Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.9 LAccepted-AOC | L1 | Accepted-AOC AEE/PyIP/23/2020-21 dt.30.12.2020 | |
| 2 | L2₹4.9 L+₹2,486.24 (0.51%)Rejected-Finance | L2 | Rejected-Finance L2 |
Tender Value
₹4.9 L
EMD Value
₹12,300
Closing Date
28 Oct 2020, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Assistant Executive Engineer
Assistant Executive Engineer PyIP Sub Division Mattannur at Veliyambra
PyIP_SDRF_Rectfication of Mahe branch canal between ch 0_665km and ch 1_565km Desilting 5 schemes
2020_Irrig_392839_1
ET- 01/AEE/PYIP/2020-21
Open Tender
Civil Works - Canal
Item Rate
90 days
Keerachi
Please refer Tender documents.
3 documents required · 3 mandatory
₹1,100
Yes
online
₹12,300
Yes
4 Jan 2021
19 Oct 2020
5 Nov 2020
19 Oct 2020
28 Oct 2020
19 Oct 2020
60 days
Amount
Scheme 1-PyIP-SDRF-Rectification of Mahe branch canal between ch:0/665km and ch:1/565km-Desilting-Reach 1
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.26.1 : Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil
Scheme 2 -PyIP-SDRF-Rectification of Mahe branch canal between ch:0/665km and ch:1/565km-Desilting-Reach 2
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.26.1 : Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil
Scheme 3 -PyIP-SDRF-Rectification of Mahe branch canal between ch:0/665km and ch:1/565km-Desilting-Reach 3
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.26.1 : Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil
scheme 4 -PyIP-SDRF-Rectification of Mahe branch canal between ch:0/665km and ch:1/565km-Desilting-Reach 4
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.26.1 : Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil
Scheme 5-PyIP-SDRF-Rectification of Mahe branch canal between ch:0/665km and ch:1/565km -Desilting-Reach 5
2.33.4 : Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Above 240 cm girth
2.33.3 : Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyond 120 cm girth up to and including 240 cm girth
2.33.2 : Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 60 cm girth up to and including 120 cm girth
od21227/2020_2021/P1 : conveyiing timber logs (cut and removed) from the site to the Kuthuparamba office premises including loading unloading and stacking varoius girth logs separately atKuthuparamba office premices etc. complete
SIBIN.T.K.
Bidder Name
SIBIN.T.K.
SREEJITH TK
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_558955.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .