Damages exceed the 10% of the Contract Price,
the Employer may consider Termination of Contract. The Employer may deduct Liquidated
Damages from payments due to the Contractor and/or from the Performance Security
.Payment of Liquidated Damages shall not affect Contractor's other liabilities.
43.2 If the Intended Completion Date is extended after Liquidated Damages have been paid, the
Engineer shall correct any overpayment of Liquidated Damages by the Contractor by
adjusting the nextpayment certificate.
C. Quality Control
44.1 The contractor shall be responsible for the true and proper setting out of the works and the
correctness of positions, levels, dimensions and alignments of all parts of the work and for the
provisions of all necessary instruments, appliance and labour in connection therewith.
44.2 The Contractor shall abide by the standards and provisions specified in Technical
Specifications, Drawings and BoQs.
44.3 If, at any time, during the progress of the work, any errors, appear or arise in the position,
levels, dimensions or alignments of any part of the work, the contractor, on being required to
rectify such errors by the Engineer in charge shall at his own expense do so to the satisfaction or
the Engineer in charge. If however, such error is based on incorrect data supplied in writing by
the Engineer in charge, the expenses of rectifying the same shall be borne by the Department. The
checking of and setting out of any line or level by the Engineer in charge or his representative
shall not in any way, relive the contractor of his responsibilities for the correctness of the error.
The contractor shall carefully protect and observe all benchmarks and other things used in the
44.4 The Owner/Employer / Engineer-in-charge shall have the power to order removal or
replacement ofall unauthorized/defective materials/works which in his opinion should be
removed or replaced All defects, be removed, replaced, or corrected as may be directed by the
Engineer in charge, where after the refund of Performance Security could be considered and in
that case he will take action under clause 13 of SECTION IV (B) - SPECIAL CONDITIONS OF
VOL -1 Technical Bid |
45 Works to be under direction of Employer
45.1 All works to be executed under the contract shall be executed under the direction and subject to
the approval in all respects of Engineer in charge of the Surat Municipal Corporation, who shall
be entitled to direct at what point and in what manner they are to be commenced and from time to
time carried on.
46 Quality Checks Register
46.1 A register in the prescribed form showing day to day receipt, consumption and balance of
inventory for the Works will be maintained by the Contractor, which shall invariably be signed
daily by the contractor or his authorized representative in token of its correctness. The Engineer
shall inspect the storage facility and in case of mismatch between actual balance and balance in
register, take appropriate action including payment of work done at reduced rate.
46.2 A register in the prescribed from showing day to day receipt, consumption and balance, of cement
on site of work by the Contractor and every entry thereof shall invariably be signed by the
Engineer or his authorized representative in token of its correctness.
47 Identifying Defects
47.1 The Engineer or authorised Supervision Engineer appointed by Employer shall check the
Contractor's work and notify the Contractor of any Defects that are found. Such checking shall not
affect the Contractor's responsibilities. The Engineer may instruct the Contractor to search for a
Defect and to uncover and test any work that the Engineer considers may have a Defect.
47.2 The Contractor is responsible to remedy any such defects identified by Engineer or its
representative. In such cases, Contractor shall take appropriate measures indicated by Engineer.
48.1 The Contractor shall be solely responsible for :
a) Carrying out the mandatory tests prescribed by the Technical Specifications / Specifications for
Building Works of Surat Municipal Corporation / Relevant Indian Roads Congress Specifications
/ Relevant Bureau of Indian Standards (BIS)/ Test mentioned in the Technical Specification and
any other relevant standards as specified by Engineer or Employer.
b) For the correctness of the test results, whether preformed in his laboratory or elsewhere.
48.2 If the Engineer instructs the Contractor to carry out a test not specified above, to check
whether any work has a Defect and the test shows that it does, the Contractor shall pay for the test
and any samples.
48.3 The cost of all such Tests shall be borne by the Contractor.
48.4 Approval to samples of construction materials.
48.5 Samples of each class of material shall be submitted by the contractor for the approval of the
Engineer in charge and after satisfying the test of samples, quality and approved by the engineer
in charge,these samples, shall be deposited at place, which the Engineer in charge may suggest
and the contractor shall be required to perform all the works of this contract in accordance with
the approved samples.
49 Correction of Defects or unsatisfactory andPoor quality works
49.1 The contractor shall be responsible to make good and remedy at his own expense any defect or
unsatisfactory works or not as per the Technical Specifications which may be noticed or observed
during the testing or inspection/supervision of Engineer.
VOL -1 Technical Bid |
49.2 The Engineer shall give the contractor a notice through phone call/ email/ fax writing about the
defects and the contractor shall make rectify the same within time period specified by it on receipt
of the notice. In the case of failure on the part of the contractor, the Engineer-incharge may rectify
or remove or re-execute the work at the risk & cost of the Contractor. The Engineer-in-charge
shall be entitled to appropriate the whole or any part of the amount of security deposit
(i.e.Performance Security) or from the outstanding bills towards the expenses, if any, incurred by
him in rectification, removal of defects.
49.3 The Engineer-in-charge may impose penalties/damages for non rectification of defects or
liabilities in specified time period. The amount of penalties/damages shall be commensurate with
types of breach,
D. Cost Control
50 Bills of Quantities
50.1 The Bill of Quantities shall contain items for the construction, supply, installation, testing and
commissioning work to be done by the Contractor.
50.2 The Bill of Quantities is used to calculate the Contract Price. The Contractor shall be paid for the
quantity of the work done at the rate in the Bill of Quantities for each completed item for the
Works carried out by the Contractor.
51 Variations in Quantities
51.1 Variation in ± 5% of the total Contract Price.
51.2 The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price
isexceeded by more than 5 percent except with the Prior approval of the Employer.
51.3 If requested by the Engineer where the quoted rate (s) of any item(s) is abnormally high, the
Contractor shall provide the Engineer with a detailed cost breakdown of such rate in the Bill of
52 Payment for Variation permitted
Variation permitted ± 5% of the total contract price. The payment for varied quantity of work shall
be made as per rates quoted by the Contractor in its prices Bid and as agreed between the
Employer and the Contractor prior to award and specified in LOA (Letter of Award) If there is
delay in the Employer and the contractor coming to an agreement on the rate of an extra item,
rates as proposed by the Employer shall be payable provisionally till such time as the rates are
finally determined or till a date mutually agreed.
52.1 If the Engineer decides that the urgency of varying the work prevent a quotation being given and
considers not delaying the work, no quotation shall be given and the Variation shall be treated as
a Compensation Event.
52.2 Extra Items:
Extra Items of Work shall not vitiate the Contract. The Contractor shall be bound to execute
extra items of Work as directed by the Engineer-in-Charge. The rates for extra items shall be
derived from the S.O.R. of R&B /S.M.C year 2024-25, TATA Trust Built Heritage
Conservation SOR (2021), RUIDP SOR-2023, INTACH S.O.R-2015-16, CPWD DSOR-2023
and quoted premium of tender. If the rate of extra item is not available in S.O.R. it shall be
derived onprevailing market rate.
53 Payment Certificate and Payment
The payment to the contractor will be made as per following procedures for the Works executed:
VOL -1 Technical Bid |
a) The contractor shall submit monthly bills on or before the date fixed by the Engineer-in-
Charges for all works executed in the previous month supported with detailed measurement
specifying the quantities of each item executed, rates quoted by the Contractor in its prices
Bid and as agreed betweenthe Employer and the Contractor prior to award and specified in
LOA (Letter of Award). This statement shall also state estimated value of the work
completed less the cumulative amount certified previously.
b) Items of the works for which no rate or price has been entered by the Contractor will not be
paid for by the Employer and shall be deemed covered by other rates and prices in the
c) The Contractor is required to provide the colour photographs displaying the date and time of
Completed Work along with the Bill as and when demanded by Engineer In Charge.
d) The Engineer shall check the Contractors’ monthly statement within 14 days and certify the
amount to be paid to the Contractor.
e) The value of work executed shall be determined by the Engineer and it shall also include the
valuation of Variations and Compensation Events.
f) The Engineer may exclude any item certified in a previous certificate or reduce the proportion
of any item previously certified in any certificate in the light of later information.
g) Engineer- In- Charge shall verify the quantities claim in the bill with the progress registered in
measurement books or through the actual measurement of Engineer. Joint measurement shall
also be taken continuously and need not be connected with billing stage. Measurement
recorded in the measurement books shall be signed by both contractor and Engineer‘s
representative. Payments shall be adjusted for deduction for Performance Securities,
damages/penalties and other recoveries in terms of contract and taxes, at source, as
applicable under the law.
h) Upon above process specified in above (a) to (g), the Engineer shall issue Payment
Certificate.The Employer shall pay the Contractor the amounts certified by the Engineer
within 14 days of the date of each certificate.
i) No Advance Payment shall be made. There shall not be Mobilization Advance.
j) Quantities shown in the tender are approximate and no claim shall be entertained for
quantities of work executed being either more or less than those entered in the tender of
k) No. compensation shall be allowed for any delay caused in the starting of the work on account
of any acquisition of land and in the case of clearance work, for any delay in accordance to
l) No compensation shall be allowed for any delay in execution of the work on account of water
standing in borrows pits or compartments. The rates are inclusive for hard or cracked soil,
excavation in mud, sub-soil water or water standing in borrow pits, and no claim for an extra
rate shall be entertained, unless otherwise expressly specified.
54.1The rates quoted by the Contractor shall be deemed to be inclusive of the all levies, duties,
royalties, cess, toll, taxes of Central and State Governments, local bodies and authorities. labour,
materials, shuttering, scaffoldings, plants, equipment’s, supervision, survey works, power, water,
testing charge and other taxes, duties etc, that may be levied and all liaison with concerned
authorities like traffic police, utility providers like DGVCL, GGCL, BSNL departments of
VOL -1 Technical Bid |
S.M.C. and Forest department of Govt. that the Contractor will have to pay for the performance of
54.2GST (Goods & Service Tax) has come in existence from 1st July, 2017 Contractor/Successful
Bidder is bound to pay any amount of GST prescribed by the Govt of India as per the Term of
Contract agreed upon during the course of execution of this contract.
54.3From last date of submission of tender and During the course of execution of contract if there is
any change in Rate of GST (Goods & Service tax) by the Government the same i.e. only the
difference shall be reimbursed / recovered separately by SMC subject to the submission of
original Receipt /Proof for the amount actually remitted by the Successful Tenderer / Contractor /
successful bidder certifying that the amount of GST paid to the Government and the same shall be
intimated / submitted / claimed within 30 (Thirty) days from the date of payment Remittance of
GST within stipulated period shall be the sole responsibility of the successful Bidder / contractor,
failing which, SMC may recover the amount due from any other payable dues with SMC and
decision of Municipal commissioner shall be final and binding on the contractor / successful
Bidder in this regard further, the non-payment of GST to the Government may lead to the
termination of contract and forfeiture of Security deposit/ Performance Guarantee Amount.
54.4 Except GST, if imposition of any other new Taxes / Duties / Levies / Cess or any other
incidentals etc. or any increase in he existing Taxes /Duties / Levies / Cess or any other
Incidentals etc.(Excluding GST) are imposed during the course of the contract, the same shall be
borne by the contractor / successful bidder only, in no case SMC shall be liable for the same and
obliged to reimbursed and no dispute regarding same shall be entertained by SMC. Bidder / firm
should have to produce attested copy of sale tax certificate with proof of residence.
54.5 The Construction labour welfare cess shall be deducted from R.A. and Final bill of the contractor
at the prevailing rate. The current rate of labourcess is 1% of the capital amount.
NOTE:- The Rates mentioned in BOQ are excluding GST. GST will be reimbursed separately (if
applicable as per the opinion of Account department of SMC / GST Consultant of SMC) as per
the prevailing GST Rates decided by the Government. The contractor is invariably bound to any
changes in GST Rates made during the course of the work. The payment (if applicable) for GST
will be only released only after the applicable Amount reflects on Government portal. Decision of
Account Department of SMC regarding applicable GST Rates will be final.
55.1 All payments will be made in Indian Rupees only.
55.2 Mode of payments
Payment to Contractors shall be made by cheques drawn on any Bank at Surat or through
e- Payment/RTGS/NEFT if possible.
Retention money shall be charged from the Contractor as per memorandum.
57 Performance Security
The Contractor hereby assures, entrusts and covenants unto the Employer that:
a) The Contractor shall provide the Performance Security of amount, form (Bank Guarantee or
Demand Draft) and by the date specified in the Clause 35 of ITB. The validity period of
Performance Security shall be as specified in Clause 35 of ITB.
VOL -1 Technical Bid |
b) Provided that if the contract is terminated for reasons other than that which can be attributable to
the Contractor, the Performance Security, shall, subject to the Employer’s right to receive
amounts, if any, due from the Contractor under this contract, be duly discharged and released to
the Contractor.
57.1 Encashment of Performance Guarantee
The Employer shall be entitled to encash the Performance Security fully or partially as the case
maybe, through a notice of 30 days (“Encashment Notice”) under the following circumstances:
57.1.1 Non-payment of any dues by the Contractor to the Employer as required to be paid as per
the terms of the Contract including Liquidated Damages as provided.
57.1.2 An Event of Default not being remedied by the Contractor in reasonable Period specified
by the Engineer during construction and Defect Liability Period despite repeated notice as
provided in this regards.
57.1.3 Non removal of deficiencies during the handover or Defect liability period as per the terms
of the Contract.
Provided the extend of such encashment shall be no greater in amount than that required to
remedy the circumstances warranting encashment stipulated above and provided further that in
case of any encashment of the Performance Security pursuant to the Encashment Notice, the
Employer may return the amount so encashed if the circumstances requiring the encashment have
been remedied to the full satisfaction of the Employer.
The provision under this Sub-Clause authorizing the Employer to encash the Performance
Security shall be exercisable in addition to and without prejudice to the Employer’s right to do so
under any other similar provision in this Contract permitting encashment.
57.2 Fresh Performance Security
In the event of the encashment of the Performance Security by the Employer pursuant to
Encashment Notice issued, the Contractor shall within 20 (twenty) days of the Encashment
Notice furnish fresh Performance Security to the Employer, failing which the Employer shall be
entitled to terminate the Contract by giving 30 days notice in accordance with the provisions
58 Price Variation
The Price Variation is not applicable for the subjected work.
59 Cost of Repairs
Loss or damage to the Works or Materials to be incorporated in the Works between the Start Date
and the end of the Defects Liability period shall be repaired /fixed by the Contractor at his cost if
the loss or damage arises from the Contractor's acts or omissions.
60 Events Leading to Extension of Intended Completion Date
Compensation is not applicable for any events leading to delays in any case.
61 Damage by storms, fire, rains or accidents:
The contractor shall take all precautions against damage by storms, fire or rains or from accidents
in protecting the works done and the materials, plants procured by him. No compensation will be
allowed to the contractor for damages to works or for his plant or materials lost or damaged by
storm, fire or rains or from any other causes. The contractor shall be liable to make good any
VOL -1 Technical Bid |
plant or materials of every description belonging to Owner/Employer’s loss or damages by storm,
fire, or rains or from any other causes while in charge of the Contractor.
62 Co-Operation with other construction Agencies:
The contractor shall in accordance with the requirement of the Engineer-in-charge accord all
reasonable facilities for any other contractors or piece workers engaged by the Owner/Employer
and their work in and of any other properly authorized authorities or statutory bodies who may be
employed on the execution on or near the site of any work not included in the contract or of any
contract which the Owner/Employer may enter into, in connection with ancillary works if any.
The Contractor shall conduct his work so as not to interfere with or hinder the progress or
completion of the work being performed by other contractor or piece workers or by the
Owner/Employer and shall as far as possible arrange his work and shall place and dispose of the
materials being used or removed so as not to interfere with the operations of the other contractors,
piece workers or the Owner/Employer. He shall co-ordinate his work with that of the other in an
acceptable manner and shall perform it in proper sequence to that of others.
Contractor shall have to carry out all types of lisioning with Forest Dept., DGVCL, Irrigation
dept, GGCL, BSNL etc. if requirement arises to get permission to work/ shifting etc. of
hindrances which effects the project or to carryout work & shifting of unwanted elements from
subjected work.
The contractor shall assume all liability, financial or otherwise, in connection with his contract
and shall protect and save harmless to Owner/Employer from any and all damages and claims that
may arise because of inconvenience, delay or loss, experienced by him because of the presence
and operations of other working or residing on or near the site if any. He shall assume all
responsibility for all work not completed or accepted because of the presence and operations of
other contractors or piece workers of the Owner/Employer.
63 PRICE ESCALATION
The price escalation is not applicable for above subjected work.
E. Finishing the Contract
64 Completion Certificate/ Final Certificate
64.1 Tests on Completion
a) At least 20 (Twenty) days prior to likely completion of Project/ Works or any parts thereof,
the Contractor shall notify the Employer/ Engineer to its intent subject to Project/ Works or any
parts thereof to Test. The date and time of each of the Tests shall be determined by the Engineer
in consultation with the Contractor to carry out Tests. The Contractor shall provide such
assistance as Engineer or authorized representative of the Employer may reasonably require for
conducting the Tests.
b) All Tests shall be conducted as per clause 48 of GCC. The Engineer shall observe, monitor
and reviewthe results of the Tests to determine compliance of the Project/Works with Technical
Specifications and Designs and if it is reasonably anticipated or determined by the Engineer
during the course of any Test that the performance of the Project or any part thereof does not
meet the Technical Specifications or Design Specification, it shall have the right to suspend or
delay such Test and require the Contractor to remedy and rectify the defects or deficiencies. Upon
completion of each Test, the Contractor shall provide to the Engineer copies of all Test data
including detailed Test results. For the avoidance of doubt, it is expressly agreed that Engineer
VOL -1 Technical Bid |
may require the Contractor to carry out additional Tests, in accordance with Good Industry
Practice, for determining the compliance of the Project with Technical Specifications and
c) The cost of Tests shall be borne by the Contractor.
64.2 Completion Certificate
a) Upon completion of Works and Engineer determining the Tests to be Successful and no defect to
befound during the joint inspection and thereafter acceptance report be signed jointly by the
contractor and the Engineer. This joint acceptance report shall be treated as “Completion
b) The Completion Certificate shall be issued / (i.e. Joint Inspection Report shall be signed) subject
to clearance of site specified in Clause 64.4 of this GCC, the defects any pointed out by the
Engineer shall be rectified by the contractor to the satisfaction of Engineer. The engineer may
perform required test on whole/part of construction site/items when he has doubt about the
quality of work and the cost of such test shall be borne by the contractor.
64.3 Rescheduling of Test
a) If the Engineer certifies to the Employer and Contractor that it is unable to issue Completion
Certificate because of events or circumstances on account of which the Tests could not be held or
suspended, the Contractor shall be entitled to re- schedule the Tests and held the same as soon as
reasonably practical. All the cost of Test shall be borne by the Contractor.
64.4 Clearance of Site
a) All unused materials and all plants, implements not removed by the contractor within two months
of the completion date of the works or extension granted if any, it shall become the property of
Owner/Employer and the contractor shall not entitled to any payment or compensation whatever
inrespect thereof, except for any sum actually realized by the sale thereof, less the
Owner/Employer’s other expenses incurred in transporting, storing in safe custody there of etc.
b) The Works shall be deemed to be considered complete only after the Contractor shall have
removed the debris, surplus material, machineries, scaffolding from the Project Site upon
completion of work. The Contractor is responsible for clearing the site from all debris and surplus
c) If the contractor shall fail to comply with requirements of this clause as to the removal of
scaffolding surplus materials and rubbish and cleaning off dirt on or before the date fixed for the
completion of the work, the Engineer-in-Charge may at the expense of the contractor remove
such scaffolding, surplus material and rubbish and dispose off as the thinks fit and clean off such
dirt as aforesaid and the contractor shall forth with pay the amount off all expenses so incurred
but shall have no claim in respect of any such scaffolding or surplus materials as aforesaid
except for any sum act by realized by the sale thereof.
64.5 Taking Over
a) The Employer shall take over the Site and the Works within 30 (Thirty) days of the Engineer's
issuing a certificate of Completion. The Contractor shall continue to remain responsible for its
maintenance during the Defect Liability Period.
VOL -1 Technical Bid |
65 Defect Liability Period
The Defect Liability Period is 01 Year from the date of issue of Completion Certificate. While
Defect Liability Period for water proofing work is 10years from the date of issue of Completion
Certificate for which contractor has to provide a judicial guarantee bond to authority.
a) The Contractor shall be responsible for all Defects/ deficiencies during the Defect Liability
Period cum Maintenance Period and remedy at his own expense any defect or deficiencies on
account of regularwear and tear, regular repair and maintenance requirements which may be
notice or observed by Engineer/Contractor. The Contractor shall also be responsible for
repair/maintenance required owing to accident and vandalism at a cost of Employer, which
may be noticed or observed by Engineer during the Defect Liability Period cum Maintenance
b) Employer shall issue Indent/Maintenance Notice during the Defect Liability Period cum
Maintenance Period specifying the need for repair & maintenance work (the “Indent”). Such
Indent shall be in writing and shall also specify the types of Works to be carried out and also
Intended Completion Date of all such Work. It will also specify work arises owing Vandalism
and Accident or regular defects in initial work, manufacturing defect or requirement of regular
maintenance. The decision of Engineer in charge shall be final. All such Work shall be
completed in an Intended Completion Date specified in the Indent after consulting the
contractor. However, the decision of Employer/Engineer in Charge shall be final in this
Any breach or delay in work shall be resulted in to damages. Damages shall be commensurate
with types of breach.
c) The Contractor is further also required to carry out weekly inspection of the site during the
Defect Liability cum Maintenance Period and send a weekly inspection report to Engineer.
The Contractor shall indicate status of elements, need of maintenance/repair/replacement and
name, designation and contact details of Supervisor deployed for daily Inspection. The format
of the Inspection Report shall be finalized in consultation with SMC Engineer. The engineer
shall also give the contractor a notice through phone calls/email/fax writing about the defect
and contractor shall make rectify the same if urgent/critical need of rectification arise.
d) The Contractor is required to carry out repair and maintenance work as per the Indent and in
conformity with Technical Specification in time period specified in clause 65 (c ) above.
e) The contractor shall be obliged to regular maintenance and repair, during this Defect liability
cum maintenance period, and keeping the Project/Works in proper condition through repair
f) or remedy of any defective, broken, or worn out parts or elements of the works, irrespective of
whether this requirement is owing to defect of initial works, wear and tear, vandalism, of any
other reason. The cost of repair and maintenance shall be borne by the Contractor except for
the vandalism and accidents. The decision of Deputy Commissioner shall be final in
establishing the fact that vandalism or accident has been incurred or not.
g) The Contractor shall ensure quality assurance of various components of the repair and
maintenance Works as per the Technical Specification and relevant standards of BIS.
h) Upon completion of Works specified in Indent/Maintenance Notice and Engineer determining
the Tests to be Successful and all the defects/unsatisfactory work/poor quality work has been
remedied pursuant to clause 47 and 48 of GCC, Engineer in charge shall proceed for payment for
repair and maintenance work arise owing to vandalism and accident.
VOL -1 Technical Bid |
i) The Contractor is required to maintain adequate inventory of material/consumables as prescribed
inrelevant Technical Specification and BoQs and as directed by the Deputy Commissioner and
complete the repair and maintenance Work in time period as per the clause above.
j) Upon completion of repair/ maintenance work, Contractor is required to clear the Project Site from
the debris and additional consumables immediately.
k) The Contractor is required to take appropriate safety measures and ensure the safety of its
employee and users of the Project Site during the Construction and Repair& Maintenance Period
as per the relevant clause of GCC and Technical Specification.
l) In the case of failure on the part of the contractor, the Engineer-in-charge may rectify or remove
or re-execute the work at the risk & cost of the Contractor. The Engineer-in-charge shall be
entitled to appropriate the whole or any part of the amount of security deposit (i.e. Performance
Security) or from the outstanding bills towards the expenses, if any, incurred by him in
rectification, removal of defects to the satisfaction of Engineer. The Engineer-incharge may
impose penalties for non-rectification of defects or liabilities in specified time period. The
amount of penalties shall be commensurate with types of breach.
m) Even after repeatedly (maximum three times) directed by Engineer if Contractor shall not take
any action towards remedy or fully rectify the defects without any valid reason, In such events,
Deputy Commissioner shall terminate the contract and forfeit Performance Guarantee (i.e.
Security Deposit).
66 Remedy of Defects or Poor Quality Work During the Defect Liability Period
The Contractor shall be responsible for maintenance of the Works/Project till the Defect Liability
If, at any time before the expiry of Defect Liability period, It shall appear to the Engineer-
inchargeor his sub-ordinate in charge of the work that/ any work has been executed unsound,
imperfect or unskilled workmanship or with materials of inferior quality or that any materials or
articles provided by him for the execution of the work are unsound, or of a quality inferior to that
contracted for or are otherwise not in accordance with the contract, it shall be lawful for the
Engineer-in-charge to intimate this fact in writing to the contractor and then notwithstanding the
fact that the work; materials or articles complained of may have been passed, certificate and paid
for the contractor shall be bound forthwith to rectify, or remove and reconstruct the work so
specified in whole or in part as the case may require, or if so required, shall remove the materials
or articles so specified in whole or in part and provide other proper and suitable materials or
articles at his own charge and cost, and in the event of his failing to do so within a period to be
specified by the Engineer-in-charge in the written intimation aforesaid, the Engineer- in- charge
may take following actions.
a) The Engineer-in-charge may rectify or remove, and re-execute the work or remove and replace
the materials complained of as the case may be at the risk and expense in all respects of the
contractor and in such events the contractor shall be liable to pay compensation in addition to
the cost of rectification at the rate of one percent on the amount of the estimate of the
rectification for every day not exceeding ten days.
b) To employ labour paid by the Employer and to supply material and carry out the work or any part
of the works, debiting the Contractor with the cost of the labour and the price of the materials (as
to the correctness of which cost and price the certificate of the Deputy Commissioner shall be
final and conclusive against the Contractor) and crediting him with the value of the work done, in
all respects in the same manner and at the same rates as if it had been carried out by the
VOL -1 Technical Bid |
Contractor under the terms of this contract, and in that case the certificate of the Deputy
Commissioner as to the value of the work done shall be final and conclusive against the
c) Employ another Contractor and any expenses may be incurred shall be borne and paid by the
original Contractor and shall be deducted from any money due to him by Employer under the
contract or otherwise or from his security deposit or the part thereof.
In the event of any of above course specified in clause above being adopted by the Deputy
Commissioner the Contractor shall have no claim to compensation for any loss sustained by him
by reason of his having purchased or procured any materials or entered into any engagements or
any advance on account of or with a view to the execution of the work or the performance of the
contract. And in case the contract shall be rescinded under the provision aforesaid, the contractor
shall not be entitled recover or be paid any sum for any work therefore actually performed by him
under this contract unless and until the Deputy Commissioner shall have certified in writing the
performance of such work and the amount payable in respect thereof and he shall only be entitled
to be paid the amount so certified.
67 Certificate of Performance
a) The Contractor shall request the Engineer within 28 (Twenty Eight) days after the completion of
Defect Liability Period, to issue a Certificate of Performance (the “Certificate of Performance”)
of completion of all maintenance obligation during the Defect Liability Period in accordance with
the terms of Contract. The Engineer shall issue Certificate of satisfactory Performance upon
deciding that Maintenance Works were completed and effects, if any, brought to the Notice of the
Contractor under the Defect Liability Period have been Remedied.
68 Maintenance during the Defect Liability Period
a) During the Defect Liability Period, the Contractor shall maintain the Project/ Works in
accordance with the Best Industry Practice, Technical Specifications and terms specified in the
b) The Contractor is obliged to undertake routine maintenance including prompt repairs of the
Works (i.e. structures and any other components).
c) The Contractor shall comply with all Safety requirements specified in Technical Specifications,
relevant BIS Codes.
d) The Contractor shall comply with the Maintenance Standards specified in the Maintenance
Manual and Monthly maintenance programmed during the Defect Liability Period.
e) The Contractor shall carry out the maintenance of Works in a manner so as to minimum
disruption of the Traffic.
f) The Contractor shall carry out joint maintenance inspection every month during the Defect
Liability Period and undertake the maintenance work accordingly.
g) The Maintenance work shall be as per the satisfaction of Engineer.
h) In case of any Deficiencies, Defect found during the Defect Liability Period, the Contractor is
obliged to take prompt actions and remedied the Defect or Deficiencies to the Satisfaction of
69 Maintenance Manual and Drawings
a) The Contractor shall in consultation with Engineer shall prepare, Maintenance Manual before
completion of Works and incorporate any suggestions, modification received from the Engineer.
VOL -1 Technical Bid |
The Maintenance Manual shall be in conformity of Technical Specifications, relevant BIS codes
guidelines about the Maintenance, and Good Industry Practice.
b) The Maintenance Manual shall comprise the monthly maintenance programme detailing the plans
for monthly maintenance works to be undertaken.
c) Upon completion of Works, the Contractor shall submit the "as built" Drawings and any other
information or manuals requested by Engineer on or before the period specified in such request.
d) If the Contractor does not submit the Drawings and/or manuals by the dates stated in request, or
they do not receive the Engineer's approval, the Engineer shall withhold the outstanding amount
from payments due to the Contractor.
e) Contractor shall provide bills of material used for repairing/ maintenance purpose.
70 Final Account
a) The Contractor shall supply the Engineer with a detailed account of the total amount that the
a) The Contractor shall supply the Engineer with a detailed account of the total amount that the
Contractor considers payable under the Contract before the end of the Defects Liability Period.
The Engineer shall issue Defect Liability Certificate after verification of rectification of any
defects found subsequent to at the Completion Date. The Engineer shall then certify any final
payment that is due to the Contractor within 60 days of receiving the Contractor‘s account if it is
correct and complete. If it is not, the Engineer shall issue within 15 days a schedule that states the
scope of the corrections, additions or alterations that are necessary for the correction. The
Contractor shall resubmit the bill, with correction within 30 days of the return by the Engineer. If
the Final Account is still unsatisfactory after it has been resubmitted the Enfinalgineer shall
decide on the amount payable to the Contractor and issue a payment certificate, within 60 days of
receiving the Contractor‘s revised account.
71 Termination in Event of Default of Contractor
Occurrence of following Events shall be considered as the Default by Contractor (the
“Contractor’s Event of Default”):
a) Repeatedly fails to carry out any obligation under the contract event after repeatedly directed
by Engineer/Employer in a reasonable time period.
b) Fails to carry out any obligation under the contract which has Material Adverse Effect for this
c) Without reasonable excuse fails -
a To commence the works on Site within the period stated in the Notice to Proceed Work after
signing the agreement or
b To proceed with the works, or any section thereof as indicated by the Employer, within
daysafter received notice.
d) Has failed to comply with a notice issued or an instruction issued within 28 days after having
e) Abandons the works or otherwise plainly demonstrates the intention not to continue
performance of his obligation under the contract.
f) The Contractor does not maintain a Performance Security, which is required as per terms of
g) Subcontracting is not permissible under this contract.
VOL -1 Technical Bid |
h) Has failed to furnish the required Performance Security or extension of its validity
period thereof as per the terms of this contract.
i) Becomes bankrupt or insolvent, goes into liquidation, has a receiving or administration order
made against him, compounds with his creditors, or carries on business under receiver, trustee
or manager for the benefit of his creditors, or if any act is done or event occurs which (under
applicable Laws) has a similar effect to any of these acts or events.
j) Change in Contractor’s Ownership during this Contract with prior consent of Employer.
k) The Contractor fails to provide insurance cover as required as per terms of this Contract.
l) The amount of Liquidated Damages exceeds the 10% of the Contract Price.
m) Contractor carries out any other activities other than the execution of Works on the Project
n) Any time it is found that the Contractor has carried out Fraudulent Practice or Malpractice in
execution of Works.
o) The Contractor fails to make any payments/damages/penalties due to Employer within period
specified in the Contract without any valid reason.
p) The Contractor repudiates this Agreement or otherwise evidences an intention not to be bound
by this Agreement.
q) The Contractor fails to accompany with the applicable laws, rules, regulation.
r) Any representation made or warranties given by the Contractor under this Agreement is
found to be false or misleading.
s) The Contractor repudiates this Contract.
t) If the Contractor, in the judgment of the Employer has engaged in corrupt or fraudulent
practices in competing for or in the executing the Contract.
(i) Corrupt practice: means the offering, giving, receiving or soliciting of anything of value to
influence the action of a public official or Engineer in the procurement process or in contract
(ii) Fraudulent practice means a misrepresentation of facts in order to influence a procurement
processor the execution of a contract to the detriment of the Employer, and includes collusive
On occurrence of any of above events or circumstances, the Employer shall provide notice to
Contractor to remedy the breach/ Default in reasonable time period specified in the notice. If the
Contractor shall not cure or remedy the default/ breach then Employer may at its sole discretion,
upon giving 15 days notice to the contractor, terminate the contract and expel the contractor from
The Employer’s election to terminate the contract shall not prejudice any other rights of the
Employer, under the contract or otherwise. Employer may at its sole discretion forfeit the
Performance Security and may recover from the amount due to the contractor on occurrence of
any of the Contractor’s Event of Default.
If the Contract is terminated the Contractor shall stop work immediately, make the Site safe and
secure and leave the Site as soon as reasonably possible.
VOL -1 Technical Bid |
After termination, the Employer may complete the Works and/or arrange for any other entities to
doso.The Employer and these entities may then use any goods, contractor’s documents and
other design documents made by or on behalf of the contractor.
72 Termination Payment for Event of Default
a) If the Contract is terminated because of an Event of Default of Contractor then there shall not
be any Termination Payment to be paid to the Contractor.
b) If the Contract is terminated at the Employer's Event of Default or convenience then the
Engineer shall issue a certificate for the value of the work done, the reasonable cost of
removal of Equipment and the Contractor's costs of protecting and securing the Works and
less advance payments received up to the date of the certificate, less other recoveries due in
terms of the Contract, and less taxes due to be deducted at source as per applicable law. The
amount derived shall be payable to Contractor.
a) All Materials on the Site, Plant, Equipment, Temporary Works, and Works shall be deemed
to be the property of the Employer for use for completing balance construction work if the
Contract is terminated because of the Contractor's default, till the Works is completed after
which it will be transferred to the Contractor and credit, if any, given for its use.
b) Treasure Trove :-
In the event of the discovery by the Contractor or his employees during the progress of the
works of any treasure, coins, antiquities, fossils, minerals or other articles or things of
value or interest, whether geological, archaeological or any other such treasure or other
things also like a metal, rubble, etc. shall be deemed to be the absolute property of
Owner/Employer.
The contractor shall take all reasonable precautions to prevent his workmen or any other
persons from removing such things as above and shall immediately upon discovery thereof
and before removal, acquaint the Engineer-in-charge of such discovery and carry out his
orders as to the disposal of the same which will be at the contractor’s expense.
a) The Contractor shall on behalf of the Owner/Employer shall indemnify their officers,
employees etc. against all actions, suits, claims and demands of any character brought, in respect
of any matteror thing done or omitted to be done by the contractor in the execution of or in
connection with the works of this contract and against any loss or damage to Owner/Employer his
workman/labourers in consequence, for any action or suit being brought against the contractor for
anything done or omitted to be done in the execution of the works of the contract or
compensation to be paid by contractor to his workman/labourers in consequence of accidents
causing damage or loss of life of his workman/labourers etc. All such payments made by the
Owner/Employer shall be recovered from the contractor from his dues outstanding, or remains to
be paid or that which becomes payable.
b) The Owner/Employer shall not be liable to the contractor for damages or losses of delays
resulting, from work by third parties or by injunction or other restraining orders obtained by
75 Force Majeure
VOL -1 Technical Bid |
1. Neither party shall be to liable to the other for any loss or damage occasioned by or arising out
of Acts of God, and in particular, unprecedented Floods, volcanic eruption, earth quake or
other convulsion of nature, and other acts such as but not restricted to general strike, invasion,
the act of foreign countries, hostilities or war like operations before or after declaration of
war, rebellion,military or unsurped power, strikes or boycotts (other than those involving the
Contractor or their respective employees/representatives or attributable to any act or omission
of any of them), An act of war (whether declared or undeclared), invasion, armed conflict or
act of foreign enemy, blockade, embargo, riot, insurrection, terrorist or military action, civil
commotion, or politicallymotivated sabotage, Expropriation or compulsory acquisition by any
Government Agency of any Project Assets or rights of the Contractor, which prevent
performance of the contract and which could not have been for seen or avoided by a
contractor or Employer (the “Force Majeure”).
2. On occurrence of Force Majeure Event, Parties are excused from the Performance of their
3. In the Event of occurrence of Force Majeure Event both the party shall try to continue to
perform their obligation stipulated in this contract. If Force Majeure Event subsists for
days then either party may by notice to other party terminate the Contract.
4. In the event that Parties are unable to agree in good faith about the occurrence of or existence
of a Force Majeure event, such dispute shall be finally settled in accordance with the Dispute
Resolution Procedure; provided that the burden of the proof as to the occurrence of Force
Majeure Event shall be upon the Party claiming relief and/or excuse on account of such Force
5. Termination of the Contract (a) shall not relieve the Contractor or Employer of any
obligations hereunder which expressly or by implication survives Termination hereof, and (b)
except as otherwise provided in any provision of the Tender expressly limiting the liability of
either Party, shall not relieve either Party of any obligations or liabilities for loss or damage to
the other Party arising out of or caused by acts or omissions of such Party prior to the
effectiveness of such Termination or arising out of such Termination.
a)Termination of the Contract (a) shall not relieve the Contractor or Employer of any obligations
hereunder which expressly or by implication survives Termination hereof, and (b) except as
otherwise provided in any provision of the Tender expressly limiting the liability of either
Party, shall not relieve either Party of any obligations or liabilities for loss or damage to the
other Party arising out of or caused by acts or omissions of such Party prior to the effectiveness
of such Termination or arising out of such Termination.
F. SCHEDULE – A
77 Cement, steel and other materials
The Surat Municipal Corporation shall not issue cement, reinforcement steel or any of the
material.Contractor shall make his own arrangement to procure all materials, cement,
reinforcement steel, asphalt etc.
The cement to be used shall be 53 grade OPC and out of following brands only:
4. Sanghi Cement
VOL -1 Technical Bid |
Thereinforcement steel i.e. HYSD bars shall be only following makes and shall be Thermo-
Mechanically Treated (TMT).FE-500
2. Rastriya Ispat Nigam Ltd.(RINL)
4. Electrotherm (India) ltd.
6. JSW steel Ltd
8. Mono Steel India Ltd.
9.Metaroll Ispat Pvt. Ltd.Jalna
10. Welspun Shield TMT
The test certificates regarding its property including indication of its Thermo-Mechanically
treated must accompany every lot and shall be submitted to Surat Municipal Corporation before
utilizing the same. Unless and until such certificate is submitted, the steel procure at site will not
be allowed to be used.The cement and steel shall not be issued by Surat Municipal Corporation.
a) No penalty, if actual total consumption matches with standard theoretical total consumption.
b) Penalty at Rs. 5640/- per M.T. (Without GST) for variation up to - (Minus) 5% in actual total
consumption against standard theoretical total consumption shall be recovered.
c) Penalty at Rs. 11280/- per M.T. (Without GST) for variation beyond- (Minus) 5% in actual
total Consumption against standard theoretical total consumption shall be recovered.
REINFORCEMENT STEEL:
a) No penalty if actual total consumption matches with standard theoretical total Consumption.
b) Penalty at Rs.54,500/- per M.T. (Without GST) for TMT steel and Rs.57,000/- pr M.T.
(Without GST) for TMT CRS steel for variation up to - (Minus) 7.5% in actual total
consumption against standard theoretical total consumption shall be recovered.
c) Penalty Rs.1,09,000/- per M.T. (Without GST) for for TMT steel and Rs.1,14,000/- per M.T
(Without GST) for TMT CRS steel for variation beyond - (Minus) 7.5% i.e. actual total
consumption theoretical total consumption shall be recovered.
d) The payment for reinforcement bar will be made on theoretical weight basis but not exceeding
actual procurement at site. The weight shall be computed on the basis of the length of the steel
used in the work multiplied by the standard unit weight of MS/HYSD (TMT) bar as
mentioned in IS Code No. 1786/85.
e) No separate payment shall be made for any kind of wastage/excess consumption in the
f) Ultimately the liability for assurance of the good quality work as per tender provision lies with
the contractor.
VOL -1 Technical Bid |
Testing of Cement, Steel and other materials:
It should be specifically noted that the Cement, Steel, bitumen etc. brought by the contractor at site
of work shall be used only after the same is tested at the approved laboratory as per the direction of
Engineer-in-charge. The testing of all the materials shall be carried out as per relevant BIS codes.
All the charge for the transport and testing of the samples etc. shall have to be borne by the
contractor. The frequency of testing such material shall be in accordance to the relevant Indian
Standards as directed by Engineer-in charge. The contractor shall have to make his own
arrangement for transportation of inspecting authorities/ agencies/ at his own cost.
Storage of Cement and steel:
For storage of cement and steel, the contractor shall have to make his own arrangements as per the
prevalent practices in the exercising care for protection of all kinds as prescribed in relevant Indian
Standards BIS codes of practice. Such storage facility shall be located at sites approved by the
Engineer in charge and shall be not less than 15 days for the work.
The contractor shall also take necessary measures forcemeat minimizing deterioration and loss of
The steel shall be handled with reasonable care while transporting and storing to prevent the bars
getting kinked, twisted or bent. If kept in open, the bars shall be protected from corrosion with
tarpaulin covering or as may be directed. All possible care shall be taken to prevent any effect
under rusting and to preserve fitness and quality of work.
78. RESPONSIBILITY OF CONTRACTOR UNDER CONSTRUCTION AND DEMOLITION
WASTE (C & D WASTE) RULES
Contractor shall remove All Construction and Demolition Waste (C & D Waste) and clean the
area every day, or depending upon (1) The type & schedule of the work, (2) The quantity and
type of waste generated, appropriate storage and collection facility shall be developed at site.
Reasonable time frame shall be worked out in consultation with engineer in charge of the project,
for storage & usage of C & D Waste.
If it's found that contractor is irregular and showing negligence to management of C & D Waste,
than If deem fit, Engineer in charge would arrange to dispose the said C & D Waste through an
Authorized C & D Waste Contractor/agency of Surat Municipal Corporation and All the
expenditure made towards disposal of this C & D Waste shall be recovered from the contractor as
per the prevailing charges.
Contractor shall have to bear the expenses towards management of C & D Waste as per the
prevailing norms, no extra payment shall be entertained for the same.
Contractor shall keep record of the generation and disposal of Construction and Demolition
waste (C & D Waste) and proof of its disposal as per the provision of C & D Waste rules and he
has to submit along with running bills. If contractor fails to upkeep and maintain records of C &
D Waste generation- Disposal records etc. than it shall be calculated as per the provision of the
Standing Committee Resolution no. 1621/2016, Dt:01/10/2016 and charges shall be recovered
from due of contractor with Surat Municipal Corporation.
Contractor shall also ensure use of recycled products made from SMC authorized C & D Waste
agency as far as possible to promote the C & D Waste management project.
VOL -1 Technical Bid |
79. WORK IN MONSOON: When the Work continues in monsoon, the Contractor shall maintain
minimum labour force required, for the Work and plan and execute the construction and erection
Work according to the prescribed schedule. No extra rate shall be considered for such Work in
monsoon. During monsoon and entire constructing period the Contractor shall keep the site free
from water at his own cost.
Date & Signature of the Contractor Executive Engineer
Surat Municipal Corporation
VOL -1 Technical Bid |
SECTION IV (B) - SPECIAL CONDITIONS OF CONTRACT
Table of Contents
Special Conditions of Contract
1. Labour 2. Compliance with Labour Regulations
3. Drawings and Photographs of the Works 4. The Apprenticeship Act,
5. Brands of Cement and Steel to be used for all Works 6. Security deposit
7. Action when whole of Performance Security is 8.Contract may be rescinded and performance security
Forfeited forfeited for subletting it without approval:
10. Contractor remains liable to pay compensation of action
9. Compensation for delay at 0.2% per day for not
not taken under
achieving the specified milestones
(Section -IV-B 7)
11. No compensation for alteration in or rectification of 12. Time limit for unforeseen claims
works to be carried out
11.1. No claims to compensation on account of
loss due to delay in supply of materials by the
11.2. Claims for quantities of work entered in
13. Action and compensation payable in case of 14. Sum payable by way of compensation to be
bad work considered as reasonable compensation without
reference to actual loss
15. Work to be open for inspection/Contractor’s 16. Maintenance survey and measuring instrument
responsible agent to remain present:
17. Protection of work against weather 18. Approval to samples of construction materials
19. Sheds / temporary buildings for goods etc 20. Setting out lines levels by contractor
21. Executing of other works, by 22. Contractor to supply plant, scaffolding etc. and is
Owners/Employer’s agents liable for damages arising from provision of tight
23. No Refund to quarry fees & Royalties 24. Time for bill & Minimum Amount of Bill to be
submitted Contractor shall have to submit duly
checked and approved bill by competent
representative of subjected works PMC once in
each month on or before date fixed by the engineer
in charge for all works executed in the previous
25. Bills to be on printed forms. 26. Payment of intermediate certificate to be regarded
27. Payment of reduced rate on account of items 28. Stores supplied by Municipal Corporation.
of work not accepted as complied to be the
discretion of engineer in charge
29. Lump sum in estimates 30. Power to take possession of or require removal of
sell contractor’s plant
31. Work on Sunday and holidays 32. Changes in the constitution of firm to be notified
VOL -1 Technical Bid |
33. The employment of donkeys and or other 34. Drinking water facilities for labourers& workers
35. Special causes regarding refund/recovery 36. Recovery of charges from original contractor
of additional performance security. for re advertising.
37. Safety requirement 38. Submission of as built drawing
39Handling over and Taking over charge
VOL -1 Technical Bid |
B. SPECIAL CONDITIONS OF CONTRACT
All additional conditions given in the clauses appearing herein after shall be deemed to form
part ofthe contract and shall be deemed as supplementary to the same. These additional
conditions shall be binding on the contractor in the same manner as other terms and conditions in
this percentage rate contract.
1.1 The Contractor shall, unless otherwise provided in the Contract, make his own
arrangements forthe engagement of all staff and labour, local or other, and for their payment,
housing, feeding and transport.
1.2 The Contractor shall, if required by the Engineer, deliver to the Engineer a return in detail,
in such form and at such intervals as the Engineer may prescribe, showing the staff and the
numbers of the several classes of labour from time to time employed by the Contractor on the
Site and such other information as the Engineer may require.
2 Compliance WithLabour Regulation
2.1 During continuance of the Contract, the Contractor and his sub Contractors shall abide at all
times by all existing labour enactments and rules made there under, regulations, notifications
and bye laws of the State or Central Government or local authority and any other labour law
(including rules), regulations, bye laws that may be passed or notifications that may be issued
under any labour law in future either by the State or the Central Government or the local
authority. Salient features of some of the major labour laws that are applicable to construction
industry are given in Appendix to Special Conditions of Contract. The Contractor shall keep
the Employer indemnified in case any action is taken against the Employer by the any
Government Authority/ Agency on account of contravention of any of the provisions of any
Act or rules made there under, regulations or notifications including amendments. If the
Employer is caused to pay or reimburse, such amounts as may be necessary to cause or
observe, or for non-observance of the provisions stipulated in the notifications/ bye laws/
Acts/ Rules/ regulations including amendments, if any, on the part of the Contractor, the
Engineer/ Employer shall have the right to deduct any money due to the Contractor including
his amount of Performance Security.
2.2 The Employer/Engineer shall also have right to recover from the Contractor any sum
required or estimated to be required for making good the loss or damage suffered by the
Employer. The employees of the Contractor in no case shall be treated as the employees of the
Employer at any point of time.
3 Drawings and Photographs of the Works
3.1 The Contractor shall do photography/video photography of the site firstly before the start of
the work, secondly mid-way in the execution of different stages of work and lastly after the
completion of the work. No separate payment will be made to the Contractor for this. The
photography shall be done as instructed by engineer-in-charge.
3.2 Contractor shall provide 3 sets of photographs (hardcopy + soft copy in DVD) as directed by
Engineer-in-charge. Photograph set shall be provided at the time of presenting each and every
3.3 The Contractor shall not disclose details of Drawings furnished to him and works on which
he is engaged without the prior approval of the Engineer in writing. No photographs/
VOL -1 Technical Bid |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
VOL- 1 TECHNICAL BID.pdf
VOL- 2 merged.pdf
VOL- 3 Item Wise Detailed Specification.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .