| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹32.4 LAccepted-AOC | L1 | Accepted-AOC LOWEST REASONABLE BID | |
| 2 | L2₹44.9 L+₹5.0 L (12.6%)Rejected-Finance H 10 KARNI NAGAR NEW NAGAUR ROAD NEAR MANDORE POLICE STATION 8TH MILL MANDORE JODHPUR 342304 | JODHPUR | JODHPUR | RAJASTHAN | 342304 | L2 | Rejected-Finance NOT LOWEST | |
| 3 | Rejected-Technical | - | Rejected-Technical Not Eligible as No remarks in WLR of QE Mar 2023 of HQ CESWC. |
Tender Value
₹60 L
EMD Value
₹1.1 L
Closing Date
15 Sept 2023, 6:00 pmClosed
CWE ARMY JODHPUR
CWE ARMY MULTAN LINE ARMY AREA JODHPUR -342010
REPAIR / MAINT OF DISTRIBUTION AND POWER TRANSFORMERS INCL DEHYDRATION / FILTRATION OF OIL INCLUIDNG OTHER ALLIED WORKS AT SECTOR A, B, C, D, E AND F AREA AT ARMY AREA JODHPUR UNDER GE (ARMY) NO.01
2023_MES_613357_1
82324/59/E8
Open Tender
Electrical and Maintenance Works
Item Rate
270 days
JODHPUR
Please refer Tender documents.
8 documents required · 8 mandatory
₹1,000
GE (A) NO. 01
₹1.1 L
Yes
7 Nov 2023
11 Aug 2023
22 Sept 2023
11 Aug 2023
15 Sept 2023
1 Sept 2023
12 Aug 2023 - 31 Aug 2023
Amount
M&L for minor repairing of 33/11 KV power transformer capacity from 1.6 MVA to 5.0 MVA at site by disconnecting primery and secondary side electrical connection including rectification of leakage problem of any type, replacement of bush insulators, gaskets/packings after opening of top cover of transformer, required nuts, bolt and washers and radiator brazing work etc and reconnection of all electrical connection including replacement of cable gland of suitable size required, complete all as specified and directed. Note: (i) The cost of minor spare parts e.g. gaskets/packing, nut-bolts-washers, lugs, neoprene rubber, ACSR jumper, etc. are deemed to be included in quoted rate. (ii) The cost fabricated copper strip/bus bar to connect secondary side bushing will be measured and paid separately. (iii) The cost of required T&P is deemed to be included in rate quoted by the contractor.
S&F in replacement of HT 33/11 KV transformer primery side bush insulator suitable for power transformer of any type Up to 5 MVA, complete all as specified and directed.
S&F in replacement of HT 33/11 KV transformer secondry side bush insulator suitable for power transformer of any type Up to 5 MVA, complete all as specified and directed.
S&F in replacement of HT 33/11 KV transformer primery side bush rod made out of brass with nut bolt, rubber packing and washer suitable for power transformer of any type Up to 5 MVA, complete all as specified and directed.
S&F in replacement of HT 33/11 KV transformer secondry side bush rod made out of brass with nut bolt, rubber packing and washer suitable for power transformer of any type Up to 5 MVA, complete all as specified and directed.
M&L for factory repair / servicing of step down transformer including repair/ replacement of worn out spares, replacement of transformer oil after cleaning the transformer body thoroughly in side and out side with cotton and sand paper and reassembling, installation the same on its existing position connecting and testing complete 11/0.433 KV transformer of 25 to100 KVA capacity including loading, unloading, transportation of faulty transformer from army area to factory premises and back for major repairs complete all as specified and directed by Engr-in-Charge. Note: 1. New spares required for replacement of faulty parts will be measured and paid separately under relevant item of schedule. 2. The cost for fault checking/ fault finding, servicing and repairing including minor parts such as gasket/packing, neoprene rubber, nut, bolts, washers, lugs etc are deemed to be included in quoted rate. 3. The transformer will be opened in the presence of EIC.
All as per Sl. item No. 6.00 here-in-above, but capacity of 125 KVA to 200 KVA.
All as per Sl. item No. 6.00 here-in-above, but capacity of 250 KVA to 630 KVA.
Supply, fabrication, assembling, and testing HT/LT coil rewinding of transformer with super enameled or double paper insulated mass impregnated complete limbs of three phase complete with all insulating material copper winding wire/strip of appropriate size and gauge with equal No of turns to match the existing coil of respective distribution power transformer of any type and capacity all as directed by EIC. Note: 1. The cost for dismantling of burned transformer winding including other necessary work required is deemed to be included in quoted rate. 2. The cost for testing is also included in above rate. The old winding will be dismantled in the presence of EIC.
All as per Sl. item No. 9.00 here-in-above,, but aluminium winding wire/strip
M&L for replacement of HT 11 KV bush insulator suitable for distribution transformer of any type Up to 200 KVA, complete all as specified and directed.
All as per Sl. item No. 11.00 here-in-above,, but capacity above 250 KVA to 630 KVA
M&L for replacement of LT bush insulator suitable for distribution transformer of any type upto 200 KVA, complete all as specified and directed.
All as per Sl. item No. 13.00 here-in-above, but capacity above 250 KVA to 630 KVA
M&L in replacement of HT bush rod made out of brass with nut bolt and washer suitable for distribution transformer any type upto 200 KVA, complete all as specified and directed.
All as per Sl. item No. 15.00 here-in-above, but capacity above 250 KVA to 630 KVA
M&L in replacement of LT bush rod made out of brass with nut bolt, rubber packing and washer suitable for distribution transformer any type upto 200 KVA, complete all as specified and directed.
All as per Sl. item No. 17.00 here-in-above, but capacity above 250 KVA to 630 KVA
M&L for filling of new transformer oil up to minimum level, dielectric strength of oil should not be less than 50KV at 2.5mm. Gap , complete all as specified and directed.
M&L for replacement of unserviceable tap changer suitable for existing transformer upto 100 KVA, complete all as specified and directed.
All as per Sl. item No. 20.00 here-in-above, but capacity above 125 KVA to 250 KVA
All as per Sl. item No. 20.00 here-in-above, but capacity above 315 KVA to 630 KVA
M&L for replacement of silica gel of existing breathers and all as directed by EIC
M&L for filtration/dehydration of transformer oil at site to increase dielectric strength up to 50 KV at 2.5mm gap by filtration / dehydration machine and improvement of acidity within limit all as directed by EIC. Note: - (a) The cost of testing of dielectric strength of transformer is deemed to be included in quoted rate. (b) A test sheet to be prepared for before and after filteration di-electric strength.
M&L for replacement of 3 mm thick cable box cover of distribution transformer of any capacity complete including replacement of gasket 6 mm thick and bolts / nuts, washer complete all as specified and directed by EIC.
M&L for cleaning, scrapping incl. necessary preparation of surface at site and spray painting of distribution transformer of any type complete incl. marking of date of dehydration on the body of capacity 25 KVA to 200 KVA all as directed by EIC.
All as per Sl. item No. 26.00 here-in-above, but capacity above 250 KVA to 630 KVA.
M&L in replacement of thermometer/Temperature gauge having brass sensor bulb to be placed in oil filled packet, analogue type with two bands for instant oil temp and max oil temp raised, Radial dial 100mm dia ramp 0 to 150 degree Cent. suitable for distribution transformer complete all as specified and directed by Engr-in-Charge.
M&L in replacement of silica gel breather transparent type with first filling of silica gel compete suitable for distribution transformer and all as directed by EIC.
M&L for minor repairing of transformer from 63 KVA to 250 KVA at site by disconnecting electrical connection including rectification of leakage problem of any type, from bush insulators, gasket etc and radiator brazing work, etc and reluging of LT side cable ends with suitable aluminium lugs after properation of cable end after cutting damaged / burnt cable and insulating with tape etc incl. replacement of cable gland of suitable size, complete all as specified and directed. Note: (i) The cost of minor spare parts e.g. gasket, nut-bolts-washers, lugs, neoprene rubber, ACSR jumper, etc. are deemed to be included in quoted rate. (ii) New spares shall be measured and paid seperatly under respective item.
All as per Sl. item No. 30.00 here-in-above, but size 315 KVA to 630 KVA.
M&L for disconnecting the electric connection of 33/11 KV Power Transformer capacity 1.6 MVA to 5.0 MVA by isolating primary and secondary side connection, earthing including removal from site and shifting carefully without causing any damage to factory premisses at appropriate reputed workshop for detection of fault and finding remedial measures for making the transfromer including loading, unloading, transportation of faulty transformer from Army area to factory premises and back from major repair including checking / finding of major fault, opening / dismantling, necessary testing, reassembling and refixing on existing site after rectification of fault etc complete all as specified and directed by Engr-in-Charge. Note: 1. New spares required for replacement of faulty parts will be measured and paid separately under relevant item of schedule. 2. The cost for fault checking/ fault finding, servicing and repairing including minor parts such as gasket/packing, neoprene rubber, nut, bolts, washers, lugs etc are deemed to be included in quoted rate. 3. The transformer will be opened in the presence of EIC.
M&L for disconnecting loading, unloading and transportation for shifting of transformer of any capacity and type from one location to another within the army area by wheeled crane incl. connecting complete necessary electrical connection, installation, testing and commissioning of repaired/serviced transformer all as directed by EIC.
Shri Electrical Enterprises
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .