| 1 | 1₹8.9 LAccepted-AOC | ₹8.9 L Quoted ₹9.3 L | 1 | Accepted-AOC L1 |
| 2 | 2₹9.4 L+₹5,031 (0.54%)Rejected-Finance | ₹9.4 L+₹5,031 (0.54%) | 2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | MUJEEB M K L2 | A BALAN L1 |
|---|---|---|---|---|---|
| 1.00Compound Wall Construction | |||||
| 1.00 | 2.32:Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared. | 280 | sqm | 15 ₹4,200 | 9.37 ₹2,623.6 Lowest |
| 1.00 | OD369778/2025-2026:DRY RUBBLE MASONRY - Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labor charges etc complete as per direction Departmental officers at site. | 32.94 | cum | 4,100 ₹1,35,054 | 4,034 ₹1,32,879.96 Lowest |
| 1.00 | 7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand) | 18.3 | cum | 8,500 ₹1,55,550 | 8,430 ₹1,54,269 Lowest |
| 1.00 | 4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. | 18.3 | sqm | 848 ₹15,518.4 Lowest | 848 ₹15,518.4 Lowest |
| 1.00 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 251.62 | kilogram | 113 ₹28,433.63 Lowest | 113 ₹28,433.63 Lowest |
| 1.01 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 4.58 | cum | 9,331 ₹42,689.33 Lowest | 9,331 ₹42,689.33 Lowest |
| 1.01 | 50.6.7.2:Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for super structure above plinth level up to floor two level including all cost of materials, labour charges etc. | 37.88 | cum | 9,129 ₹3,45,815.65 Lowest | 9,129 ₹3,45,815.65 Lowest |
| 1.01 | 13.4.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 coarse sand) | 350.44 | sqm | 389 ₹1,36,323.11 Lowest | 389 ₹1,36,323.11 Lowest |
| 1.01 | 13.60.1:Wall painting with acrylic emulsion paint of approved brand and manufacture to give an even shade:Two or more coats on new work | 371.49 | sqm | 174 ₹64,639.26 Lowest | 174 ₹64,639.26 Lowest |
Tender Value
₹8.5 L
EMD Value
₹21,186
Closing Date
9 Feb 2026, 6:00 pmClosed
ASSISTANT ENGINEER
AE LSGD VETTOM GP
COMPOUND WALL
2026_LSGD_832587_1
36/AE/LSGD/VGP/25-26
Open Tender
Civil Works - Buildings
Item Rate
270 days
VETTOM GP
Please refer Tender documents.
9 documents required · 9 mandatory
₹1,870
Yes
₹21,186
Yes
31 Aug 2026
2 Feb 2026
11 Feb 2026
2 Feb 2026
9 Feb 2026
2 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Compound Wall Construction | |||||
| 1.001 | 2.32:Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared. | - | sqm | - | - |
| 1.002 | OD369778/2025-2026:DRY RUBBLE MASONRY - Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labor charges etc complete as per direction Departmental officers at site. | 1 | cum | - | - |
| 1.003 | 7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand) | - | cum | - | - |
| 1.004 | 4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. | - | sqm | - | - |
| 1.005 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | - | kilogram | - | - |
| 1.006 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | - | cum | - | - |
| 1.007 | 50.6.7.2:Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for super structure above plinth level up to floor two level including all cost of materials, labour charges etc. | - | cum | - | - |
| 1.008 | 13.4.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 coarse sand) | 1 | sqm | - | - |
| 1.009 | 13.60.1:Wall painting with acrylic emulsion paint of approved brand and manufacture to give an even shade:Two or more coats on new work | - | sqm | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1399553.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.21 MB
BOQ_1399553.xls
BOQ • 0.30 MB
PRE.pdf
Tender Documents • 0.26 MB
viewsbd.pdf
Tender Documents • 1.73 MB
FT.pdf
Tender Documents • 0.25 MB
AFFI.pdf
Tender Documents • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .