| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.5 CrAdmitted-Finance | -5.50% | ₹1.5 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.5 CrAdmitted-Finance | -3.25% | ₹1.5 Cr | L2 | Admitted-Finance |
| 3 | L3₹1.5 CrAdmitted-Finance | -3.11% | ₹1.5 Cr | L3 | Admitted-Finance |
| 4 | L4₹1.5 CrAdmitted-Finance 13 138 SHAKTINAGAR SHUKLAGANJ UNNAO | UNNAO | UTTAR PRADESH | 209801 | -1.94% | ₹1.5 Cr | L4 | Admitted-Finance |
Tender Value
₹1.6 Cr
EMD Value
₹3.1 L
Closing Date
20 Apr 2026, 5:00 pmClosed
GENERAL MANAGER CIVIL
SEC 6 NOIDA
M/o Building (C/o of Boundary Wall of Vacant Land in Sector-43 Near Som Bazar) Noida
2026_NOIDA_1132935_1
75/NOIDA/GM/WC-3/2025-26
Open Tender
Civil Works - Others
180 days
NOIDA
Please refer Tender documents.
3 documents required · 3 mandatory
₹5,310
NOIDA
₹3.1 L
3 Jun 2026
6 Apr 2026
21 Apr 2026
6 Apr 2026
20 Apr 2026
6 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by machanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. The contrator has to detect different utilities like sewer line, water supply line, Electric cable, Telephone cable, Gas pipe line etc. using utility detecting machine before start of excavation and shall start excavation only after getting permission of Engineer-in-charge. | - | Cum | - | - |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level 1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) DSR 18/I.No. 4.1.8/P- | - | Cum | - | - |
| 3 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 100 in foundation and plinth in: Cement mortar 1:4 (1 cement : 4 coarse sand AOR 6.1.1 | - | Cum | - | - |
| 4 | Brick work with FPS bricks of class designation 150 in superstructure above plinth level up to floor V level in all shapes and sizes in : Cement mortar 1:4 (1 cement : 4 coarse sand). | - | Cum | - | - |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level, Thermo Mechanically Treated bars of grade Fo_500D or more. Iten No.-5.22.6 | - | Kg | - | - |
| 6 | Reinforced cement concrete work in beams, suspended floors roofs having slope up to 15 degree landings balconies shelves chajjas lintels bands plain window sills staircases and spiral stair cases above plinth level up to floor five level excluding the cost of centering shuttering finishing and reinforcement with 1:1.5:3(1 cement: 1.5 coars sand ( zone- III ) : graded stone aggregate 20 mm nominal size ). | 64 | Cum | 8,444.41 | ₹5,40,442.24 |
| 7 | Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the surface even and smooth complete | - | Sqm | - | - |
| 8 | 12 mm cement plaster of mix : 1:4 (1 cement : 4 coarse sand) (DSR-18/I-13.4.1/P-222) | - | Sqm | - | - |
| 9 | Distempering (first coat) with oil bound distemper of approved brand and manufacture and of required shade on undercorated wall surface to give an even shade over and including a priming coat with cement primer of approved brand and manufacture such as Berger, J&N, Shalimar Asian Paint after thoroughly brushing the surface free from mortar dropping and other foreign matters and also including the surface even with plaster of paris or approved synthetic materials and sand papered smooth including supply of all materials labour Tools & plants etc required for proper completion of the work.SOR I.NO. 15.09 649 | - | Sqm | - | - |
| 10 | Steel work welded in built up sections/ framed work including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. DSR 18/I.No. 10.25.2./P- | - | Kg | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.07 MB
TD.pdf
Tender Documents • 5.40 MB
C.xls
Additional Documents • 0.05 MB
BOQ_2114773.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid