Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.2 CrAccepted-AOC | ₹3.2 Cr | L1 | Accepted-AOC Quoted L1 rate |
| 2 | L2₹3.2 Cr+₹6.4 L (2.00%)Rejected-AOC | ₹3.2 Cr+₹6.4 L (2.00%) | L2 | Rejected-AOC Quoted L2 rate |
Tender Value
₹3.3 Cr
EMD Value
₹3.3 L
Closing Date
27 Dec 2023, 3:00 pmClosed
Project Director
DRDA Tiruchirappalli
Construction of Bridge across Iyyaru at Kattapalli (Maradi to Kattappalli Road R - 43 at CH 750) in Uppiliyapuram Block in Tiruchirappalli District under NABARD RIDF XXIX 2023-24 Package No.4
2023_RDTN_398524_4
DIPR/6574/Tender/2023 Dated 12.12.2023
Open Tender
Civil Works - Bridges
Item Rate
540 days
Tiruchirappalli
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹3.3 L
DRDA Tiruchirappalli
11 Jan 2024
15 Dec 2023
27 Dec 2023
15 Dec 2023
27 Dec 2023
15 Dec 2023
20 Dec 2023
Amount
Construction of Bridge across Iyyaru River at Kattappalli Maradi to Kattappalli Road at CH 750 in Uppiliyapuram Block Dismantling of existing structures like culverts, bridges and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.Removal Of Existing Bed Level Causeway For PCC
Earthwork excavation in all classes of soil except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for DRESSING THE BED UP TO SILL LEVEL.
Earthwork excavation in all classes of soil except hardrock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION UNDER ABUTMENTS & PIERS.
Earthwork excavation in Soft Disintegrated Rock not Requiring Blasting except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for FOUNDATION OF ABUTMENTS, PIERS AND WINGS.
Vibrated Cement Concrete of grade M 15 using 20mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Levelling Course Below Abutments, Piers Footing.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm, 12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Footing Under Abutment, Wing Wall & Piers Below Sill Level.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, WINGS, Below SILL LEVEL.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, WINGS, ABOVE SILL LEVEL.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for Circular Column Pier Below SILL LEVEL.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for Circular Column Pier Above SILL LEVEL.
Vibrated Reinforced Cement Concrete of grade M 35 using 20mm,12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for RCC Capping beam above column pier.
Vibrated Reinforced Cement Concrete of grade M35 using 20mm,12mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for DIRT WALL CUM BED BLOCK OVER ABUTMENTS AND BED BLOCK OVER PIERS.
Providing and Fixing Seepage pipes of 100 mm dia. PVC pipes of required lengths for abutments and wings including cost and conveyance of all materials to work site, cost and labour for 900 mm. Dia. Semi spherical back fill arrangements with 100 mm. size broken granite chips at the periphery and labour charges for fixing, etc., to drain of the BACKFILL IN BETWEEN THE ABUTMENTS AND RETURNS.
Providing and Fixing Kraft Paper for full width of seating of deck slab and including including cost and conveyance to work site Labour for fixing the same in correct position and all other incidental charges etc., compelte.
Vibrated Reinforced Cement Concrete M-35 Grade using 20mm, 12mm ISS size hard granite broken graded metal including cost and conveyance of all materials to site and cement at site but excluding cost and fabrication of steel and cost of formworks including labour charges for mixing, transporting, laying, curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges, etc., complete for DECK SLAB.
Providing and laying Filter Media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8
Filling behind Abutment and Wings with clean gritty gravel of Ø value not less than 35° including cost and conveyance of gravel to worksite, laying, handling charges and filling in layers, tamping under optimum moisture content to get the maximum density including watering, with all leads for water and all other incidental charges etc., complete as per standard specifications.
Providing and Fixing PVC EXPANSION JOINT in between Deck Slabs over abutment and pier as shown in the drawing including cost and conveyance of expansion joints including Shalimar Pad and joint Sealent etc., Complete.
Vibrated Cement Concrete of grade M 15 using 20mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for BASECOURSE BELOW APPROACH SLAB.
Vibrated Reinforced Cement Concrete M 35 Grade using 20mm, 12mm ISS size hard granite broken graded metal including cost and conveyance of all materials to site and cement at site but excluding cost and fabrication of steel but including cost of form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete working at heights, hire chargs for tools and plants, including all other incidental charges etc., complete as per standard specifications for Approach Slab.
Vibrated cement Concrete M35 using 20mm, 12mm IRC Metal HBG graded metal including cost and conveyance of all materials to worksite and cement at site including all labour charges for fixing concrete, laying, vibrating, hire charges for tools and plants, compacting, curing with all leads for soft water, including all other incidental charges, formwork, cost of premoulded expansion joints and fixing the same in position etc., complete for Wearing Coat of 75mm Uniform Thickness Over Deck Slab and Approach Slab.
Vibrated Reinforced Cement Concrete M40 using 20mm, 12mm ISS Size HBG metal including cost and conveyance of all materials to site including cement at site but excluding cost and fabrication of steel, including labour charges for mixing, transporting, laying, and curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges, etc., complete for CRASH BARRIER.
Vibrated Cement Concrete M20 grade using 20mm, 12mm ISS size hard granite broken metal including cost and form work and centering conveyance of all materials to site and cement at site including labour charges for mixing, transporting, laying, and curing concrete,working at heights for PCC PARAPET OVER WINGS.
Providing and Fixing of Cast Iron Drainage Spouts 100mm dia as per MOST drawing SD/205 with grating arrangements at top as shown in the drawing using 12mm x 25mm flats for grating arrangements, and 100mm dia drainage spout projecting beyond the bottom of Deck Slab as shown in the drawing including cost and conveyance of cast iron pipes and flats and fixing them in position etc, complete.
Supply and Fabrication of High Yield Strength Deformed Bar with Grade Designation Fe500, conforming to IS:1786 2008, steel required for all RCC items of works involved in the schedule cost of steel at site fabrication labour charges for cleaning, bending tying grills, including overlapping to the required length whenever necessary and placing the Reinforcement in position as specified in the drawings, including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc., complete, Fe500 grade.
Approach Road Excavation Including Removal and Satisfactory Disposal of all materials necessary for the Construction of Road Way and side drains in accordance with specifications and the lines, grades and cross sections shown in the drawings or as indicated by the Engineer using the carted earth with a lead of 2km for Formation.98% Compaction
100% Compaction
Collection and Supply of Gritty Gravel from approved quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, For SHOULDERS.
Construction of Granular Sub Base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20% & 2.36 mm below IRC HBG metal @15%) & (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% respectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix - in - place method) GSB-III.
Providing and Laying 75mm Compacted Thick WBM Grade II using 1 cum of 75mm to 22.4mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete For BOTTOM LAYER WBM Grade II.
Providing and Laying 75mm Compacted Thick WBM Grade III using 1 cum of 63mm to 11.20mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm. of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete For TOP LAYER WBM Grade III.
Providing and Laying of Prime Coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and Laying Tack coat over WMM surface (treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Providing and laying Open Graded Premix Carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.
Diversion Road Excavation including removal and satisfactory disposal of all materials necessary for the construction of road way and side drains in accordance with specifications and the lines, grades and cross sections shown in the drawings or as indicated by the Engineer using the carted earth with a lead of 2km for Formation.98% Compaction
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20% & 2.36 mm below IRC HBG metal @15%) & (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% respectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix - in - place method) GSB-III.
Providing and laying 75mm compacted thick WBM Grade II using 1 cum of 75mm to 22.4mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10 Sqm of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to work site and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel, forming edge bunds, watering with all leads for good water slurrying, rolling and consolidation by power roller and finishing as per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all incidental charges etc., complete for BOTTOM LAYER WBM Grade II.
Providing and laying Reinforced Cement Concrete Pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry.
Earthwork excavation in all classes of soil except hardrock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION UNDER RETAINING WALL.
Vibrated Cement Concrete of grade M 15 using 20mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Levelling Course Below Abutments, Footing & Retaining Wall.
Vibrated Cement Concrete of Grade M-20 using 20mm, 12 mm ISS HBG metal including cost and conveyance of all materials to site including cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, Tools and Plants and incidental charges such as maintaining of protective bunds, cofferdams, shoring, strutting etc; complete as per relevant standard specification, etc, complete as per relevant standard specification for FOOTINGS OF RETAINING WALLS.
Vibrated Cement Concrete of grade M20 using 20mm, 12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for STEM OF RETAINING WALLS.
Providing and Fixing Seepage Pipes of 100 mm dia. PVC pipes of required lengths for abutments and wings including cost and conveyance of all materials to work site, cost and labour for 900 mm Dia. Semi spherical back fill arrangements with 100 mm. size broken granite chips at the periphery and labour charges for fixing, etc., to drain of the BACKFILL IN BETWEEN THE ABUTMENTS AND RETURNS.
Earthwork excavation in all classes of soil except hardrock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION FOR RIGID APRON.
Vibrated Cement Concrete of grade M 15 using ISS 20mm size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for RIGID APRON.
Vibrated Cement Concrete of Grade M-20 using 20mm, 12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for RIGID APRON.
Vibrated Cement Concrete of Grade M-20 using 20mm, 12mm ISS HBG metal including cost and conveyance of all materials to site including cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, Tools and Plants and incidental charges such as maintaining of protective bunds, cofferdams, shoring, strutting etc; complete as per relevant standard specification, etc, for Cut - Off wall.
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
K SARAVANAN
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .