Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.0 CrAdmitted-Finance | ₹2.0 Cr | L1 | Admitted-Finance |
| 2 | L2₹2.0 Cr+₹1.7 L (0.87%)Admitted-Finance | ₹2.0 Cr+₹1.7 L (0.87%) | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | abdul shereef L1 | SHAHEEN SULAIMAN L2 |
|---|---|---|---|---|---|
| 1.00 | Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material. Above 240 cm girth | 2 | nos | 21,300 ₹42,600 | 5,841 ₹11,682 Lowest |
| 1.00 | Taking out doors, windows and clerestory window shutters (steel or wood ) including stacking within 50 metres lead: Of area 3 sq. metes and below | 12 | nos | 139 ₹1,668 Lowest | 455 ₹5,460 |
| 1.00 | Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges: In Lime Mortar | 70 | cum | 1,117 ₹78,190 Lowest | 1,500 ₹1,05,000 |
| 1.00 | Dismantling steel work in single sections including dismembering and stacking within 50 metes lead in: Channels, angles, tees and flats | 820 | kg | 2 ₹1,640 Lowest | 116 ₹95,120 |
| 1.00 | Dismantling steel work manually / by mechanical means in built up sections without dismembering and stacking within 50 metres lead as per directions of Engineer -in-Charge. | 270 | kg | 3 ₹810 Lowest | 125 ₹33,750 |
| 1.01 | Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge. | 21 | cum | 3,427 ₹71,967 | 3,000 ₹63,000 Lowest |
| 1.01 | Dismantling roofing including ridges, hips, velleys and gutters etc., and stacking the material within 50 metres lead of : G.S. Sheet | 140 | sqm | 159 ₹22,260 Lowest | 200 ₹28,000 |
| 1.01 | Dismantling roofing including ridges, hips, velleys and gutters etc., and stacking the material within 50 metres lead of : Asbestos Sheet | 275 | sqm | 90 ₹24,750 Lowest | 225 ₹61,875 |
| 1.01 | Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil | 18 | cum | 100 ₹1,800 Lowest | 460 ₹8,280 |
| 1.01 | Laterite masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for foundation and basement including all cost of materials, labour charges etc. | 20 | cum | 8,976 ₹1,79,520 | 6,000 ₹1,20,000 Lowest |
Tender Value
₹2.0 Cr
EMD Value
₹50,000
Closing Date
26 May 2026, 3:00 pmClosed
Chief Engineer PE and B North
Office of the Chief Engineer Project Execution and Buildings North Vydyuthi Bhavanam Gandhi Road Kozhikode
Construction of Control center Building for supervisory Control and Data Acquisition (SCADA) Distribution Management System (DMS) under the Revamped Distribution Sector Scheme (RDSS) at Kannur.
2026_KSEB_841970_2
CE(PEB)N/03/2025-26 dtd.28.02.2026
Open Tender
Civil Works - Buildings
Item Rate
365 days
Kannur
Please refer tender documents.
3 documents required · 3 mandatory
₹5,900
₹50,000
15 Sept 2026
14 May 2026
30 May 2026
14 May 2026
26 May 2026
14 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.001 | Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material. Above 240 cm girth | - | nos | 21,299.92 | - |
| 1.002 | Taking out doors, windows and clerestory window shutters (steel or wood ) including stacking within 50 metres lead: Of area 3 sq. metes and below | - | nos | 138.42 | - |
| 1.003 | Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges: In Lime Mortar | - | cum | 1,117.51 | - |
| 1.004 | Dismantling steel work in single sections including dismembering and stacking within 50 metes lead in: Channels, angles, tees and flats | - | kg | 2.21 | - |
| 1.005 | Dismantling steel work manually / by mechanical means in built up sections without dismembering and stacking within 50 metres lead as per directions of Engineer -in-Charge. | - | kg | 3.72 | - |
| 1.006 | Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge. | - | cum | 3,426.77 | - |
| 1.007 | Dismantling roofing including ridges, hips, velleys and gutters etc., and stacking the material within 50 metres lead of : G.S. Sheet | - | sqm | 159.16 | - |
| 1.008 | Dismantling roofing including ridges, hips, velleys and gutters etc., and stacking the material within 50 metres lead of : Asbestos Sheet | - | sqm | 74.64 | - |
| 1.009 | Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil | - | cum | 335.74 | - |
| 0.000 | Laterite masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for foundation and basement including all cost of materials, labour charges etc. | - | cum | 7,543.69 | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 0.50 MB
Volume1prequalificationbid.pdf
Tender Documents • 0.97 MB
Volume2conditionsofcontract.pdf
Tender Documents • 2.55 MB
Volume3technicalspecifications.pdf
Tender Documents • 2.67 MB
Drawing2electrical.pdf
Other Document • 1.66 MB
Drawing1civil.pdf
Other Document • 1.05 MB
BOQ_1437290.xls
BOQ • 0.53 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .