| 1 | 1₹4.1 LAccepted-AOC | 1 | Accepted-AOC lowest quoted bidder | |
| 2 | 2₹4.4 L+₹28,045.54 (6.86%)Rejected-AOC | 2 | Rejected-AOC second lowset bidder |
Tender Value
₹3.7 L
EMD Value
₹9,322
Closing Date
3 Dec 2024, 5:00 pmClosed
Assisstant Executive Engineer
Buildings Subdivision Munnar
this estimate includesscrapping,Repairs to plaster,Painting with synthetic enamel paint,Acryllic Smooth exterior paint,Demolishing cement concrete, PCC ,vitrified floor tiles ,Steel work for purlin/single section,galvanised iron profile sheets
2024_PWD_707550_1
PWD/BLDG/TR/10912/2023_5_1_1/1
Open Tender
Civil Works - Buildings
Item Rate
180 days
Adimaly
Please refer Tender documents.
12 documents required · 12 mandatory
₹825
₹9,322
3 Feb 2025
20 Nov 2024
5 Dec 2024
20 Nov 2024
3 Dec 2024
20 Nov 2024
Amount
Appendix -A Maintenance work
14.43:Removing white or colour wash by scrapping and sand papering and preparing the surface smooth including necessary repairs to scratches etc. complete.
14.1.1:Repairs to plaster of thickness 12 mm to 20 mm in patches of area 2.5 sq meters and under, including cutting the patch in proper shape, raking out joints and preparing and plastering the surface of the walls complete, including disposal of rubbish to the dumping ground within 50 meters lead:With cement mortar 1:4 ( 1 cement : fine sand)
14.54.1:Painting with synthetic enamel paint of approved brand and manufacture of required colour to an give even shade:One or more coats on old work
14.66.1:Finish walls with Acryllic Smooth exterior paint of required shade:Old work ( Two or more coats applied @ 1.67 ltr/10 sqm) on existing cement paint surface
15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
11.41.2:Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS : 15622, of approved make, in all colours and shades, laid on 20 mm thick cement mortar 1:4(1 cement : 4 coarse sand), including grouting the joints with white cement and matching pigments etc., complete.Size of Tile 600 x 600 mm.
50.10.2:Steel work for purlin/single section with G I pipes including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete
12.50:Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+0.05%), total coated thickness with zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 metre or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling/self tapping screws of size (5.5x55mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required.
12.51.1:Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm (+ 0.05%) total coated thickness, zinc coating 120 grams per sqm as per IS:mm(+0.05%) total coated thickness, Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/self tapping screws complete:Ridges plain (500-600 mm)
5.22A.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
OD150551/2024-2025:Patch Plastering for Roof After removing all loose materials by using hammer , scrapper , and remove rust from the exposed reinforcement that should clean by using rust remover then clean the reinforcement with emery paper and wash thoroughly after that zinc cromate primer should apply to the dry enforcement . after drying of the primer coat a paste of cement and pedilite LW should be applyed with brush . then apply second coat of cement mortar 1:3 with pedilite LW and URP liquid folatted find traweled in as per the direction of site in charger
OD55187/2023-2024:Engaging coolie for cleaning roof top ,sunshade etc and premises ofbuildings
JOHNY YOHANNAN (BID ID -1998775)
Bidder Name
JOHNY YOHANNAN
Johny K P
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1108348.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .