| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹76.1 LAccepted-AOC V P ASSAGAO IN SIOLIM CONSTITUENCY MLA LAD SCHEME | SOUTH GOA | GOA | 403103 | ₹76.1 L | L1 | Accepted-AOC L1Bidder |
| 2 | L2₹76.1 LRejected-Finance SADGURU SMARAN H NO 1502 50 MADEL HOUSING BOARD THIVIM BARDEZ GOA | ₹76.1 L | L2 | Rejected-Finance Second Lowest bidder |
| 3 | L3₹76.1 LRejected-Finance | ₹76.1 L | L3 | Rejected-Finance Third Lowest bidder |
| 4 | L4₹76.1 LRejected-Finance HOUSE NO 195 3 NAIKWADA CANCA BARDEZ GOA | ₹76.1 L | L4 | Rejected-Finance Fourth Lowest bidder |
| 5 | Rejected-Technical | - | - | Rejected-Technical Reject |
| Sl No | Description | Qty | Unit | rohidas vaigankar L2 | I B CONSTRUCTIONS L1 | Shri Sateri Construction L2 | PAI.COM CONSTRUCTION L2 |
|---|---|---|---|---|---|---|---|
| 1.00 | Earthwork in excavation by mechanical means (hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sq.m on plan) including disposal of excavated earth lead upto 50 m and lift upto 1.5m disposed earth to be leveled and neatly dressed including providing barricading, danger lighting guarding as directed in : A) All kinds of soil | 758.2 | Cum | 100.03 ₹75,842.75 | 100.67 ₹76,327.99 | 15.39 ₹11,668.70 | 190.01 ₹1.4 L |
| 2.00 | Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete. | 142.8 | Cum | 350.09 ₹49,992.85 | 1,200.93 ₹1.7 L | 82.95 ₹11,845.26 | 1,300.01 ₹1.9 L |
| 3.00 | Supplying jamba wooden bally piles 150 mm mean diameter cut to length required (not exceeding 9 meters) and planted in position ready for driving: a) Upto 2.5 meters long pile | 1,700 | Metre | 150.43 ₹2.6 L | 249.99 ₹4.2 L | 15 ₹25,500 | 120 ₹2.0 L |
| 4.00 | Driving down wooden piles of 150mm diameter either in vertical or battered work to approved lines and level through various strata including arranging all the appliances necessary for pile driving complete at site (portion in ground only to be measured) A) Upto 2.5 meters long pile | 1,496 | Metre | 99.98 ₹1.5 L | 149.49 ₹2.2 L | 15 ₹22,440 | 180 ₹2.7 L |
| 5.00 | Centering and shuttering including struttings, propping etc. and removal of formwork for : a) Foundations, footings, bases for columns and mass concrete. | 1,836 | Sq.m | 150.02 ₹2.8 L | 199.95 ₹3.7 L | 72.49 ₹1.3 L | 330 ₹6.1 L |
| 6.00 | Providing & laying cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded granitic or basaltic stone aggregate. 20 mm. nominal size) excluding cost of centering, shuttering and finishing in: a) All works upto plinth level | 877.2 | Cum | 6,416 ₹56.3 L | 5,889.65 ₹51.7 L | 7,114 ₹62.4 L | 5,720.09 ₹50.2 L |
| 7.00 | Providing and fixing weepholes with rigid PVC make laid in position with a required slope and level while layingpipes of approved the concrete of retaining wall,wing wall and earth retaining structure complete as directed by the Engineer in charge B) 75 mm dia | 119 | RM | 100.13 ₹11,915.47 | 139.95 ₹16,654.05 | 13.93 ₹1,657.67 | 168.69 ₹20,074.11 |
Tender Value
₹95.1 L
EMD Value
₹1.9 L
Closing Date
25 Oct 2024, 5:00 pmClosed
EE I WRD Porvorim
EE I WRD Porvorim
Construction of Protection wall in Sy. No.6/01 at Manshechobund, Gublawada, Oxel Siolim Bardez Goa.
2024_WRD_17864_1
6-9/WDI/WRD/ASW/2024-25/e-13/1
Open Tender
Miscellaneous Works
120 days
EEI WRD Porvorim Goa
Please refer Tender documents.
3 documents required · 3 mandatory
₹8,000
₹1.9 L
18 May 2026
14 Oct 2024
28 Oct 2024
14 Oct 2024
25 Oct 2024
14 Oct 2024
Amount
Earthwork in excavation by mechanical means (hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sq.m on plan) including disposal of excavated earth lead upto 50 m and lift upto 1.5m disposed earth to be leveled and neatly dressed including providing barricading, danger lighting guarding as directed in : A) All kinds of soil
Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete.
Supplying jamba wooden bally piles 150 mm mean diameter cut to length required (not exceeding 9 meters) and planted in position ready for driving: a) Upto 2.5 meters long pile
Driving down wooden piles of 150mm diameter either in vertical or battered work to approved lines and level through various strata including arranging all the appliances necessary for pile driving complete at site (portion in ground only to be measured) A) Upto 2.5 meters long pile
Centering and shuttering including struttings, propping etc. and removal of formwork for : a) Foundations, footings, bases for columns and mass concrete.
Providing & laying cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded granitic or basaltic stone aggregate. 20 mm. nominal size) excluding cost of centering, shuttering and finishing in: a) All works upto plinth level
Providing and fixing weepholes with rigid PVC make laid in position with a required slope and level while layingpipes of approved the concrete of retaining wall,wing wall and earth retaining structure complete as directed by the Engineer in charge B) 75 mm dia
Shri Sateri Construction (BID ID -39364)
rohidas vaigankar (BID ID -39540)
PAI.COM CONSTRUCTION (BID ID -39567)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.96 MB
Tendernotice_2.pdf
PDF • 1.09 MB
BOQ_18301.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid