Tender Value
₹11.3 L
EMD Value
₹11,300
Closing Date
25 May 2026, 6:00 pmClosed
Executive Engineer, K. B. C. Division No.1/1,Radhanpur -385340
Fabrication and erection of Height Gauge Barrier at major road crossing on SR side of Radhanpur Branch Canal (slice-2) Ch 11.469 km to 24.608 km
301616
03 of 2026-2027
Open
Civil Works - Canal
Works
Patan
4 documents required · 4 mandatory
₹1,062
Executive Engineer, K.B.C Dn.No.- 1/1, Radhanpur
₹11,300
5 May 2026
5 May 2026
5 May 2026
25 May 2026
5 May 2026
BILL OF QUANTITIES
BILL OF QUANTITIES
1. The bill of Quantities shall be read in conjunction with the Instructions to Bidder,
Conditions of Contract, Technical Specifications and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional, and are
given to provide a common basis for bidding. The basis of payment will be the actual
quantities of work ordered and carried out, as measured by the Contractor and
verified by the Engineer and valued at the rates and prices tendered in the priced
Bill of Quantities, where applicable, and otherwise at such rates and prices as the
Engineer may fix within the terms of the Contract.
3. The rates and prices tendered in the priced Bill of Quantities shall, except in so far
as it is otherwise provided under the Contract, include all constructional plant,
layout, supervision, materials, erection, maintenance, insurance, profit, taxes and
duties, together with all general risks, liabilities and obligations set out or implied
in the Contract.
4. The rates and prices shall be quoted entirely in Indian Currency.
5. A rate or prices shall be entered against each item in the Bill Quantities, whether
quantities are stated or not. The cost of Items against which Contractor has failed
to enter a rate or price shall be deemed to be covered by other rates and prices
entered in the Bill of Quantities (in case of Item rate contract).
6. The whole cost of complying with the provisions of the Contract shall be included
in the items provided in the priced Bill of Quantities, and where no Items are
provided the cost shall be deemed to be distributed among the rates and prices
entered for the related items of Work.
7. General direction and descriptions of work and materials are not necessarily
repeated or summarized in the Bill of Quantities. References to the relevant
sections of the contract documentation shall be made before entering rates or
prices against each item in the Bill of Quantities.
8. The method of completed work of payment shall be in accordance with the
specification for Road and Bridge works. For building works specifications for
building are to be followed.
9. Errors will be corrected by the Employer for any arithmetic errors pursuant to
Clause 29 of the Instructions to Bidder.
10. Rock is defined as all materials which, in the opinion of the Engineer, required
blasting, or the use of metal wedges and sledgehammers, or the use of compressed
air drilling for its removal, and which cannot be extracted by ripping with a tractor
of at least 150 kw with a single rear mounted heavy duty ripper.
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr. )
Item Description of Item (with brief Quantity Unit Rate In Amount
No. specification and reference to figures
book of specifications)
Excavation for foundation in all
sorts of soil including yellow sandy
gravelly soils ,soft & hard murrum
etc. in dry condition including
depositing the excavated stuff in
uniform layers in banks or as and
where directed etc. complete for
lead up to 500m and all lift. (BY
MACHINERY) Excluding
Providing & Laying in position
"NOMINAL MIX" cement concrete
using cement, sand and crushed
aggregate by mass and machine
mix for C.C./R.C.C work incl.
necessary formworks centering,
2 scaffolding, compaction by 12.00 Cum 3935
vibrator, curing as directed with
all lead & lift etc complete Without
Dewatering and excluding cost of
steel reinforcement. (A) For
Foundation concrete / General
purpose (c) C. C. Nominal Mix, M-
15 and MSA-20 mm
Providing & Laying in position
"DESIGN MIX" cement concrete
using cement sand and crushed
aggregate for C.C./ R.C.C work by
"FLORI" including necessary
formwork, centering, scaffolding,
3 compaction by vibrator, curing as 26.00 Cum 4651
directed with all lead & lift etc
complete without dewatering and
excluding the cost of steel
reinforcement.e) Concrete grade
M-25 and MSA-20 mm
Providing and laying HYSD/TMT
Fe-415,500 D steel bar
reinforcement forR.C.C.works and
anchor bars with providing
binding wires including cutting,
bending, welding,binding in
4 position, hooking, placing in 2.20 MT 71366.00
position with all leads & lifts etc.
complete c) TMT Fe-500D
Back filling the foundation
trenches around the structure etc
with selected excavated stuff
including watering, ramming,
5 Compacting etc.complete.(By 149.00 cum 36.90
Fabrication and erection of Main
Girder section and Leg support
section for constructing of Height
6 Gauge for super structure
including foundation bolt, ISMB, 8.31 MT 93727.00
ISMC,CLEAT ANGLE, Bolts, plates
I/We am/are willing to carry out the work at… ...................... % above/below
percent(Should be written in figures and words) of the estimated rate mentioned above.
Amount of my /our tender works out as under.
Estimated amount put to tender Estimated amount put to tender
Deduct………% below Add………% Above
In words In words
(B) For Item Rate Tender (For above INR 50 Cr.):
Item Description of Item Quantity Unit Rate Amount
No (with brief specification
and reference to book of In In
specifications) figures Words
(A) Total Tendered Amount
(B) Rebate on above tendered amount (if any) % (in figure)
(C)Net Tendered Amount (A-B) (in figure) ………………………………
1. The Contractor shall exhibit a board with brief details of work as directed by
the Engineer-In-Charge for which no extra payment shall be made.
2. The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3. GST and Income tax TDS will be deducted at a source while making payments of
4. In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as
per Govt. G.R. NO.: MIS102010/17/K1 Dated:30/07/2018 as stated in S.O.R.
therefore in R.C.C. items where there is a change as per actual mix design the
cost of difference of cement consumption have been deducted from the rate of
original item at the rate of input rate mentioned in all the tend
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
BOQ-Slice-II Barrier.pdf
SBD Height barrier RBC slice-2.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .