| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹6.5 LAccepted-AOC KUNNEL HOUSE SOUTH PARAVOOR LSGD AMBALLOOR PANCHAYATH | IDUKKI | KERALA | 685501 | 1 | Accepted-AOC 1 |
Tender Value
₹5.9 L
EMD Value
₹14,827
Closing Date
20 Feb 2024, 11:00 amClosed
ASSISTANT ENGINEER,LID EW
ASSISTANT ENGINEER,LID EW
PUBLIC POND MAINTENANCE IN AMBALLOOR GP
2024_LSGD_649039_2
E58/ambr/23-24
Open Tender
Civil Works - Roads
Item Rate
180 days
AMBALLOOR
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,310
₹14,827
10 Jul 2024
9 Feb 2024
21 Feb 2024
9 Feb 2024
20 Feb 2024
9 Feb 2024
Amount
MAINTANENCE
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.33.2:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 60 cm girth up to and including 120 cm girth
2.33.1:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 30 cm girth up to and including 60 cm girth
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
OD299470/2023-2024:Removing water hyacinth and other vegetational floating bodies from the water way cutting, collecting, conveying and depositing own convenient places with all lead and lift and other incidental charges such as hire charges for country boats and other necessary equipment required for the work etc. complete as per direction of departmental officers at site.
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
51.2.3:Filling with Quarry Muck <br> Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade
OD299686/2023-2024:Providing and laying 60 mm thick factory made cement concrete interlocking paver block of M - 30 grade made by block making machine with strong vibratory compaction, of approved size, design & shape, laid in required colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge.
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
11.20.4:Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar 1:4 ( 1 cement : 4 coarse sand).Ordinary cement without any pigment
60.7.3:DISMANTLING DR - Dismanling , clearing away and carefully stacking materials useful for reuse for any thickness of walls in DR masonry including disposal of debris within a distance of 150m.
60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
60.7.8:DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
10.25.1:Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In stringers, treads,landings etc. of stair cases, including use of chequered plate wherever required, all complete
13.61.1:Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work
14.54.1:Painting with synthetic enamel paint of approved brand and manufacture of required colour to an give even shade:One or more coats on old work
OD344183/2023-2024:Coolie
Bidder Name
Manoj K S
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1015115.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .